- CN208472581U CN208472581U CN201821057441.5U CN201821057441U CN208472581U CN 208472581 U CN208472581 U CN 208472581U CN 201821057441 U CN201821057441 U CN 201821057441U CN 208472581 U CN208472581 U CN 208472581U
- Authority
- CN
- China
- Prior art keywords
- pier shaft
- maintenance
- regulation pipe
- water
- spray head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of pier shaft automatic maintenance systems, belong to technical field of building construction, which includes pier shaft ontology, further include distribution box, water storage box, water pump, maintenance skeleton, water delivery general pipeline, delivery pipe branch and spray head;Unlatching and closure in the distribution box equipped with the time relay and for controlling the water pump, the water pump are located in the water storage box, and the water pump is connect with the water delivery main pipe;The maintenance skeleton is fixed on the pier shaft bodies top, and the water delivery general pipeline is fixed on the maintenance skeleton and connect with the delivery pipe branch;The maintenance skeleton surrounding is connected with activity adjustment mechanism, the spray head is located at the pier shaft body upper part surrounding and is fixed in the activity adjustment mechanism, the spray head is connect with the delivery pipe branch, solve the problems, such as that traditional bridge pier pier shaft concrete curing is more time-consuming, water resource is saved, using flexible is stronger.
Description
Technical field
The utility model relates to technical field of building construction, in particular to a kind of pier shaft automatic maintenance system.
Background technique
Pier shaft is the main body of the intermediate support structure of multiple span bridge, and main material is timber, building stones, concrete, reinforced concrete
Soil, steel etc..Pier shaft is conserved after cement final set, to keep the wet of concrete surface, to guarantee that cement is hard
Change can be gone on smoothly, if conserved not in time, after concrete surface dehydration, the hydration reaction of cement will stop, while surface
Dry contraction is generated, under the action of convergent force, concrete structure generates slight crack, influences the safety and normal use of structure.
Currently, the maintenance process of bridge pier pier shaft concrete is usually to be taken out with sprinkling truck wet curing or nearest river, pool
Water curing, water waste is larger, and worker operation large labor intensity, and time-consuming and laborious, security risk is big, and operating efficiency is low.
Utility model content
The purpose of the utility model is to provide a kind of pier shaft automatic maintenance systems, and which solve traditional bridge pier pier shaft concrete
Conserve more time-consuming problem.
The above-mentioned technical purpose of the utility model has the technical scheme that
A kind of pier shaft automatic maintenance system, including pier shaft ontology, further include distribution box, water storage box, water pump, maintenance skeleton,
Water delivery general pipeline, delivery pipe branch and spray head;
Unlatching and closure in the distribution box equipped with the time relay and for controlling the water pump, the water pump are located at
In the water storage box, the water pump is connect with the water delivery main pipe;
The maintenance skeleton is fixed on the pier shaft bodies top, the water delivery general pipeline be fixed on the maintenance skeleton and
It is connect with the delivery pipe branch;
The maintenance skeleton surrounding is connected with activity adjustment mechanism, the spray head be located at the pier shaft body upper part surrounding and
It is fixed in the activity adjustment mechanism, the spray head is connect with the delivery pipe branch.
Using the above structure, spray time is arranged to relay, so that the unlatching of water pump is effectively controlled with closure, spray
When leaching, the water in water storage box is input in water delivery general pipeline by water pump by pipeline, and maintenance water successively passes through water delivery general pipeline and defeated
It will be sprayed on maintenance face by spray head after water branch pipe.The defect manually without legal time maintenance is eliminated, it can be according to concrete core
Portion's temperature, the variation of environment temperature carry out concrete after pouring to be retained moist maintenance, and it is uneven to eliminate artificial maintenance
Lead to the difference of bridge pier surface temperature, effectively prevents the cracking of concrete surface.Ensure the safety of maintenance personnel, conserves people
Member does not need the climbing bridge pier of high frequency time, reduces maintenance personnel in wet relatively sliding bridge pier top surface high frequency time operation bring safety
Hidden danger reduces workload, alleviates labor intensity, time saving and energy saving, and can be effectively controlled maintenance water consumption, reduces water resource wave
Take.
