CN209686461U - Deep basal pit outer wall of basement waterproof system layer - Google Patents

Deep basal pit outer wall of basement waterproof system layer Download PDF

Info

Publication number
CN209686461U
CN209686461U CN201822229343.1U CN201822229343U CN209686461U CN 209686461 U CN209686461 U CN 209686461U CN 201822229343 U CN201822229343 U CN 201822229343U CN 209686461 U CN209686461 U CN 209686461U
Authority
CN
China
Prior art keywords
protection wall
wall
prefabricated
basement
upper section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822229343.1U
Other languages
Chinese (zh)
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Jiangrun Technology Co Ltd
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201822229343.1U priority Critical patent/CN209686461U/en
Application granted granted Critical
Publication of CN209686461U publication Critical patent/CN209686461U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model relates to deep basal pit outer wall of basement waterproof system layer, including building enclosure, bed course, prefabricated protection wall upper section, prefabricated protection wall lower section, adjustable socket part, screed-coat, coil waterproof layer and protective layer;The mortise of the tenon of the prefabricated protection wall upper section and the prefabricated protection wall lower section forms complete protection wall by tenon formula grafting; by the adjustable verticality for socketing part and connecting and adjusting protection wall between the building enclosure and the prefabricated protection wall upper section, prefabricated protection wall lower section, the screed-coat, coil waterproof layer and protective layer are successively laid on mat surface and protection surface within the walls.The beneficial effects of the utility model are: the protection wall of the utility model is using the anti-water cutting grafting of tenon formula after segmentation prefabrication and lifting; traditional masonry or cast-in-place concrete structure are substituted, prefabricated components are produced using factory normalization, reliable in quality; construction efficiency is high, and waterproof performance is good.

Description

Deep basal pit outer wall of basement waterproof system layer
Technical field
The utility model belongs to housing construction technical field, and in particular to a kind of deep basal pit outer wall of basement combined type Waterproof layer.
Background technique
In conventional outer wall of basement formwork construction, often using has the two-sided formwork support process of Screw arbor with nut at both-ends.But it builds If the utilization rate in place is higher and higher, cause the crust of New Buildings with a distance from existing building and facility also increasingly Closely.Have in construction the requirement for meeting underground construction using working measure, such as vertical retaining wall, reduces fertile groove width Deng.When encountering the narrow situation of operation side, since the space requirement of personnel's construction is unable to get satisfaction, normal wall is two-sided Formwork, two side template of wall cannot achieve using the construction technology of the reinforcing of split bolt, to generate unilateral support shuttering construction Technique.
Outer wall of basement construction based on single side formwork is influenced in limited fertile slot space by live complex working condition, Its water-proofing treatment has certain problems.Since fertile groove width is smaller, i.e. the space of outer wall of basement and margin of foundation pit is smaller, outside The waterproof construction space of wall is limited, can not guarantee the concrete quality of outer wall of basement, and existing guarantor using outer anti-outer patch method Revetment generallys use traditional brick masonry or cast-in-place concrete technique, construction efficiency are to be improved.
Utility model content
The purpose of the utility model is to overcome deficiencies in the prior art, provide a kind of with reliable in quality, high construction efficiency Convenient, the features such as waterproof performance is good deep basal pit outer wall of basement waterproof system layer.
This deep basal pit outer wall of basement waterproof system layer, including it is building enclosure, bed course, prefabricated protection wall upper section, pre- System protection wall lower section adjustable sockets part, screed-coat, coil waterproof layer and protective layer;The tenon of the prefabricated protection wall upper section Head with it is described it is prefabricated protection wall lower section mortise by tenon formula grafting formed completely protect wall, the building enclosure with it is described pre- Pass through the adjustable verticality for socketing part and connecting and adjusting protection wall, institute between system protection wall upper section, prefabricated protection wall lower section It states screed-coat, coil waterproof layer and protective layer and is successively laid on mat surface and protection surface within the walls.
As preferred: the adjustable part that sockets includes turnbuckle, pre-buried pedestal, rotating handle and bolt, the gaily decorated basket spiral shell Silk is preset in building enclosure, prefabricated protection wall upper section and prefabricated protection wall lower section, and turnbuckle is symmetrically arranged with reverse thread, flower Basket screw both ends are bolted with pre-buried pedestal, and rotating handle is equipped in the middle part of turnbuckle.
As preferred: being additionally provided between the tenon of the prefabricated protection wall upper section and the mortise of the prefabricated protection wall lower section Water swelling rubber ring.
As preferred: being tamped using cast-in-place concrete in the gap between the building enclosure and protection wall.
As preferred: being basement bottom board and outer wall of basement on the outside of the protective layer.
The beneficial effects of the utility model are:
(1) the protection wall of the utility model is using the anti-water cutting grafting of tenon formula after segmentation prefabrication and lifting, substitute traditional masonry or Cast-in-place concrete structure, prefabricated components are produced using factory normalization, reliable in quality, and construction efficiency is high, and waterproof performance is good.
(2) it is embedded in the foundation pit enclosure structure of the utility model and adjustable is socketed with what prefabricated protection wall segment was connected Part, to guarantee its verticality, it is convenient to operate, and recyclable recycling.
Detailed description of the invention
Fig. 1 is the transverse cross of the utility model deep basal pit outer wall of basement waterproof system layer;
Fig. 2 is adjustable in the utility model deep basal pit outer wall of basement waterproof system layer to socket the partially schematic of part Figure.
Description of symbols: 1- building enclosure;2- bed course;The prefabricated protection wall upper section of 3-;The prefabricated protection wall lower section of 4-;5- can Mode sockets part;6- screed-coat;7- coil waterproof layer;8- protective layer;9- tenon;10- mortise;11- protects wall;12- gaily decorated basket spiral shell Silk;The pre-buried pedestal of 13-;14- rotating handle;15- water swelling rubber ring;16- bottom plate;17- bolt;18- outer wall of basement.
Specific embodiment
The utility model is described further below with reference to embodiment.The explanation of following embodiments is only intended to help to manage Solve the utility model.It should be pointed out that for those skilled in the art, not departing from the utility model principle Under the premise of, several improvements and modifications can be made to this utility model, these improvement and modification also fall into the utility model In scope of protection of the claims.
As shown in Fig. 1~2, the deep basal pit outer wall of basement waterproof system layer includes: building enclosure 1, bed course 2, pre- System protection wall upper section 3, adjustable sockets part 5, screed-coat 6, coil waterproof layer 7 and protective layer 8 at prefabricated protection wall lower section 4;Institute The mortise 10 of the tenon 9 and the prefabricated protection wall lower section 4 of stating prefabricated protection wall upper section 3 forms complete guarantor by tenon formula grafting Revetment 11 is socketed by adjustable between the building enclosure 1 and the prefabricated protection wall upper section 3, prefabricated protection wall lower section 4 Part 5 connects and adjusts the verticality of protection wall 11, and the screed-coat 6, coil waterproof layer 7 and protective layer 8 are successively laid on bed course 2 Surface and protection 11 inner surface of wall.
Specifically, the adjustable part 5 that sockets includes being preset at building enclosure 1, prefabricated protection wall upper section 3 and prefabricated guarantor Turnbuckle 12, pre-buried pedestal 13, rotating handle 14 and bolt 17, the turnbuckle 12 in revetment lower section 4 are symmetrically arranged with reversely Screw thread, both ends are connect with pre-buried pedestal 13 by bolt 17, and rotation rotating handle 14 can change the adjustable length for socketing part 5;Institute It states and is additionally provided with water swelling rubber ring between the tenon 9 of prefabricated protection wall upper section 3 and the mortise 10 of the prefabricated protection wall lower section 4 15;The building enclosure 1 and protection wall 11 between gap it is synchronous when pouring exterior wall tamped using cast-in-place concrete, while by Layer dismounting recycling is adjustable to socket part 5;It is basement bottom board 16 and outer wall of basement 18 on the outside of the protective layer 8.
The process for carrying out water-proofing treatment using deep basal pit outer wall of basement waterproof system layer is as follows:
When construction, first clear up Deep Foundation Pit bottom surface, pour bed course 2, hoisting prefabricated protection wall lower section 4 with bed course 2 is wet connects, By 12 both ends of turnbuckle respectively with building enclosure 1 and it is prefabricated protection wall lower section 4 in pre-buried pedestal 13 connect to be formed it is adjustable Part 5 is socketed, the rotating handle 14 that rotary adjustable sockets part 5 is adjusted to prefabricated protection wall lower section 4 and keeps vertical.
The mortise 10 for clearing up prefabricated protection wall lower section 4, water swelling rubber ring 15 is embedded in mortise 10, is then lifted Prefabricated protection wall upper section 3, makes its tenon 9 and mortise 10 coincide grafting.Equally, by 12 both ends of turnbuckle respectively with building enclosure 1 and it is prefabricated protection wall upper section 3 in pre-buried pedestal 13 connection formed it is adjustable socket part 5, rotary adjustable sockets the rotating handle of part 5 14, which are adjusted to prefabricated protection wall upper section 3, keeps vertically, ultimately forming complete protection wall 11.
Cement mortar screeding layer 6 is smeared on 2 surface of bed course and protection 11 inner surface of wall, is successively laid with coiled material again after its drying Waterproof layer 7 and protective layer 8 form deep basal pit outer wall of basement waterproof system layer.

Claims (5)

1. deep basal pit outer wall of basement waterproof system layer, which is characterized in that including building enclosure (1), bed course (2), prefabricated guarantor Revetment upper section (3), prefabricated protection wall lower section (4), it is adjustable socket part (5), screed-coat (6), coil waterproof layer (7) and protection Layer (8);The tenon (9) of prefabricated protection wall upper section (3) and the mortise (10) of prefabricated protection wall lower section (4) pass through tenon formula Grafting, which is formed, completely protects wall (11), under the building enclosure (1) and the prefabricated protection wall upper section (3), prefabricated protection wall Pass through the adjustable verticality for socketing part (5) and connecting and adjusting protection wall (11), the screed-coat (6), coiled material between section (4) Waterproof layer (7) and protective layer (8) are successively laid on bed course (2) surface and protection wall (11) inner surface.
2. deep basal pit outer wall of basement waterproof system layer according to claim 1, it is characterised in that: the adjustable drawing Fitting (5) includes turnbuckle (12), pre-buried pedestal (13), rotating handle (14) and bolt (17), and the turnbuckle (12) is preset In building enclosure (1), prefabricated protection wall upper section (3) and prefabricated protection wall lower section (4), turnbuckle (12) is symmetrically arranged with reversely Screw thread, turnbuckle (12) both ends are connect with pre-buried pedestal (13) by bolt (17), and rotating handle is equipped in the middle part of turnbuckle (12) (14)。
3. deep basal pit outer wall of basement waterproof system layer according to claim 1, it is characterised in that: the prefabricated protection Water swelling rubber ring is additionally provided between the tenon (9) of wall upper section (3) and the mortise (10) of prefabricated protection wall lower section (4) (15)。
4. deep basal pit outer wall of basement waterproof system layer according to claim 1, it is characterised in that: the building enclosure (1) gap between protection wall (11) is tamped using cast-in-place concrete.
5. deep basal pit outer wall of basement waterproof system layer according to claim 1, it is characterised in that: the protective layer (8) outside is basement bottom board (16) and outer wall of basement (18).
CN201822229343.1U 2018-12-28 2018-12-28 Deep basal pit outer wall of basement waterproof system layer Active CN209686461U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822229343.1U CN209686461U (en) 2018-12-28 2018-12-28 Deep basal pit outer wall of basement waterproof system layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822229343.1U CN209686461U (en) 2018-12-28 2018-12-28 Deep basal pit outer wall of basement waterproof system layer

Publications (1)

Publication Number Publication Date
CN209686461U true CN209686461U (en) 2019-11-26

Family

ID=68597287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822229343.1U Active CN209686461U (en) 2018-12-28 2018-12-28 Deep basal pit outer wall of basement waterproof system layer

Country Status (1)

Country Link
CN (1) CN209686461U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113802722A (en) * 2021-09-23 2021-12-17 武汉建工集团股份有限公司 Construction method for recyclable deep foundation pit and outer wall integrated structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113802722A (en) * 2021-09-23 2021-12-17 武汉建工集团股份有限公司 Construction method for recyclable deep foundation pit and outer wall integrated structure
CN113802722B (en) * 2021-09-23 2022-09-06 武汉建工集团股份有限公司 Construction method for recyclable deep foundation pit and outer wall integrated structure

Similar Documents

Publication Publication Date Title
CN208502433U (en) A kind of prefabricated assembled Assembled surrounding wall with vertical curtain wall penel component
CN202850596U (en) Industrialized prefabricated assembly type fence
CN209556348U (en) Deep basal pit outer wall of basement frame body is to support single side formwork system
CN113513015A (en) A kind of semi-prefabricated concrete reinforced cage underground continuous wall and construction method
CN209686461U (en) Deep basal pit outer wall of basement waterproof system layer
CN205955003U (en) Take prefabricated coincide wallboard of vertical moulding
CN112412013A (en) Construction method for plugging reserved hole of structural outer wall
CN211257093U (en) Underground cast-in-place structure outer wall post-cast strip template pre-supporting device
CN209686857U (en) Deep basal pit outer wall of basement shape steel bracket diagonal brace single side formwork system
CN216587897U (en) Precast concrete bathroom chassis
CN110886311A (en) Large-volume assembly type ground tire mold
CN105822068B (en) Ultralong thin walled concrete walls under hot environment pour and maintenance process
CN109441099A (en) Basement single side formwork system and the method for utilizing its outer wall of basement of constructing
CN103216102A (en) Construction method for tremie guiding pouring inside steel pipe column
CN204418229U (en) Poured band of outer wall of basement concrete draw-in groove
CN101265704A (en) Underground cast-in-place concrete structure outer wall neck construction method
CN210049550U (en) Adjustable concrete terrace construction template
CN204753783U (en) Prefabricated concrete rain sewage inspection shaft device
CN103572786A (en) Pile head joint waterproof processing device and construction method thereof
CN208486282U (en) A kind of vertical layered assembled environment-friendly concrete basis
CN203977451U (en) Electric power overhaul well
CN213358881U (en) Secondary drainage device for ground of sinking type toilet
CN206986918U (en) A kind of asymmetric template for blower fan crab-bolt foundation grouting
CN204637848U (en) A kind of ceramic water film dust-remover
CN209508998U (en) Open caisson slag flushing type unearthing system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant