CN208279171U - A kind of device for prefabricated components hoisting and hanging - Google Patents

A kind of device for prefabricated components hoisting and hanging Download PDF

Info

Publication number
CN208279171U
CN208279171U CN201820575672.9U CN201820575672U CN208279171U CN 208279171 U CN208279171 U CN 208279171U CN 201820575672 U CN201820575672 U CN 201820575672U CN 208279171 U CN208279171 U CN 208279171U
Authority
CN
China
Prior art keywords
prefabricated components
shackle
wirerope
hanging
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820575672.9U
Other languages
Chinese (zh)
Inventor
王成
张俊松
王虓
龚亮
李操
周蓉峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201820575672.9U priority Critical patent/CN208279171U/en
Application granted granted Critical
Publication of CN208279171U publication Critical patent/CN208279171U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model proposes a kind of devices for prefabricated components hoisting and hanging, comprising: the first built-in fitting and the second built-in fitting are connected to prefabricated components;First vertical hanger and the second vertical hanger are connected by bolt with described two built-in fittings;First platform sling and the second platform sling, are connected to described two vertical hangers;First wirerope and the second wirerope, the first roller, the second roller are bypassed respectively, it is connected by the first shackle, the second shackle with described two platform slings, described two rollers pass through third shackle respectively, the 4th shackle is connected with fringed iris herb, and third wirerope, the 4th wirerope are connected around third shackle, the 4th shackle with the suspension hook of lifting equipment.Device proposed by the present invention for prefabricated components hoisting and hanging is exempted and needs to change suspender during hoisting and hanging prefabricated components or change the processes such as position of suspender, provides and a kind of lifts high-efficient and small risk Prefabricated element slings.

Description

A kind of device for prefabricated components hoisting and hanging
Technical field
The invention belongs to foundation basic construction technical fields, and in particular to a kind of dress for prefabricated components hoisting and hanging It sets, for hoisting large-size prefabricated components in constructing, specifically, be that a kind of component by multiple and different functions forms a set of hangs The device can accurately be connected securely and with prefabricated components by means of built-in fitting, pass through vertical hanger, steel wire by assembling apparatus The co-operation such as rope, fringed iris herb can be convenient, reliably and securely lifting figure is big, quality is big, complex-shaped prefabricated components.
Background technique
Now, Building Trade in China rapidly develops, and prefabricated assembled construction is widely popularized in the realm of building construction, constructs In the hoisting and hanging demand of large-scale component is also increasingly increased.Currently, adopting single machine lifting or double when China's lifting prefabricated components more Machine lifting carries out vertical lifting after binding to prefabricated components, later, may need to change suspender or change the position of suspender, so Prefabricated components are installed in place using construction methods such as rotary process, coastdown, delivering methods afterwards.Existing hoisting and hanging device is most Than cumbersome, using the influence also tended to by live ambient conditions and the component sole mass that need to be lifted by crane and shape, whole It may need to be replaced as frequently as suspender during a.Therefore, existing hanging apparatus use is not convenient enough, and process is more, hangs It is inefficient to pretend industry, and existing risk factor is more, is restricted in large-scale component lifting application aspect.
Summary of the invention
The present invention proposes a kind of device for prefabricated components hoisting and hanging, and exempt hoisting and hanging prefabricated components needs in the process It replaces suspender or changes the processes such as position of suspender, provide and a kind of lift high-efficient and small risk Prefabricated element slings.
In order to achieve the above object, the present invention proposes a kind of device for prefabricated components hoisting and hanging, comprising:
First built-in fitting and the second built-in fitting, are connected to prefabricated components;
First vertical hanger and the second vertical hanger are connected by bolt with described two built-in fittings;
First platform sling and the second platform sling, are connected to described two vertical hangers;
First wirerope and the second wirerope bypass the first roller, the second roller respectively, are unloaded by the first shackle, second Button is connected with described two platform slings, and described two rollers pass through third shackle respectively, the 4th shackle is connected with fringed iris herb, third steel Cord, the 4th wirerope are connected around third shackle, the 4th shackle with the suspension hook of lifting equipment.
Further, first platform sling and the second platform sling by two groups of pins, round nut, gasket structure be connected to it is described Two vertical hangers, the platform sling can be freely rotated with vertical hanger around round nut.
Further, during prefabricated components lift by crane, first wirerope and the second wirerope are respectively with described two A roller fits closely, and can do opposite sliding.
Further, it during prefabricated components lift by crane, is lifted by crane using rotary process, prefabricated components is sling and are installed to mesh Cursor position.
Further, which further includes horizontal embedded part, is connected to prefabricated components, and the horizontal embedded part is connected to level and hangs Tool.
Device proposed by the present invention for prefabricated components hoisting and hanging is not needed with changing suspender in the construction process, The positional relationship for not needing replacement suspender and prefabricated components, bring is numerous during eliminating replacement suspender and replacement spreader position General labourer's sequence and insecurity factor, improve work efficiency.
Detailed description of the invention
Fig. 1 and Fig. 2 show the device different directions for prefabricated components hoisting and hanging of present pre-ferred embodiments Structural schematic diagram.
Fig. 3 show the built-in fitting and vertical hanger attachment structure schematic diagram of present pre-ferred embodiments.
Specific embodiment
A specific embodiment of the invention is provided below in conjunction with attached drawing, but the present invention is not limited to the following embodiments and the accompanying drawings.Root According to following explanation and claims, advantages and features of the invention will be become apparent from.It should be noted that attached drawing be all made of it is very simple The form of change and use non-accurate ratio, be only used for conveniently, lucidly aid in illustrating the embodiment of the present invention purpose.
The present invention provides that a kind of applicability is wide, the device for hoisting and hanging easy to operate, lifts high-efficient and dangerous Property is small.
Please refer to FIG. 1 to FIG. 3, Fig. 1 and Fig. 2 show present pre-ferred embodiments for prefabricated components hoisting and hanging The structural schematic diagram of device different directions.Fig. 3 show the built-in fitting and vertical hanger connection structure of present pre-ferred embodiments Schematic diagram.
The present invention proposes a kind of device for prefabricated components hoisting and hanging, comprising: the first built-in fitting 110 and second is pre-buried Part 120 is connected to prefabricated components 10;First vertical hanger 210 and the second vertical hanger 220, by bolt 300 with it is described two Built-in fitting 110,120 is connected;First platform sling 410 and the second platform sling 420 are connected to described two vertical hangers 210,220;First Wirerope 510 and the second wirerope 520 bypass the first roller 610, the second roller 620 respectively, pass through the first shackle 710, second Shackle 720 is connected with described two platform slings 410,420, and described two rollers 610,620 pass through third shackle the 810, the 4th respectively Shackle 820 is connected with fringed iris herb 800, and third wirerope 910, the 4th wirerope 920 bypass third shackle 810, the 4th shackle 820 It is connected with the suspension hook 20 of lifting equipment.
, need to be first secured by built-in fitting and the reinforcement welding in prefabricated components when making prefabricated components, it is prefabricated with after-pouring The concrete of component needs the position of strict control built-in fitting in concreting process.
Preferred embodiment according to the present invention, first platform sling 410 and the second platform sling 420 pass through two groups of pins, round nut, pads The structure of piece is connected to described two vertical hangers 210,220, and the platform sling and vertical hanger can freely turn around round nut It is dynamic.
During prefabricated components lifting, first wirerope 510 and the second wirerope 520 respectively with described two rollers Wheel 610,620 fits closely, and can do opposite sliding.
Further, it during prefabricated components lift by crane, is lifted by crane using rotary process, prefabricated components is sling and are installed to mesh Cursor position.During this period, no replacement is required suspender, need not also adjust the position of suspender, securely and reliably.The processing is simple for the device, applies Work is at low cost, detachably recycles, and maximum function is exactly that can improve the lifting efficiency of prefabricated components.
Preferred embodiment according to the present invention, the device further include horizontal embedded part 130, are connected to prefabricated components 10, the water Flat embedded part 130 is connected to horizontal sling 230.
In the suspension hook uphill process of lifting equipment, the power transmission of suspension hook elder generation is to third wirerope 910, the 4th wirerope 920, and Three wirerope 910,920 power transmission of the 4th wirerope are to third shackle 810, the 4th shackle 820, third shackle 810, the 4th shackle 820 power transmissions give the first wirerope 510 to roller 610,620, roller 610,620 power transmissions to fringed iris herb 800,800 power transmission of fringed iris herb With the second wirerope 520, the first shackle 710, the second shackle 720 are given in the first wirerope 510 and 520 power transmission of the second wirerope, the The first platform sling 410 and the second platform sling 420, the first platform sling 410 and the second platform sling 420 are given in one shackle 710,720 power transmission of the second shackle Power transmission gives 110 and of the first built-in fitting by pin, round nut, gasket power transmission to vertical hanger 210,220, vertical hanger 210,220 Second built-in fitting 120, the first built-in fitting 110 and 120 power transmission of the second built-in fitting are to prefabricated components 10, to overcome gravity to complete It hangs.
During lifting, it not will form dead angle when each connecting portion all can be rotated in the device, be particularly suitable for prefabricated Wall, prefabricated post, the lifting of prefabricated board and installation exercise.
In conclusion the device proposed by the present invention for prefabricated components hoisting and hanging, in the construction process, do not need with Suspender is changed, the positional relationship of replacement suspender and prefabricated components is not needed yet, eliminates replacement suspender and replacement spreader position process The many and diverse process of middle bring and insecurity factor, improve work efficiency.
Although the present invention has been disclosed as a preferred embodiment, however, it is not to limit the invention.Skill belonging to the present invention Has usually intellectual in art field, without departing from the spirit and scope of the present invention, when can be used for a variety of modifications and variations.Cause This, the scope of protection of the present invention is defined by those of the claims.

Claims (5)

1. a kind of device for prefabricated components hoisting and hanging characterized by comprising
First built-in fitting and the second built-in fitting, are connected to prefabricated components;
First vertical hanger and the second vertical hanger are connected by bolt with described two built-in fittings;
First platform sling and the second platform sling, are connected to described two vertical hangers;
First wirerope and the second wirerope, respectively bypass the first roller, the second roller, by the first shackle, the second shackle with Described two platform slings are connected, and described two rollers pass through third shackle respectively, the 4th shackle is connected with fringed iris herb, third steel wire Rope, the 4th wirerope are connected around third shackle, the 4th shackle with the suspension hook of lifting equipment.
2. the device according to claim 1 for prefabricated components hoisting and hanging, which is characterized in that first platform sling and Second platform sling is connected to described two vertical hangers, the platform sling and vertical hanger by the structure of two groups of pins, round nut, gasket It can be freely rotated around round nut.
3. the device according to claim 1 for prefabricated components hoisting and hanging, which is characterized in that lifted by crane in prefabricated components In the process, first wirerope and the second wirerope are fitted closely with described two rollers respectively, and can do opposite sliding.
4. the device according to claim 1 for prefabricated components hoisting and hanging, which is characterized in that lifted by crane in prefabricated components In the process, it is lifted by crane, prefabricated components are sling and is installed to target position using rotary process.
5. the device according to claim 1 for prefabricated components hoisting and hanging, which is characterized in that the device further includes water Flat embedded part, is connected to prefabricated components, and the horizontal embedded part is connected to horizontal sling.
CN201820575672.9U 2018-04-20 2018-04-20 A kind of device for prefabricated components hoisting and hanging Active CN208279171U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820575672.9U CN208279171U (en) 2018-04-20 2018-04-20 A kind of device for prefabricated components hoisting and hanging

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820575672.9U CN208279171U (en) 2018-04-20 2018-04-20 A kind of device for prefabricated components hoisting and hanging

Publications (1)

Publication Number Publication Date
CN208279171U true CN208279171U (en) 2018-12-25

Family

ID=64751872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820575672.9U Active CN208279171U (en) 2018-04-20 2018-04-20 A kind of device for prefabricated components hoisting and hanging

Country Status (1)

Country Link
CN (1) CN208279171U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108516454A (en) * 2018-04-20 2018-09-11 上海市机械施工集团有限公司 A kind of hanging apparatus of prefabricated components

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108516454A (en) * 2018-04-20 2018-09-11 上海市机械施工集团有限公司 A kind of hanging apparatus of prefabricated components

Similar Documents

Publication Publication Date Title
CN205045698U (en) Reinforcement cage hoisting utensil
CN104925672B (en) The all-hydraulic self-crawling type two-sided tower crane of suspension
CN204588444U (en) Prefabricated superimposed sheet special hanger
CN208279171U (en) A kind of device for prefabricated components hoisting and hanging
CN108516454A (en) A kind of hanging apparatus of prefabricated components
CN204057659U (en) The prefabricated superimposed panel lifting appliance of super large
CN207684788U (en) Hand pulling block frame
CN207566719U (en) Prefabricated element slings
CN106121259B (en) The hanging apparatus and its hanging method of embedded integrated outer wall plate
CN203998604U (en) The be threaded vertical reinforcement erecting equipment of form of employing
CN207390887U (en) A kind of hanging apparatus
CN205653104U (en) Movable crane for installing unit plate curtain wall
CN205116033U (en) A reinforcing bar hoist device that is used for high mound of bridge to be under construction
CN208898385U (en) A kind of concrete prefabricated element hanging device
CN209242475U (en) A kind of suspender
CN211775988U (en) Steel construction high-rise tower high altitude protector
CN204265302U (en) One can dismounting loop wheel machine flexibly
CN113636444A (en) Hoisting method and tool capable of adjusting different weights
CN209352424U (en) A kind of hoisting prefabricated part of embedded small hoisting ring group
CN108529404A (en) A kind of build uses elevator
CN209052276U (en) A kind of lifting stick for concrete prefabricated element hanging
CN207986495U (en) A kind of Bridge High-pier main reinforcement hanging apparatus
CN208054770U (en) A kind of adjustable hoisting balance beam device of light-duty center of gravity
CN208265608U (en) Large-tonnage hoisting device for reinforcement cage
CN207932896U (en) Ring beam and ring rail integral hoisting tool

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant