CN108951675A - HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation - Google Patents

HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation Download PDF

Info

Publication number
CN108951675A
CN108951675A CN201710348618.0A CN201710348618A CN108951675A CN 108951675 A CN108951675 A CN 108951675A CN 201710348618 A CN201710348618 A CN 201710348618A CN 108951675 A CN108951675 A CN 108951675A
Authority
CN
China
Prior art keywords
bentonite
clay
wall
hdpe geomembrane
geomembrane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710348618.0A
Other languages
Chinese (zh)
Inventor
甄胜利
郑峰
郑中华
孙晓东
刘力奇
齐长青
刘泽军
霍成立
丁仕文
郭智
罗彬�
洪慧兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Geoenviron Engineering and Technology Inc
Original Assignee
Beijing Geoenviron Engineering and Technology Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Geoenviron Engineering and Technology Inc filed Critical Beijing Geoenviron Engineering and Technology Inc
Priority to CN201710348618.0A priority Critical patent/CN108951675A/en
Publication of CN108951675A publication Critical patent/CN108951675A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/001Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing unburned clay

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Organic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Dispersion Chemistry (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Revetment (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The present invention relates to a kind of HDPE geomembrane-bentonite complex vertical cut-pff wall and its construction methods of installation, the vertical impermeable wall is arranged on the relative water resisting layer of underground, the vertical impermeable wall is made of HDPE geomembrane and bentonite-clay lenses, and according to the following steps, engineering geology and Hydrogeologic Survey are carried out to contaminated area and prevention and cure of pollution place;Smooth location;It is inserted perpendicularly into and is laid with HDPE geomembrane;Interruption supplement bentonite-clay mortar;It forms and leads wall and lead the cipollettic dam that wall platform is linked together;Pass through the technical program, have many advantages, such as that installation is simple, low in cost, do not destroy impervious barrier structure, pollution in situ remediation, it is available locally in work progress, on the basis of meeting original antiseepage requirement, the security and stability that geomembrane anti-seepage layer can be increased avoids geomembrane destruction caused by by external environment disturbance or due to the backwater effect of bottom.

Description

HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its installation Method
Technical field
The present invention relates to a kind of underground anti-seepage technologies, anti-more particularly to a kind of HDPE geomembrane-bentonite complex vertical Seep wall and its construction method of installation.
Background technique
In petrochemical plant, filling station, household refuse landfill sites, Industrial Solid Waste landfill yard, danger wastes landfill All there is earth's surface hidden leakage defect or have already appeared leakage problems in the place such as field, and seriously polluted periphery underground water and soil, shadow The living environment and life safety of people are rung.
With environmental protection consciousness enhancing and environmental regulation it is more stringent, people especially pollute underground anti-seepage The underground anti-seepage research of place is more and more, many industrial workings, the filling station, Industrial Solid Waste heap that domestic early stage builds Field, Tailings Dam and household refuse landfill sites, these old plant areas, landfill area are mostly directly to topple over, and it is anti-not do any earth's surface It seeps treatment measures or earth's surface Anti-seeping technology standard cannot be met environmental requirements or impervious element has been destroyed, pollutant is straight Connect to surrounding and spread, thus contaminated soil and underground water, for contamination control, vertical seepage control be underground anti-seepage engineering very Important one aspect.
For danger wastes landfill yard, if addressing is unsatisfactory for associated contamination control standard requirements, corresponding engineering hand Section is also that vertical seepage control is done in selection, and it is vertical that existing underground vertical seepage control technique can be divided into rigid vertical seepage control technique, plasticity Seepage control technique and flexible vertical seepage control technique;Rigid seepage control technique has both mainly by materials such as cement as main impervious material Structure load-bearing and antiseepage effect, as seepage control technique, there are distinct disadvantages for rigid antiseepage, such as elasticity modulus height, non-deformability Less than 1%, be also easy to produce stress concentration there is crack, connect with elasticity modulus lesser soil layer it is extremely difficult, it is easy to form leak it is hidden Affected part position, and cement corrosion resistance ability is poor, easily contaminated object corrosion failure, while rigid cut-pff wall removes difficulty pole Greatly, the disadvantages of subsequent development & construction is influenced;Plasticity seepage control technique be improved according to the shortcomings that rigid seepage control technique it is anti- Infiltration wall technology, the low-intensity formed with part of cement in the rigid cut-pff wall of the admixtures such as bentonite, clay substitution, low bullet Property modulus, low-permeability cut-pff wall material, but it only improves deficiency of rigid cut-pff wall, can not be fully solved resistance The disadvantages of shape ability is poor, is easy to produce pre-existing fracture when constructing, and corrosion resistance is general.
Summary of the invention
In view of this, the main purpose of the present invention is to provide a kind of HDPE geomembrane-bentonite complex vertical cut-pff walls And its construction method of installation is applied on environment-friendly engineering by the technical program, have barrier performance strong, corrosion resistance and good, Durability is good, non-deformability is strong and has multiple seepage prevention system collective effect, construction site can spies such as development & construction again Point, while bentonite-clay mortar has very strong adsorption capacity, polluter can be adsorbed, to effectively compensate for Deficiency present in existing single vertical seepage control technology.
In order to achieve the above object, the technical scheme of the present invention is realized as follows:
The opposite of underground is arranged in a kind of HDPE geomembrane and bentonite-clay complex vertical cut-pff wall, the vertical impermeable wall On water barrier, the vertical impermeable wall is made of HDPE geomembrane and bentonite-clay lenses, and the HDPE geomembrane is vertical It is arranged in bentonite-clay lenses.
The HDPE geomembrane is 3.0mm thick, the infiltration coefficient < 1 × 10 of HDPE geomembrane-12Cm/s, the bentonite- Clay lenses with a thickness of 300-600mm, the bentonite-clay lenses infiltration coefficient < 1 × 10-7cm/s。
Positioned at bentonite-clay lenses top two sides be provided with and lead wall, be provided on leading wall above it is viscous with bentonite- What native impervious barrier flushed leads wall platform, is provided in being coated on HDPE geomembrane upper end on leading wall platform, and formed with It leads wall and leads the cipollettic dam that wall platform is linked together.
A kind of HDPE geomembrane and bentonite-clay complex vertical cut-pff wall construction method of installation, sequentially include the following steps:
(a) engineering geology and Hydrogeologic Survey are carried out to contaminated area and prevention and cure of pollution place, measure groundwater level and water quality, Relative water resisting layer lithology, infiltration coefficient, depth and thickness, water-bearing layer lithology and property, contamination range determine vertical seepage control The cutting depth and thickness of wall;
(b) smooth location prepares bentonite-clay mortar, and in pollution antiseepage region, unpolluted area periphery excavates groove And it will be in prepared bentonite-clay mortar injection respective grooves;
(c) it is inserted perpendicularly into bentonite-clay mortar in the groove and is laid with HDPE geomembrane;
(d) after moisture content exudation or evaporation are reduced in bentonite-clay mortar, interruption supplement bentonite-clay mortar to groove In;
(e) after moistening soil-clay mortar and expiring groove solidification, bentonite-clay lenses is formed, is returned on leading wall platform with clay It fills out in being coated on HDPE geomembrane upper end, and is formed and lead wall and lead the cipollettic dam that wall platform is linked together.
Bentonite-the clay mortar be can self-solidifying mud, and by following Ingredient Wt part constitute: bentonite 8-12, Cohesive soil 50-70, water 20-30, additive 8-10.
The additive is polycarboxylic acids PVA, acrylates, lignosulfonates.
Beneficial effect after by adopting the above technical scheme is: a kind of HDPE geomembrane and bentonite-clay complex vertical are anti- Seep wall and its construction method of installation, by the technical program, have install it is simple, low in cost, do not destroy impervious barrier structure, dirt The advantages that contaminating in situ remediation is available locally in work progress, on the basis of meeting original antiseepage requirement, can increase geotechnique The security and stability of film impervious barrier avoids geomembrane destruction caused by by external environment disturbance or due to the backwater effect of bottom.
Detailed description of the invention
Fig. 1 is overall structure diagram of the invention.
Fig. 2 is HDPE geomembrane-bentonite-clay vertical impermeable wall structural schematic diagram in the present invention.
In figure, 1 relative water resisting layer, 2 HDPE geomembranes, 3 bentonites-clay lenses, 4 lead wall, 5 lead wall platform, 6 ladder Shape dam, 7 soil layers or rock stratum, 8 contaminated areas.
Specific embodiment
The specific embodiment in the present invention is described in further detail below in conjunction with attached drawing.
As depicted in figs. 1 and 2, HDPE geomembrane and bentonite of the present invention-clay complex vertical cut-pff wall, it is described Vertical impermeable wall is arranged on the relative water resisting layer 1 of underground, and the vertical impermeable wall is by HDPE geomembrane 2 and bentonite-clay Impervious barrier 3 is constituted, and the HDPE geomembrane 2 is vertically set in bentonite-clay lenses 3.
The HDPE geomembrane 2 is 3.0mm thick, the infiltration coefficient < 1 × 10 of HDPE geomembrane 2-12Cm/s, the swelling Soil-clay lenses 3 with a thickness of 300-600mm., the 3 infiltration coefficient < 1 × 10 of bentonite-clay lenses-7cm/ s。
Be provided with positioned at 3 top two sides of bentonite-clay lenses and lead wall 4, be provided on leading wall 4 above and swelling What soil-clay lenses 3 flushed leads wall platform 5, is provided in being coated on 2 upper end of HDPE geomembrane on leading wall platform 5, and And it is formed and leads wall 4 and lead the cipollettic dam 6 that wall platform 5 is linked together.
HDPE geomembrane and bentonite of the present invention-clay complex vertical cut-pff wall construction method of installation, by following Step carries out:
(a) engineering geology and Hydrogeologic Survey are carried out to contaminated area 8 and prevention and cure of pollution place, measures groundwater level and water Matter, relative water resisting layer 1, infiltration coefficient, depth and thickness, water-bearing layer lithology and property, contamination range determine vertical seepage control Position, cutting depth and the thickness of wall;
(b) smooth location prepares bentonite-clay mortar, and in pollution antiseepage region, unpolluted area periphery excavates groove And it will be in prepared bentonite-clay mortar injection respective grooves;
(c) it is inserted perpendicularly into bentonite-clay mortar in the groove and is laid with HDPE geomembrane 2;
(d) after moisture content exudation or evaporation are reduced in bentonite-clay mortar, interruption supplement bentonite-clay mortar to groove In;
(e) after moistening soil-clay mortar and expiring groove solidification, bentonite-clay lenses 3 is formed, uses clay on leading wall platform 5 In 2 upper end of HDPE geomembrane is coated on by backfill, and is formed and lead wall 4 and lead the cipollettic dam 6 that wall platform 5 is linked together.
Bentonite-the clay mortar be can self-solidifying mud, and by following Ingredient Wt part constitute: bentonite 8-12, Cohesive soil 50-70, water 20-30, additive 8-10.
The additive is polycarboxylic acids PVA, acrylates, lignosulfonates.
Sodium bentonite and cohesive soil, and the infiltration coefficient < 1 × 10 of HDPE geomembrane 2 are used in the present invention-12Cm/s, Its excellent barrier performance makes the barrier performance of entire vertical seepage control wall construction reach Environmental Design requirement, bentonite-clay The cut-pff wall that impervious barrier 3 and HDPE geomembrane 2 are constituted belongs to flexible wall, and outstanding feature is elasticity modulus and surrounding soil phase Seemingly, it is easy to construct, low cost, construction site can development & construction again.
It, can also be using the fixed HDPE geomembrane 2 of anchoring groove, by the upper end of HDPE geomembrane 2 in the embodiment of the present invention Extend, distance, which is excavated to dig on the ground groove >=1m, anchoring groove, is backfilled with cohesive soil or sandy soil, and anchoring groove can allow Later use HDPE geomembrane 3 is more convenient, and band steel can additionally be selected to be fixed to the modes such as lead on wall 4.
In the embodiment of the present invention, when 2 area of HDPE geomembrane is excessive, operation difficulty can be very big, therefore generally using 4m's Breadth carries out the decentralization of HDPE geomembrane 2, and two HDPE geomembranes 2 are connected using lock connection, latches junction in order to prevent Leakage, can use sealing rod and bentonite-clay mortar composite anti-penetrating.
In the present invention, bentonite-clay lenses 3 and HDPE geomembrane 2 constitute vertical impermeable wall, vertical impermeable wall two Side is soil layer or rock stratum 7, and vertical impermeable wall must be deep into 1 or less 1.0 ~ 1.5m of relative water resisting layer, backfills bentonite-clay mortar After can prevent pollutant from cut-pff wall bottom leaky, leading wall 4 is builds along cut-pff wall metope upper end two sides with sufficiently strong Degree, rigidity and precision play the role of earth-retaining, guiding, supporting heavy, save mud and the twice of measuring basis are parallel to cut-pff wall The works of central axis, above it overlay lead wall platform 5 and bentonite-clay lenses 3 are encapsulated in interior, HDPE geomembrane 2 upper ends are stretched out from leading in wall platform 5, are led and cipollettic dam 6 are arranged on wall platform 5 HDPE geomembrane 2 is encapsulated in cipollettic dam 6.
The above, preferable possible embodiments only of the invention, the protection scope being not intended to limit the invention.

Claims (6)

1. the phase of underground is arranged in a kind of HDPE geomembrane and bentonite-clay complex vertical cut-pff wall, the vertical impermeable wall To on water barrier, which is characterized in that the vertical impermeable wall is made of HDPE geomembrane and bentonite-clay lenses, described HDPE geomembrane is vertically set in bentonite-clay lenses.
2. HDPE geomembrane according to claim 1 and bentonite-clay complex vertical cut-pff wall, which is characterized in that institute Stating HDPE geomembrane is 3.0mm thick, the infiltration coefficient < 1 × 10 of HDPE geomembrane-12Cm/s, the bentonite-clay lenses With a thickness of 300-600mm., the bentonite-clay lenses infiltration coefficient < 1 × 10-7cm/s。
3. HDPE geomembrane according to claim 1 and bentonite-clay complex vertical cut-pff wall, which is characterized in that position It is neat with bentonite-clay lenses above bentonite-clay lenses top two sides are provided with and lead wall, are provided on leading wall Flat leads wall platform, is provided in being coated on HDPE geomembrane upper end on leading wall platform, and is formed and lead wall and lead wall The cipollettic dam that platform is linked together.
4. a kind of HDPE geomembrane and bentonite-clay complex vertical cut-pff wall construction method of installation, which is characterized in that by following Step carries out:
(a) engineering geology and Hydrogeologic Survey are carried out to contaminated area and prevention and cure of pollution place, measure groundwater level and water quality, Relative water resisting layer lithology, infiltration coefficient, depth and thickness, water-bearing layer lithology and property, contamination range determine vertical seepage control Position, cutting depth and the thickness of wall;
(b) smooth location prepares bentonite-clay mortar, and in pollution antiseepage region, unpolluted area periphery excavates groove And it will be in prepared bentonite-clay mortar injection respective grooves;
(c) it is inserted perpendicularly into bentonite-clay mortar in the groove and is laid with HDPE geomembrane;
(d) after moisture content exudation or evaporation are reduced in bentonite-clay mortar, interruption supplement bentonite-clay mortar to groove In;
(e) after moistening soil-clay mortar and expiring groove solidification, bentonite-clay lenses is formed, is returned on leading wall platform with clay It fills out in being coated on HDPE geomembrane upper end, and is formed and lead wall and lead the cipollettic dam that wall platform is linked together.
5. HDPE geomembrane according to claim 4 and bentonite-clay complex vertical cut-pff wall construction method of installation, Be characterized in that, the bentonite-clay mortar be can self-solidifying mud, and by following Ingredient Wt part constitute: bentonite 8-12, Cohesive soil 50-70, water 20-30, additive 8-10.
6. HDPE geomembrane according to claim 5 and bentonite-clay complex vertical cut-pff wall construction method of installation, It is characterized in that, the additive is polycarboxylic acids PVA, acrylates, lignosulfonates.
CN201710348618.0A 2017-05-17 2017-05-17 HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation Pending CN108951675A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710348618.0A CN108951675A (en) 2017-05-17 2017-05-17 HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710348618.0A CN108951675A (en) 2017-05-17 2017-05-17 HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation

Publications (1)

Publication Number Publication Date
CN108951675A true CN108951675A (en) 2018-12-07

Family

ID=64461775

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710348618.0A Pending CN108951675A (en) 2017-05-17 2017-05-17 HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation

Country Status (1)

Country Link
CN (1) CN108951675A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984238A (en) * 2019-10-28 2020-04-10 上海市政工程设计研究总院(集团)有限公司 HDPE (high-density polyethylene) film-bentonite composite vertical anti-seepage wall system and construction equipment and construction method thereof
CN111074920A (en) * 2020-01-16 2020-04-28 周同和 Construction method for inserting anti-seepage blanket into cement-soil continuous wall to form composite curtain and composite curtain prepared by construction method
CN111441375A (en) * 2020-05-08 2020-07-24 天津建昌环保股份有限公司 Flexible continuous wall for underground pollution blocking and construction method thereof
CN113062296A (en) * 2021-04-02 2021-07-02 交通运输部天津水运工程科学研究所 Vacuum preloading boundary sealing method
CN113338349A (en) * 2021-06-09 2021-09-03 中冶节能环保有限责任公司 Novel steel slag landfill vertical separation system and implementation method
CN113914374A (en) * 2021-09-30 2022-01-11 中节能大地(杭州)环境修复有限公司 Construction method of flexible barrier wall of refuse landfill suitable for high water level condition
CN114130784A (en) * 2021-11-08 2022-03-04 中煤科工集团西安研究院有限公司 Waste packaging device and method
CN114525818A (en) * 2022-02-11 2022-05-24 中钢集团马鞍山矿山研究总院股份有限公司 Construction method of combined anti-seepage body with horizontal anti-seepage function and vertical anti-seepage function
CN115233717A (en) * 2022-07-27 2022-10-25 中国矿业大学(北京) Vertical and horizontal combined tailing pond stable structure and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4601615A (en) * 1983-02-22 1986-07-22 Finic, B.V. Environmental cut-off for deep excavations
US5388931A (en) * 1993-10-18 1995-02-14 Carlson; Robert J. Cutoff wall system to isolate contaminated soil
CN103174173A (en) * 2013-03-08 2013-06-26 浙江大学 Method for shallow part enhancement type soil-swell soil vertical antifouling separating wall
CN103321256A (en) * 2013-07-09 2013-09-25 中国瑞林工程技术有限公司 Anti-pollution three-dimensional composite seepage-proofing barrier system
CN104805871A (en) * 2015-04-30 2015-07-29 北京高能时代环境技术股份有限公司 Compound type perpendicular seepage-proofing screen and application thereof
CN105672365A (en) * 2016-03-31 2016-06-15 天津中联格林科技发展有限公司 GCL vertical anti-seepage wall and preparation method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4601615A (en) * 1983-02-22 1986-07-22 Finic, B.V. Environmental cut-off for deep excavations
US5388931A (en) * 1993-10-18 1995-02-14 Carlson; Robert J. Cutoff wall system to isolate contaminated soil
CN103174173A (en) * 2013-03-08 2013-06-26 浙江大学 Method for shallow part enhancement type soil-swell soil vertical antifouling separating wall
CN103321256A (en) * 2013-07-09 2013-09-25 中国瑞林工程技术有限公司 Anti-pollution three-dimensional composite seepage-proofing barrier system
CN104805871A (en) * 2015-04-30 2015-07-29 北京高能时代环境技术股份有限公司 Compound type perpendicular seepage-proofing screen and application thereof
CN105672365A (en) * 2016-03-31 2016-06-15 天津中联格林科技发展有限公司 GCL vertical anti-seepage wall and preparation method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
何廷树: "《混凝土外加剂》", 31 August 2003, 陕西科学技术出版社 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984238A (en) * 2019-10-28 2020-04-10 上海市政工程设计研究总院(集团)有限公司 HDPE (high-density polyethylene) film-bentonite composite vertical anti-seepage wall system and construction equipment and construction method thereof
CN111074920A (en) * 2020-01-16 2020-04-28 周同和 Construction method for inserting anti-seepage blanket into cement-soil continuous wall to form composite curtain and composite curtain prepared by construction method
CN111441375A (en) * 2020-05-08 2020-07-24 天津建昌环保股份有限公司 Flexible continuous wall for underground pollution blocking and construction method thereof
CN113062296A (en) * 2021-04-02 2021-07-02 交通运输部天津水运工程科学研究所 Vacuum preloading boundary sealing method
CN113338349A (en) * 2021-06-09 2021-09-03 中冶节能环保有限责任公司 Novel steel slag landfill vertical separation system and implementation method
CN113914374A (en) * 2021-09-30 2022-01-11 中节能大地(杭州)环境修复有限公司 Construction method of flexible barrier wall of refuse landfill suitable for high water level condition
CN114130784A (en) * 2021-11-08 2022-03-04 中煤科工集团西安研究院有限公司 Waste packaging device and method
CN114130784B (en) * 2021-11-08 2022-12-13 中煤科工集团西安研究院有限公司 Waste packaging device and method
CN114525818A (en) * 2022-02-11 2022-05-24 中钢集团马鞍山矿山研究总院股份有限公司 Construction method of combined anti-seepage body with horizontal anti-seepage function and vertical anti-seepage function
CN114525818B (en) * 2022-02-11 2023-07-28 中钢集团马鞍山矿山研究总院股份有限公司 Construction method of combined impermeable body with horizontal impermeable and vertical impermeable functions
CN115233717A (en) * 2022-07-27 2022-10-25 中国矿业大学(北京) Vertical and horizontal combined tailing pond stable structure and construction method

Similar Documents

Publication Publication Date Title
CN108951675A (en) HDPE geomembrane and bentonite-clay complex vertical cut-pff wall and its construction method of installation
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN101298782B (en) Method and system for basement engineering water proof and water drain
CN204940237U (en) A kind of multifunctional monitoring well repaired with improvement for informal landfill pollution surveys
CN102817366B (en) Prevention and treatment method for full-mechanized caving mining collapse trap area water disaster for shallow-buried ultra-thick coal seam
CN102995599B (en) Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal
CN108330953B (en) Novel composite underground seepage-proofing bentonite wall and construction method thereof
CN203991655U (en) A kind of in situ chemical oxidation Injection Well system
CN102367672A (en) Method for installing vertical soft barrier system based on soil-stone foundation
CN104099943A (en) Underground diaphragm wall and deserted underground civil air defense engineering intersection processing method
CN111441375A (en) Flexible continuous wall for underground pollution blocking and construction method thereof
CN101144281B (en) Floating flashboard machine and large area ultra-weak foundation fast directly draining concretion method
CN106284434A (en) The anti-float method of a kind of underground structure and every oozing device
CN202559379U (en) Vertical flexible barrier mounting structure with debris foundation conditions
CN107687175A (en) The vertical antifouling isolation wall construction of both sides ground local stiffening type and method
CN208884586U (en) A kind of solid waste stockpiling barrier structure
CN202273236U (en) Inner dams in karst reservoir
CN207891929U (en) A kind of ecotype Tailings Dam leakage preventing structure
CN101029486A (en) Construction for fastly fastening flexible ground
CN202108045U (en) Sleeve pipe with anchor rod penetrating through underground continuous wall
CN209194466U (en) A kind of Reservoir Bank leakage preventing structure
CN108203990B (en) Construction method of composite underground seepage-proofing bentonite wall
CN203383316U (en) Municipal solid waste sanitary landfill percolate leakage monitoring structure
Dixit Damage mechanism in problematic soils
CN111519647A (en) Novel foundation suitable for marine soft foundation treatment and reinforcement and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181207

RJ01 Rejection of invention patent application after publication