It advanced optimizes are as follows: the activity adjustment mechanism includes that the first regulation pipe, the second regulation pipe, connecting rod and first are tight
Fixing bolt, first regulation pipe are located at the maintenance skeleton surrounding, and first regulation pipe is plugged in the maintenance skeleton
And setting is slided with it, first fastening bolt is mounted on the maintenance skeleton and for limiting the first regulation pipe water
It is smooth dynamic;
Second regulation pipe is vertically arranged and is located at first regulation pipe outer end, the connecting rod upper end and institute
The connection of the second regulation pipe is stated, lower end is located at the pier shaft body upper part surrounding and connect with the spray head.
Using the above structure, according to the pier pattern formula of pier shaft ontology, activity adjustment institutional adjustment maintenance skeleton can be used
Length and width when adjustment, rotates the first fastening bolt, slides the first regulation pipe again after the first fastening bolt loosens, so that
First regulation pipe moves horizontally, and screws after being moved to suitable position, then by the first fastening bolt.Suitable for different pier shafts
Pattern, guarantees maintenance effect, and using flexible is stronger.
It advanced optimizes are as follows: the activity adjustment mechanism further includes sleeve and the second fastening bolt, and the sleeve is fixed on
First regulation pipe outer end, second regulation pipe pass through the sleeve both ends and slide setting with it, and described second is tight
Fixing bolt is mounted on the sleeve and slides up and down for limiting second regulation pipe.
Using the above structure, according to the difference of maintenance face upper and lower position, the height of activity adjustment institutional adjustment spray head can be used
Degree when adjustment, rotates the second fastening bolt, slides the second regulation pipe again after the second fastening bolt loosens, so that second is adjusted
Pipe moves up and down, and screws after being moved to suitable position, then by the second fastening bolt.So that each position is all above and below bridge pier
It can be conserved, using flexible is stronger, can effectively reduce bridge pier cracking.
It advanced optimizes are as follows: second regulation pipe upper end, which is fixed with, skids off downwards institute for limiting second regulation pipe
State the limited block of sleeve.
Using the above structure, prevent the second regulation pipe from removing sleeve when moving down.
It advanced optimizes are as follows: the activity adjustment mechanism further includes connecting plate, and the connecting plate is L-shaped, the spray head
It is mounted on the connecting plate, the connecting plate and the connecting rod lower end are hinged.
Using the above structure, according to the difference of maintenance face horizontal position, the spray of activity adjustment institutional adjustment spray head can be used
Firing angle degree, since connecting rod is hinged with connecting plate, when spray angle needs to adjust by a small margin, be rotatably connected plate, so that
For showerhead face towards maintenance face, using flexible is stronger, and maintenance effect is good and sprinkling is uniform.
It advanced optimizes are as follows: the connecting rod upper end and second regulation pipe lower end are hinged.
Using the above structure, according to the difference of maintenance face horizontal position, the spray of activity adjustment institutional adjustment spray head can be used
Firing angle degree, since connecting rod and the second regulation pipe are hinged, when spray angle needs significantly to adjust, rotatable connecting rod,
So that showerhead face is towards maintenance face, using flexible is stronger, and maintenance effect is good and sprinkling is uniform.
It advanced optimizes are as follows: the water delivery general pipeline is stereoplasm tube and is bundled on maintenance skeleton that the delivery pipe branch is soft
Pipe.
Using the above structure, it can smoothly be controlled convenient for activity adjustment mechanism, slide up and down adjusting, and adjusting is facilitated to spray
Angle, not will receive delivery pipe branch pulls limitation.
It advanced optimizes are as follows: the spray head is rain shape rotary nozzle.
Using the above structure, spraying effect is good, and cheap durable.
It advanced optimizes are as follows: the maintenance skeleton is made of 42 scaffold tubes.
Using the above structure, it stocks up on building site more, and is made using the waste and old pipe in building site, save cost.
In conclusion the utility model has the following beneficial effects: spray time is arranged to relay, so that water pump is opened
It opens and is effectively controlled with closure, when spray, the water in water storage box is input in water delivery general pipeline by water pump by pipeline, and maintenance is used
Water will be successively sprayed on maintenance face after water delivery general pipeline and delivery pipe branch by spray head.It eliminates manually without legal time maintenance
Defect can carry out water conservation humidity to concrete after pouring and support according to concrete core temperature, the variation of environment temperature
Shield, eliminating artificial maintenance unevenly leads to the difference of bridge pier surface temperature, effectively prevents the cracking of concrete surface.Ensure
The safety of maintenance personnel, maintenance personnel do not need the climbing bridge pier of high frequency time, reduce maintenance personnel in wet relatively sliding top of bridge pier
Face high frequency subjob bring security risk, and reduce workload, labor intensity is alleviated, it is time saving and energy saving, and can effectively control
System maintenance water consumption, reduces water resource waste.By the left and right adjusting of activity adjustment mechanism, make that it is suitable for different pier shaft samples
Spray height and spray angles are adjusted according to the difference of maintenance face position in formula, and using flexible is stronger, maintenance effect it is good and
Sprinkling is uniform.
Detailed description of the invention
Fig. 1 is the front schematic view of embodiment, is mainly used for embodying pier shaft ontology and conserves the structure of skeleton;
Fig. 2 is the side schematic view of embodiment, is mainly used for embodying the structure of curing system;
Fig. 3 is the structural schematic diagram of embodiment, is mainly used for embodying the structure of maintenance skeleton and activity adjustment mechanism;
Fig. 4 is the partial schematic diagram of embodiment, is mainly used for embodying the structure of activity adjustment mechanism.
In figure, 1, pier shaft ontology;2, skeleton is conserved;3, spray head;4, distribution box;5, water storage box;6, water pump;7, upper hose;
8, support rod;9, activity adjustment mechanism;91, the first regulation pipe;92, the second regulation pipe;93, connecting rod;94, the first fastening spiral shell
Bolt;95, limited block;96, sleeve;97, the second fastening bolt;98, connecting plate;10, water delivery general pipeline;11, delivery pipe branch.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment: a kind of pier shaft automatic maintenance system, as shown in Figure 1,2,3, 4, including pier shaft ontology 1, distribution box 4, storage
Water tank 5, water pump 6, maintenance skeleton 2, water delivery general pipeline 10, upper hose 7, delivery pipe branch 11, activity adjustment mechanism 9 and spray head 3.Distribution
Case 4 and water storage box 5 are respectively positioned on ground, and distribution box 4 is three-level distribution box and inside is furnished with the time relay, the time relay and water
Pump 6 is electrically connected and unlatching and closure for controlling water pump 6, and water pump 6 is immersible pump and is located in water storage box 5.6 lift of water pump
It should be higher than that bridge highest pier shaft 5m, have enough hydraulic pressure after being pumped to highest pier construction work surface enough to ensure maintenance with water energy
Spray is ejected on concrete curing face.7 lower end of upper hose is connect with water pump 6, upper end extend to the top of pier shaft ontology 1 and with
The connection of water delivery general pipeline 10, upper hose 7 and water delivery general pipeline 10 are hard pipeline.Skeleton 2 is conserved using 42 scaffold tubes processing system
It makes, conserves and be fixed with support rod 8 on skeleton 2, maintenance skeleton 2 is located at 1 top of pier shaft ontology and by support rod 8 and pier shaft
Fixed at the top of ontology 1, water delivery general pipeline 10 is bundled on maintenance skeleton 2 and connect with delivery pipe branch 11, and delivery pipe branch 11 is hose
Setting and be equipped with it is multiple, multiple delivery pipe branches 11 be located at maintenance 2 surrounding of skeleton.11 one end of delivery pipe branch and water delivery general pipeline 10
Connection, the other end are located at 1 top surrounding of pier shaft ontology and connect with spray head 3, and spray head 3 is rain shape rotary nozzle and is fixed on activity
On regulating mechanism 9.
Referring to Fig.1,2,3,4, activity adjustment mechanism 9 be equipped with it is multiple, multiple activity adjustment mechanisms 9 are located at maintenance skeleton
2 surroundings.Activity adjustment mechanism 9 includes the first regulation pipe 91, the second regulation pipe 92, connecting rod 93, the first fastening bolt 94, sleeve
96, the second fastening bolt 97 and connecting plate 98.First regulation pipe 91 is located at maintenance 2 surrounding of skeleton, and the first regulation pipe 91 is plugged in
Setting is slided in maintenance skeleton 2 and with it, maintenance skeleton 2 offers threaded hole, and the first fastening bolt 94 is installed by threaded hole
On maintenance skeleton 2 and for limiting the horizontal sliding of the first regulation pipe 91.Sleeve 96 is fixed on 91 outer end of the first regulation pipe, the
Two regulation pipes 92 are vertically arranged and pass through 96 upper and lower ends of sleeve and slide setting with it, offer threaded hole on sleeve 96,
Second fastening bolt 97 is mounted on sleeve 96 by threaded hole and is slided up and down for limiting the second regulation pipe 92.Second is adjusted
92 upper end of pipe is fixed with the limited block 95 for skidding off sleeve 96 downwards for limiting the second regulation pipe 92,92 lower end of the second regulation pipe with
93 upper end of connecting rod is hinged, and 93 lower end of connecting rod and connecting plate 98 are hinged, and connecting plate 98 is L-shaped, and spray head 3 is mounted on connecting plate
On 98.
The course of work and principle: spray time is arranged to relay, so that the unlatching of water pump 6 is effectively controlled with closure
System, when spray, the water in water storage box 5 is input in water delivery general pipeline 10 by water pump 6 by upper hose 7, and maintenance water successively passes through
It will be sprayed on maintenance face by spray head 3 after upper hose 7, water delivery general pipeline 10 and delivery pipe branch 11.
According to the pier pattern formula of pier shaft ontology 1, the length and width of the adjustment maintenance skeleton 2 of activity adjustment mechanism 9 can be used,
When adjustment, the first fastening bolt 94 is rotated, slides the first regulation pipe 91 again after the first fastening bolt 94 loosens, so that first adjusts
Section pipe 91 moves horizontally, and screws after being moved to suitable position, then by the first fastening bolt 94.
According to the difference of maintenance face upper and lower position, activity adjustment mechanism 9 can be used to adjust the height of spray head 3, when adjustment, turns
Dynamic second fastening bolt 97, slides the second regulation pipe 92 after the second fastening bolt 97 loosens, so that in the second regulation pipe 92 again
Lower movement screws after being moved to suitable position, then by the second fastening bolt 97.
According to the difference of maintenance face horizontal position, activity adjustment mechanism 9 can be used to adjust the spray angle of spray head 3, due to
Connecting rod 93 and connecting plate 98 are hinged, therefore when spray angle needs to adjust by a small margin, be rotatably connected plate 98, so that spray head 3
It just, can when spray angle needs significantly to adjust since connecting rod 93 and the second regulation pipe 92 are hinged facing towards maintenance face
It is rotatablely connected bar 93, so that spray head 3 is just facing towards maintenance face.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but
As long as all by the protection of Patent Law in the scope of the claims of the utility model.
Claims (9)
1. a kind of pier shaft automatic maintenance system, including pier shaft ontology (1), it is characterized in that: further including distribution box (4), water storage box
(5), water pump (6), maintenance skeleton (2), water delivery general pipeline (10), delivery pipe branch (11) and spray head (3);
Unlatching and closure in the distribution box (4) equipped with the time relay and for controlling the water pump (6), the water pump
(6) it is located in the water storage box (5), the water pump (6) connect with water delivery general pipeline (10) pipeline;
The maintenance skeleton (2) is fixed at the top of the pier shaft ontology (1), and the water delivery general pipeline (10) is fixed on the maintenance bone
It is connect on frame (2) and with the delivery pipe branch (11);
Maintenance skeleton (2) surrounding is connected with activity adjustment mechanism (9), and the spray head (3) is located on the pier shaft ontology (1)
It portion's surrounding and is fixed on the activity adjustment mechanism (9), the spray head (3) connect with the delivery pipe branch (11).
2. a kind of pier shaft automatic maintenance system according to claim 1, it is characterized in that: the activity adjustment mechanism (9) is wrapped
Include the first regulation pipe (91), the second regulation pipe (92), connecting rod (93) and the first fastening bolt (94), first regulation pipe
(91) it is located at maintenance skeleton (2) surrounding, first regulation pipe (91) is plugged in the maintenance skeleton (2) and slides with it
Dynamic setting, first fastening bolt (94) are mounted on the maintenance skeleton (2) and for limiting first regulation pipe
(91) horizontal sliding;
Second regulation pipe (92) is vertically arranged and is located at the first regulation pipe (91) outer end, the connecting rod (93)
Upper end is connect with second regulation pipe (92), and lower end is located at pier shaft ontology (1) the top surrounding and connects with the spray head (3)
It connects.
3. a kind of pier shaft automatic maintenance system according to claim 2, it is characterized in that: the activity adjustment mechanism (9) is also
Including sleeve (96) and the second fastening bolt (97), the sleeve (96) is fixed on the first regulation pipe (91) outer end, institute
The second regulation pipe (92) are stated across the sleeve (96) both ends and slide setting with it, second fastening bolt (97) is mounted on
It is slided up and down on the sleeve (96) and for limiting second regulation pipe (92).
4. a kind of pier shaft automatic maintenance system according to claim 3, it is characterized in that: second regulation pipe (92) upper end
It is fixed with the limited block (95) for skidding off the sleeve (96) downwards for limiting second regulation pipe (92).
5. a kind of pier shaft automatic maintenance system according to claim 2, it is characterized in that: the activity adjustment mechanism (9) is also
Including connecting plate (98), the connecting plate (98) is L-shaped, and the spray head (3) is mounted on the connecting plate (98), the company
Fishplate bar (98) and the connecting rod (93) lower end are hinged.
6. a kind of pier shaft automatic maintenance system according to claim 2, it is characterized in that: the connecting rod (93) upper end and institute
It is hinged to state the second regulation pipe (92) lower end.
7. a kind of pier shaft automatic maintenance system according to claim 1, it is characterized in that: the water delivery general pipeline (10) is hard
It manages and is bundled in maintenance skeleton (2), the delivery pipe branch (11) is hose.
8. a kind of pier shaft automatic maintenance system according to claim 1, it is characterized in that: the spray head (3) is the rotation of rain shape
Spray head.
9. a kind of pier shaft automatic maintenance system according to claim 1, it is characterized in that: the maintenance skeleton (2) uses 42
Scaffold tube is made.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821057441.5U CN208472581U (en) | 2018-07-05 | 2018-07-05 | A kind of pier shaft automatic maintenance system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821057441.5U CN208472581U (en) | 2018-07-05 | 2018-07-05 | A kind of pier shaft automatic maintenance system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208472581U true CN208472581U (en) | 2019-02-05 |
Family
ID=65212990
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821057441.5U Active CN208472581U (en) | 2018-07-05 | 2018-07-05 | A kind of pier shaft automatic maintenance system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208472581U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111706058A (en) * | 2020-06-22 | 2020-09-25 | 中国五冶集团有限公司 | Building spraying system based on attached lifting scaffold |
-
2018
- 2018-07-05 CN CN201821057441.5U patent/CN208472581U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111706058A (en) * | 2020-06-22 | 2020-09-25 | 中国五冶集团有限公司 | Building spraying system based on attached lifting scaffold |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206941416U (en) | A kind of road and bridge high pier automatic concrete spraying curing system | |
CN203919328U (en) | The circulating automatic spray curing system in bridge prefabrication field | |
CN208472581U (en) | A kind of pier shaft automatic maintenance system | |
CN106836663B (en) | The construction method of water-proof insulating roof | |
CN210999305U (en) | Automatic concrete curing means for sewage engineering | |
CN113047341B (en) | Comprehensive pipe gallery waterproof construction of sponge city ecosystem | |
CN110787938A (en) | Spraying system for building material | |
CN210969332U (en) | Bridge construction is with spraying maintenance system | |
CN208897847U (en) | One kind pushing and pulling closed atomizing refuse depot entirely | |
CN115075103B (en) | Concrete pavement maintenance device for road and bridge engineering | |
CN212688729U (en) | Moisturizing device for bridge engineering maintenance | |
CN105856404A (en) | Double-side spraying device and method for high-speed rail precast bridge | |
CN206428591U (en) | A kind of concrete curing device based on Hanging Basket | |
CN207003351U (en) | A kind of engineering watering implement | |
CN206154492U (en) | Bury shower nozzle intelligence maintenance system | |
CN206503069U (en) | trestle drainage system | |
CN206066676U (en) | Caisson automatic spray curing system | |
CN215278029U (en) | Brick fragment prevents that dry crack soaks device for civil engineering | |
CN211566328U (en) | Automatic maintenance device for highway engineering concrete member | |
CN208803852U (en) | A kind of tunnel double-lining concrete movable maintenance type rack | |
CN211342935U (en) | A lining concrete watering device for tunnel construction | |
CN210126541U (en) | Efficient material loading and unloading device for building | |
CN220768120U (en) | Reinforced structure of foundation pit slope | |
CN209686461U (en) | Deep basal pit outer wall of basement waterproof system layer | |
CN207794566U (en) | Mechanical float for building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |