CN207794062U - Compound underground anti-seepage swelling cob wall - Google Patents

Compound underground anti-seepage swelling cob wall Download PDF

Info

Publication number
CN207794062U
CN207794062U CN201721780778.4U CN201721780778U CN207794062U CN 207794062 U CN207794062 U CN 207794062U CN 201721780778 U CN201721780778 U CN 201721780778U CN 207794062 U CN207794062 U CN 207794062U
Authority
CN
China
Prior art keywords
isolation
seepage
swelling
layer
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
CN201721780778.4U
Other languages
Chinese (zh)
Inventor
张畅
唐强
许可
陆聪
高琰
傅丽
高静祎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Rui Rui Analytical Instrument Technology Co Ltd
Suzhou University
Shandong Polytechnic College
Original Assignee
Shandong Rui Rui Analytical Instrument Technology Co Ltd
Suzhou University
Shandong Polytechnic College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=63281331&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN207794062(U) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Shandong Rui Rui Analytical Instrument Technology Co Ltd, Suzhou University, Shandong Polytechnic College filed Critical Shandong Rui Rui Analytical Instrument Technology Co Ltd
Priority to CN201721780778.4U priority Critical patent/CN207794062U/en
Application granted granted Critical
Publication of CN207794062U publication Critical patent/CN207794062U/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The compound underground anti-seepage swelling cob wall of the utility model, belong to contaminated site isolation recovery technique field, including matrix and isolation features layer, isolation features are placed on the inside of matrix, matrix, which is sprayed by bentonite siccative in slurry coat method, to harden, isolation features layer is tiled by several flexibility function layers, the flexibility function layer lower suspension variable weights of the bottom.The utility model can be according to the specific pollution condition in required isolation place, the effective isolation adsorbed film of selection and the suitable number of plies, keep design more targeted, wall inherently has certain impermeability, isolation features layer has prodigious isolation adsorption capacity, multiple different isolation adsorbed films that the leaching that can effectively obstruct mixed pollutants is used in combination pollutant.

Description

Compound underground anti-seepage swelling cob wall
Technical field
The utility model belongs to contaminated site isolation recovery technique field, and in particular to a kind of compound underground anti-seepage swelling Cob wall.
Background technology
City is industrial production and life compact district, and since the beginning of the eighties in last century, Urbanization in China is very fast Speed, industry relatively lag behind with municipal and environment-friendly infrastructure construction and operation management level, and China's Urban Underground water and soil is caused to pollute Getting worse.The definition of soil pollution is:Since harmful, noxious material that mankind's activity generates enter soil, run up to certain Degree from net energy is to lead to soil property and mass change more than soil itself, constitute influence to human body and ecological environment and Harm.According to《National Soil Pollution Investigation bulletin》(2014), soil total point exceeding standard rate in China's is up to 16.1%, due to It drenches with rain and necessarily leads to the percolate containing oxious component the effects that washing away, if do not taken effective seepage control measure, percolate meeting It is migrated with the seepage flow of underground water, pollutes pollution ecological around place.
There are three main sources for China's Urban Underground water and soil pollution:(1) urban industry enterprise dismantles and move to another place that leave contaminated sites tight Weight.Urban land is in short supply, and a large amount of poisonous and harmful industrial sites moved or discarded are utilized by redevelopment, and former industrial pollution place is such as Do not carry out effectively assessment and control measures, easily periphery water and soil is caused to seriously affect.(2) ten hundreds of chemicals storage caverns and The storage facilities such as storage tank farm leak direct polluted underground water soil.These storage facilities often because design improper, operation management be not good at or Ageing equipment becomes the direct pollution sources of Urban Underground water and soil environment.China's refined oil Kuku holds up to 78,000,000 cubes within 2015 Rice, about 600,000 tons of oil cause serious pollution through approach such as run, drip, leak every year.(3) city centralization offal treatment Place pollution prevention level is relatively low, causes that water and soil is circumferentially descended seriously to pollute.Existing more than 1000 seat of city solid waste landfill site in China, Separately there are the up to ten thousand simple stockyards of city solid waste.China's consumer waste landfill percolate yield is high, is percolated output of fluid and amount of landfill Ratio can reach 30% or so (U.S. is only 5% or so).Hangzhou, Nanjing, Suzhou, Shanghai, Xi'an, six, Shenzhen city Typical percolate from garbage filling field pollutant kind and concentration are shown in Table 1.
Pollutant component and concentration (mg/L) in 1.6 Landfills of table
Landfill Leachate Pollutants include mainly 3 types:(1) water soluble organic substance, be represented by COD (COD) or Total organic carbon (TOC), including volatile fatty acid and fulvic acid class and humic acids compound etc..(2) xenobiotic Organic matter (XOCs) is mainly derived from family and industrial chemicals, including a series of aromatic hydrocarbons, benzene class Substance and chlorinated aliphatic hydrocarbon etc..(3) heavy metal pollution, including Cd2+、Cr3+、Cu2+、Pb2+、Ni2+And Zn2+Deng.
The pollution of Urban Underground water and soil has following features:(1) spatial spreading is big, and it is tired to pollute Site evaluation It is difficult;(2) soil body and underground water pollution coexist, and soil sample chemistry original sample keeps difficulty big in sampling process;(3) with combined pollution Based on, often there is heavy metal and organic pollution coexists, it is desirable that it is wide to administer restorative procedure applicability;(4) Contaminants Transport depth Larger, it is high to repair difficulty for complex geologic conditions.Urban Underground water and soil pollution These characteristics are reconnoitred for it, are administered and reparation is brought Huge Science and Technology challenge.
Insufficient due to administering recovery technique levels, the pollution control reparation of China's Urban Underground water and soil at present mostly uses Simple dystopy administration way.For example, being the Shanghai World's Fair that the heavy industry using metal as raw material or processing object is concentrated originally Garden place is polluted by serious heavy metal and persistent organism, and most of pollution plot is administered (to be dug using displacement method Pick-outward transport-cleaning earthen backfill);Three factory of Beijing's original chemical industry with nearly 50 years Chemical Manufacture history, part plant area soil It is serious by organic pollutions such as tetrabutyltin, dioctyl phthalates, using disposition is excavated when improvement, by high-enriched organics Contaminated soil burning disposal, slight pollution soil are filled.The showering processing cost in municipal pollution place is higher, and difficult To administer soil and the deeper place of underground water pollution, pollution water and soil under structures can not be repaired or against important building Contaminated site.
Compared with dystopy is administered and repaired, restorative procedure in situ of administering is not required to excavate the soil body, and rehabilitation cost is low, is suitble to state of China Feelings.Protect administration's statistics according to the U.S., be completed or the contaminated site recovery project that just carries out in about half repaired using in situ administer, Wherein vertical antifouling divider wall is most basic and effective technology.Vertical antifouling isolation wall technology is contaminated site prevention and control, repairs And leave the effective ways of Mini nutritionalassessment pollution control.
Divider wall early stage is mainly used in large-scale or reservoir seepage control project.With the development of technology, as shown in Figure 1 every It is more and more used in pollution control engineering from wall.Commonly using vertical divider wall engineering can following several class:Soil-swelling Native divider wall, plastic concrete divider wall, normal concrete divider wall (rigid concrete divider wall), Soil-cement piling wall with Compound divider wall of geomembrane-bentonite etc..
(1) soil-bentonite divider wall
The materials for wall of soil-bentonite divider wall is by excavating upper and dry bentonite in powder in situ and excavating swollen in groove The native mud of profit mixes, and bentonite volume is 4%~8%, and solid concentration is about 70% in materials for wall.Soil-bentonite every It is relatively low from wall permeability, usually 1 × 10-8M/s~5 × 10-11Between m/s.
(2) cement-bentonite divider wall
The materials for wall of cement-bentonite divider wall is matched by ordinary cement, bentonite slurry, water and some additives It makes, cement mixing content is 10%~15%, and solid concentration is about 20% in materials for wall.Cement-bentonite divider wall intensity It is higher than soil-bentonite divider wall intensity, the osmotic coefficient ratio soil-order of magnitude greater left and right of bentonite divider wall, about 1 × 10-8M/s~5 × 10-8m/s。
(3) normal concrete divider wall (rigid concrete divider wall)
Concrete partition wall (rigid concrete divider wall) be primarily referred to as prefabricated or cast in situs armored concrete every From wall, such divider wall intensity is big.
(4) plastic concrete divider wall
Plastic concrete divider wall is mainly made of cement, clay (or bentonite), stone and sand, and cement mixing content 3%~ 10%.Plastic concrete divider wall has the characteristics that deformation modulus is small, limiting strain is big, can be by changing material mix proportion people For control deform the amount of touching.
(5) cement mixing method divider wall
Cement mixing method divider wall is that curing agent (materials such as cement, lime) is sprayed into weak soil using deep mixer Layer depth portion makes curing agent be sufficiently mixed with the soil body under construction machinery stirring, and with the soil body a series of physical chemistry occurs for curing agent Reaction, forms the divider wall of hypotonicity, infiltration coefficient 1 × 10-9M/s~5 × 10-10m/s。
(6) the compound divider wall of geomembrane-bentonite
The compound divider wall of geomembrane-bentonite is made of geomembrane and materials for wall.Grooving is excavated using groover, Geomembrane and backfill materials for wall (such as cement bentonite hardening slurry, soil-bentonite mixture etc.), shape are laid in groove At compound divider wall.
Country variant is to the difference that stresses also of vertical divider wall type, and the European countries such as Britain are mainly using cement- The vertical divider wall of bentonite, and the U.S. mainly uses soil-vertical divider wall of the swelling soil series, China mostly uses cement (plasticity at present Concrete or soil cement) grouting curtain is as main divider wall form, to obstruct percolate in landfill yard.
As shown in table 2, on the one hand, existing common divider wall due to drying and watering cycle and Frozen-thawed cycled influence, long-term Anti-seepage effect can weaken after military service, on the other hand, in face of increasingly complicated water and soil pollution situation, the vertical antiseepage of single structure every It has been difficult to meet complicated pollution situation from wall.Some researches show that the presence of certain heavy metals can hinder hydrated cementitious, and It exerts an adverse impact in a long time to solidified cement body, reduces the intensity of cut-pff wall, and generate perforation in firming body Crack makes wall lose antiseepage isolation effect, so needing the phase of consideration cement and pollutant when using cement system cut-pff wall Capacitive.Although bentonite is better than cement for the compatibility of pollutant, the cut-pff wall intensity formed is relatively low, application range by Limitation, and the antiseepage barrier property of wall is generally difficult to reach the anti-of code requirement under the erosion of the combined pollutant of high concentration Ooze standard.
Table 2. commonly uses vertical divider wall disadvantage
Obstructing capacity of 3. geomembrane of table for pollutant
P-poor (poor), G-generallygoodresistance (good), IIR-Butylrubber (butyl rubber), CPE-Chlorinatedpolyethylene (haloflex), CSM-Chlorosulfonatedpolyethylene (chlorine sulphur Change polyethylene rubber), ECO-epichlorohydrincopolymer (copoly type epichlorohydrin rubber), EPDM- Ethylenepropylenedienemonomer (ethylene propylene diene rubber), CR-Polychloroprene (neoprene), PE- Polyethylene (polyethylene), PVC-Polyvinylchloride (polyvinyl chloride)
Although the compound divider wall permeability coefficient of geomembrane-bentonite is low, about 1 × 10-10M/s, isolation effect is good, so And often there is various heavy and the case where organic equal pollutants coexist often based on combined pollution in contaminated site in engineering, Pollution condition is extremely complex, on the one hand, the earth working material of conventional single kind has certain limitation, and complicated pollution condition Under, a large amount of pollutants of percolate and its carrying are easier to puncture barrier, service life are greatly shortened, so this single structure Divider wall be difficult to meet it is complicated every dirty antiseepage requirement;On the other hand, the strength of wall body of bentonite clay material is low, the scope of application by To limitation.
Utility model content
The purpose of this utility model is to provide a kind of compound underground anti-seepage swelling cob wall, to solve the above problems.
To achieve the goals above, the technical solution adopted in the utility model is:
The compound underground anti-seepage swelling cob wall of the utility model, including matrix and isolation features layer, isolation features are placed on On the inside of matrix, matrix, which is sprayed by bentonite siccative in slurry coat method, to harden, and isolation features layer is put down by several flexibility function layers It spreads, the flexibility function layer lower suspension variable weights of the bottom.
Flexibility function layer includes 2 layers of geotextiles, and at least one layer of isolation adsorbed film is equipped among geotextiles.
Isolation adsorbed film be polythylene resin film, polyacrylonitrile carbon based fibers film, fluorubber, silicon rubber, fluorine silicone rubber, One kind in electro spinning nanometer fiber membrane, mesoporous carbon/Si oxide compound film or the compound high hydroscopic resin of acrylamide.
The polythylene resin film is high density polyethylene (HDPE) (HDPE) resin film.
The beneficial effects of the utility model are:
The compound underground anti-seepage swelling cob wall of the utility model, can be according to the specific pollution condition in required isolation place, choosing Effective isolation adsorbed film and the suitable number of plies are selected, keeps design more targeted, in compound underground anti-seepage swelling earth wall construction, On the one hand, wall inherently has certain impermeability, and on the other hand, isolation features layer has prodigious isolation for pollutant The leaching that can effectively obstruct mixed pollutants is used in combination in adsorption capacity, multiple different isolation adsorbed films.The association of these two aspects Same-action greatly reduces the possibility that polluter leaches in place, is provided " multiple security " for engineering;Isolation features layer It is set to the interior survey of divider wall, it is possibility to have erosion of the prevention pollutant of effect for bentonite wall.
Description of the drawings
Fig. 1 is the structural schematic diagram of the compound underground anti-seepage swelling cob wall of the utility model;
Fig. 2 is the structural schematic diagram of flexibility function layer;
In figure:1, matrix, 2, isolation features layer, 3, variable weights, 4, flexibility function layer, 5, geotextiles, 6, isolation adsorbed film.
Specific implementation mode
Specific embodiment of the present utility model is made into one by the description to optimum embodiment below against attached drawing Step detailed description.
As illustrated in fig. 1 and 2, the compound underground anti-seepage swelling cob wall of the utility model, including matrix 1 and isolation features layer 2, Isolation features layer 2 is placed in 1 inside of matrix, and matrix 1, which is sprayed by bentonite siccative in slurry coat method, to harden, isolation features layer 2 It is tiled by several flexibility function layers 4, the flexibility function layer lower suspension variable weights 3 of the bottom.
Flexibility function layer 4 includes 2 layers of geotextiles 5, and at least one layer of isolation adsorbed film 6 is equipped among geotextiles 5.
Isolation adsorbed film 6 is polythylene resin film, polyacrylonitrile carbon based fibers film, fluorubber, silicon rubber, fluorine silicon rubber One kind in glue, electro spinning nanometer fiber membrane, mesoporous carbon/Si oxide compound film or the compound high hydroscopic resin of acrylamide.
Polythylene resin film is high density polyethylene (HDPE) (HDPE) resin film.
Embodiment 1
Since the change of urban planning is with greater need for factory site resettlement is carried out, sheet has been left in genuine location for certain plant area of Chemical Co., Ltd. Contaminated site, pollutant is mainly oil pollution and heavy metal pollution in place.Three layers are distributed in this contaminated area ground closely The clay of 13m thickness, at impermeable stratum about 17m located underground.
Pollutant is carried out using compound underground anti-seepage swelling cob wall described in the utility model for the above situation It is isolated, the isolation features layer of the compound underground anti-seepage swelling cob wall used in the present embodiment uses fluorubber coiled material and high density The thickness of polyethylene (HDPE) resin film, compound underground anti-seepage swelling cob wall is 500mm, and wall end stretch enters impermeable stratum 500mm。
Project measures wall saturation permeability coefficient 1 × 10 after being completed-11M/s or so is not detected in the underground water outside wall Pollutant, by nearly use in 5 years, infiltration coefficient not significant change is still good for the iris action of pollutant, uses Period, monitored quality of groundwater was normal, demonstrated the validity and reliability of scheme.

Claims (4)

1. a kind of compound underground anti-seepage swelling cob wall, which is characterized in that including matrix (1) and isolation features layer (2), work(is isolated Ergosphere (2) is placed on the inside of matrix (1), and matrix (1), which is sprayed by bentonite siccative in slurry coat method, to harden, isolation features layer (2) it is tiled by several flexibility function layers (4), the flexibility function layer lower suspension variable weights (3) of the bottom.
2. compound underground anti-seepage swelling cob wall according to claim 1, which is characterized in that flexibility function layer (4) includes 2 Layer geotextiles (5), geotextiles (5) are intermediate to be equipped at least one layer of isolation adsorbed film (6).
3. compound underground anti-seepage swelling cob wall according to claim 2, which is characterized in that isolation adsorbed film (6) is poly- Vinyl resins film, polyacrylonitrile carbon based fibers film, fluorubber, silicon rubber, fluorine silicone rubber, electro spinning nanometer fiber membrane, mesoporous carbon/ One kind in Si oxide compound film or the compound high hydroscopic resin of acrylamide.
4. compound underground anti-seepage swelling cob wall according to claim 3, which is characterized in that the polythylene resin film For high density polyethylene (HDPE) (HDPE) resin film.
CN201721780778.4U 2017-12-19 2017-12-19 Compound underground anti-seepage swelling cob wall Ceased CN207794062U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721780778.4U CN207794062U (en) 2017-12-19 2017-12-19 Compound underground anti-seepage swelling cob wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721780778.4U CN207794062U (en) 2017-12-19 2017-12-19 Compound underground anti-seepage swelling cob wall

Publications (1)

Publication Number Publication Date
CN207794062U true CN207794062U (en) 2018-08-31

Family

ID=63281331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721780778.4U Ceased CN207794062U (en) 2017-12-19 2017-12-19 Compound underground anti-seepage swelling cob wall

Country Status (1)

Country Link
CN (1) CN207794062U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914374A (en) * 2021-09-30 2022-01-11 中节能大地(杭州)环境修复有限公司 Construction method of flexible barrier wall of refuse landfill suitable for high water level condition
CN115651421A (en) * 2022-11-09 2023-01-31 山东科技大学 Slow-release controllable grouting water plugging material and preparation method and application thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914374A (en) * 2021-09-30 2022-01-11 中节能大地(杭州)环境修复有限公司 Construction method of flexible barrier wall of refuse landfill suitable for high water level condition
CN115651421A (en) * 2022-11-09 2023-01-31 山东科技大学 Slow-release controllable grouting water plugging material and preparation method and application thereof
CN115651421B (en) * 2022-11-09 2023-08-22 山东科技大学 Slowly-releasing controllable grouting water plugging material, and preparation method and application thereof

Similar Documents

Publication Publication Date Title
CN108330953A (en) New type compound underground anti-seepage swelling cob wall and its construction method
CN105032916B (en) The in-situ injection extracting moisturizing circulation disposal system and combined remediation method of a kind of organic material contaminated soil and underground water
CN114149203B (en) Compound polymer modified bentonite anti-seepage barrier material and preparation method and application thereof
CN101773928B (en) In-situ solidification and segregation treatment method of heavy-metal industrial polluted field
CN106077074B (en) A kind of in-situ remediation method of deep layer heavy-metal contaminated soil
CN106914482A (en) The in-situ remediation system of contaminated soil and underground water
CN105149335A (en) In-situ chemical oxidation restoration construction method for organic contaminated soil
CN106734178A (en) Comprehensive restoration system and method for polluted site
CN103435241A (en) Oil-gas field drilling waste mud treatment process
CN205099474U (en) Stake formula permeable reaction wall system of repairing of arc shooting
CN108951675A (en) HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation
CN103639193A (en) Restoration method for organically polluted site soil through circular in-situ chemical oxidation
CN206476859U (en) A kind of leachate collection applied to refuse landfill handles backflow device
CN207794062U (en) Compound underground anti-seepage swelling cob wall
CN107159698A (en) A kind of method that three-dimensional well elution joint stabilizes in-situ remediation soil polluted by heavy metals
CN104353666A (en) In-situ stirring curing and repairing method for heavy metal polluted soil
CN204225137U (en) For the radial well dewatering structure of contaminated water and soil integration in-situ immobilization
CN111456106A (en) In-situ bottom barrier structure, semi-barrier, barrier and liquid discharge system and construction method
CN103723786B (en) Self-repairing method for anti-seepage wall body of heavy metal pollutant place
CN107558492A (en) A kind of compound underground anti-seepage isolation wall construction and construction method
CN108203990B (en) Construction method of composite underground seepage-proofing bentonite wall
CN103290830B (en) Develop and the overall planning method of pollution treatment brownly
CN107700509A (en) Compound underground anti-seepage isolation wall construction and construction method
CN110357241A (en) The method for repairing underground water using permeable reactive barrier
CN102086085A (en) Method for solidifying drilling waste slurry

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
IW01 Full invalidation of patent right

Decision date of declaring invalidation: 20210624

Decision number of declaring invalidation: 50162

Granted publication date: 20180831

IW01 Full invalidation of patent right