CN208415292U - For the novel foundation structure of charging pile - Google Patents
For the novel foundation structure of charging pile Download PDFInfo
- Publication number
- CN208415292U CN208415292U CN201821014632.3U CN201821014632U CN208415292U CN 208415292 U CN208415292 U CN 208415292U CN 201821014632 U CN201821014632 U CN 201821014632U CN 208415292 U CN208415292 U CN 208415292U
- Authority
- CN
- China
- Prior art keywords
- side wall
- inspection
- pit
- inlet wire
- wire cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of novel foundation structures for charging pile, the inspection-pit part of foundation and equipment inlet wire cable including main equipment installation, the main body of the foundation is made of bottom plate and surrounding side wall, the surrounding side wall includes front side wall, right side wall, left side wall and rear side wall, the front side wall of the inspection-pit part of the rear side wall and equipment inlet wire cable of the foundation of the body equipment installation is coplanar, interface channel is offered on the rear side wall, catch pit is provided on the bottom plate of the inspection-pit of the equipment inlet wire cable, the rear side wall of the inspection-pit of the equipment inlet wire cable is embedded with steel pipe, the inspection-pit portion top surface hole of the equipment inlet wire cable is covered using cover board.The beneficial effects of the utility model are: high safety, applicability is good, high reliablity, flexible compact.
Description
Technical field
The utility model relates to charging pile facility technology field, specially a kind of novel foundation structure for charging pile.
Background technique
In recent years under the driving of national " green energy resource " policy, new-energy automobile is fast-developing, the base of charging pile facility
Plinth construction has entered fast-developing road.The operation of charging pile equipment needs reliable foundation structure as support.This structure
Basis will not only meet the requirement of safety, more meet the requirement of applicability and reliability.
Currently, the producer for producing charging pile equipment in the market is numerous, according to different charging pile power, corresponding equipment
Outer dimension is also varied.And the addressing of most of charging pile construction is existing general park position, therefore charging pile is set
The construction applied faces the limited problem in construction site.So lack a kind of foundation structure and meets safety, applicability, reliability
Under the premise of, to accomplish the feature of flexible compact.
Utility model content
In view of the above drawbacks of the prior art, the technical purpose of the utility model is to provide a kind of for charging pile
Novel foundation structure.The novel foundation structure for charging pile have high safety, applicability is good, high reliablity, flexibly
Compact feature.
To realize the above-mentioned technical purpose, the utility model provides a kind of novel foundation structure for charging pile, including
The foundation of main equipment installation and the inspection-pit part of equipment inlet wire cable, the main body of the foundation is by bottom plate and four
All side walls are constituted, and the surrounding side wall includes front side wall, right side wall, left side wall and rear side wall, the body equipment peace
The front side wall of the inspection-pit part of the rear side wall and equipment inlet wire cable of the foundation of dress is coplanar, on the rear side wall
Interface channel is offered, catch pit, the equipment inlet wire cable are provided on the bottom plate of the inspection-pit of the equipment inlet wire cable
The rear side wall of inspection-pit be embedded with steel pipe, the inspection-pit portion top surface hole of the equipment inlet wire cable is carried out using cover board
Capping.
Preferably, the side wall and bottom plate of the foundation structure its having a size of 200mm.
Preferably, the foundation top surface of the main equipment installation is higher by nature terrace 200mm, equipment inlet wire cable
The same nature terrace of inspection-pit part ground elevation.
Preferably, piece diameter of rear side wall pre-embedded of the inspection-pit part of the standby inlet wire cable is the steel pipe of 175mm
Channel as basic structure and external cable disengaging.
Preferably, concrete prefabricated cover board or new material finished product cover board can be used in the cover board.
The utility model has the beneficial effects that
The utility model is due to said structure design, and high safety, applicability is good, high reliablity, flexible compact.
Detailed description of the invention
Fig. 1 is the plan view of charging pile foundation structure;
Fig. 2 is the A-A sectional view of Fig. 1;
Fig. 3 is the B-B sectional view of Fig. 1;
Fig. 4 is the left and right side elevational view of Fig. 1;
Fig. 5 is the front elevational view of Fig. 1;
Fig. 6 is the rear side elevation of Fig. 1.
Figure label: the maintenance of wall, 2 right side walls, 3 left side walls, 4 rear side walls, 5 equipment inlet wire cables is surveyed before 1
The left side wall of well, the right side wall of the inspection-pit of 6 equipment inlet wire cables, 7 equipment inlet wire cables inspection-pit rear side wall,
8 charging pile apparatus bodies, 9 catch pits, the inspection-pit top surface cover board of 10 equipment inlet wire cables, 11 sole plates, 12 embedded steel tubes,
13 pre-buried equipment install bolt, 14 flexible blockage materials, 15 equipment cables.
Specific embodiment
Make furtherly below with reference to technical effect of the attached drawing to the design of the utility model, specific structure and generation
It is bright, to be fully understood from the purpose of this utility model, feature and effect.
Embodiment:
As shown in Figure 1, one specific embodiment of novel foundation structure for charging pile of the utility model, mainly by being located at
The foundation (1,2,3,4) of the equipment installation of front and equipment inlet wire cable positioned at rear portion inspection-pit part (5,6,7,
8,10) it forms.
The rear side wall (4) of foundation and the front side wall (4) of inspection-pit of equipment inlet wire cable of equipment installation be
Coplanar portions, the two connect into an entirety by common ground.
The sole plate of the two equally shares one piece of bottom plate, and the bottom of the two is connected into an entirety by this bottom plate.
The outer center line of wall of foundation surrounding of the equipment installation of front is overlapped with the outer contour of physical device, outside surrounding
Wall extends out the outer contour 100mm of physical device.
The foundation that the width of the outer profile of the inspection-pit of the equipment inlet wire cable at rear portion is installed with the equipment of front
Width is 100+B+100mm (B is charging pile equipment outer profile width), and internal clear length is 1m.Top is by cable channel cover plate
(9) it covers.
The thickness of the surrounding exterior wall of the inspection-pit of equipment inlet wire cable is 200mm thick with the foundation that equipment is installed.
The foundation top surface pre-embedded bolt (13) of equipment installation is for fixing top charging pile equipment.
Pre-buried position and number can be arranged according to the requirement of charging pile producer.
Catch pit may be provided at the middle part of the inspection-pit of equipment inlet wire cable.
Fig. 2 is the A-A sectional view of the utility model embodiment charging pile novel foundation structure.
As shown in Fig. 2, the total length of charging pile basis superstructure is that (L is charging pile to 100+L+100+1000+200mm
Equipment outer profile length), the total length of sole plate is that length (150mm) is grown on total length+basis both sides of superstructure.
The foundation top surface of superstructure front equipment installation exceeds nature terrace 200mm, the inspection of equipment inlet wire cable
Well workover top surface absolute altitude is the same as nature terrace absolute altitude.
Sole plate with a thickness of 200mm, enclosed jointly by sole plate (11) and surrounding wall (1,2,3,4,5,6,7) and at
One internal cavities is used for the installation and maintenance of equipment cable (15).
The clear height of this cavity can be set as 800~1200mm according to the concrete model of equipment cable.Length, the depth of catch pit
Degree, width are 400mm.When having ready conditions, can a pre-buried drainpipe catch pit and the catch-basin near place are connected,
Ponding in significantly more efficient exclusion foundation structure.
In the case that site condition limits, periodically can manually it be extracted out using mobile water pump.Due to connecting front and rear part
Wall (4) on opening square hole make wall height smaller, therefore can be configured according to structural beams.
The coating steel pipe (12) of pre-buried diameter 175 is used as and sets on the rear side wall (7) of the inspection-pit of equipment inlet wire cable
The hole of standby cable (15) disengaging.It carves after to equipment cable construction and installation and is blocked using fire resistant flexible mud (14).
Fig. 3 is the B-B sectional view of the utility model embodiment charging pile novel foundation structure.
As shown in figure 3, the overall width of charging pile basis superstructure is that (B is charging pile equipment outer profile to 100+B+100mm
Width), the overall width of sole plate is that length (150mm) is grown on overall width+basis both sides of superstructure.Other in this figure have
The explanation of body construction can be found in the declaratives of Fig. 1, Fig. 2.
Fig. 4 is the left and right side figure of the utility model embodiment charging pile novel foundation structure.
As shown in figure 4, the built-up section for the pile foundation structure that charges in this figure is no longer described in detail one by one, for details, reference can be made to attached drawings to say
Bright and Fig. 1, Fig. 2, Fig. 3 content.Fig. 4 mainly reflects each component part in left and right side of charging pile novel foundation structure
Connection relationship.
Fig. 5, Fig. 6 are the forward and backward side views of the utility model embodiment charging pile novel foundation structure.
As shown in Figure 5, Figure 6, the built-up section of charging pile foundation structure is no longer described in detail one by one in this figure, and for details, reference can be made to attached
The content of figure explanation and Fig. 1, Fig. 2, Fig. 3.Fig. 5, Fig. 6 mainly reflect each group of front and back sides of charging pile novel foundation structure
At the connection relationship of part.
Other specific embodiments can be under the premise of keeping foundation structure overall construction constant, and thin portion specific size is adjustable
It is whole.The utility model only provides a kind of reference dimension of relatively optimization.
Working principle
The construction of the utility model can be according to cast in situs and two kinds of prefabrication in-site installation.
According to the construction method of cast in situs, main construction course can be divided into: excavation of foundation pit-blinding layer pours-base
Plinth bottom plate installation-sole plate concreting-basis surrounding wall form installation-basis surrounding walls concrete
Pour exterior plaster in-basic maintenance-form removable-foundation pit backfill-basis.
Prefabricated reinforced concrete cover board can be used in the cover board on the inspection-pit top of equipment inlet wire cable, can also be used in the market
Other new material cover boards.
In order to guarantee the globality of utility model structure, engineering material uses concrete.It can also exist according to detailing requiments
Corresponding reinforcing bar is configured in concrete to improve the strength and stiffness of foundation structure.
The preferred embodiments of the present invention have been described in detail above.It should be appreciated that the ordinary skill people of this field
Member according to the present utility model can conceive without creative work makes many modifications and variations.Therefore, all this technology necks
Technical staff passes through logic analysis, reasoning or limited reality according to the design of the utility model on the basis of existing technology in domain
Available technical solution is tested, it all should be within the scope of protection determined by the claims.
Claims (5)
1. a kind of novel foundation structure for charging pile, foundation and equipment inlet wire cable including main equipment installation
The main body of inspection-pit part, the foundation is made of bottom plate and surrounding side wall, it is characterised in that: the surrounding side wall includes
Front side wall (1), right side wall (2), left side wall (3) and rear side wall (4), after the foundation of body equipment installation
The front side wall of the inspection-pit part of side wall body and equipment inlet wire cable is coplanar, and it is logical that connection is offered on the rear side wall (4)
Road, is provided with catch pit on the bottom plate of the inspection-pit of the equipment inlet wire cable, after the inspection-pit of the equipment inlet wire cable
Side wall body is embedded with steel pipe, and the inspection-pit portion top surface hole of the equipment inlet wire cable is covered using cover board.
2. the novel foundation structure according to claim 1 for charging pile, it is characterised in that: the side of the foundation structure
Wall and bottom plate its having a size of 200mm.
3. the novel foundation structure according to claim 1 for charging pile, it is characterised in that: the main equipment installation
Foundation top surface be higher by nature terrace 200mm;The same nature terrace of inspection-pit part ground elevation of equipment inlet wire cable.
4. the novel foundation structure according to claim 1 for charging pile, it is characterised in that: the standby inlet wire cable
Channel of the rear side wall embedded steel tube of inspection-pit part as basic structure and external cable disengaging.
5. the novel foundation structure according to claim 1 for charging pile, it is characterised in that: the cover board can be used mixed
The solidifying prefabricated cover board of soil.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821014632.3U CN208415292U (en) | 2018-06-28 | 2018-06-28 | For the novel foundation structure of charging pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821014632.3U CN208415292U (en) | 2018-06-28 | 2018-06-28 | For the novel foundation structure of charging pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208415292U true CN208415292U (en) | 2019-01-22 |
Family
ID=65107417
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821014632.3U Active CN208415292U (en) | 2018-06-28 | 2018-06-28 | For the novel foundation structure of charging pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208415292U (en) |
-
2018
- 2018-06-28 CN CN201821014632.3U patent/CN208415292U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104452795B (en) | A kind of old house additional elevator base structure and construction method thereof | |
CN105862910B (en) | A kind of the inverse of assembled stereoscopic underground garage makees formula method of construction | |
CN100473790C (en) | Tower crane foundation for construction and manufacturing method thereof | |
CN110617083A (en) | Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness | |
CN103306289B (en) | Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof | |
CN105804089B (en) | Locally increase deep support system and its construction method after a kind of former deep foundation pit construction | |
CN208363127U (en) | A kind of retaining wall structure of combined type high-speed rail platform | |
CN107795749A (en) | A kind of precast spliced pipe fitting jacking system and its construction method | |
CN104878776B (en) | A kind of underground shallow layer automatic parking garage the library structure | |
CN108798059A (en) | A kind of old masonry seismic reinforcing structure and construction method | |
CN100473791C (en) | Installing method for rail beam structure of magnetic suspension tunnel shoreside section | |
CN110578339A (en) | construction method of shaft type underground stereo garage | |
CN101638898B (en) | Suspension type construction method of top pipe shaft | |
CN111535300A (en) | Water conservancy construction environment-friendly bridge pile foundation construction method | |
CN107326928A (en) | A kind of part is related to the construction method in the deeper subsurface garage of basement | |
CN110295624A (en) | Crossroad underground pedestrian walk and pipe gallery build structure and its construction method jointly | |
CN107905609A (en) | Underground people's air defense construction method | |
CN112681376A (en) | Construction method of shaft type underground stereo garage | |
Macaulay | Underground | |
CN208415292U (en) | For the novel foundation structure of charging pile | |
CN205116220U (en) | Pour cable pit after assembly of L type precast concrete spare | |
CN106638610A (en) | Large-difference staggered connection structure and construction method thereof | |
CN207392241U (en) | A kind of ultra-high performance concrete precast assembly pipe gallery | |
CN207176737U (en) | A kind of mechanical underground parking of inclined shaft | |
CN110512594A (en) | The simple and easy method of churning driven opportunity cavity pore-forming |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |