CN208105184U - A kind of geotechnological pavement structure of ecology and application have the dykes and dams of the pavement structure - Google Patents
A kind of geotechnological pavement structure of ecology and application have the dykes and dams of the pavement structure Download PDFInfo
- Publication number
- CN208105184U CN208105184U CN201820497407.3U CN201820497407U CN208105184U CN 208105184 U CN208105184 U CN 208105184U CN 201820497407 U CN201820497407 U CN 201820497407U CN 208105184 U CN208105184 U CN 208105184U
- Authority
- CN
- China
- Prior art keywords
- dykes
- dams
- mask
- laid
- matrix
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model relates to a kind of geotechnological pavement structures of ecology, it is laid on the dykes and dams matrix piled up, it is pressed on the upper end of the first mask body including the first mask body being laid on dykes and dams matrix inclined surface and the second mask body for being laid on dykes and dams matrix top surface, the outer end of the second mask body.First mask body includes the mask pad that at least one is laid with along dykes and dams extending direction, and mask pad has multiple longitudinally disposed bag bodies, and the cuff to be formed for filling filler is arranged in the upper end opening of bag body.Ecology geotechnique's pavement structure and application have the dykes and dams of the pavement structure, the the first mask body used is in construction, after the mask pad for constituting the first mask body being laid on the inclined surface of dykes and dams matrix, sand is filled into each bag body by the cuff of each bag body of mask pad again, and then form the mask of the inclined surface of dykes and dams matrix, construction is simple is convenient, reduces construction cost.In addition, filling the mask pad after sand is integral structure, and surface is in undaform, and capacity of anti-storm is stronger, and it is also more obvious to protect sand ability.And overall aesthetic degree and ageing resistance also get a promotion.
Description
Technical field
The utility model relates to marine traffic engineering technical fields, and in particular to a kind of geotechnological pavement structure of ecology further relates to answer
With the dykes and dams of the geotechnological pavement structure of the ecology.
Background technique
As shown in Figure 1, being piled up on the outside of the embankment improvement project ecology pipe band of inland sea frequently with small-sized woven bag, to improve sand
Guarantor's sand ability on beach.Small-sized woven bag needs to be assembled by carrying after manually filling, and woven bag usage quantity is huge, and holds
It is easy to aging, cause cost input higher, is affected to the duration.And on the outside of debris dam under the influence of larger stormy waves, individually
Sandbag can cause debris dam effect to decline, and influence beauty because specific gravity is not enough damaged by stormy waves.It is transformed in inland sea embankment
In project, more particularly, to the landscapes intermediate item such as artificial beach, pavement structure made of being assembled using small woven bag its wind and wave resistance,
Anti-aging and aesthetics is all unable to reach the requirement used steadily in the long term.
Utility model content
First technical problem to be solved in the utility model is that a kind of easy construction is provided for the above-mentioned prior art
The geotechnological pavement structure of ecology.
Second technical problem to be solved in the utility model be provided for the above-mentioned prior art it is a kind of anti-aging, anti-
The strong dykes and dams of stormy waves ability.
The utility model solves technical solution used by above-mentioned first technical problem:A kind of geotechnological mask knot of ecology
Structure is laid on the dykes and dams matrix piled up, it is characterised in that:Including the first mask body for being laid on dykes and dams matrix inclined surface with
And it is laid on the second mask body of dykes and dams matrix top surface, the outer end of the second mask body is pressed on the first mask body
Upper end on;
The first mask body includes the mask pad that at least one is laid with along dykes and dams extending direction, and the mask pad has more
The cuff to be formed for filling filler is arranged in a longitudinally disposed bag body, the upper end opening of the bag body.
The mask pad is sewed by two layers of armour layer, the sewing with the setting of a plurality of longitudinal gap on two layers of armour layer
Line, and the lower end of two layers of armour layer is sewed together, and then forms the bag body.
The first mask body includes at least two mask pads, and the side for the mask pad being laid with afterwards is pressed on adjacent protection pad
On side.
The first mask body uses and is filled with the geotextile tube bag of filler.
The utility model solves technical solution used by above-mentioned second technical problem:A kind of application has ecological geotechnique
The dykes and dams of pavement structure, it is characterised in that:It further include dykes and dams matrix, the dykes and dams matrix includes debris dam and is arranged described
The embankment of debris dam side.
The embankment is piled up by least two layers polypropylene woven bag filled with filler, the outside shape of the embankment
At the inclined surface of dykes and dams matrix.
Compared with prior art, the utility model has the advantage of:Ecology geotechnique's pavement structure and application have the mask
The mask pad for constituting the first mask body can be laid on dykes and dams base in construction by the dykes and dams of structure, the first mask body used
After on the inclined surface of body, then sand filled into each bag body by the cuff of each bag body of mask pad, and then forms the inclination of dykes and dams matrix
The mask in face, construction is simple is convenient, reduces construction cost.In addition, the mask pad filled after sand is integral structure, and surface
In undaform, capacity of anti-storm is stronger, and it is also more obvious to protect sand ability.And overall aesthetic degree and ageing resistance are also mentioned
It rises.
Detailed description of the invention
Fig. 1 is the schematic cross-section of dykes and dams in the prior art.
Fig. 2 is the schematic cross-section of dykes and dams in the utility model embodiment.
Fig. 3 is the first mask body structural schematic diagram in the utility model embodiment.
Specific embodiment
The utility model is described in further detail below in conjunction with figure embodiment.
As shown in Figures 2 and 3, the dykes and dams in the present embodiment are disposed around on seashore, prevent seashore soil erosion, the dykes and dams packet
The geotechnological pavement structure of ecology for including dykes and dams matrix 1 and being laid on dykes and dams matrix 1, is used for protecting ecology geotechnique pavement structure dike
Dam foundation body 1, and then anti-aging, the capacity of anti-storm of dykes and dams matrix 1 can not only be improved, additionally it is possible to improve whole aesthetics.
Wherein dykes and dams matrix 1 includes debris dam 11 and is arranged in the embankment 12 of 11 side of debris dam, and embankment 12 is close to blocking
Sand dam 11 is arranged.After embankment 12 is arranged, the top surface of embankment 12 constitutes a plane substantially, and the outside of embankment 12 forms inclined surface,
The gradient of inclined surface in the present embodiment is 1:2.The top surface of embankment 12 then constitutes the top surface of dykes and dams matrix 1, and embankment 12 tilts
Lateral surface then constitute the inclined surface of dykes and dams matrix 1.
The bottom of debris dam 11 uses I type ecology pipe bag, and top uses II type ecology pipe bag, in each ecological pipe bag respectively
It is packed into filler.In the present embodiment, the bottom of embankment 12 is laid with using the anti-aging big woven bag of three-layer polypropylene.Every strata
When the anti-aging big woven bag of propylene is constructed, the anti-aging big woven bag of polypropylene is laid in place, is consolidated woven bag with the rope made of hemp
It is scheduled on corresponding position, is avoided during irrigation since momentum effect causes to generate displacement.Then by the anti-aging big volume of polypropylene
It knits the cuff among bag and starts the irrigation sea sand for arriving surrounding equilibrium again.After the completion of the anti-aging big woven bag construction of three-layer polypropylene,
Start to carry out the construction of ecological geotechnological pavement structure.
Ecological geotechnique's pavement structure includes the first mask body 2 being laid on 1 inclined surface of dykes and dams matrix and is laid on dike
Second mask body 3 of 1 top surface of dam foundation body, the outer end of the second mask body 3 are pressed on the upper end of the first mask body 2.Therefore it is applying
Working hour is laid with the first mask body 2 first, then re-lays the second mask body 3.
In the present embodiment, the first mask body 2 includes at least two mask pads being laid with along dykes and dams extending direction, is laid with afterwards
The side of mask pad is pressed on the side of adjacent protection pad.Mask pad in the present embodiment is sewed by two layers of armour layer, and two
Sewing line with the setting of a plurality of longitudinal gap on layer armour layer, and the lower end of two layers of armour layer is sewed together, and then shape
At multiple longitudinal bag bodies 21.The cuff 211 to be formed for filling filler is arranged in the upper end opening of each bag body 21.
In use, mask made of ecological geotextile tube bag same material is leveled up to the inclined surface for being layered on dykes and dams matrix 1 first,
So that cuff 211 is located at upper end position, two adjacent mask pads, the mask that the side for the mask pad being laid with afterwards is laid with before being pressed in
On the side of pad.In subsequent filling, preceding laying mask pad is not refilled sea sand in the bag body 21 of pressure lateral location, and is pressed in
The lateral location of the preceding rear mask pad being laid on mask pad side then needs to fill sea sand.Before the irrigation sea sand into bag body 21,
Each mask pad is fixed, prevents that mask pad is caused to slide downwards under subsequent construction momentum effect.To each bag body 21 of mask pad
Interior irrigation sea sand sutures the cuff 211 on mask pad top, it is ensured that entire after two mask pads have integrally all charged sea sand
The globality of structure, and guarantee that sea sand is not lost by alluvion in structure.
After the completion of the whole laying of first mask body 2, the second mask body 3 is re-layed, the second mask body 3 uses I type ecology pipe
Second mask body 3, is laid in the top of dykes and dams matrix 1 by bag, and when laying guarantees completely will ecology geotechnique in the first mask body 2
The cuff 211 of mask pad is pushed down.Also needed in irrigation worker top trample guarantee its bag body 21 be not uneven
The phenomenon that.In the construction process, it needs to measure and follow up at any time, guarantee that its absolute altitude meets design requirement.
In ecology geotechnique's pavement structure, the mask pad after filling sand is integral structure, and surface is in undaform, wind resistance
Unrestrained ability is stronger, and it is also more obvious to protect sand ability.And overall aesthetic degree and ageing resistance also get a promotion.
Mechanized construction may be implemented in the integral construction of dykes and dams, and construction efficiency greatly improves, and project progress has been effectively ensured,
And reduce construction cost.Meanwhile first mask body 2 and the second mask body 3 be all made of ecological geotextile tube bag, ageing resistance
It is stronger while also more beautiful.
Claims (6)
1. a kind of geotechnological pavement structure of ecology, is laid on the dykes and dams matrix piled up, it is characterised in that:Including being laid on dykes and dams base
The first mask body on body inclined surface and the second mask body for being laid on dykes and dams matrix top surface, the second mask body
Outer end is pressed on the upper end of the first mask body;
The first mask body includes the mask pad that at least one is laid with along dykes and dams extending direction, and the mask pad has multiple vertical
To the bag body of setting, the cuff to be formed for filling filler is arranged in the upper end opening of the bag body.
2. the geotechnological pavement structure of ecology according to claim 1, it is characterised in that:The mask pad is stitched by two layers of armour layer
It makes, the sewing line with the setting of a plurality of longitudinal gap on two layers of armour layer, and the lower end of two layers of armour layer is sewed one
It rises, and then forms the bag body.
3. the geotechnological pavement structure of ecology according to claim 1, it is characterised in that:The first mask body includes at least two
A mask pad, the side for the mask pad being laid with afterwards are pressed on the side of adjacent protection pad.
4. the geotechnological pavement structure of ecology according to claim 1, it is characterised in that:The first mask body is used and is filled with
The geotextile tube bag of filler.
5. a kind of application is just like the dykes and dams of the geotechnological pavement structure of ecology described in Claims 1-4 any claim, feature
It is:It further include dykes and dams matrix, the dykes and dams matrix includes debris dam and the embankment that the debris dam side is arranged in.
6. the dykes and dams of the geotechnological pavement structure of ecology according to claim 5, it is characterised in that:The embankment is by least two layers
Polypropylene woven bag filled with filler is piled up, and the outside of the embankment forms the inclined surface of dykes and dams matrix.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820497407.3U CN208105184U (en) | 2018-04-09 | 2018-04-09 | A kind of geotechnological pavement structure of ecology and application have the dykes and dams of the pavement structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820497407.3U CN208105184U (en) | 2018-04-09 | 2018-04-09 | A kind of geotechnological pavement structure of ecology and application have the dykes and dams of the pavement structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208105184U true CN208105184U (en) | 2018-11-16 |
Family
ID=64120989
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820497407.3U Active CN208105184U (en) | 2018-04-09 | 2018-04-09 | A kind of geotechnological pavement structure of ecology and application have the dykes and dams of the pavement structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208105184U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111962471A (en) * | 2020-08-24 | 2020-11-20 | 中交水利水电建设有限公司 | Construction method of artificial lake reclamation dam |
-
2018
- 2018-04-09 CN CN201820497407.3U patent/CN208105184U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111962471A (en) * | 2020-08-24 | 2020-11-20 | 中交水利水电建设有限公司 | Construction method of artificial lake reclamation dam |
CN111962471B (en) * | 2020-08-24 | 2022-02-01 | 中交水利水电建设有限公司 | Construction method of artificial lake reclamation dam |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204530729U (en) | A kind of ecological protection device for greening side slope | |
CN213086712U (en) | Slope dike protection body of gabion mesh box structure | |
CN107869152A (en) | Reinforced earth bulkhead and its construction method with deformation buffer area | |
CN208105184U (en) | A kind of geotechnological pavement structure of ecology and application have the dykes and dams of the pavement structure | |
CN210684603U (en) | Rapid diking device for flood control and emergency rescue | |
CN205152888U (en) | An anchor bag and a concrete interlocking software volleyball association body structure | |
CN205134303U (en) | Compound reinforced structure of soft base of ecological bamboo raft among road engineering of field | |
CN104499459A (en) | Geotextile tube breakwater | |
CN104164854A (en) | Method for ecologically re-greening hardened slope | |
CN203420255U (en) | Ecological seepage-proofing channel with excellent seepage-proofing performance | |
CN101929141B (en) | Overlength flood control pipe bag dykes and dams of rescuing and protecting are utilized to overflow the method for unrestrained bank dangerous situation and equipment thereof | |
JP6533907B1 (en) | Composite sheet and bag made of the composite sheet | |
CN203654231U (en) | Soft raft with concrete water-pervious components | |
CN207582412U (en) | A kind of ecological revetment | |
CN207017219U (en) | A kind of new embankment | |
CN202945571U (en) | Surface protection structure suitable for soil base underwater foundation bed with ultrahigh flow rate | |
CN202830870U (en) | Double-cuff sandbag for sand soft mattress ballasting | |
CN104141285A (en) | Seepage-proofing seawall | |
CN111321700B (en) | Overflowing energy dissipation type ecological bank protection method for anti-scouring and anti-landslide barrier plugs | |
CN100593604C (en) | Flexible explosion-proof dike and construction method thereof | |
CN203007959U (en) | Net cage pad type revetment structure | |
CN204343278U (en) | A kind of flexible sand control sandbag and sand-protecting barrier | |
CN2700398Y (en) | Multifunctional flood prevention bag | |
CN208685538U (en) | A kind of big sand pocket core dike of new type of deep-water | |
CN203475388U (en) | High-strength non-woven geofabriform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 315 200 No. 221 Yanjiang East Road, Zhenhai District, Ningbo City, Zhejiang Province Patentee after: China Water Conservancy and Hydropower Construction Co., Ltd. Address before: 315 200 No. 221 Yanjiang East Road, Zhenhai District, Ningbo City, Zhejiang Province Patentee before: SDC Waterway Construction Co., Ltd. |
|
CP01 | Change in the name or title of a patent holder |