CN208501802U - A kind of bathroom caisson internal drainage construction - Google Patents
A kind of bathroom caisson internal drainage construction Download PDFInfo
- Publication number
- CN208501802U CN208501802U CN201821081615.1U CN201821081615U CN208501802U CN 208501802 U CN208501802 U CN 208501802U CN 201821081615 U CN201821081615 U CN 201821081615U CN 208501802 U CN208501802 U CN 208501802U
- Authority
- CN
- China
- Prior art keywords
- filler material
- layer
- hydrophobic filler
- drainpipe
- caisson
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 19
- 239000010410 layer Substances 0.000 claims abstract description 62
- 239000000463 material Substances 0.000 claims abstract description 55
- 239000000945 filler Substances 0.000 claims abstract description 54
- 230000002209 hydrophobic effect Effects 0.000 claims abstract description 54
- 239000011241 protective layer Substances 0.000 claims abstract description 32
- 238000005192 partition Methods 0.000 claims abstract description 21
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 21
- 239000012790 adhesive layer Substances 0.000 claims abstract description 14
- 238000009408 flooring Methods 0.000 claims abstract description 5
- 239000011248 coating agent Substances 0.000 claims abstract description 3
- 238000000576 coating method Methods 0.000 claims abstract description 3
- 238000003287 bathing Methods 0.000 claims description 9
- 239000002351 wastewater Substances 0.000 claims description 9
- 238000009825 accumulation Methods 0.000 abstract description 5
- 238000005034 decoration Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000004568 cement Substances 0.000 description 1
- 239000000919 ceramic Substances 0.000 description 1
- 238000005253 cladding Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
Landscapes
- Sink And Installation For Waste Water (AREA)
Abstract
A kind of bathroom caisson internal drainage construction, including structure floor, partition wall, catch basin drainpipe and main drainpipe, structure floor are lower than corresponding flooring height, and partition wall is centered around structure floor surrounding, the caisson under earth's surface decorative layer to form sunk type bathroom;The bottom of caisson is equipped with concrete sloping layer; hydrophobic filler material is filled in caisson; bottom surface, top surface and the surrounding of hydrophobic filler material are equipped with the protective layer for coating hydrophobic filler material, on the waterproof layer for the top surface that earth's surface decorative layer is arranged in hydrophobic filler material by adhesive layer;Catch basin drainpipe is connected with the main drainpipe for sewerage, the lowest point in space where hydrophobic filler material is arranged in the water inlet of catch basin drainpipe, the utility model is discharged after collecting the ponding in hydrophobic filler material by concrete sloping layer by catch basin drainpipe, to realize the purpose of the ponding discharge in caisson, effectively prevent from leading to the problem of leaking because of caisson internal water accumulation.
Description
Technical field
The utility model relates to bathroom waterproof, seepage control technical fields, and in particular to a kind of bathroom caisson internal drainage construction.
Background technique
There are many room and position of the indoor water of modern architecture, and antiseepage, leakage are a necessary construction contents.In order to reduce
Upstairs resident is on the interference of resident downstairs and influence, since 10 years in recent years, has risen a kind of novel architectural construction both at home and abroad, i.e., under
Heavy formula bathroom side draining, resident can't see drainpipe upstairs downstairs.But because not improved and complete drainaging scheme, does not have
There is the queueing problem for resolving caisson internal water accumulation, leakage problems is caused to go wrong repeatedly, so that sunk type side drain structure
Original intention cannot be realized perfectly.
Utility model content
The utility model in order to solve the above problems existing in the present technology, provides a kind of bathroom caisson internal drainage structure
It makes, problem that lead to leakage problems repeatedly occur equal difficult with the discharge for solving existing caisson internal water accumulation.
To achieve the above object, the utility model provides a kind of bathroom caisson internal drainage construction, including structure floor,
Partition wall, catch basin drainpipe and main drainpipe, the structure floor are lower than corresponding flooring height, and the partition wall is centered around the knot
Structure floor surrounding, the caisson under earth's surface decorative layer to form sunk type bathroom;The bottom of the caisson is equipped with concrete
Sloping layer is filled with hydrophobic filler material in the caisson, and bottom surface, top surface and the surrounding of the hydrophobic filler material are equipped with fills out hydrophobic
Charge cladding protective layer, the earth's surface decorative layer by adhesive layer be arranged in hydrophobic filler material top surface waterproof layer it
On;The catch basin drainpipe is connected with the main drainpipe for sewerage, and the water inlet setting of catch basin drainpipe is being dredged
The lowest point in space where water filler material.
As the further preferred technical solution of the utility model, first is equipped between the hydrophobic filler material and waterproof layer
Protective layer is additionally provided with the second protective layer between the waterproof layer and adhesive layer at the top of hydrophobic filler material.
As the further preferred technical solution of the utility model, the main drainpipe is vertically arranged to except partition wall, institute
It states catch basin drainpipe to be laterally arranged, water inlet sequentially passes through partition wall, waterproof layer, the first protective layer, and is arranged and fills out hydrophobic
The lowest point in space where charge.
As the further preferred technical solution of the utility model, the water inlet of the catch basin drainpipe is arranged with netted
Filter mantle.
As the further preferred technical solution of the utility model, the surrounding heap of the filter mantle is equipped with haydite.
As the further preferred technical solution of the utility model, it is additionally provided with bathing wastewater pipe in the hydrophobic filler material,
One end of the bathing wastewater pipe sequentially passes through the first protective layer, waterproof layer, partition wall positioned at hydrophobic filler material side, and with master
Drainpipe is connected, the other end sequentially pass through the first protective layer at the top of hydrophobic filler material, waterproof layer, the second protective layer,
Adhesive layer, earth's surface decorative layer, and be connected with squatting pan, closestool or Wash Units.
As the further preferred technical solution of the utility model, it is also connected with odour-proof floor drain on the bathing wastewater pipe,
The odour-proof floor drain sequentially passes through the first protective layer, waterproof layer, the second protective layer, adhesive layer at the top of hydrophobic filler material,
And it is embedded in earth's surface decorative layer.
The bathroom caisson internal drainage construction of the utility model can achieve it is following the utility model has the advantages that
The bathroom caisson internal drainage of the utility model constructs, by include structure floor, partition wall, catch basin drainpipe and
Main drainpipe, the structure floor are lower than corresponding flooring height, and the partition wall is centered around the structure floor surrounding, under being formed
Caisson under the earth's surface decorative layer of heavy formula bathroom;The bottom of the caisson is equipped with concrete sloping layer, fills out in the caisson
There is hydrophobic filler material, bottom surface, top surface and the surrounding of the hydrophobic filler material are equipped with the protective layer for coating hydrophobic filler material, institute
On the waterproof layer for stating the top surface that earth's surface decorative layer is arranged in hydrophobic filler material by adhesive layer;The catch basin drainpipe
It is connected with the main drainpipe for sewerage, space where hydrophobic filler material is arranged in the water inlet of catch basin drainpipe is most
Lower is discharged, to realize by catch basin drainpipe after collecting the ponding in hydrophobic filler material by concrete sloping layer
By the purpose of the ponding discharge in caisson, effectively prevent from leading to the problem of leaking because of caisson internal water accumulation.
Detailed description of the invention
Utility model will be further described in detail below with reference to the attached drawings and specific embodiments.
Fig. 1 is the structural schematic diagram for the example that the utility model bathroom caisson internal drainage construction provides;
Fig. 2 is the enlarged drawing in Fig. 1 at the A of part;
Fig. 3 is the enlarged drawing in Fig. 1 at the B of part;
Fig. 4 is the structural schematic diagram of filter mantle.
In figure: 1, structure floor, 2, partition wall, 3, odour-proof floor drain, 4, main drainpipe, 5, filter mantle, 6, catch basin drainpipe,
7, concrete sloping layer, 8, waterproof layer, the 9, first protective layer, 10, adhesive layer, 11, finish coat, 12, hydrophobic filler material, 13, wash
Bathe drainpipe, the 14, second protective layer.
The utility model aim is realized, the embodiments will be further described with reference to the accompanying drawings for functional characteristics and advantage.
Specific embodiment
Below in conjunction with attached drawing and specific embodiment, the utility model is described further.In preferred embodiment
Cited such as "upper", "lower", "left", "right", " centre " and " one " term, only being illustrated convenient for narration, rather than to
The enforceable range of the utility model is limited, relativeness is altered or modified, under the content of no substantial changes in technology, when also
It is considered as the enforceable scope of the utility model.
As shown in Figures 1 to 4, bathroom caisson internal drainage construction includes structure floor 1, partition wall 2, catch basin drainpipe 6
With main drainpipe 4, the structure floor 1 is lower than corresponding flooring height, and the partition wall 2 is centered around 1 surrounding of structure floor, with
Form the caisson under the earth's surface decorative layer of sunk type bathroom;The bottom of the caisson is equipped with concrete sloping layer 7, described heavy
Hydrophobic filler material 12 is filled in case, bottom surface, top surface and the surrounding of the hydrophobic filler material 12, which are equipped with, wraps hydrophobic filler material 12
The protective layer 9 covered, the earth's surface decorative layer by adhesive layer 10 be arranged in hydrophobic filler material 12 top surface waterproof layer 8 it
On;The catch basin drainpipe 6 is connected with the main drainpipe 4 for sewerage, and the water inlet setting of catch basin drainpipe 6 exists
The lowest point in hydrophobic 12 place space of filler material, using the drain structure, so that heavy in the construction of caisson internal cause and use process
What is constantly accumulated in case contains water storage, passes through collection after collecting the ponding in hydrophobic filler material 12 by concrete sloping layer 7
Sink drain 6 is discharged, to realize the purpose of the ponding discharge in caisson, effectively prevents from causing because of caisson internal water accumulation
The problem of leaking.The innovation of the utility model is, the drainpipe of bathroom not cross-layer is drained specifically for caisson and side
Building structure and the draining antiseepage function realized.
In the utility model, hydrophobic filler material 12 stirs for the haydite 5 and cement plus water for being 5 to 1 by volume ratio,
Compared to common filler material, hydrophobic function is more preferable, it is easier to dredge the ponding in caisson and flow to lowest point, and arrange by catch basin
Water pipe 6 is discharged.
In specific implementation, the first protective layer, the first protective layer position are equipped between the hydrophobic filler material 12 and waterproof layer 8
Between the bottom and waterproof layer 8 of the hydrophobic filler material 12, between the surrounding of hydrophobic filler material 12 and waterproof layer 8, and dredge
Between the top and waterproof layer 8 of water filler material 12, due to need to now first be set on partition wall 2 and concrete sloping layer 7 in work progress
Waterproof layer 8 is set, then fills out and sets hydrophobic filler material 12, the first protective layer being attached on waterproof layer 8 can effectively in order to prevent
Waterproof layer 8 is destroyed by subsequent construction.The second protection is additionally provided between waterproof layer 8 and adhesive layer at the top of hydrophobic filler material
Layer, the second protective layer can be effectively protected waterproof layer 8 and not be destroyed in surface decoration layer work progress.
In specific implementation, the main drainpipe 4 is vertically arranged to except partition wall 2, and the catch basin drainpipe 6 is laterally set
It sets, water inlet sequentially passes through partition wall 2, waterproof layer 8, protective layer 9, and the minimum of hydrophobic 12 place space of filler material is arranged in
Place, the water inlet of the catch basin drainpipe 6 are arranged with netted filter mantle 5, and the surrounding heap of the filter mantle 5 is equipped with haydite,
Haydite surrounds filter mantle 5, can be easier that ponding is made to flow into catch basin drainpipe 6.
