CN208441145U - On cover the combined water proof drainage system of underground structure in permeable stratum - Google Patents
On cover the combined water proof drainage system of underground structure in permeable stratum Download PDFInfo
- Publication number
- CN208441145U CN208441145U CN201820937360.8U CN201820937360U CN208441145U CN 208441145 U CN208441145 U CN 208441145U CN 201820937360 U CN201820937360 U CN 201820937360U CN 208441145 U CN208441145 U CN 208441145U
- Authority
- CN
- China
- Prior art keywords
- underground structure
- permeable
- underground
- stratum
- water proof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The utility model relates to cover the combined water proof drainage system of underground structure in permeable stratum in one kind, belong to the water-proof drainage systems technology field of underground structure.The utility model covers permeable stratum penetrating passage, reduces the construction time and the runtime takes out effluent cost by the way that impervious body is arranged in partition.By the way that permeable loaded filter and drainage hole is arranged, guide percolating water discharge, underground structure is avoided to bear larger water pressure, the soil pressure that will act on foundation pit enclosure structure simultaneously passes to underground structure by permeable loaded filter, under permanent operating condition, it can make underground structure and foundation pit enclosure structure shared soil pressure, guarantee structure safety.
Description
Technical field
The utility model relates to cover the combined water proof drainage system of underground structure in permeable stratum in one kind, belong to ground
The water-proof drainage systems technology field of lower structures.
Background technique
The underground engineering construction phase mainly guarantees normal construction condition by the measure of foundation pit Yield rainfall relation, and the runtime relies primarily on
Concrete self-waterproof ability simultaneously cooperates and solves the problems, such as concrete anti-seepage using measures such as waterproof roll, water-repellent paints, is tied by underground
Structure exterior wall undertakes external whole soil water pressures.
For underground structures such as ultra-deep subway station, basements, when underground water buried depth is shallower, stratum water penetration is stronger
When, the construction time may face foundation pit water percolating capacity it is larger, take out effluent cost it is higher, run-time structure exterior wall will bear larger outer hydraulic pressure
Power and the problems such as be easy to happen infiltration, and then influence normal use, threaten main structure body quality and safety.
Utility model content
The technical problem to be solved by the utility model is to provide the combinations that underground structure in permeable stratum is covered in one kind
Formula water-proof drainage system can reduce ultra-deep underground structure exterior wall external water pressure, reduce structure infiltration risk, while reducing and applying
Duration foundation pit water percolating capacity.
To solve above-mentioned technical problem the technical scheme adopted by the utility model is on cover underground in permeable stratum and construct
The combined water proof drainage system of object, including underground structure, the stratum on the outside of underground structure successively include saturating from top to bottom
Water stratum and opposite impervious stratum, the structure outer lateral surface of underground structure and plate outer side face are provided with waterproof roll,
Foundation pit enclosure structure is equipped on the outside of the structure outer of underground structure, foundation pit enclosure structure top is far from underground structure knot
The side of structure exterior wall is provided with impervious body, and bottom end insertion velatively waterproof layer, top and the underground structure outside of impervious body are tightly
The wall of contiguity touching or insertion underground structure.
Further, the structure outer of underground structure be provided between waterproof roll and foundation pit enclosure structure it is permeable
Loaded filter, the structure outer bottom of underground structure are provided with the permeable loaded filter of connection and underground structure internal drainage structure
Drainage hole.
Further, permeable loaded filter is filled using sandy gravel class dank material.
Further, the structure outer of underground structure is obliquely installed drainage hole, and outside underground structure structure
The lateral ends of wall are eminence end, inner opposite end is lower end, can draw underground water.
Further, being equipped with catch basin on bottom plate inside underground structure for drainage hole, infiltration can be led to collection
Concentrate pump drainage in puddle.
Further, impervious body is cut-pff wall, high-pressure rotary jet grouting pile or steel sheet pile.
The beneficial effects of the utility model are: covering permeable stratum penetrating passage in partition, reduction is applied by setting impervious body
Duration and runtime take out effluent cost.By the way that permeable loaded filter and drainage hole is arranged, guidance percolating water discharge avoids underground from constructing
Object bears larger water pressure, while the soil pressure that will act on foundation pit enclosure structure passes to subterranean by permeable loaded filter
Object is built, under permanent operating condition, underground structure and foundation pit enclosure structure shared soil pressure can be made, guarantees structure safety.
Detailed description of the invention
Fig. 1 is the cross-sectional structural schematic diagram of the utility model;
Marked in the figure: 1- underground structure, 2- waterproof roll, 3- permeable stratum, 4- are enclosed with respect to impervious stratum, 5- foundation pit
Protection structure, 6- impervious body, the permeable loaded filter of 7-, 8- drainage hole, the ground 9- high level, 10- are with respect to impervious stratum crest level.
Specific embodiment
For ease of understanding with implementation the utility model, the preferred embodiment combination attached drawing work of anthology utility model is furtherly
It is bright.
As shown in Figure 1, the utility model includes underground structure 1, the stratum in 1 outside of underground structure is from top to bottom successively
Including permeable stratum 3 and opposite impervious stratum 4, the structure outer lateral surface of underground structure 1 and plate outer side face are provided with
Waterproof roll 2, the structure outer outside of underground structure 1 are equipped with foundation pit enclosure structure 5, and 5 top of foundation pit enclosure structure is remote
Side from 1 structure outer of underground structure is provided with impervious body 6, the bottom end insertion velatively waterproof layer of impervious body 6, top with
The wall of underground structure 1 is in close contact or is embedded on the outside of underground structure 1.Impervious body 6 can be cut-pff wall, high-pressure rotary jet grouting pile
Or the stop waters measure such as steel sheet pile, permeable stratum penetrating passage is covered by the way that impervious body 6 is arranged, in partition, reduce the construction time and
Runtime takes out effluent cost.
When implementing, the generally vertical setting of impervious body 6, when the structure outer of underground structure 1 has traversing section, impervious body
6 bottom end is embedded in velatively waterproof layer, top is directly embedded into 1 wall of underground structure, embodiment as shown in Figure 1.When
When impervious body 6 needs to be embedded in the situation of structure outer vertical section of underground structure 1, L can be set by the top of impervious body 6
Type structure.
The structure outer of underground structure 1 is provided with permeable loaded filter 7 between waterproof roll 2 and foundation pit enclosure structure 5,
The structure outer bottom of underground structure 1 is provided with the draining for being connected to permeable loaded filter 7 and 1 internal drainage structure of underground structure
Hole 8.Permeable loaded filter 7 can be used sandy gravel class dank material and fill.Drainage hole 8 is preferably obliquely installed, and
The lateral ends of 1 structure outer of underground structure are eminence end, inner opposite end is lower end.By the way that permeable 7 He of loaded filter is arranged
Drainage hole 8, guidance percolating water discharge, avoids underground structure 1 from bearing larger water pressure, while will act at foundation pit enclosure structure
Soil pressure on 5 passes to underground structure 1 by permeable loaded filter 7, under permanent operating condition, can make underground structure 1 and base
5 shared soil pressure of pit enclosure structure guarantees structure safety.
For convenience of draining, it is equipped with catch basin for drainage hole 8 on bottom plate inside underground structure 1, infiltration can be led to
Catch pit concentrates pump drainage.
Claims (6)
- The combined water proof drainage system of underground structure in permeable stratum, including underground structure (1) are covered on 1., underground is constructed Stratum on the outside of object (1) successively include from top to bottom it is permeable stratum (3) and opposite impervious stratum (4), underground structure (1) Structure outer lateral surface and plate outer side face are provided with waterproof roll (2), are equipped on the outside of the structure outer of underground structure (1) Foundation pit enclosure structure (5), it is characterised in that: in one far from underground structure (1) structure outer at the top of foundation pit enclosure structure (5) Side is provided with impervious body (6), and bottom end insertion velatively waterproof layer, top and underground structure (1) outside of impervious body (6) are closely The wall of contact or insertion underground structure (1).
- 2. covering the combined water proof drainage system of underground structure in permeable stratum on as described in claim 1, feature exists In: the structure outer of underground structure (1) is provided with permeable loaded filter between waterproof roll (2) and foundation pit enclosure structure (5) (7), the structure outer bottom of underground structure (1) is provided with the permeable loaded filter (7) of connection and underground structure (1) internal drainage The drainage hole (8) of structure.
- 3. covering the combined water proof drainage system of underground structure in permeable stratum on as claimed in claim 2, feature exists In: permeable loaded filter (7) is filled using sandy gravel class dank material.
- 4. covering the combined water proof drainage system of underground structure in permeable stratum on as claimed in claim 2, feature exists In: the structure outer of underground structure (1) is obliquely installed drainage hole (8), and in the outside of underground structure (1) structure outer One end is eminence end, inner opposite end is lower end.
- 5. covering the combined water proof drainage system of underground structure in permeable stratum on as claimed in claim 2, feature exists In: underground structure (1) is internal to be equipped with catch basin on bottom plate for drainage hole (8).
- 6. covering the combined water proof draining of underground structure in permeable stratum on as described in any one of claim 1 to 5 System, it is characterised in that: impervious body (6) is cut-pff wall, high-pressure rotary jet grouting pile or steel sheet pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820937360.8U CN208441145U (en) | 2018-06-15 | 2018-06-15 | On cover the combined water proof drainage system of underground structure in permeable stratum |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820937360.8U CN208441145U (en) | 2018-06-15 | 2018-06-15 | On cover the combined water proof drainage system of underground structure in permeable stratum |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208441145U true CN208441145U (en) | 2019-01-29 |
Family
ID=65089907
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820937360.8U Active CN208441145U (en) | 2018-06-15 | 2018-06-15 | On cover the combined water proof drainage system of underground structure in permeable stratum |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208441145U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560610A (en) * | 2018-06-15 | 2018-09-21 | 中国电建集团成都勘测设计研究院有限公司 | The combined water proof drainage system of underground structure in overlying permeable stratum |
-
2018
- 2018-06-15 CN CN201820937360.8U patent/CN208441145U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560610A (en) * | 2018-06-15 | 2018-09-21 | 中国电建集团成都勘测设计研究院有限公司 | The combined water proof drainage system of underground structure in overlying permeable stratum |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105002913B (en) | A kind of highly permeable stratum deep basal pit back cover water sealing structure and its construction method | |
CN202416382U (en) | Waterproof structure of basement | |
CN102995599B (en) | Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal | |
CN105421500B (en) | It is a kind of based on low-level curtain and the basement anti-floating system of blood pressure lowering of drawing water | |
CN100373013C (en) | Treatment method for thick collapsed loess foundation | |
CN105544622B (en) | A kind of anti-floating system and its checking device of underground structure | |
CN104404974A (en) | High-pressure-bearing water and thick sand and pebble formation deep foundation pit grouting bottom-sealing structure and construction technology thereof | |
CN208441145U (en) | On cover the combined water proof drainage system of underground structure in permeable stratum | |
CN104196046B (en) | Reduce the water proof drainage system of underground hydrostatic water table | |
CN212772481U (en) | Anti earthquake liquefaction system of sand foundation building | |
CN105525633A (en) | Pumping-irrigating self-circulation control system for floating resistance of basement | |
CN102787608B (en) | Gravity type foundation pit supporting system under vacuum effect and construction method | |
CN104805873A (en) | Multi-defense line type anti-floating system capable of monitoring release of water pressure of basement | |
CN104831742B (en) | The Method on Dewatering of Foundation Pit that adjacent two layers low pressure water layer is not cut off by water barrier | |
CN101634140B (en) | Consolidation method of soft earth foundation | |
CN115075264A (en) | Foundation pit basement fertilizer groove backfilling structure | |
CN216615927U (en) | Emergency structure system applied to single-row enclosure of foundation pit | |
CN206928341U (en) | A kind of device of the outer side hydraulic pressure of reduction basement | |
CN206289732U (en) | A kind of active antiseepage basement shear wall | |
CN202187360U (en) | Well point positioning water pumping tube well | |
CN214245855U (en) | Water-proof pressure-control anti-floating structure | |
CN108560610A (en) | The combined water proof drainage system of underground structure in overlying permeable stratum | |
CN204825916U (en) | Highly permeable stratum deep basal pit back cover stagnant water structure | |
CN210712967U (en) | Impervious anti structure that floats of basement | |
CN203654332U (en) | Novel water prevention and dredge construction structure of basement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |