CN207811107U - A kind of three trolley bridge crane of three beam - Google Patents

A kind of three trolley bridge crane of three beam Download PDF

Info

Publication number
CN207811107U
CN207811107U CN201820082020.1U CN201820082020U CN207811107U CN 207811107 U CN207811107 U CN 207811107U CN 201820082020 U CN201820082020 U CN 201820082020U CN 207811107 U CN207811107 U CN 207811107U
Authority
CN
China
Prior art keywords
girder
trolley
bridge crane
beams
assembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820082020.1U
Other languages
Chinese (zh)
Inventor
董富祥
杨棋剑
宋兴海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG QILONG CRANES CO Ltd
Original Assignee
ZHEJIANG QILONG CRANES CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG QILONG CRANES CO Ltd filed Critical ZHEJIANG QILONG CRANES CO Ltd
Priority to CN201820082020.1U priority Critical patent/CN207811107U/en
Application granted granted Critical
Publication of CN207811107U publication Critical patent/CN207811107U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)
  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)

Abstract

The utility model provides a kind of three trolley bridge crane of three beam, belong to crane field, including trolley assembly, equipped with three beam bridge framves and secondary trolley assembly, the three beam bridges frame includes the first girder, the second girder, third girder of three parallel arrangeds, trolley assembly, which slides, to be installed on two the first girder, the second girder girders, and secondary trolley assembly, which slides, to be installed on two the second girder, third girder girders.Three beams, three trolley bridge crane provided by the utility model, its structure is to be arranged side by side three girders in cart direction, four tracks are set on three girders, major and minor trolley is placed side by side on four tracks, main carriage assembly is set to secondary trolley assembly in two parallel sliding rails, it can make every independently moving dolly or two secondary trolleies by operation while link or linking with three vehicle of main carriage, to meet the different demands of different object handlings.

Description

A kind of three trolley bridge crane of three beam
Technical field
The utility model is related to crane fields, specifically a kind of three trolley bridge crane of three beam.
Background technology
General indoor cranes are single-beam or double girder overhead crane, and structure is single girder, two girders, two butts Beam or several trolleys composition, generally arrange one or two trolleies in girder span direction.Some thin plate coil of strip enterprise, pipe fittings Product handling, overturning, the rotation of manufacturing enterprise.And common double beams double bogies, single crab double hook can not be met the requirements sometimes.
Based on this, the application is made.
Invention content
The purpose of this utility model is to provide a kind of three trolley bridge cranes of three beam, can be in the direction that runs parallel Multiple trolley auxiliary handlings are set, in order to which the enterprise products handlings such as pipe fitting, thin plate coil of strip use.
To achieve the above object, the technical solution adopted in the utility model is as follows:A kind of three trolley bridge crane of three beam, Including trolley assembly, three beam bridge framves and secondary trolley assembly are equipped with, the three beam bridges frame includes the first master of three parallel arrangeds Beam, the second girder, third girder, trolley assembly, which slides, to be installed on two the first girder, the second girder girders, and secondary trolley is total It is installed on two the second girder, third girder girders at sliding.
As further setting:A track is respectively provided on first girder, third girder, the second girder is equipped with two A parallel track, the track both ends are equipped with trolley backstop.
As further setting:First girder, the second girder, third girder both ends be equipped with a trolley, it is above-mentioned The both ends of girder are respectively placed on its corresponding trolley.
As further setting:It is connected as one by tie-beam and free bearing between the trolley.
As further setting:First girder, the second girder both ends bottom be equipped with cart driving mechanism, third master The both ends bottom of beam is equipped with several wheels or cart driving mechanism.
As further setting:The cart driving mechanism structure includes adhesion wheel group, passive wheel group, antitorque holder With the three-in-one driving device being installed on antitorque holder, the fixed peace of the adhesion wheel group, passive wheel group, antitorque holder Bottom loaded on the first girder or the second girder, the rotation axis of adhesion wheel group connect with the drive shaft transmission of three-in-one driving device It connects.
As further setting:The trolley assembly, secondary trolley assembly include lifting mechanism, wheeling mechanism, trolley, Suspension hook, suspension hook are installed on lifting mechanism bottom, and lifting mechanism is installed on trolley frame bottom;Wheeling mechanism is fixedly installed in small On vehicle frame, the trolley uses common twin beams suspension hook trolley.
As further setting:The outer side-lower of first girder or third girder is equipped with and walks on stage, and lower section of walking on stage is equipped with two The I-steel of parallel arrangement is hung with a mobile operator cabin between two I-steel.Drivers' cab can individually press the needs of driver It is moved to any position on girder length direction.
As further setting:The section of first girder, the second girder and third girder is box-structure, big It is small to be all different, it is designed according to its actual use.
As further setting:In on first girder, the second girder one at or two at be equipped with trolley cable power supply Device.
The utility model has the beneficial effect that:One, the utility model is arranged side by side three in crane traffic direction Four tracks, main carriage is arranged in girder on three girders(Trolley in trolley assembly i.e. described above), secondary trolley(On i.e. Trolley in the text secondary trolley assembly)It is placed side by side on four tracks, three trolleies laterally can be lifted longitudinally, be turned over Turn, rotation, to fully meet the use demands such as carrying, turn, the rotational positioning of big part or long part article.Also, major and minor hook (Main hook is the suspension hook being hung on main carriage, auxiliary hook is the suspension hook being hung on secondary trolley)Can carry out independent handling use, Can also handling simultaneously use, compare common twin-spar construction, major and minor trolley has the use degree of freedom and use scope of bigger.
Two, three girders are designed and produced by different cross section structures, utmostly save manufacture steel, and are all box knot Structure, suitable for welding processing on automatic welding machine.
Three, major and minor trolley can be designed by requirement according to different tonnages, can individually handling between major and minor trolley It can cooperate and lift, use scope is wider.
Four, articulated structure is used between the utility model trolley, is convenient to mount and dismount, and installation, maintenance is easy.
Five, the utility model complete machine is integrated, so compared to independent two cranes, cart direction length is shorter, increases Cart directional run;The cooperation of whole suspension hook lifts effect, safety and is all got well than two mutually independent cranes, equipment at This also below two independent cranes.
Description of the drawings
Fig. 1 is the overall schematic of three beam of the utility model, three trolley bridge crane.
Fig. 2 is the structural schematic diagram of three beam of the utility model, three trolley bridge crane.
Fig. 3 is the trolley connection structure diagram of three beam of the utility model, three trolley bridge crane.
Fig. 4 is three beam bridge frame structure charts of three beam of the utility model, three trolley bridge crane.
Fig. 5 is the main beam structure figure of three beam of the utility model, three trolley bridge crane.
Fig. 6 is the cart driving schematic diagram of three beam of the utility model, three trolley bridge crane.
As shown in the figure:1-three beam bridge framves, 2-cart driving mechanisms, 3-main carriage assemblies, 4-secondary trolley assemblies, 5- Pulley cable sliding apparatus, 6-mobile operator cabins, the 7-the first girder, the 8-the second girder, 9-third girders, 10-third platforms Vehicle, 11-tie-beams one, 12-tie-beam free bearings, the 13-the second trolley, 14-tie-beams two, the 15-the first trolley, 16-three Unify driving device, 17-antitorque holders, 18-adhesion wheel groups/passive wheel group.
Specific implementation mode
To make the technical means, creative features, achievement of purpose, and effectiveness of the utility model be easy to understand, below In conjunction with specific implementation mode, the utility model is expanded on further.
As shown in Figure 1, a kind of three trolley bridge crane of three beam, including three beam bridge framves 1, cart driving mechanism 2, main carriage Assembly 3, secondary trolley assembly 4, trolley cable power supply device 5, mobile operator cabin 6.Under the outside of first girder 7 or third girder 9 Side is equipped with and walks on stage, and lower section of walking on stage is equipped with the I-steel of two parallel arrangements, and a mobile operator cabin is hung between two I-steel 6.Drivers' cab can be individually by any position of driver needed to be moved on girder length direction.
In conjunction with shown in Fig. 4,5, three beam bridge framves 11 are mainly by the first girder 7, the second girder 8, third of three parallel arrangeds Girder 9 forms, and the section of the first girder 7, the second girder 8 and third girder 9 is box-structure, and specific size and width are roots According to actual conditions design, in the present embodiment, secondly, third girder 9 is most for the area of section maximum of the second girder 8, the first girder 7 It is small.In conjunction with shown in Fig. 2, it is respectively provided with a track on the first girder 7, third girder 9, sets that there are two parallel on the second girder 8 Track, track both ends are equipped with trolley backstop.Main carriage assembly 3 slide install in the first girder 7,8 two girders of the second girder it On, secondary trolley assembly 4, which slides, to be installed on 9 two the second girder 8, third girder girders.
The bottom of the front and rear ends of first girder 7 is respectively equipped with the bottom of the front and rear ends of the first trolley 15, the second girder 8 The bottom that portion is respectively equipped with the front and rear ends of the second trolley 13, third girder 9 is respectively equipped with third trolley 10(Above total six A trolley).The both ends of first girder 7 are respectively placed on two the first trolleys 15, and the both ends of the second girder 8 are respectively placed in two On a second trolley 13, the both ends of third girder 9 are respectively placed on two third trolleys 10.7 lower section of above-mentioned first girder Two the second trolleys 13 of 8 lower section of two the first trolleys 15 and the second girder are mounted on cart driving mechanism 2.Third girder The third trolley 10 of 9 lower sections is provided only with adhesion wheel and by motor car wheel.First girder 7, the second girder 8 are supplied equipped with trolley cable Electric installation is the power supplies such as main carriage assembly 3, cart driving mechanism 2 and secondary trolley assembly 4.
In conjunction with shown in Fig. 3, it is connected with tie-beam 1 between the first trolley 15 second trolley 13 adjacent thereto, second It is connected with tie-beam 2 14 between the third trolley 10 adjacent thereto of vehicle 13.Tie-beam 1, tie-beam 2 14 both ends pass through Tie-beam free bearing 12 is connect with 13/ third trolley 10 of the first 15/ second trolley of trolley, and tie-beam 1, tie-beam 2 14 will be same The first trolley 15, the second trolley 13 of side are connected with third trolley 10, to make three beam bridge framves 1 be connected as one.
In conjunction with shown in Fig. 6,2 structure of cart driving mechanism includes adhesion wheel group 18, passive wheel group 18, antitorque holder 17 With the three-in-one driving device 16 being installed on antitorque holder 17, adhesion wheel group 18, passive wheel group 18, antitorque holder 17 are equal It is fixedly installed in the bottom of the first girder 7 or the second girder 8, the rotation axis of adhesion wheel group 18 and three-in-one driving device 16 Drive shaft is sequentially connected.
Trolley assembly, secondary trolley assembly 4 include lifting mechanism, wheeling mechanism, trolley, suspension hook, and suspension hook has been installed on Actuator base is risen, lifting mechanism is installed on trolley frame bottom.Wheeling mechanism is fixedly installed on trolley frame, and trolley is using general Logical twin beams suspension hook trolley.
The present embodiment crane course of work is as follows:
Cart driving mechanism 2 starts task driven the first trolley 15, the second trolley 13 slides on the track of workshop, due to Third trolley 10 has been connected as one by tie-beam 2 14 and the second trolley 13, therefore third trolley 10 and the first trolley 15,13 synchronous slide of the second trolley, be placed on the first trolley 15, the second trolley 13 on third trolley 10 the first girder 7, the Two girders 8, third girder 9 are driven movement.After three beam bridge framves 1 are moved to operating position, cart driving mechanism 2 stops work Make, the driver in mobile operator cabin 6 manipulates the secondary trolley assembly 4 of main carriage assembly 3, two along the first girder 7, the second girder 8, the tracks travel on third girder 9 then passes through the suspension hook on the mechanism controls trolley assembly such as lifting mechanism to designated position Decentralization.After waiting for that cargo is connect with suspension hook, then lifting mechanism rising is controlled, cargo is risen.Then, secondary control is big again by driver Vehicle driving mechanism 2 works, and three beam bridge framves 1 of driving are moved to setting point, and cargo is transferred.
In the above process:1. the main carriage of main carriage assembly 3 is on the track on the first girder 7, the second girder 8 along master Beam length direction moves.2. two secondary trolleies are on the track on the second girder 8, third girder 9 along girder length direction Move, can with every independently moving dolly, can also two secondary trolleies link simultaneously, or with the linkage of three vehicle of main carriage.3. The hoisting motor positive and negative rotation of main carriage, secondary trolley, to realize main hook, two auxiliary hook raisings or decline, main hook, auxiliary hook can be with Independent raising or decline, can also two or three suspension hook linkage liftings.4. cart driving motor positive and negative rotation realizes that whole is risen Heavy-duty machine is moved back and forth along cart orbital direction.
Based on above-mentioned, three beams, three trolley bridge crane provided by the utility model, structure be cart direction side by side It arranges three girders, four tracks is set on three girders, and major and minor trolley is placed side by side on four tracks, by main carriage Assembly 3 is set to secondary trolley assembly 4 in two parallel sliding rails, can make every independently moving dolly or two by operation Secondary trolley links or links with three vehicle of main carriage simultaneously, to meet the different demands of different object handlings, stable structure, It operates steadily, the article handling particularly suitable for long part, big part uses.
As known by the technical knowledge, the utility model can pass through other essence without departing from its spirit or the reality of essential feature Scheme is applied to realize.Therefore, embodiment disclosed above, all things considered are all merely illustrative, and are not only 's.All changes that come within the scope of the invention or equivalents of the invention are by the utility model packet Contain.

Claims (9)

1. a kind of three trolley bridge crane of three beam, including trolley assembly, it is characterised in that:It is total equipped with three beam bridge framves and secondary trolley At the three beam bridges frame includes the first girder, the second girder, third girder of three parallel arrangeds, and trolley assembly slides peace On two the first girder, the second girder girders, secondary trolley assembly, which slides, to be installed in two the second girder, third girder masters Liang Shang.
2. one kind as described in claim 1 three beams, three trolley bridge crane, it is characterised in that:First girder, third It is respectively provided with a track on girder, is set on the second girder there are two parallel track, the track both ends are equipped with trolley backstop.
3. one kind as described in claim 1 three beams, three trolley bridge crane, it is characterised in that:First girder, second Girder, third girder both ends be equipped with a trolley, the both ends of above-mentioned girder are respectively placed on its corresponding trolley.
4. one kind as claimed in claim 3 three beams, three trolley bridge crane, it is characterised in that:Pass through company between the trolley It connects beam and free bearing is connected as one.
5. one kind as described in claim 1 three beams, three trolley bridge crane, it is characterised in that:First girder, second The both ends bottom of girder is equipped with cart driving mechanism, the both ends bottom of third girder is equipped with several wheels or cart driving mechanism.
6. one kind as claimed in claim 5 three beams, three trolley bridge crane, it is characterised in that:The cart driving mechanism knot Structure includes adhesion wheel group, passive wheel group, antitorque holder and the three-in-one driving device being installed on antitorque holder, the master Motor car wheel group, passive wheel group, antitorque holder are fixedly installed in the bottom of the first girder or the second girder, adhesion wheel group The drive shaft of rotation axis and three-in-one driving device is sequentially connected.
7. one kind as described in claim 1 three beams, three trolley bridge crane, it is characterised in that:The trolley assembly, pair are small Vehicle assembly includes lifting mechanism, wheeling mechanism, trolley, suspension hook, and suspension hook is installed on lifting mechanism bottom, lifting mechanism installation In trolley frame bottom;Wheeling mechanism is fixedly installed on trolley frame, and the trolley uses common twin beams suspension hook trolley.
8. one kind as described in claim 1 three beams, three trolley bridge crane, it is characterised in that:First girder or third girder Outer side-lower be equipped with and walk on stage, lower section of walking on stage is equipped with the I-steel of two parallel arrangements, is hung with a shifting between two I-steel Dynamic drivers' cab.
9. three trolley bridge crane of a kind of three beam as described in any of the claims 1 to 8, it is characterised in that:First master The section of beam, the second girder and third girder is box-structure, and size is all different, and is designed according to its actual use.
CN201820082020.1U 2018-01-17 2018-01-17 A kind of three trolley bridge crane of three beam Active CN207811107U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820082020.1U CN207811107U (en) 2018-01-17 2018-01-17 A kind of three trolley bridge crane of three beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820082020.1U CN207811107U (en) 2018-01-17 2018-01-17 A kind of three trolley bridge crane of three beam

Publications (1)

Publication Number Publication Date
CN207811107U true CN207811107U (en) 2018-09-04

Family

ID=63324161

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820082020.1U Active CN207811107U (en) 2018-01-17 2018-01-17 A kind of three trolley bridge crane of three beam

Country Status (1)

Country Link
CN (1) CN207811107U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109019325A (en) * 2018-10-22 2018-12-18 国家电网有限公司 Easy-to-mount bridge crane displacement major-minor trolley

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109019325A (en) * 2018-10-22 2018-12-18 国家电网有限公司 Easy-to-mount bridge crane displacement major-minor trolley

Similar Documents

Publication Publication Date Title
CN110053933B (en) Electric power and free car group conveyor
CN105751954B (en) A kind of plate obstacles removing car
CN106627603B (en) A kind of multimodal transport intercommunication control system
CN101323415A (en) Crossing type double trolley bridge type crane
CN111153309A (en) Combined and independent hybrid drive double-car elevator and driving method thereof
CN207877135U (en) A kind of wheel-track type girder gantry crane
CN201292213Y (en) Mechanically lift roll-over crane
CN207811107U (en) A kind of three trolley bridge crane of three beam
CN202429920U (en) Multi-trolley and double-girder gantry crane
CN201882783U (en) Crane for hoisting concrete finished blank body
CN202465099U (en) Single-girder partial hanging gantry crane
CN209873593U (en) Bridge erecting machine
CN210710412U (en) Device is striden in driving
CN111056245A (en) Overhead trolley conveying system for side wall of body-in-white
CN1010237B (en) Synchronous long-rail positioning hoister
CN208604495U (en) A kind of Bridge Erector low level trolley
CN214141300U (en) Special double-beam bridge crane for metallurgy
CN107724193B (en) Turning correction type turnout for running surface of suspension type monorail traffic system
CN205873697U (en) Control hoist rise to rise with differential actuating mechanism of mixture of dolly sideslip
CN202193562U (en) Manual chain bridge crane with I-shaped steel track
CN202201632U (en) Double-rail travelling trolley
CN201362255Y (en) Two-way track transport vehicle
CN100534890C (en) Bridge type lifting composite device for car body transportation
CN219363044U (en) Double-beam multi-hoisting trolley gantry crane
CN101734558A (en) Metallurgy hopper bridge crane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant