CN207878799U - Build conversion layer bar reinforcement positioning device - Google Patents

Build conversion layer bar reinforcement positioning device Download PDF

Info

Publication number
CN207878799U
CN207878799U CN201721743582.8U CN201721743582U CN207878799U CN 207878799 U CN207878799 U CN 207878799U CN 201721743582 U CN201721743582 U CN 201721743582U CN 207878799 U CN207878799 U CN 207878799U
Authority
CN
China
Prior art keywords
conversion layer
substrate
location hole
locating rod
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721743582.8U
Other languages
Chinese (zh)
Inventor
张德伟
韩建成
叶长宏
郭清明
张兰芳
周景瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Sixth Group Co Ltd
Original Assignee
Beijing Urban Construction Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Sixth Group Co Ltd filed Critical Beijing Urban Construction Sixth Group Co Ltd
Priority to CN201721743582.8U priority Critical patent/CN207878799U/en
Application granted granted Critical
Publication of CN207878799U publication Critical patent/CN207878799U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a kind of building conversion layer bar reinforcement positioning devices comprising:Steel bar positioning plate and embedded frame;Steel bar positioning plate includes substrate and is vertically connected on the side plate on substrate both sides;Substrate location hole and reinforcing bar location hole are set on substrate;Embedded frame includes the embedded board, pre-buried angle steel and locating rod of rectangular configuration;Pre-buried angle steel is respectively perpendicular four corner positions for being fixedly connected on embedded board, towards embedded board lower section;Locating rod is respectively perpendicular fixed four corner positions for being connected on embedded board, towards embedded board top;Pre-buried angle steel is embedded in conversion layer substrustion structure wall;The locating rod of embedded frame is inserted into the substrate location hole of steel bar positioning plate.When carrying out the positioning of conversion layer reinforcing bar, conversion layer reinforcing bar is sequentially inserted into corresponding reinforcing bar location hole, since the position of reinforcing bar location hole is previously set, is not necessarily to carry out dimensional measurement in operation, accelerates the speed and precision of reinforcing bar positioning.

Description

Build conversion layer bar reinforcement positioning device
Technical field
The utility model belongs to building conversion layer technical field of construction, is positioned more particularly to a kind of building conversion layer reinforcing bar Device.
Background technology
From lower part because plane is different using function, which uses different knots from lower part on the top of building floor Structure type, and structure conversion is carried out by the floor, then the floor is known as structural transition layer.
The adjustment permission of conversion layer reinforcing bar is secondary fault-tolerant, is adjusted twice, so that it is guaranteed that reserved steel bar is accurate.It is first fixed When the adjustment of position, wall steel bar is pressed before conversion layer concreting and is not more than 1:6 ratio is adjusted, by reinforcement location It is transferred to the center of the grout sleeve of precast facade, reinforcement location is locked in away from the top of wall with positioning bar later.Reinforcing bar Secondary positioning timing, the number of steel bars positioned is more, if there is positioning speed by the manual method positioned for the first time Spend slow and positioning accuracy difference problem.
Utility model content
The purpose of this utility model is to provide a kind of building conversion layer bar reinforcement positioning device, to solve the positioning of conversion layer reinforcing bar Speed is slow and the problem of positioning accuracy difference.
The technical solution that the utility model solves above-mentioned technical problem is as follows:A kind of building conversion layer bar reinforcement positioning device, It includes:Steel bar positioning plate and embedded frame;The steel bar positioning plate includes substrate and is vertically connected on the side plate on substrate both sides; Substrate location hole and reinforcing bar location hole are set on the substrate;The embedded frame includes the embedded board of rectangular configuration, pre-buried angle Steel and locating rod;The pre-buried angle steel is respectively perpendicular four corner positions for being fixedly connected on embedded board, towards embedded board lower section; The locating rod is respectively perpendicular fixed four corner positions for being connected on embedded board, towards embedded board top;Pre-buried angle steel is embedded in In conversion layer substrustion structure wall;The locating rod of embedded frame is inserted into the substrate location hole of steel bar positioning plate;Utilize reinforcing bar The reinforcing bar location hole of positioning plate positions conversion layer reinforcing bar.
The utility model builds conversion layer bar reinforcement positioning device as described above, further, the number of the substrate location hole Amount is two, and position is corresponding in the locating rod of diagonal position;Alternatively, the quantity of the substrate location hole is four, position It sets corresponding with the locating rod of four corner positions.
The utility model builds conversion layer bar reinforcement positioning device as described above, and further, the substrate further includes positioning Sleeve, abutment sleeve are the small tapered configuration in the big one end in one end, and the diameter of the smaller one end of sleeve is equal with substrate positioning bore dia; The abutment sleeve is fixed on the lower section of substrate location hole.
The utility model builds conversion layer bar reinforcement positioning device as described above, further, is set at the top of the locating rod Helicitic texture is set, the locating rod of embedded frame is inserted into the substrate location hole of steel bar positioning plate, screw is mounted on to the top of locating rod Portion.
The utility model builds conversion layer bar reinforcement positioning device as described above, and further, pre-buried angle steel is under conversion layer Pre-buried depth in layer building structure wall is more than or equal to 200mm;The length of locating rod is more than 100mm.
The utility model has the beneficial effects that:
When carrying out the positioning of conversion layer reinforcing bar, the substrate location hole of steel bar positioning plate is inserted into corresponding locating rod, realizes steel Muscle positioning plate is accurately positioned, and then conversion layer reinforcing bar is sequentially inserted into corresponding reinforcing bar location hole, due to reinforcing bar location hole Position be previously set, in operation be not necessarily to carry out dimensional measurement, accelerate reinforcing bar positioning speed and precision.
Description of the drawings
By being described in detail made by conjunction with the following drawings, the above-mentioned and/or otherwise advantage of the utility model will It becoming more apparent upon and is easier to understand, these attached drawings are only schematical, are not intended to limit the utility model, wherein:
Fig. 1 is a kind of building conversion layer bar reinforcement positioning device construction schematic diagram of embodiment of the utility model;
Fig. 2 is a kind of embedded frame schematic diagram of embodiment of the utility model;
Fig. 3 is a kind of steel bar positioning plate schematic diagram of embodiment of the utility model.
In attached drawing, parts list represented by the reference numerals are as follows:
1, embedded frame, 2, steel bar positioning plate, 3, conversion layer reinforcing bar, 4, template, 5, concrete, 11, embedded board, 12, pre- Bury angle steel, 13, locating rod, 21, substrate, 22, reinforcing bar location hole, 23, substrate location hole, 24, abutment sleeve.
Specific implementation mode
Hereinafter, the embodiment of the building conversion layer bar reinforcement positioning device of the utility model is described with reference to the accompanying drawings.
The embodiment recorded herein is the specific specific implementation mode of the utility model, for illustrating the utility model Design, is explanatory and illustrative, should not be construed as the limit to the utility model embodiment and the scope of the utility model System.In addition to the embodiment recorded herein, those skilled in the art can also be based on the application claims and specification institute is public For the content opened using obvious other technical solutions, these technical solutions include doing using the embodiment to recording herein Go out the technical solution of any obvious substitutions and modifications.
The attached drawing of this specification is schematic diagram, aids in illustrating the design of the utility model, it is schematically indicated each section Shape and its correlation.It note that the structure of each component for the ease of clearly showing the utility model embodiment, respectively It is not drawn according to identical ratio between attached drawing.Identical reference marker is for indicating identical part.
Fig. 1 shows a kind of building conversion layer bar reinforcement positioning device of embodiment of the utility model comprising:Steel bar positioning plate 2 and embedded frame 1;
Steel bar positioning plate 2 includes substrate 21 and the side plate for being vertically connected on 21 both sides of substrate;It is fixed that substrate is set on substrate 21 Position hole 23 and reinforcing bar location hole 22;The effect that two side plates are arranged is prevent wall around during positioning operation fine crushing miscellaneous Object drops down onto substrate, blocks substrate location hole or reinforcing bar location hole;
As shown in Fig. 2, embedded frame 1 includes embedded board 11, pre-buried angle steel 12 and the locating rod 13 of rectangular configuration;Pre-buried angle Steel 12 is respectively perpendicular four corner positions for being fixedly connected on embedded board 11, towards 11 lower section of embedded board;Locating rod 13 is hung down respectively Straight fixed four corner positions for being connected on embedded board 11, towards 11 top of embedded board;Pre-buried angle steel 12 is embedded in conversion layer lower layer In building structure wall, in embodiment as shown in Figure 1, conversion layer substrustion structure wall utilizes template 4 and concrete 5 It carries out pouring completion;
The locating rod 13 of embedded frame 1 is inserted into the substrate location hole 23 of steel bar positioning plate 2;Utilize the steel of steel bar positioning plate 2 Muscle location hole 22 positions conversion layer reinforcing bar 3.In a kind of preferred building conversion layer bar reinforcement positioning device embodiment, in advance It buries pre-buried depth of the angle steel 12 in conversion layer substrustion structure wall and is more than or equal to 200mm;The length of locating rod 13 is more than 100mm。
The building conversion layer bar reinforcement positioning device of above-described embodiment is in construction application, in conversion layer substrustion structural wall When body construction, the pre-buried angle steel of embedded frame is cast in concrete;When carrying out the positioning of conversion layer reinforcing bar, reinforcing bar is determined first The substrate location hole of position plate is inserted into corresponding locating rod, realizes being accurately positioned for steel bar positioning plate, then by conversion layer reinforcing bar according to It is secondary to be inserted into corresponding reinforcing bar location hole, since the position of reinforcing bar location hole is previously set, it is not necessarily to carry out size in operation It measures, accelerates the speed and precision of reinforcing bar positioning.
In a kind of preferred building conversion layer bar reinforcement positioning device embodiment, the quantity of substrate location hole 23 is two, Position is corresponding in the locating rod 13 of diagonal position;Alternatively, the quantity of substrate location hole 23 is four, position and four tops The locating rod 13 of Angle Position is corresponding.The positioning of steel bar positioning plate can be realized using any two locating rod, therefore substrate is fixed Position hole can also be other distribution forms outside above-described embodiment, if the quantity of substrate location hole 23 is two, position with it is arbitrary Two adjacent locating rods 13 are corresponding.
When the substrate location hole of steel bar positioning plate is inserted into corresponding locating rod, due to there is interference around construction site Factor tends not to one-time positioning success.In a kind of preferred building conversion layer bar reinforcement positioning device embodiment, such as Fig. 3 institutes Show, substrate 21 further includes abutment sleeve 24, and abutment sleeve 24 is the small tapered configuration in the big one end in one end, the smaller one end of sleeve it is straight Diameter is equal with 23 diameter of substrate location hole;Abutment sleeve 24 is fixed on the lower section of substrate location hole 23.It is arranged according to above structure, Locating rod is firstly inserted into the abutment sleeve of opening bigger, then leads into substrate location hole using abutment sleeve.
In a kind of preferred building conversion layer bar reinforcement positioning device embodiment, the top of locating rod 13 is threaded knot Structure, the locating rod 13 of embedded frame 1 are inserted into the substrate location hole 23 of steel bar positioning plate 2, screw are mounted on to the top of locating rod 13 Portion.The interim connection that steel bar positioning plate and embedded frame are realized using helicitic texture and screw, is prevented in reinforcing bar position fixing process Fall off displacement.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed and other feature combination, and those skilled in the art are also Other combinations between each technical characteristic can be carried out according to the purpose of invention, be subject to the purpose for realizing the utility model.

Claims (5)

1. a kind of building conversion layer bar reinforcement positioning device, which is characterized in that including:Steel bar positioning plate and embedded frame;The steel Muscle positioning plate includes substrate and is vertically connected on the side plate on substrate both sides;Substrate location hole and reinforcing bar positioning are set on the substrate Hole;The embedded frame includes the embedded board, pre-buried angle steel and locating rod of rectangular configuration;The pre-buried angle steel is respectively perpendicular fixation Four corner positions of embedded board are connected to, towards embedded board lower section;The locating rod is respectively perpendicular fixation and is connected on embedded board Four corner positions, towards embedded board top;Pre-buried angle steel is embedded in conversion layer substrustion structure wall;Embedded frame Locating rod is inserted into the substrate location hole of steel bar positioning plate;Conversion layer reinforcing bar is determined using the reinforcing bar location hole of steel bar positioning plate Position.
2. building conversion layer bar reinforcement positioning device according to claim 1, which is characterized in that the number of the substrate location hole Amount is two, and position is corresponding in the locating rod of diagonal position;Alternatively, the quantity of the substrate location hole is four, position It sets corresponding with the locating rod of four corner positions.
3. building conversion layer bar reinforcement positioning device according to claim 1, which is characterized in that the substrate further includes positioning Sleeve, abutment sleeve are the small tapered configuration in the big one end in one end, and the diameter of the smaller one end of sleeve is equal with substrate positioning bore dia; The abutment sleeve is fixed on the lower section of substrate location hole.
4. building conversion layer bar reinforcement positioning device according to claim 1, which is characterized in that set at the top of the locating rod Helicitic texture is set, the locating rod of embedded frame is inserted into the substrate location hole of steel bar positioning plate, screw is mounted on to the top of locating rod Portion.
5. building conversion layer bar reinforcement positioning device according to claim 1, which is characterized in that pre-buried angle steel is under conversion layer Pre-buried depth in layer building structure wall is more than or equal to 200mm;The length of locating rod is more than 100mm.
CN201721743582.8U 2017-12-14 2017-12-14 Build conversion layer bar reinforcement positioning device Active CN207878799U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721743582.8U CN207878799U (en) 2017-12-14 2017-12-14 Build conversion layer bar reinforcement positioning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721743582.8U CN207878799U (en) 2017-12-14 2017-12-14 Build conversion layer bar reinforcement positioning device

Publications (1)

Publication Number Publication Date
CN207878799U true CN207878799U (en) 2018-09-18

Family

ID=63502281

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721743582.8U Active CN207878799U (en) 2017-12-14 2017-12-14 Build conversion layer bar reinforcement positioning device

Country Status (1)

Country Link
CN (1) CN207878799U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610736A (en) * 2018-11-26 2019-04-12 中冶天工集团有限公司 A kind of mold and its localization method of abutment sleeve reserved steel bar
CN111101655A (en) * 2019-12-19 2020-05-05 中建一局集团第三建筑有限公司 Steel bar positioning device and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610736A (en) * 2018-11-26 2019-04-12 中冶天工集团有限公司 A kind of mold and its localization method of abutment sleeve reserved steel bar
CN111101655A (en) * 2019-12-19 2020-05-05 中建一局集团第三建筑有限公司 Steel bar positioning device and construction method thereof
CN111101655B (en) * 2019-12-19 2021-07-30 中建一局集团第三建筑有限公司 Steel bar positioning device and construction method thereof

Similar Documents

Publication Publication Date Title
CN209636847U (en) A kind of adjustable tower crane built-in fitting accurate positioning tool
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN104695557B (en) Steel structure building construction method for one-step pre-burying of foundation bolts
CN207878799U (en) Build conversion layer bar reinforcement positioning device
CN106639327A (en) Positioning and reinforcing system and method for assembly type building cast-in-place connection layer reserved reinforcing steel bar
CN204645268U (en) A kind of infilled wall tie bar built-in fitting
CN205735482U (en) A kind of structure of fixing built-in fitting
CN109208921A (en) The localization method of building element assembled sleeve embedded bar
CN104110083A (en) One-step-forming pouring construction method of ultrahigh thin wall
CN206616827U (en) One kind box filled piece of built-in line of building
CN202731936U (en) Tunnel inverted arch end mold
CN109779241A (en) A kind of multifunctional wall body formwork root positioning system and its construction method
CN202882438U (en) Cast-in-situ concrete inclined wall and inclined column tumbling barrel
CN103132494B (en) Embedded anchor cone accurate positioning method
CN209509221U (en) Exposed inversion reinforcing bar grout sleeve concrete shear force wall
CN207296429U (en) A kind of cast-in-situ floor thickness control instrument
CN106499180B (en) A kind of novel exterior sheathing is reinforced and external scaffolding drawknot device and its construction method
CN103352568A (en) Method for building constructional column on foundation pad
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN207794321U (en) Monoblock type fills walling steel tie bar embedded part
CN203514778U (en) Wall guide wall template erecting device with adjustable height
CN207582978U (en) A kind of floorslab thickness control device
CN207526143U (en) Slab thickness controls tool during a kind of concreting
CN106285005B (en) Grout construction method at the top of constructional column
CN207314886U (en) Filling walling is built by laying bricks or stones with skin number rope instrument

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 101500 No. 3 science and technology road, Miyun District Economic Development Zone, Beijing

Patentee after: BEIJING URBAN CONSTRUCTION SIXTH GROUP CO., LTD.

Address before: 101500 No. 3 science and technology road, Daxing District Economic Development Zone, Beijing

Patentee before: BEIJING URBAN CONSTRUCTION SIXTH GROUP CO., LTD.

CP02 Change in the address of a patent holder