In specific implementation, it is additionally provided with bathing wastewater pipe 13 in the hydrophobic filler material 12, the one of the bathing wastewater pipe 13
The first protective layer 9, waterproof layer 8, partition wall 2 that sequentially pass through positioned at hydrophobic 12 side of filler material is held to be connected with main drainpipe 4, separately
One end sequentially pass through the first protective layer 9 positioned at 12 top of hydrophobic filler material, waterproof layer 8, the second protective layer 14, adhesive layer 10,
Earth's surface decorative layer, and be connected with squatting pan, closestool or Wash Units.Odour-proof floor drain 3, institute are also connected on the bathing wastewater pipe 13
Odour-proof floor drain 3 is stated to sequentially pass through the first protective layer 9 positioned at hydrophobic 12 top of filler material, waterproof layer 8, the second protective layer 14, glue
Layer 10 is connect, and is embedded in earth's surface decorative layer, ground decoration layer is ceramic tile or stone material.
Although those skilled in the art should manage the foregoing describe specific embodiment of the present utility model
Solution, these are merely examples, various changes or modifications can be made to present embodiment, without departing from the original of the utility model
Reason and essence, the protection scope of the utility model are only limited by the claims that follow.
Claims (7)
1. a kind of bathroom caisson internal drainage construction, which is characterized in that including structure floor, partition wall, catch basin drainpipe and master
Drainpipe, the structure floor are lower than corresponding flooring height, and the partition wall is centered around the structure floor surrounding, are sunk with being formed
Caisson under the earth's surface decorative layer of formula bathroom;The bottom of the caisson is equipped with concrete sloping layer, is filled in the caisson
Hydrophobic filler material, bottom surface, top surface and the surrounding of the hydrophobic filler material are equipped with the protective layer for coating hydrophobic filler material, described
Earth's surface decorative layer is arranged on the waterproof layer of the top surface of hydrophobic filler material by adhesive layer;The catch basin drainpipe with
Main drainpipe for sewerage is connected, and space is minimum where hydrophobic filler material is arranged in the water inlet of catch basin drainpipe
Place.
2. bathroom caisson internal drainage construction according to claim 1, which is characterized in that the hydrophobic filler material and waterproof
It is equipped with the first protective layer between layer, is additionally provided with the second protective layer between the waterproof layer and adhesive layer at the top of hydrophobic filler material.
3. bathroom caisson internal drainage construction according to claim 2, which is characterized in that the main drainpipe is vertically arranged
Except partition wall, the catch basin drainpipe is laterally arranged, and water inlet sequentially passes through partition wall, waterproof layer, the first protective layer, and
The lowest point in space where hydrophobic filler material is set.
4. bathroom caisson internal drainage construction according to claim 3, which is characterized in that the catch basin drainpipe enters
The mouth of a river is arranged with netted filter mantle.
5. bathroom caisson internal drainage construction according to claim 4, which is characterized in that the surrounding heap of the filter mantle is set
There is haydite.
6. bathroom caisson internal drainage construction according to claim 5, which is characterized in that also set in the hydrophobic filler material
There is bathing wastewater pipe, one end of the bathing wastewater pipe sequentially passes through the first protective layer positioned at hydrophobic filler material side, waterproof
Layer, partition wall, and are connected with main drainpipe, and the other end sequentially passes through the first protective layer at the top of hydrophobic filler material, waterproof
Layer, the second protective layer, adhesive layer, earth's surface decorative layer, and be connected with squatting pan, closestool or Wash Units.
7. bathroom caisson internal drainage construction according to claim 6, which is characterized in that also connect on the bathing wastewater pipe
It is connected to odour-proof floor drain, the odour-proof floor drain sequentially passes through the first protective layer, waterproof layer, the second guarantor at the top of hydrophobic filler material
Sheath, adhesive layer, and be embedded in earth's surface decorative layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821081615.1U CN208501802U (en) | 2018-07-06 | 2018-07-06 | A kind of bathroom caisson internal drainage construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821081615.1U CN208501802U (en) | 2018-07-06 | 2018-07-06 | A kind of bathroom caisson internal drainage construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208501802U true CN208501802U (en) | 2019-02-15 |
Family
ID=65285147
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821081615.1U Expired - Fee Related CN208501802U (en) | 2018-07-06 | 2018-07-06 | A kind of bathroom caisson internal drainage construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208501802U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593794A (en) * | 2020-06-08 | 2020-08-28 | 四川海之科技股份有限公司 | Ponding structure is prevented to indoor formula bathroom that sinks |
TWI759721B (en) * | 2019-05-23 | 2022-04-01 | 日商松下知識產權經營股份有限公司 | Drain socket |
CN114941394A (en) * | 2022-06-30 | 2022-08-26 | 苏州阳地钢装配式建筑技术有限公司 | Backfill construction process for assembled public washroom |
-
2018
- 2018-07-06 CN CN201821081615.1U patent/CN208501802U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI759721B (en) * | 2019-05-23 | 2022-04-01 | 日商松下知識產權經營股份有限公司 | Drain socket |
CN111593794A (en) * | 2020-06-08 | 2020-08-28 | 四川海之科技股份有限公司 | Ponding structure is prevented to indoor formula bathroom that sinks |
CN111593794B (en) * | 2020-06-08 | 2021-07-09 | 四川海之科技股份有限公司 | Ponding structure is prevented to indoor formula bathroom that sinks |
CN114941394A (en) * | 2022-06-30 | 2022-08-26 | 苏州阳地钢装配式建筑技术有限公司 | Backfill construction process for assembled public washroom |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202745335U (en) | Sunken type toilet water-resistant deodorization settling basin structure | |
CN208501802U (en) | A kind of bathroom caisson internal drainage construction | |
CN107816138A (en) | A kind of construction technology of subsided rest room | |
CN104234089B (en) | The construction method that a kind of basement guarded drainage combines | |
CN208718112U (en) | Novel anti-ponding structure based on toilet geothermal heating ground surface finishing | |
CN204435496U (en) | A kind of building co-layer draining structure | |
CN207646973U (en) | A kind of vacation wall heel row formula co-layer draining waterproof system and the building including the system | |
CN207376723U (en) | A kind of subsided rest room | |
CN210887906U (en) | Caisson formula bathroom floor antiseep structure | |
CN201660935U (en) | Multifunctional guiding cylinder type anti-clogging water leaking device | |
CN107882124A (en) | Toilet | |
CN207499071U (en) | toilet | |
CN201428178Y (en) | Settlement water-saving toilet | |
CN206521812U (en) | A kind of anti-leakage structure of toilet | |
CN211547908U (en) | Secondary drainage water draining and draining device for kitchen and bathroom | |
CN101881041B (en) | Floor drain sunk same-layer drainage construction method | |
CN203821521U (en) | Soil stack connection piece for caisson type toilet | |
CN104790472B (en) | Same floor drainage structure of toilet | |
CN207499072U (en) | toilet | |
CN103556841B (en) | A kind of hollow type residence toilet substructure | |
CN207295866U (en) | Caisson of toilet secondary drainage system | |
CN208167931U (en) | Socket joint type double-layer floor drain | |
CN207003572U (en) | A kind of Multifunctional water drainer | |
CN206554180U (en) | A kind of integrated water-proof chassis of toilet pipeline | |
CN215926335U (en) | Backfill waterproof construction with layer drainage bathroom |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 518000 No. 17, Xihongtao Road, Nigang, Luohu District, Shenzhen City, Guangdong Province Patentee after: Shenzhen Hongtao Group Co.,Ltd. Address before: 518000 No. 17, Xihongtao Road, Nigang, Luohu District, Shenzhen City, Guangdong Province Patentee before: SHENZHEN HONGTAO DECORATION Co.,Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190215 |