CN207757158U - A kind of welding bench of aluminum alloy pattern plate welding robot - Google Patents
A kind of welding bench of aluminum alloy pattern plate welding robot Download PDFInfo
- Publication number
- CN207757158U CN207757158U CN201820032649.5U CN201820032649U CN207757158U CN 207757158 U CN207757158 U CN 207757158U CN 201820032649 U CN201820032649 U CN 201820032649U CN 207757158 U CN207757158 U CN 207757158U
- Authority
- CN
- China
- Prior art keywords
- welding
- welding bench
- fixedly connected
- welding station
- shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
本实用新型公开了一种铝模板焊接机器人的焊接工作台,包括机架、第一焊接台、转轴、第二焊接台和夹具,夹具设置在第一焊接台上,转轴转动连接在机架上,第一焊接台和第二焊接台均固定连接在转轴上,第一焊接台和第二焊接台的中部均设置有通槽,第一焊接台和第二焊接台的两端均固定连接有挡板,第一焊接台和第二焊接台上均滑动设置有压板,压板与挡板之间固定连接有弹簧,转轴的一端固定连接有第一皮带轮,机架上还设置有驱动电机,驱动电机的输出轴上固定连接有第二皮带轮,第一皮带轮和第二皮带轮之间张紧有皮带。本实用新型能同时进行待焊接铝模板的焊接和新铝模板的安装,提高焊接机器人的工作效率,降低铝模板的焊接成本。
The utility model discloses a welding workbench of an aluminum formwork welding robot, which comprises a frame, a first welding platform, a rotating shaft, a second welding platform and a fixture, the fixture is arranged on the first welding platform, and the rotating shaft is rotatably connected to the frame , the first welding station and the second welding station are fixedly connected on the rotating shaft, the middle parts of the first welding station and the second welding station are provided with through grooves, and the two ends of the first welding station and the second welding station are fixedly connected with The baffle plate, the first welding station and the second welding station are all slidably provided with a pressing plate, a spring is fixedly connected between the pressing plate and the baffle plate, one end of the rotating shaft is fixedly connected with the first pulley, and a driving motor is also arranged on the frame to drive A second pulley is fixedly connected to the output shaft of the motor, and a belt is tensioned between the first pulley and the second pulley. The utility model can carry out the welding of the aluminum template to be welded and the installation of the new aluminum template at the same time, improves the working efficiency of the welding robot, and reduces the welding cost of the aluminum template.
Description
技术领域technical field
本实用新型涉及焊接设备技术领域,尤其涉及一种铝模板焊接机器人的焊接工作台。The utility model relates to the technical field of welding equipment, in particular to a welding workbench of an aluminum template welding robot.
背景技术Background technique
目前在建筑用铝模板行业,铝模板焊接主要由人工焊接,由于人工焊接存在工人水平参差不齐、人工费用高、焊接环境差,并且焊接工作效率低等问题,所以,使用铝模板焊接机器人进行铝模板的焊接逐渐成为趋势。At present, in the aluminum formwork industry for construction, aluminum formwork welding is mainly performed by manual welding. Due to the problems of uneven worker levels, high labor costs, poor welding environment, and low welding efficiency in manual welding, aluminum formwork welding robots are used. The welding of aluminum templates is gradually becoming a trend.
铝模板焊接机器人都拥有一个焊接工作台,但是目前的焊接工作台一般一次只能安装一套铝模板,在使用时,先在工作台上安装一套待焊接的铝模板,使用夹具将铝模板固定,然后再利用机械手带动焊枪对铝模板进行焊接,待焊接完毕后,将焊接完毕的铝模板取下,再将下一套待焊接的铝模板放在工作台上进行该套铝模板的焊接,但是这样的焊接工作台存在以下问题:焊枪在对铝模板进行焊接的时候,工人处于闲置状态,而工人在取下已焊接铝模板和安装待焊接铝模板的时候,机械手和焊枪又处于闲置状态,如此,就会存在焊接效率不高,浪费机械手、焊枪和工人的很大部分能力的问题,直接导致铝模板的成本增加。Aluminum formwork welding robots all have a welding workbench, but the current welding workbench can only install one set of aluminum formwork at a time. Fix it, and then use the manipulator to drive the welding torch to weld the aluminum formwork. After the welding is completed, remove the welded aluminum formwork, and then put the next set of aluminum formwork to be welded on the workbench for welding of this set of aluminum formwork. , but such a welding workbench has the following problems: when the welding torch is welding the aluminum formwork, the worker is in an idle state, and when the worker removes the welded aluminum formwork and installs the aluminum formwork to be welded, the manipulator and the welding torch are idle again In this way, there will be a problem of low welding efficiency, wasting a large part of the capabilities of manipulators, welding torches and workers, which directly leads to an increase in the cost of aluminum templates.
实用新型内容Utility model content
有鉴于此,本实用新型的目的是提供一种铝模板焊接机器人的焊接工作台,该工作台能同时进行待焊接铝模板的焊接和新铝模板的安装,提高焊接机器人的工作效率,降低铝模板的焊接成本。In view of this, the purpose of this utility model is to provide a welding workbench for an aluminum template welding robot, which can simultaneously perform welding of the aluminum template to be welded and installation of a new aluminum template, improve the work efficiency of the welding robot, and reduce the Welding costs for formwork.
本实用新型通过以下技术手段解决上述技术问题:The utility model solves the above-mentioned technical problems by the following technical means:
一种铝模板焊接机器人的焊接工作台,包括机架、第一焊接台、转轴、第二焊接台和夹具,所述夹具设置在第一焊接台上,所述转轴转动连接在机架上,所述第一焊接台和第二焊接台均固定连接在转轴上,且第一焊接台与第二焊接台处于同一平面上,所述第一焊接台和第二焊接台的中部均设置有通槽,所述第一焊接台和第二焊接台的两端均固定连接有挡板,所述第一焊接台和第二焊接台上均滑动设置有压板,所述压板与挡板之间固定连接有弹簧,所述转轴的一端固定连接有第一皮带轮,所述机架上还设置有驱动电机,所述驱动电机的输出轴上固定连接有第二皮带轮,所述第一皮带轮和第二皮带轮之间张紧有皮带。A welding workbench of an aluminum template welding robot, comprising a frame, a first welding station, a rotating shaft, a second welding station and a fixture, the fixture is arranged on the first welding station, and the rotating shaft is rotatably connected to the frame, Both the first welding station and the second welding station are fixedly connected on the rotating shaft, and the first welding station and the second welding station are on the same plane, and the middle parts of the first welding station and the second welding station are provided with through trough, both ends of the first welding station and the second welding station are fixedly connected with baffle plates, both of the first welding station and the second welding station are slidably provided with a pressing plate, and the pressing plate and the baffle plate are fixed A spring is connected, a first pulley is fixedly connected to one end of the rotating shaft, a drive motor is also arranged on the frame, a second pulley is fixedly connected to the output shaft of the drive motor, and the first pulley and the second pulley A belt is tensioned between the pulleys.
进一步,所述转轴上还固定连接有第一遮挡板和第二遮挡板,所述第一遮挡板和第二遮挡板分别位于第一焊接台的两侧,且均与第一焊接台垂直。第一焊接台上的铝模板正在焊接的时候,操作工人正在第二焊接台上安装待焊接的铝模板,第一遮挡板和第二遮挡板的设置,可以遮挡在第一焊接台和第二焊接台之间,工人在第二焊接台上工作的时候,可以避免第一焊接台上焊接时的焊渣和电焊弧光对工人身体的伤害。Further, a first shielding plate and a second shielding plate are fixedly connected to the rotating shaft, and the first shielding plate and the second shielding plate are respectively located on both sides of the first welding table, and both are perpendicular to the first welding table. When the aluminum formwork on the first welding station is being welded, the operator is installing the aluminum formwork to be welded on the second welding station. Between the welding stations, when workers work on the second welding station, it is possible to avoid injury to the worker's body caused by welding slag and electric welding arc light during welding on the first welding station.
进一步,所述第一遮挡板和第二遮挡板远离转轴的一侧端面上均固定连接有卡块,所述卡块上设置有第一通孔,所述机架的底部设置有横梁,所述横梁上设置有U型槽,所述U型槽上设置有与第一通孔配合的第二通孔,所述第一通孔和第二通孔之间穿设有销轴。在焊接的时候,第一焊接台和第二焊接台一般是与地面平行,第一遮挡板和第二遮挡板是与地面垂直的,此时,使用销轴穿过第一通孔和第二通孔,将第一遮挡板或者第二遮挡板固定在横梁上,进而将第一焊接台和第二焊接台固定,避免在焊接和安装操作时,第一焊接台和第二焊接台发生转动而影响焊接质量。Further, the end faces of the first shielding plate and the second shielding plate away from the rotating shaft are fixedly connected with a block, the block is provided with a first through hole, and the bottom of the frame is provided with a beam, so The beam is provided with a U-shaped groove, and the U-shaped groove is provided with a second through hole matched with the first through hole, and a pin shaft is pierced between the first through hole and the second through hole. When welding, the first welding station and the second welding station are generally parallel to the ground, and the first shielding plate and the second shielding plate are perpendicular to the ground. At this time, use a pin to pass through the first through hole and the second The through hole is used to fix the first shielding plate or the second shielding plate on the beam, and then fix the first welding station and the second welding station, so as to avoid rotation of the first welding station and the second welding station during welding and installation operations And affect the welding quality.
进一步,所述夹具包括固定杆和压杆,所述固定杆固定连接在第一焊接台和第二焊接台上靠近转轴的一侧,所述压杆的一端铰接在固定杆上,所述压板的另一端上设置有第一螺纹孔,所述第一螺纹孔内螺纹连接有紧固螺栓,所述第一焊接台和第二焊接台上均设置有与紧固螺栓配合的第二螺纹孔,所述紧固螺栓的端部固定连接有旋柄。使用时,将铝模板放置在第一焊接台或者第二焊接台上,转动压板,利用压板将铝模板压紧固定,然后旋转紧固螺栓,紧固螺栓旋进到第二螺纹孔内,实现对铝模板的压紧,如此,使用起来方便快捷,压紧效果好,铝模板不会发生移动。Further, the fixture includes a fixed rod and a pressing rod, the fixed rod is fixedly connected to the first welding station and the second welding station on the side close to the rotating shaft, one end of the pressing rod is hinged on the fixing rod, and the pressing plate A first threaded hole is provided on the other end of the first threaded hole, and fastening bolts are threaded in the first threaded hole, and second threaded holes that cooperate with the fastening bolts are provided on the first welding station and the second welding station , the end of the fastening bolt is fixedly connected with a handle. When in use, place the aluminum formwork on the first welding station or the second welding station, turn the pressure plate, use the pressure plate to press and fix the aluminum formwork, then rotate the fastening bolt, and the fastening bolt is screwed into the second threaded hole to realize The compression of the aluminum formwork is so convenient and quick to use, the compression effect is good, and the aluminum formwork will not move.
进一步,所述压板远离弹簧的一侧和压杆靠近第一焊接台的一侧均固定连接有缓冲橡胶。压板和压杆在对铝模板的压紧时,缓冲橡胶可以使得压板和压杆在对铝模板压紧时起到缓冲压力的作用,避免对铝模板压出压痕,影响铝模板的外观。Further, the side of the pressure plate away from the spring and the side of the pressure rod close to the first welding station are fixedly connected with buffer rubber. When the pressure plate and the pressure rod are pressing the aluminum formwork, the buffer rubber can make the pressure plate and the pressure rod play the role of buffering the pressure when pressing the aluminum formwork, avoiding the indentation of the aluminum formwork and affecting the appearance of the aluminum formwork.
进一步,所述转轴与机架的转动连接处均内衬有滚珠轴承。滚珠轴承的设置使得转轴在转动时,与机架之间的摩擦力更小,阻力更小,工作噪音也更小。Furthermore, ball bearings are lined at the rotating joints between the rotating shaft and the frame. The setting of the ball bearing makes the friction between the rotating shaft and the frame smaller when rotating, the resistance is smaller, and the working noise is also smaller.
本实用新型的有益效果:The beneficial effects of the utility model:
1、本实用新型的焊接工作台上设置有第一焊接台和第二焊接台,第一焊接台焊接的时候,第二焊接台可以同时进行待焊接模板的安装,如此,第一焊接台和第二焊接台交替进行,减少对工人、机械手和焊枪的时间浪费,大大提高铝模板焊接的工作效率,降低铝模板的焊接成本;1. The welding workbench of the present utility model is provided with a first welding station and a second welding station. When the first welding station is welding, the second welding station can simultaneously install the template to be welded. In this way, the first welding station and the second welding station The second welding station is carried out alternately, reducing the time waste of workers, manipulators and welding torches, greatly improving the work efficiency of aluminum template welding, and reducing the welding cost of aluminum templates;
2、本实用新型操作简单,不会对工人造成身体伤害,焊接时压紧牢固,也不会发生转动,焊接质量好,适宜推广使用。2. The utility model is easy to operate, does not cause bodily harm to workers, is firmly pressed during welding, does not rotate, has good welding quality, and is suitable for popularization and use.
附图说明Description of drawings
图1是本实用新型一种铝模板焊接机器人的焊接工作台的俯视图;Fig. 1 is the top view of the welding workbench of a kind of aluminum template welding robot of the present invention;
图2是本实用新型的正视图;Fig. 2 is the front view of the utility model;
其中,机架1、第一焊接台2、转轴3、第二焊接台4、通槽5、挡板6、压板7、弹簧8、第一皮带轮9、驱动电机10、第二皮带轮11、皮带12、第一遮挡板13、第二遮挡板14、观察窗15、卡块16、横梁17、U型槽18、销轴19、固定杆20、压杆21、紧固螺栓22、旋柄23、缓冲橡胶24、铝模板25。Among them, the frame 1, the first welding station 2, the rotating shaft 3, the second welding station 4, the through groove 5, the baffle plate 6, the pressing plate 7, the spring 8, the first pulley 9, the driving motor 10, the second pulley 11, the belt 12. The first shading plate 13, the second shading plate 14, the observation window 15, the block 16, the beam 17, the U-shaped groove 18, the pin 19, the fixing rod 20, the pressure rod 21, the fastening bolt 22, the handle 23 , Buffer rubber 24, aluminum formwork 25.
具体实施方式Detailed ways
以下将结合附图对本实用新型进行详细说明:The utility model will be described in detail below in conjunction with accompanying drawing:
如图1~图2所示:As shown in Figure 1 ~ Figure 2:
一种铝模板焊接机器人的焊接工作台,包括机架1、第一焊接台2、夹具、转轴3和第二焊接台4,夹具设置在第一焊接台2上,转轴3转动连接在机架1上,第一焊接台2和第二焊接台4均焊接在转轴3上,且第一焊接台2与第二焊接台4处于同一平面上,第一焊接台2和第二焊接台4的中部均设置有通槽5,第一焊接台2和第二焊接台4的两端均焊接有挡板6,第一焊接台2和第二焊接台4上均滑动设置有压板7,压板7与挡板6之间固定连接有弹簧8,转轴3的右端通过平键固定连接有第一皮带轮9,机架1上还通过螺栓固定设置有驱动电机10,驱动电机10的输出轴上通过平键固定连接有第二皮带轮11,第一皮带轮9和第二皮带轮11之间张紧有皮带12,其中驱动电机10可以为带驱动器和PLC控制系统的步进电机,其能控制转轴进行间断性180°的旋转。A welding workbench for an aluminum template welding robot, including a frame 1, a first welding station 2, a fixture, a rotating shaft 3 and a second welding station 4, the fixture is arranged on the first welding station 2, and the rotating shaft 3 is rotatably connected to the frame 1, the first welding station 2 and the second welding station 4 are welded on the rotating shaft 3, and the first welding station 2 and the second welding station 4 are on the same plane, the first welding station 2 and the second welding station 4 The middle part is provided with a through groove 5, the two ends of the first welding station 2 and the second welding station 4 are welded with baffles 6, the first welding station 2 and the second welding station 4 are slidingly provided with a pressing plate 7, the pressing plate 7 A spring 8 is fixedly connected with the baffle plate 6, and the right end of the rotating shaft 3 is fixedly connected with a first pulley 9 through a flat key. The key is fixedly connected with a second pulley 11, and a belt 12 is tensioned between the first pulley 9 and the second pulley 11, wherein the driving motor 10 can be a stepping motor with a driver and a PLC control system, which can control the rotating shaft to perform discontinuous 180° rotation.
其中,转轴3上还焊接有第一遮挡板13和第二遮挡板14,第一遮挡板13和第二遮挡板14分别位于第一焊接台2的两侧,且均与第一焊接台2垂直,第一挡板6和第二挡板6上均设置有观察窗15,所述观察窗15正对通槽5处,观察窗15上设置有滤光片。Wherein, the rotating shaft 3 is also welded with a first shielding plate 13 and a second shielding plate 14, the first shielding plate 13 and the second shielding plate 14 are respectively located on both sides of the first welding station 2, and are all connected to the first welding station 2. Vertically, observation windows 15 are provided on the first baffle plate 6 and the second baffle plate 6, and the observation windows 15 are facing the through groove 5, and optical filters are provided on the observation windows 15.
其中,第一遮挡板13和第二遮挡板14远离转轴3的一侧端面上均固定连接有卡块16,卡块16上设置有第一通孔,机架1的底部焊接有横梁17,横梁17上设置有U型槽18,U型槽18上设置有与第一通孔配合的第二通孔,第一通孔和第二通孔之间穿设有销轴19。Wherein, the end surfaces of the first shielding plate 13 and the second shielding plate 14 away from the rotating shaft 3 are fixedly connected with a block 16, the block 16 is provided with a first through hole, and the bottom of the frame 1 is welded with a beam 17, The beam 17 is provided with a U-shaped groove 18, and the U-shaped groove 18 is provided with a second through hole matched with the first through hole, and a pin shaft 19 is pierced between the first through hole and the second through hole.
其中,夹具包括固定杆20和压杆21,固定杆20固定连接在第一焊接台2和第二焊接台4上靠近转轴3的一侧,压杆21的一端铰接在固定杆20上,压板7的另一端上设置有第一螺纹孔,第一螺纹孔内螺纹连接有紧固螺栓22,第一焊接台2和第二焊接台4上均设置有与紧固螺栓22配合的第二螺纹孔,紧固螺栓22的端部固定连接有旋柄23。Wherein, clamp comprises fixed rod 20 and pressure rod 21, and fixed rod 20 is fixedly connected on the side near rotating shaft 3 on first welding platform 2 and second welding platform 4, and one end of pressure rod 21 is hinged on the fixed rod 20, and pressing plate The other end of 7 is provided with a first threaded hole, and the first threaded hole is internally threaded with fastening bolts 22, and the first welding station 2 and the second welding station 4 are both provided with second threads that cooperate with the fastening bolts 22. The end of the fastening bolt 22 is fixedly connected with a rotary handle 23.
其中,压板7远离弹簧8的一侧和压杆21靠近第一焊接台2的一侧均固定连接有缓冲橡胶24。Wherein, both the side of the pressing plate 7 away from the spring 8 and the side of the pressing bar 21 close to the first welding station 2 are fixedly connected with a buffer rubber 24 .
其中,转轴3与机架1的转动连接处均内衬有滚珠轴承。Wherein, the rotating joints of the rotating shaft 3 and the frame 1 are lined with ball bearings.
本实用新型的使用方法如下:The using method of the present utility model is as follows:
使用时,先在第一焊接台2上安装两块铝模板25,安装时,滑动压板7,压板7压缩弹簧8,利用第一焊接台2两侧的压板7和弹簧8将两块铝模板25实施压紧,压紧时,两块铝模板25的接缝位于通槽5处,再转动压板7,利用压板7将铝模板25压紧固定,然后旋转紧固螺栓22,紧固螺栓22旋进到第二螺纹孔内,实现对铝模板25的压紧。During use, two aluminum templates 25 are installed on the first welding station 2 earlier. 25 to carry out compaction. When compacting, the seam of two aluminum templates 25 is located at the through groove 5, and then turn the pressing plate 7, and use the pressing plate 7 to compress and fix the aluminum template 25, and then rotate the fastening bolt 22, and the fastening bolt 22 Screw into the second threaded hole to realize the compression of the aluminum template 25.
然后驱动电机10运转,使得转轴3转动180°,第一焊接台2到达原第二焊接台4处,第二焊接台4又到了原第一焊接台2处,并且,第一焊接台2的背部朝上,此时,利用销轴19插入第一通孔和第二通孔,使得转轴3、第一焊接台2和第二焊接台4固定,然后机械手和焊机启动,在通槽5处对两块铝模板25的接缝进行焊接。Then the drive motor 10 runs, so that the rotating shaft 3 rotates 180 °, the first welding station 2 arrives at the original second welding station 4, and the second welding station 4 arrives at the original first welding station 2, and the first welding station 2 The back is facing upwards. At this time, use the pin shaft 19 to insert the first through hole and the second through hole, so that the rotating shaft 3, the first welding station 2 and the second welding station 4 are fixed, and then the manipulator and the welding machine are started. The seam of two aluminum templates 25 is welded.
在焊接的同时,操作工人可以在第二焊接台4上按照在第一焊接台2上的方法安装待焊接的两块铝模板25;待第一焊接台2上的铝模板25焊接完毕之后,驱动电机10带动转轴3旋转180°,按照上述原理,机械手和焊枪再对第二焊接台4上两块铝模板25进行焊接,同时,操作工人取下第一焊接工作台上已焊接完毕的铝模板25,然后再安装新的待焊接铝模板25,如此循环操作,铝模板焊接的工作效率更高。While welding, the operator can install two aluminum templates 25 to be welded according to the method on the first welding station 2 on the second welding station 4; after the aluminum template 25 on the first welding station 2 has been welded, The driving motor 10 drives the rotating shaft 3 to rotate 180°. According to the above principles, the manipulator and the welding torch weld the two aluminum templates 25 on the second welding table 4. At the same time, the operator removes the welded aluminum plate on the first welding table template 25, and then install a new aluminum template 25 to be welded, so the cycle operation, the work efficiency of aluminum template welding is higher.
以上实施例仅用以说明本实用新型的技术方案而非限制,尽管参照较佳实施例对本实用新型进行了详细说明,本领域的普通技术人员应当理解,可以对本实用新型的技术方案进行修改或者等同替换,而不脱离本实用新型技术方案的宗旨和范围,其均应涵盖在本实用新型的权利要求范围当中。本实用新型未详细描述的技术、形状、构造部分均为公知技术。The above embodiments are only used to illustrate the technical solution of the utility model without limitation. Although the utility model has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical solution of the utility model can be modified or Equivalent replacement without departing from the purpose and scope of the technical solution of the utility model shall be covered by the claims of the utility model. The technologies, shapes and construction parts not described in detail in the utility model are all known technologies.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201820032649.5U CN207757158U (en) | 2018-01-09 | 2018-01-09 | A kind of welding bench of aluminum alloy pattern plate welding robot |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201820032649.5U CN207757158U (en) | 2018-01-09 | 2018-01-09 | A kind of welding bench of aluminum alloy pattern plate welding robot |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN207757158U true CN207757158U (en) | 2018-08-24 |
Family
ID=63183295
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201820032649.5U Expired - Fee Related CN207757158U (en) | 2018-01-09 | 2018-01-09 | A kind of welding bench of aluminum alloy pattern plate welding robot |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN207757158U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109352253A (en) * | 2018-10-19 | 2019-02-19 | 湖州锐舰机械科技有限公司 | A kind of artificial welding auxiliary device |
-
2018
- 2018-01-09 CN CN201820032649.5U patent/CN207757158U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109352253A (en) * | 2018-10-19 | 2019-02-19 | 湖州锐舰机械科技有限公司 | A kind of artificial welding auxiliary device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN205271248U (en) | Truck chassis tail lamp scaffold weldment frock | |
| CN104959754A (en) | Automobile axle housing drain plug seat welding device | |
| CN109967304A (en) | For smearing the automatic oiling device of lubricating MoS 2 oil to complete machine bolt | |
| CN219746746U (en) | Welding device for machining machine tool plate | |
| CN218487491U (en) | Quick clamping device of gantry laser cutting machine | |
| CN116871647A (en) | Multi-point welding device for automobile plate | |
| CN211387843U (en) | Clamp structure for CNC (computer numerical control) machining | |
| CN211277215U (en) | High-efficient welding frock | |
| CN218426476U (en) | Air pipe welding device | |
| CN217889811U (en) | Automatic welding device for studs of stainless steel panels | |
| CN214161743U (en) | An automatic welding device for civil air defense door | |
| CN201931218U (en) | A linear welding machine | |
| CN206702474U (en) | An automatic welding machine for sealing strips of civil air defense door frames | |
| CN209532572U (en) | A kind of pipe counterpart specific purpose tool | |
| CN223160190U (en) | Argon arc welding machine with work piece location centre gripping function | |
| CN219852966U (en) | Rotary welding fixture | |
| CN222307906U (en) | A simple automatic pneumatic capping mechanism for post-processing of workpieces | |
| CN223338585U (en) | Aluminum alloy car body welding device | |
| CN223588585U (en) | Automatic welding system for civil air defense door frame sealing strip | |
| CN221890812U (en) | Riveting press for sheet metal machining | |
| CN221791892U (en) | Post-treatment device for high-strength finish-rolled deformed steel bar | |
| CN219201863U (en) | New energy battery detection platform | |
| CN217799917U (en) | Welding device for outer plate of plate spring lifting lug | |
| CN223172281U (en) | General type machine case welding positioning jig | |
| CN222696231U (en) | Rotary multi-angle stud welding gun device, stud welding mechanism and stud welding equipment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP02 | Change in the address of a patent holder |
Address after: 402660 5-5 and 5-6 plots of South District of Tongnan Industrial Park, Chongqing Patentee after: CHONGQING XINJIURONG TECHNOLOGY Co.,Ltd. Address before: 402660 Blocks 5-5 and 5-6 in Nanan Industrial Park, Chongqing Patentee before: CHONGQING XINJIURONG TECHNOLOGY Co.,Ltd. |
|
| CP02 | Change in the address of a patent holder | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180824 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |