CN208072409U - Metro station excavation bracing members set up personnel's fall arrest facility - Google Patents

Metro station excavation bracing members set up personnel's fall arrest facility Download PDF

Info

Publication number
CN208072409U
CN208072409U CN201721266249.2U CN201721266249U CN208072409U CN 208072409 U CN208072409 U CN 208072409U CN 201721266249 U CN201721266249 U CN 201721266249U CN 208072409 U CN208072409 U CN 208072409U
Authority
CN
China
Prior art keywords
personnel
bracing members
expansion bolt
fender post
fall arrest
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721266249.2U
Other languages
Chinese (zh)
Inventor
祁海峰
郭振华
文一
李宗奇
梁高峰
李法永
王来所
王新豪
赵伟
张志胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
PowerChina Railway Construction Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
PowerChina Railway Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd, PowerChina Railway Construction Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201721266249.2U priority Critical patent/CN208072409U/en
Application granted granted Critical
Publication of CN208072409U publication Critical patent/CN208072409U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

Metro station excavation bracing members set up personnel's fall arrest facility, to fully ensure that the safety of the operating personnel in steel purlin, and advantageously reduce construction cost.Including spaced fender post and the steel purlin being fixedly mounted on each fender post, expansion bolt is fixedly installed in the top of the steel purlin on each fender post, and the overhanging end of expansion bolt has hook part, elongated round steel is hung in the hook portion of each expansion bolt.

Description

Metro station excavation bracing members set up personnel's fall arrest facility
Technical field
The utility model is related to Tunnel Engineering, more particularly to a kind of Metro station excavation bracing members set up personnel's fall arrest and set It applies.
Background technology
In recent years with the fast development in city since, city incity urban rail transit construction is more like a raging fire, subway station Most of support forms for adding inner support for fender post, since station is typically all two layers or three-decker, foundation depth reaches 15m~25m, bracing members erection quantities is bigger, and personnel need walk in steel purlin on foot in erection process.There are operation people Member's high falling risk, security risk are larger.
Traditional bracing members erection method be personnel climbed to by cat ladder need set up bracing members one layer of steel purlin on, then Pad it need to extremely set up Support Position, whole process since travel distance is long, and periphery without safety belt can bolt hang position, worker All it is often very long a distance of walking in steel purlin without any safety measure, it is very dangerous.Therefore, A kind of method for being badly in need of in bracing members erection process preventing personnel from falling, to solve such technical problem.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of Metro station excavation bracing members, erection personnel are anti-fall Facility is fallen, to fully ensure that the safety of the operating personnel in steel purlin, and advantageously reduces construction cost.
Technical solution is as follows used by the utility model solves its technical problem:
The Metro station excavation bracing members of the utility model set up personnel's fall arrest facility, including spaced fender post With the steel purlin being fixedly mounted on each fender post, it is characterized in that:The top of the steel purlin is fixedly installed on each fender post The overhanging end of expansion bolt, expansion bolt has hook part, and elongated round steel is hung in the hook portion of each expansion bolt.
The utility model has the beneficial effects that being formed by expansion bolt, elongated round steel and existing fender post fixed Combination Falling proof device can fully ensure that operating personnel's safety in steel purlin, and not influence it and freely walk;It is easy to operate, it applies Work is rapid, simple with material, and structure is common, and easy to assembly, strong applicability can effectively reduce construction cost.
Description of the drawings
This specification includes following two width attached drawing:
Fig. 1 is that the utility model Metro station excavation bracing members set up personnel's fall arrest service plan;
Fig. 2 is that the utility model Metro station excavation bracing members set up personnel's fall arrest facility elevation.
Component and corresponding label are shown in figure:Fender post 10, steel purlin 11, bracing members 12, expansion bolt 21, elongated circle Steel 22.
Specific implementation mode
The utility model is further illustrated with reference to the accompanying drawings and examples.
Referring to Figures 1 and 2, the Metro station excavation bracing members of the utility model set up the fall arrest facility of personnel, including Spaced fender post 10 and the steel purlin 11 being fixedly mounted on each fender post 10.The top of the steel purlin 11 is each Expansion bolt 21 is fixedly installed on fender post 10, the overhanging end of expansion bolt 21 has hook part, in the curved of each expansion bolt 21 Hook portion hangs elongated round steel 22.
With reference to Fig. 2, while setting up steel purlin 11, the position of certain distance is arranged and is respectively going along with sb. to guard him above steel purlin 11 Expansion bolt 21 is set in stake 10, then elongated round steel 22 is hung in the hook part of 21 exposed junction of expansion bolt.With elongated circle Steel 22 is used as the fixed tie point of construction personnel's safety belt.Under construction personnel to after in steel purlin, as long as safety belt is bolted to logical On long round steel 22,12 decorating position of bracing members can be run to safely in steel purlin 11, it is extremely convenient.In general, expansion bolt 21 bearing capacity is not less than 8KN, and the diameter of elongated round steel 22 is not less than 16mm.
The above is the utility model Metro station excavation bracing members erection personnel's fall arrest facility that explains through diagrams Some principles, be not intended to by the utility model be confined to shown in and the concrete structure and the scope of application in, therefore it is every It is possible that the corresponding modification being utilized and equivalent, belong to the apllied the scope of the claims of the utility model.

Claims (1)

1. Metro station excavation bracing members set up personnel's fall arrest facility, including spaced fender post (10) and fixed installation Steel purlin (11) on each fender post (10), it is characterized in that:The top of the steel purlin (11) is solid on each fender post (10) Surely the overhanging end of setting expansion bolt (21), expansion bolt (21) has hook portion, is hung in the hook part of each expansion bolt (21) Elongated round steel (22).
CN201721266249.2U 2017-09-29 2017-09-29 Metro station excavation bracing members set up personnel's fall arrest facility Active CN208072409U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721266249.2U CN208072409U (en) 2017-09-29 2017-09-29 Metro station excavation bracing members set up personnel's fall arrest facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721266249.2U CN208072409U (en) 2017-09-29 2017-09-29 Metro station excavation bracing members set up personnel's fall arrest facility

Publications (1)

Publication Number Publication Date
CN208072409U true CN208072409U (en) 2018-11-09

Family

ID=64031736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721266249.2U Active CN208072409U (en) 2017-09-29 2017-09-29 Metro station excavation bracing members set up personnel's fall arrest facility

Country Status (1)

Country Link
CN (1) CN208072409U (en)

Similar Documents

Publication Publication Date Title
CN205077885U (en) Building core section of thick bamboo hydraulic pressure intelligence protection platform that climbs
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN103147408A (en) Bridge rotation constructing process and rotation system
CN102383815B (en) Suspension type driftage temporary supporting device and use method thereof
CN104288935A (en) Wire rope anti-falling system and installation method thereof
CN102828608A (en) Hydraulic climbing protection device for high-rise building construction
CN205709343U (en) The inverse dress special building hoist of moldeed depth foundation ditch
CN207226965U (en) High slope hoist engine slideway lifting system
CN204626930U (en) A kind of integrated form crane operating platform
CN208072409U (en) Metro station excavation bracing members set up personnel's fall arrest facility
CN204326493U (en) Unidirectional rising catching device
CN103866985A (en) Butt joint method and device for construction elevator and creeping formwork frame body
CN201172921Y (en) Slideway on oblique roof and pulley system
CN204474106U (en) Deep shaft manned lift device
Zhou et al. Study on prevention measures of falling accidents during construction
CN205916932U (en) Hand over -and -under type coal mine tunnel environment monitoring sensor cable suspension device
CN106012854B (en) The transporting equipment of prefabricated assembled overpass bridge plate
CN203938968U (en) The auxiliary hanging basket of installation of continuous beam arch suspension rod bottom anchored end
CN202245789U (en) Special typhoon prevention device for gantry crane
CN103669889B (en) A kind of high-altitude safe guardrail for Steel Structure Installation and preparation method thereof
CN106245531A (en) Steel structural bridge installation method is hung under bilateral derrick type
CN106121238A (en) A kind of high-altitude delivering concrete device
CN207499525U (en) A kind of installation support construction for the main stage girder steel of theater
CN203923917U (en) Job platform at the bottom of a kind of packaged type bridge
CN206233119U (en) The cradle structure of antidumping

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant