CN207794696U - One kind moving plug-type reinforcing steel processing shed - Google Patents
One kind moving plug-type reinforcing steel processing shed Download PDFInfo
- Publication number
- CN207794696U CN207794696U CN201820160547.1U CN201820160547U CN207794696U CN 207794696 U CN207794696 U CN 207794696U CN 201820160547 U CN201820160547 U CN 201820160547U CN 207794696 U CN207794696 U CN 207794696U
- Authority
- CN
- China
- Prior art keywords
- reinforcing steel
- canopy
- steel processing
- processing shed
- raw material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model belongs to technical field of building construction, plug-type reinforcing steel processing shed is moved more particularly to one kind, it solves under the long distance constructions environment such as subway or road, reinforcing steel processing shed assembles, dismounting, it is mobile more difficult, and it can not effectively meet the problem of protecting processing former material and finished product, canopy is stored including raw material, reinforcing steel processing shed and products storage canopy, raw material stores canopy and products storage canopy is separately positioned on the both sides of reinforcing steel processing shed, the width of reinforcing steel processing shed, height is all higher than the height of raw material storage canopy and products storage canopy, width, raw material stores canopy, reinforcing steel processing shed and products storage canopy bottom are both provided with traveling wheel, traveling wheel is arranged in orbit, raw material stores canopy and products storage canopy and can be moved in reinforcing steel processing shed.The utility model solves under long distance construction environment, and reinforcing steel processing shed can not move and effectively meet the problem of protecting processing former material and finished product.
Description
Technical field
The utility model belongs to technical field of building construction, and in particular to one kind moving plug-type reinforcing steel processing shed.
Background technology
The reinforcing steel processing shed of standard system is widely used in construction technical field of auxiliary equipment in recent years, in reinforcing bar plus
The working environment for providing processing space safety and comfort in one's power during work for construction personnel, is ensureing processing equipment safety in production etc. just
Face embodies preferable economy and social value.
Common reinforcing steel processing shed is mainly set up by steel pipe scaffold or is steel structure member assembly type, and machining shed top is set
Double-protection measure is set, takes into account side protection by increasing topside area, main support upright bar is needed through foundation bolt and base
Plinth is reliably connected, to ensure machining shed monolithic stability.Traditional reinforcing steel processing shed is primarily present following three points deficiency:1. due to upper
Layer heavy construction, basis connection and component connection need to be sufficiently tight, easily can not be moved and be reused;2. can be effective
Construction personnel and equipment are protected, but for processing former material and process finished product protection effect it is little;3. it is double-deck or
The top protection reinforcement shed of multilayer it is not high in building height but along the line construction or place range it is larger when cannot play reality
Effectiveness is continuously increased with the path of construction, the freight brought by fixed steel bars machining shed constantly increases more apparent.
Invention content
In order to solve under the long distance constructions environment such as subway or road, reinforcing steel processing shed assembling, moves at dismounting the utility model
It is dynamic more difficult, and can not effectively meet the problem of protecting processing former material and finished product, it provides a kind of removable plug-type
Reinforcing steel processing shed.
The utility model is achieved by the following technical solution:One kind moving plug-type reinforcing steel processing shed, including original
Material storage canopy, reinforcing steel processing shed and products storage canopy, raw material storage canopy and products storage canopy are separately positioned on reinforcing steel processing shed
Both sides, the width of reinforcing steel processing shed, height, the width for being highly all higher than raw material storage canopy and products storage canopy, raw material storage canopy,
Reinforcing steel processing shed and products storage canopy bottom are both provided with traveling wheel, and traveling wheel is arranged in orbit, and raw material stores canopy and finished product
Storage shed can move in reinforcing steel processing shed.
Raw material storage canopy is identical with the structure and specification of products storage canopy, includes the first frame body of several spaced sets,
It is separately connected the upper beam and bottom end rail for being useful for being fixed to each other between first frame body, is provided at the top of several first frame bodies for sealing
The arc ceiling closed.
First frame body includes arc-shaped the first truss, and the first truss both ends are symmetrically arranged with the first column, the first column
Bottom is fixed with the first traveling wheel, and the first traveling wheel is arranged in the first track, and the first track is fixed on concrete ground.
Reinforcing steel processing shed includes the second frame body of several spaced sets, is separately connected and is useful for mutually admittedly between the second frame body
Fixed upper beam and bottom end rail, several second frame bodies tops are provided with for closed arc ceiling.
Second frame body includes arc-shaped the second truss, and the second truss both ends are symmetrically arranged with the second column, the second column
Bottom is fixed with several second traveling wheels, and the second traveling wheel is arranged in the second track, the second track be fixed on concrete ground and
The spacing of second track is more than the spacing of the first track.
The bolt that first frame body is both provided with limit in the both ends of raw material storage canopy and products storage canopy in place positions dress
It sets.
Second frame body is in the bolt positioning device for being both provided with limit positioned at the both ends of reinforcing steel processing shed.
Ceiling is color steel material.
Raw material stores the storage that canopy is used for raw material, and reinforcing steel processing shed is used for the processing of reinforcing bar, and products storage canopy is for processing
The storage of finished product reinforcing bar afterwards, three, which cooperates, realizes the integration processing of reinforcing bar.Raw material store canopy, reinforcing steel processing shed and at
Product storage shed can be realized by the traveling wheel of its bottom and be moved, wherein raw material stores up in the case where bolt positioning device does not lock
Depositing canopy and products storage canopy can move to reinforcing steel processing shed direction respectively.It, can when needing to lift raw material into raw material storage canopy
Raw material storage canopy is moved into reinforcing steel processing shed, the two is made to form the state of overlapping, further can directly will by hanging device
Raw material is discharged into the rational position of storage, and after the completion of waiting for discharging, raw material storage canopy is removed out of reinforcing steel processing shed;Together
Reason can be by reinforcing steel processing shed to raw material storage canopy side movement after reinforcing bar completes processing in reinforcing steel processing shed, while will be at
Product storage shed moves in the opposite direction, is directly hung in finished product after processing is completed in products storage canopy using crane, into
One step, which moves products storage canopy, to be resetted;It, can be by products storage canopy to steel bar meter when needing to utilize finished product
It moves in canopy, directly finished product is lifted using crane, again reset products storage canopy after rigging out.
The utility model simple structure and reasonable design, has the advantages that compared with prior art:
The utility model adds traditional stationary type reinforcing steel bar machining shed improvement for the three-stage reinforcing bar of all removable push-and-pulls
Builder's temporary shed solves the problems, such as that traditional reinforcing steel processing shed can not be moved easily and reuse;Three-stage reinforcing steel processing shed includes original
Material storage canopy, reinforcing steel processing shed and products storage canopy solve former material stacking, material processing and finished product and stack three vital points, full
The problem of traditional reinforcing steel processing shed of foot can not well protect former material and finished product;The utility model is easy to operate, passes through frame
The push-and-pull convenient material handling of body is marched into the arena to the unified arrangement protection of finished product appearance from former material, is greatly reduced to material protection
Input;The unified arrangement of functions subregion is greatly facilitated construction production by the utility model, and the time is had bad luck in saving;This reality
It is the adjustable shape opened with novel the have Eagle frame wheel of fixed limit function and the frame body bolt positioning device of quadrangle
Formula ensures that frame body has the function of to ensure that the stability of frame body while push-and-pull move, improves overall security;This practicality is new
The groove steel rail of type is removable to be lengthened, and is facilitated assembly and disassembly by way of being welded with expansion bolt, can be adjusted according to condition of construction
It is whole, stock ground distance construction scene hypertelorism when solving the problems, such as to construct along the line.The bolt positioning device of the utility model is by steel
Pipe and round steel are made, and former material is simple and convenient, special-less process, environmentally protective using engineering waste material processing and fabricating;This reality
It can ensure that the protection to process each stage, the design of arc are convenient with color steel ceiling with novel top square steel truss
The discharge of rainwater, and avoid the delay of rainwater in basis instrument gutter.The three parts frame body of the utility model can push-and-pull move,
Double-protection is also served as after can merging when top protection is more demanding, security protection is further increased by increasing frame body quantity
Effect.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural schematic diagram of the first frame body in Fig. 1;
Fig. 3 is the structural schematic diagram of the second frame body in Fig. 1;
Fig. 4 is the structural schematic diagram of the first frame body and the second frame body relative position;
Fig. 5 is the structural representation front view of bolt positioning device in Fig. 2;
Fig. 6 is the structural representation side view of bolt positioning device in Fig. 2.
In figure:1- raw materials storage canopy, 2- reinforcing steel processing sheds, 3- products storage canopies, the first frame bodies of 4-, the first columns of 4.1-,
The first truss of 4.2-, the second frame bodies of 5-, the second columns of 5.1-, the second truss of 5.2-, 6- ceilings, 7- traveling wheels, 7.1- the first rows
Walk wheel, the second traveling wheels of 7.2-, 8- tracks, the first tracks of 8.1-, the second tracks of 8.2-, 9- bottom end rails, 10- bolts positioning dress
It sets, 11- concretes ground, 12- upper beams.
Specific implementation mode
The utility model is further elaborated in referring to Fig.1~Fig. 6, and one kind moving plug-type reinforcing steel processing shed, packet
Raw material storage canopy 1, reinforcing steel processing shed 2 and products storage canopy 3 are included, raw material storage canopy 1 and products storage canopy 3 are separately positioned on reinforcing bar
The both sides of machining shed 2, the width of reinforcing steel processing shed 2, height, the width for being highly all higher than raw material storage canopy 1 and products storage canopy 3
Degree, raw material storage canopy 1, reinforcing steel processing shed 2 and 3 bottom of products storage canopy are both provided with traveling wheel 7, and traveling wheel 7 is arranged in track 8
Interior, raw material storage canopy 1 and products storage canopy 3 can move in reinforcing steel processing shed 2.
Raw material storage canopy 1 is identical with the structure and specification of products storage canopy 3, includes the first frame body of several spaced sets
4, the upper beam 12 for being useful for being fixed to each other and bottom end rail 9, the 4 top setting of several first frame bodies are separately connected between the first frame body 4
It is useful for closed arc ceiling 6.Reinforcing steel processing shed 2 includes the second frame body 5 of several spaced sets, divides between the second frame body 5
It is not connected with the upper beam 12 and bottom end rail 9 for being fixed to each other, 5 top of several second frame bodies is provided with for closed arc
Ceiling 6, arc ceiling 6 help to prevent that ponding situation occurs at the top of the utility model.
When the utility model is installed, concrete ground 11 need to be first carried out, and draining is applied respectively in the both sides of reinforcing steel processing shed 2
Track 8 is arranged in ditch, the width that canopy 1, reinforcing steel processing shed 2 and products storage canopy 3 are further stored according to raw material, and track 8 can be used
Channel steel, and track 8 is fixed on concrete ground 11 using expansion bolt, the expansion bolt for trapped orbit 8 need to ensure track 8
It is firm, specific spacing need to according to calculate obtain, and interval must not exceed 1.2 meters.
The first frame body 4 as frame support and the second frame body 5, the first frame body 4 include the first arc-shaped truss
4.2,4.2 both ends of the first truss are symmetrically arranged with the first column 4.1, and 4.1 bottom of the first column is fixed with the first traveling wheel 7.1,
First traveling wheel 7.1 is arranged in the first track 8.1, and the first track 8.1 is fixed on concrete ground 11.Second frame body 5 is including being in
Second truss 5.2 of arc, 5.2 both ends of the second truss are symmetrically arranged with the second column 5.1, and 5.1 bottom of the second column is fixed with
Several second traveling wheels 7.2, the second traveling wheel 7.2 are arranged in the second track 8.2, and the second track 8.2 is fixed on concrete ground 11
Upper and the second track 8.2 spacing is more than the spacing of the first track 8.1.Wherein under the first column 4.1 and the second column 5.1
The traveling wheel 7 being just respectively welded is the Eagle frame wheel with fixed limit function.
Meanwhile first frame body 4 at the both ends for storing canopy 1 and products storage canopy 3 positioned at raw material be both provided with inserting for limit
Pin positioning device for use 10, the second frame body 5 is in the bolt positioning device 10 for being both provided with limit positioned at the both ends of reinforcing steel processing shed 2.
The bolt positioning device 10 of the utility model is made by perforative round steel in steel pipe and steel pipe, and former material is simple and convenient, no spy
Different technique, using engineering waste material processing and fabricating.When making, steel-pipe welding can be fixed on and be added positioned at raw material storage canopy 1, reinforcing bar
On the end column of builder's temporary shed 2 and products storage canopy 3, while being fixed with bench drill on preset 11 fixed position of concrete ground
Hole further utilizes round steel to be inserted into 11 mounting hole of concrete ground and realizes raw material storage canopy 1, reinforcing steel processing shed 2 and products storage canopy 3
Positioning.
Further, raw material storage canopy 1, reinforcing steel processing shed 2 and products storage canopy 3 are not locked in bolt positioning device 10
In the case of, can by traveling wheel 7 arranged at the bottom realize move, wherein raw material storage canopy 1 and products storage canopy 3 can respectively to
It moves in 2 direction of reinforcing steel processing shed.When needing to lift raw material into raw material storage canopy 1, raw material can be stored to canopy 1 to steel bar meter
2 direction of canopy is moved, and the two is made to form the state of overlapping, and further raw material directly can be discharged into raw material by hanging device stores canopy
Raw material after the completion of waiting for discharging, is stored canopy 1 from the interior removal of reinforcing steel processing shed 2 and is positioned using bolt by rational deposit position in 1
Device 10 repositions raw material storage canopy 1;It similarly, can be by reinforcing bar after reinforcing bar completes processing in reinforcing steel processing shed 2
Machining shed 2 is moved to 1 side of raw material storage canopy, while products storage canopy 3 being moved in the opposite direction, directly will using crane
Finished product after processing is completed is hung in out of reinforcing steel processing shed 2 to products storage canopy 3, is further deposited reinforcing steel processing shed 2 and finished product
The movement of canopy 3 is put to reset;When needing to be constructed using finished product, products storage canopy 3 can be moved into reinforcing steel processing shed 2
It is dynamic, directly finished product is lifted using crane, again resets products storage canopy 3 after rigging out.
Further, to improve management, the upper of canopy 1, reinforcing steel processing shed 2 and products storage canopy 3 can be stored in raw material respectively
12 position of crossbeam hangs placard, and the poster frame for fixing placard ensure that the steady of top structure by the making of small size square steel
It is fixed, safe practice poster frame can also be also served as while being protected as side, lifting construction place image further increases
The awareness of safety of construction personnel promotes safety in production.
It, can be by track advancing 8 and by raw material due to distance of constructing under the long distance constructions environment such as subway or road
It stores after canopy 1, reinforcing steel processing shed 2 and products storage canopy 3 move to required position or dismantle the utility model in required position
It sets and carries out secondary use after re-assemblying.
Claims (8)
1. one kind moving plug-type reinforcing steel processing shed, including raw material stores canopy(1), reinforcing steel processing shed(2)With products storage canopy
(3), it is characterised in that:Raw material stores canopy(1)With products storage canopy(3)It is separately positioned on reinforcing steel processing shed(2)Both sides, reinforcing bar
Machining shed(2)Width, be highly all higher than raw material storage canopy(1)With products storage canopy(3)Height, width, raw material store canopy
(1), reinforcing steel processing shed(2)With products storage canopy(3)Bottom is both provided with traveling wheel(7), traveling wheel(7)It is arranged in track(8)
Interior, raw material stores canopy(1)With products storage canopy(3)It can be in reinforcing steel processing shed(2)Interior movement.
2. a kind of removable plug-type reinforcing steel processing shed according to claim 1, it is characterised in that:Raw material stores canopy(1)
With products storage canopy(3)Structure and specification it is identical, include the first frame body of several spaced sets(4), the first frame body(4)Between
It is separately connected the upper beam for being useful for being fixed to each other(12)And bottom end rail(9), several first frame bodies(4)Top is provided with for sealing
The arc ceiling closed(6).
3. a kind of removable plug-type reinforcing steel processing shed according to claim 2, it is characterised in that:First frame body(4)Packet
Include the first arc-shaped truss(4.2), the first truss(4.2)Both ends are symmetrically arranged with the first column(4.1), the first column
(4.1)Bottom is fixed with the first traveling wheel(7.1), the first traveling wheel(7.1)It is arranged in the first track(8.1)It is interior, the first track
(8.1)It is fixed on concrete ground(11)On.
4. a kind of removable plug-type reinforcing steel processing shed according to claim 1, it is characterised in that:Reinforcing steel processing shed(2)
The second frame body including several spaced sets(5), the second frame body(5)Between be separately connected the upper beam for being useful for being fixed to each other
(12)And bottom end rail(9), several second frame bodies(5)Top is provided with for closed arc ceiling(6).
5. a kind of removable plug-type reinforcing steel processing shed according to claim 4, it is characterised in that:Second frame body(5)Packet
Include the second arc-shaped truss(5.2), the second truss(5.2)Both ends are symmetrically arranged with the second column(5.1), the second column
(5.1)Bottom is fixed with several second traveling wheels(7.2), the second traveling wheel(7.2)It is arranged in the second track(8.2)It is interior, second
Track(8.2)It is fixed on concrete ground(11)Upper and the second track(8.2)Spacing be more than the first track(8.1)Spacing.
6. a kind of removable plug-type reinforcing steel processing shed according to claim 2 or 3, it is characterised in that:First frame body(4)
Canopy is being stored positioned at raw material(1)With products storage canopy(3)Both ends be both provided with the bolt positioning device of limit(10).
7. a kind of removable plug-type reinforcing steel processing shed according to claim 4 or 5, it is characterised in that:Second frame body(5)
Positioned at reinforcing steel processing shed(2)Both ends be both provided with the bolt positioning device of limit(10).
8. a kind of removable plug-type reinforcing steel processing shed according to claim 2 or 4, it is characterised in that:Ceiling(6)For coloured silk
Steel plate material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820160547.1U CN207794696U (en) | 2018-01-31 | 2018-01-31 | One kind moving plug-type reinforcing steel processing shed |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820160547.1U CN207794696U (en) | 2018-01-31 | 2018-01-31 | One kind moving plug-type reinforcing steel processing shed |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207794696U true CN207794696U (en) | 2018-08-31 |
Family
ID=63268491
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820160547.1U Active CN207794696U (en) | 2018-01-31 | 2018-01-31 | One kind moving plug-type reinforcing steel processing shed |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207794696U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108910369A (en) * | 2018-09-14 | 2018-11-30 | 北京城建五建设集团有限公司 | One kind pushing and pulling closed atomizing refuse depot and its construction method entirely |
CN109763681A (en) * | 2019-02-26 | 2019-05-17 | 中国葛洲坝集团第一工程有限公司 | Navigation & Hydropower Junction Engineering construction of hydropower integrated arrangement method and reinforcement yard |
CN110005229A (en) * | 2019-05-08 | 2019-07-12 | 五冶集团上海有限公司 | A kind of construction site movable type machining shed |
CN110593606A (en) * | 2019-07-24 | 2019-12-20 | 济南轨道交通集团有限公司 | Totally-enclosed combined multifunctional movable work shed system |
CN110778153A (en) * | 2019-10-29 | 2020-02-11 | 武汉一冶建筑安装工程有限责任公司 | Construction site material processing shed |
-
2018
- 2018-01-31 CN CN201820160547.1U patent/CN207794696U/en active Active
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108910369A (en) * | 2018-09-14 | 2018-11-30 | 北京城建五建设集团有限公司 | One kind pushing and pulling closed atomizing refuse depot and its construction method entirely |
CN108910369B (en) * | 2018-09-14 | 2024-03-26 | 北京城建五建设集团有限公司 | Full-push-pull closed spray type garbage station and construction method thereof |
CN109763681A (en) * | 2019-02-26 | 2019-05-17 | 中国葛洲坝集团第一工程有限公司 | Navigation & Hydropower Junction Engineering construction of hydropower integrated arrangement method and reinforcement yard |
CN110005229A (en) * | 2019-05-08 | 2019-07-12 | 五冶集团上海有限公司 | A kind of construction site movable type machining shed |
CN110593606A (en) * | 2019-07-24 | 2019-12-20 | 济南轨道交通集团有限公司 | Totally-enclosed combined multifunctional movable work shed system |
CN110778153A (en) * | 2019-10-29 | 2020-02-11 | 武汉一冶建筑安装工程有限责任公司 | Construction site material processing shed |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207794696U (en) | One kind moving plug-type reinforcing steel processing shed | |
CN104695337B (en) | Self-lifting sliding and turnover construction system and construction method | |
CN103924527B (en) | System-frame integrated highway beam yard arrangement structure and construction method thereof | |
CN203347251U (en) | Movable protective canopy for road-spanning construction | |
CN110130937B (en) | Tunnel construction trolley | |
CN108265615A (en) | A kind of assembled H profile steel trestle plate | |
CN106351180A (en) | Full hydraulic opening self-propelled template system for aqueduct | |
CN105908960A (en) | Construction rack for construction of high and large space | |
CN106976157A (en) | A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape | |
CN109404010A (en) | A kind of aluminum tunnel modular system and its operating method | |
CN103410101A (en) | Tower crane conversion method for construction of parabola-shaped ultrahigh pier | |
CN204343153U (en) | Multiplex sequential production just girder construction | |
CN209083287U (en) | A kind of section of track well system based on Subway Stop line | |
CN207862973U (en) | A kind of simple trolley formwork system of concrete pipe gallery | |
CN208151837U (en) | A kind of assembled H profile steel trestle plate | |
CN111140254A (en) | Full-circle double-lining inverted arch construction template system for long-distance tunnel and template transferring method | |
CN207260156U (en) | It is a kind of to lift steel trestle device for what large volume grinding coagulation soil put in storage | |
CN206233115U (en) | A kind of supporting bracket of bridge construction | |
CN213356779U (en) | Overweight steel column translation transportation installation device | |
CN107965170A (en) | Distribution box protection canopy with assembling type base | |
CN211257769U (en) | Truss bridging based on attached lifting platform | |
CN209469044U (en) | A kind of packaged type protection canopy stored up convenient for material with processing | |
CN203822326U (en) | Reinforcing system for single-arch and large-span type shallowly buried and darkly excavated tunnel | |
CN208023608U (en) | A kind of post-cast strip can have enough to meet the need steel channel formwork system | |
CN209339578U (en) | It is a kind of be built in hoistway packaged type protection and operating platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |