CN207998799U - A kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder - Google Patents
A kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder Download PDFInfo
- Publication number
- CN207998799U CN207998799U CN201820122610.2U CN201820122610U CN207998799U CN 207998799 U CN207998799 U CN 207998799U CN 201820122610 U CN201820122610 U CN 201820122610U CN 207998799 U CN207998799 U CN 207998799U
- Authority
- CN
- China
- Prior art keywords
- underbeam
- drawstring
- upper beam
- sections
- central sill
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses 0# sections of a kind of rigid structure of cantilever, continuous beam bracket combination formula pre-pressing systems, belong to field of bridge construction, pier shaft places several groups upper beam per lateral bracket top surface direction across bridge, and pier shaft both sides upper beam quantity is consistent, every upper beam is connected as one by several drawstrings and the pre-buried drawstring of cushion cap by compression system, compression system includes central sill, underbeam and jack, underbeam is connect by drawstring with upper beam, central sill is set to above underbeam, it is connect with the pre-buried drawstring of cushion cap by very heavy top support, central sill between central sill and underbeam.The utility model can reduce precompressed workload, improve bracket pre-compressed effect, reinforce temporary structure safety when high pier construction, and install convenient, waste of material is few, and cyclic utilization rate is high.
Description
Technical field
The utility model belongs to field of bridge construction, is suitable for height pier cantilever continuous beam(Rigid structure)It constructs or other is similar
Bracket precompressed in higher works construction.
Background technology
1)Traditional cantilever casting beam 0# sections of precompressed:
0# sections of bracket precompressed of cantilever casting beam are continuous beams(Rigid structure)Important component in work progress.Conventional bracket precompressed
Using heavy duty structure article such as sandbag, concrete block, steel etc., it is placed directly on 0# sections of end templates and relies on gravity precompressed.
2)The limitation of traditional sustaining wall:
Conventional method precompressed materials are more, lift heavy workload, limited by platform size and tend not to reach precompressed weight.It throws
Enter a large amount of manpower and materials, of high cost, construction is inconvenient, and waste of material is serious, and cyclic utilization rate is low, if precompressed weight is not achieved,
Corresponding to increase bracket risk factor, high pier construction is particularly evident.
Utility model content
The purpose of this utility model is that:It is proposed a kind of cantilever continuous beam(Rigid structure)0# sections of bracket combination formula pre-pressing systems,
Reduce precompressed workload, improve bracket pre-compressed effect, reinforces temporary structure safety when high pier construction, and install convenient, material wave
Take few, cyclic utilization rate height.
The purpose of this utility model is realized by following technical proposals:
A kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder, if pier shaft is placed per lateral bracket top surface direction across bridge
Dry group upper beam, and pier shaft both sides upper beam quantity is consistent, every upper beam passes through pressurization by several drawstrings and the pre-buried drawstring of cushion cap
System is connected as one, and compression system includes central sill, underbeam and jack, and underbeam is connect by drawstring with upper beam, and central sill is set to
Above underbeam, it is connect with the pre-buried drawstring of cushion cap by very heavy top support, central sill between central sill and underbeam.
Alternatively, the upper beam, drawstring and compression system of pier shaft both sides are symmetrical arranged.
Alternatively, jack is set to the centre position of central sill and underbeam, and the drawstring of both sides is symmetrical arranged.
Alternatively, upper, middle and lower beam is 588 shaped steel of Two bors d's oeuveres work.
Alternatively, drawstring is finish rolling deformed bar.
Alternatively, pier shaft places two groups of 588 shaped steel of Two bors d's oeuveres work, spacing 1.2m, every group of type per lateral bracket top surface direction across bridge
Steel is connected as one with the pre-buried finish rolling deformed bar of cushion cap by compression system by 4 32 finish rolling deformed bars of Φ, Mei Gejia
A jack is arranged in pressure system.
The aforementioned main scheme of the utility model and its each further selection scheme can be freely combined to form multiple schemes,
The scheme that can be used and be claimed for the utility model;And the utility model,(Each non conflicting selection)Between selection and
It can also be freely combined between other selections.Those skilled in the art are after understanding the present invention program according to the prior art and public affairs
Know that common sense can be illustrated there are many combination, is the claimed technical solution of the utility model, does not do exhaustion herein.
The beneficial effects of the utility model:It is poor to overcome traditional pre-compressed effect, precompressed weight is insufficient, and risk factor is high, at
The defects of this height, construction is inconvenient, and waste of material is serious.Easy using new-type pre-pressing system, versatile, stability is high, follows
Ring utilization rate is high, and at low cost, Saving in time costs is apparent.
Description of the drawings
Fig. 1 is No. 0 block bracket general layout side schematic view of the utility model embodiment;
Fig. 2 is No. 0 block bracket general layout sectional schematic diagram of the utility model embodiment;
In figure, 1 is pier shaft, and 2 be bracket, and 3 be upper beam, and 4 be drawstring, and 5 be cushion cap, and 6 be compression system, and 7 be central sill, and 8 are
Underbeam, 9 be jack, and 10 be 0# sections, and 11 be 0# sections of end templates, and 12 are, 13 are, 14 are, 15 are, 16 are, 17 are, 18 are, 19
For 20 are.
Specific implementation mode
The utility model is further described with reference to specific embodiments and the drawings.
With reference to shown in figure 1,2, a kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder, pier shaft 1 is per lateral bracket 2
Top surface direction across bridge places several groups upper beam 3, and pier shaft 1 both sides upper beam, 3 quantity are consistent, every upper beam 3 by several drawstrings 4 with
5 pre-buried drawstring 4 of cushion cap is connected as one by compression system 6, and compression system 6 includes central sill 7, underbeam 8 and jack 9, underbeam 8
Connect with upper beam 3 by drawstring 4, central sill 7 is set to the top of underbeam 8, is supported by jack 9 between central sill 7 and underbeam 8, central sill 7 with
5 pre-buried drawstring 4 of cushion cap connects.It is preferred that the upper beam 3 of 1 both sides of pier shaft, drawstring 4 and compression system 6 are symmetrical arranged, jack 9 is set to
The drawstring 4 in the centre position of central sill 7 and underbeam 8, both sides is symmetrical arranged.
As an example, certain river grand bridge, in northern access bridge 100m continuous rigid frames construction, using combined type pre-pressing system, pier
1 height 35m of body, pier shaft 1 place the upper beam 3 of two groups of 588 shaped steel of Two bors d's oeuveres work, two groups of 3 spacing of upper beam per 2 top surface direction across bridge of lateral bracket
1.2m, every group of upper beam 3 are logical by the drawstring 4 of 4 32 finish rolling deformed bars of Φ and the drawstring 4 of 5 pre-buried finish rolling deformed bar of cushion cap
System 6 is overpressurized to be connected as one, jack 9 is that power core is mounted between the central sill 7 and underbeam 8 of two groups of Two bors d's oeuveres works 588,
It checks whether the drawstring 4 of 8 finish rolling deformed bars is vertical simultaneously when installation and tenses stress, then pressurize, when pressurization requires 4 thousand
9 synchronous averagings of jin top, synchronzed press, according to 100% → total load head of 60% → total load head of construction total load head 120% → quiet stop
1h measure it is quiet after vertical and transversely deforming value → third level load stop starting load shedding for 24 hours, and observe flexible deformation value step by step.
Both sides symmetrically carry out when pressurization, and 9 corresponding pressure on top surface of each jack is 60%, 100%, 120% and avoids holder inclined
Heart stress, load should be substantially close with beam body load assignment.The deformation that observation holder is needed in loading procedure, found the abnormal situation and want
Stop preloading immediately, ascertain the reason and can continue precompressed after adopting an effective measure.Precompressed is another in the same way for the complete side of precompressed
Side, can also both sides synchronization progress.
By such pre-pressing system precompressed, workload when precompressed is reduced, bracket pre-compressed effect is improved, strengthens high pier
The safety of temporary structure when construction, and install convenient, waste of material is few, and cyclic utilization rate is high.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this
All any modification, equivalent and improvement etc., should be included in the utility model made by within the spirit and principle of utility model
Protection domain within.
Claims (6)
1. a kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder, it is characterised in that:Pier shaft is horizontal per lateral bracket top surface
Bridge is to placement several groups upper beam, and pier shaft both sides upper beam quantity is consistent, and every upper beam passes through several drawstrings and the pre-buried drawing of cushion cap
Rope is connected as one by compression system, and compression system includes central sill, underbeam and jack, and underbeam is connected by drawstring and upper beam
It connects, central sill is set to above underbeam, is connect with the pre-buried drawstring of cushion cap by very heavy top support, central sill between central sill and underbeam.
2. 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder as described in claim 1, it is characterised in that:Pier shaft two
Upper beam, drawstring and the compression system of side are symmetrical arranged.
3. 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder as described in claim 1, it is characterised in that:Jack
Set on the centre position of central sill and underbeam, the drawstring of both sides is symmetrical arranged.
4. 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder as described in claim 1, it is characterised in that:In above,
Underbeam is 588 shaped steel of Two bors d's oeuveres work.
5. 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder as described in claim 1, it is characterised in that:Drawstring is
Finish rolling deformed bar.
6. 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder as described in claim 1, it is characterised in that:Pier shaft is every
Lateral bracket top surface direction across bridge places two groups of 588 shaped steel of Two bors d's oeuveres work, spacing 1.2m, and every group of shaped steel passes through 4 32 fining twisted steels of Φ
Muscle is connected as one with the pre-buried finish rolling deformed bar of cushion cap by compression system, and a jack is arranged in each compression system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820122610.2U CN207998799U (en) | 2018-01-24 | 2018-01-24 | A kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820122610.2U CN207998799U (en) | 2018-01-24 | 2018-01-24 | A kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207998799U true CN207998799U (en) | 2018-10-23 |
Family
ID=63837049
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820122610.2U Expired - Fee Related CN207998799U (en) | 2018-01-24 | 2018-01-24 | A kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207998799U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111749134A (en) * | 2020-05-28 | 2020-10-09 | 中建隧道建设有限公司 | Auxiliary support construction device and construction method for beam-arch combined continuous rigid frame bridge |
-
2018
- 2018-01-24 CN CN201820122610.2U patent/CN207998799U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111749134A (en) * | 2020-05-28 | 2020-10-09 | 中建隧道建设有限公司 | Auxiliary support construction device and construction method for beam-arch combined continuous rigid frame bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100519943C (en) | Non-cable single-tower stayed bridge | |
CN201254694Y (en) | Combination bridge deck | |
CN205223871U (en) | Suspension bridge bridge tower overarm brace pre -compaction device | |
CN103233588B (en) | With the shift method of raft foundation building | |
CN207998799U (en) | A kind of 0# sections of bracket combination formula pre-pressing systems of cantilever rigid frame-continuous girder | |
CN113152873A (en) | Heightening hanging basket system | |
CN205558237U (en) | Encorbelment board position and encorbelment scaffold frame and exempt from back a structure | |
CN102392422A (en) | Reinforcement structure of single-cable-plane cable-stayed bridge | |
CN206971084U (en) | The supporting construction of bridge coping template | |
CN202689491U (en) | Lower supporting type overhanging scaffold | |
CN207079714U (en) | One kind is encorbelmented balcony support system | |
CN206289544U (en) | A kind of simple electric nacelle device | |
CN113699875A (en) | Super high shock attenuation pier structure of nearly fault railway | |
CN211895796U (en) | Core cylinder movable arm type tower crane installation climbing structure | |
CN211765803U (en) | Double-block type sleeper steel bar truss's floor truck | |
CN208152067U (en) | A kind of construction Soft Soil Layer foundation pile | |
CN201043261Y (en) | Bridge tower of single-tower non-dorsal cord stayed-cable bridge | |
CN207435918U (en) | A kind of box beam hoisting platform and the lifting beam machine using the hoisting platform | |
CN106869036B (en) | Novel bridge precast beam | |
CN105095585A (en) | Method for integral collaborative design of anti-floating anchor rod type basement | |
CN216193922U (en) | Long-span through-type steel arch bridge | |
CN101591888B (en) | Method for pre-pressing bracket in construction of beam of main tower of bridge | |
CN210163026U (en) | Steel structure support frame for bridge crane | |
CN211596369U (en) | Bracket for high pier capping beam of bridge | |
CN204753343U (en) | Single tower cable -stay bridge of bridge floor is arranged to non - symmetry plane broken line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181023 Termination date: 20220124 |