CN207727555U - I-shaped prestressed concrete slabs staking pilework - Google Patents

I-shaped prestressed concrete slabs staking pilework Download PDF

Info

Publication number
CN207727555U
CN207727555U CN201721828391.1U CN201721828391U CN207727555U CN 207727555 U CN207727555 U CN 207727555U CN 201721828391 U CN201721828391 U CN 201721828391U CN 207727555 U CN207727555 U CN 207727555U
Authority
CN
China
Prior art keywords
embedded steel
steel plate
nut
embedded
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721828391.1U
Other languages
Chinese (zh)
Inventor
徐汉东
滕坤
周元
周天明
戴林建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Dingda High Tech Construction Co ltd
Joint Inspection (Jiangsu) Technology Co.,Ltd.
Original Assignee
Changzhou Institute Of Building Science Group Ltd By Share Ltd
JIANGSU DINGDA BUILDING NEW TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changzhou Institute Of Building Science Group Ltd By Share Ltd, JIANGSU DINGDA BUILDING NEW TECHNOLOGY Co Ltd filed Critical Changzhou Institute Of Building Science Group Ltd By Share Ltd
Priority to CN201721828391.1U priority Critical patent/CN207727555U/en
Application granted granted Critical
Publication of CN207727555U publication Critical patent/CN207727555U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of I-shaped prestressed concrete slabs staking pileworks, including first segment stake and the second section stake, the tail portion of the first segment stake is equipped with the first pre-embedded steel slab, the front end of the second section stake is equipped with the second pre-embedded steel slab, first pre-embedded steel slab is equipped with multiple nuts, the nut upper and lower ends are threaded with the first reinforcing bar and the second reinforcing bar respectively, second embedded board is equipped with bellows corresponding with the nut of the first embedded board, the lower end of second reinforcing bar corresponds to the front end be inserted into bellows and the tail portion of first segment stake is made to save stake with second and docks, and both the first pre-embedded steel slab and the second pre-embedded steel slab are fixedly connected.By the above-mentioned means, the I-shaped prestressed concrete slabs staking pilework of the utility model, can ensure that pile pile docking structure is stablized, at low cost, construction is convenient.

Description

工字型预应力钢筋混凝土板桩接桩结构I-shape Prestressed Reinforced Concrete Sheet Pile Connection Structure

技术领域technical field

本实用新型涉及领域,特别是涉及一种工字型预应力钢筋混凝土板桩接桩结构。The utility model relates to the field, in particular to an I-shaped prestressed reinforced concrete sheet pile connection structure.

背景技术Background technique

预制管桩是我国建设工程中大量使用的桩基产品之一,但是管桩现场拼接普遍存在问题,常规的拼接方式如焊接,其焊接接头受天气和操作人员素养影响大,通常质量不易保证,为加快工期通常出现焊缝冷却时间不够,桩就被压入土,焊缝遇地下水迅速降温,焊缝开裂,导致接桩质量较差。但如果保证焊缝冷却时间,施工效率就受影响。如焊接消耗时间太长,则因土体触变性,增加管桩沉桩难度,常常导致不能达到设计标高,给上部建筑安全带来隐患。传统机械连接如扣接等虽然减少了焊接工作量,但是沉桩过程中扣件可能脱落,质量难以得到保证,而且成本较高。Prefabricated pipe piles are one of the pile foundation products widely used in my country's construction projects, but there are common problems in the on-site splicing of pipe piles. The conventional splicing methods such as welding, the welded joints are greatly affected by the weather and the quality of the operators, and the quality is usually not easy to guarantee. In order to speed up the construction period, the cooling time of the weld is usually not enough, the pile is pressed into the soil, the weld is cooled rapidly when it meets groundwater, the weld cracks, and the quality of the pile connection is poor. However, if the cooling time of the weld is guaranteed, the construction efficiency will be affected. If the welding time is too long, the thixotropy of the soil will increase the difficulty of sinking the pipe piles, often resulting in failure to reach the design elevation, which will bring hidden dangers to the safety of the superstructure. Although traditional mechanical connections such as buckle joints reduce the welding workload, the fasteners may fall off during the pile sinking process, making it difficult to guarantee the quality and high cost.

发明内容Contents of the invention

本实用新型主要解决的技术问题是提供一种工字型预应力钢筋混凝土板桩接桩结构,能够保证管桩对接结构稳定,成本低,施工便捷。The technical problem mainly solved by the utility model is to provide an I-shaped prestressed reinforced concrete sheet pile connection structure, which can ensure the stability of the pipe pile connection structure, low cost and convenient construction.

为解决上述技术问题,本实用新型采用的一个技术方案是:提供一种工字型预应力钢筋混凝土板桩接桩结构,包括第一节桩和第二节桩,所述第一节桩的尾部设有第一预埋钢板,所述第二节桩的前端部设有第二预埋钢板,所述第一预埋钢板上设有多个螺帽,所述螺帽上下两端分别螺纹连接有第一钢筋和第二钢筋,所述第二预埋板上设有与第一预埋板的螺帽相对应的波纹管,所述第二钢筋的下端对应插入波纹管内使第一节桩的尾部与第二节桩的前端部对接,并且将第一预埋钢板和第二预埋钢板两者固定连接。In order to solve the above technical problems, a technical solution adopted by the utility model is to provide an I-shaped prestressed reinforced concrete sheet pile connection structure, including a first section pile and a second section pile, and the first section pile The tail is provided with a first pre-embedded steel plate, the front end of the second section pile is provided with a second pre-embedded steel plate, the first pre-embedded steel plate is provided with a plurality of nuts, and the upper and lower ends of the nuts are respectively threaded. The first steel bar and the second steel bar are connected, and the bellows corresponding to the nuts of the first embedded plate are provided on the second embedded plate, and the lower end of the second steel bar is correspondingly inserted into the bellows so that the first section The tail of the pile is docked with the front end of the second section pile, and the first pre-embedded steel plate and the second pre-embedded steel plate are fixedly connected.

在本实用新型一个较佳实施例中,所述螺帽的一部分与第一钢筋螺纹连接,其余部分与第二钢筋螺纹连接。In a preferred embodiment of the present invention, a part of the nut is screwed to the first steel bar, and the rest is screwed to the second steel bar.

在本实用新型一个较佳实施例中,所述第一钢筋进入螺帽深度为螺帽长度的一半,所述第二钢筋进入螺帽深度为螺帽长度的一半 In a preferred embodiment of the present invention, the depth of the first steel bar entering the nut is half the length of the nut, and the depth of the second steel bar entering the nut is half the length of the nut .

在本实用新型一个较佳实施例中,所述第一预埋钢板和第二预埋钢板之间通过焊接固定,所述螺帽下端端部与第一预埋钢板的开孔边缘焊接。In a preferred embodiment of the present invention, the first pre-embedded steel plate and the second pre-embedded steel plate are fixed by welding, and the lower end of the nut is welded to the opening edge of the first pre-embedded steel plate.

在本实用新型一个较佳实施例中,所述波纹管为中空结构并且内填充有高强结构胶。In a preferred embodiment of the present invention, the bellows is hollow and filled with high-strength structural glue.

在本实用新型一个较佳实施例中,所述第一预埋钢板和第二预埋钢板为工字型结构的钢板,所述螺帽和波纹管的数量为2个或者更多。In a preferred embodiment of the present invention, the first embedded steel plate and the second embedded steel plate are steel plates with an I-shaped structure, and the number of the nuts and bellows is 2 or more.

在本实用新型一个较佳实施例中,所述螺帽和波纹管的数量为5个。In a preferred embodiment of the present invention, the number of said nuts and bellows is five.

本实用新型的有益效果是:本实用新型工字型预应力钢筋混凝土板桩接桩结构,能够保证管桩对接结构稳定,成本低,施工便捷。The beneficial effects of the utility model are: the I-shaped prestressed reinforced concrete sheet pile connection structure of the utility model can ensure the stability of the butt joint structure of pipe piles, low cost and convenient construction.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图,其中:In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some implementations of the present invention. For example, for those of ordinary skill in the art, other drawings can also be obtained based on these drawings without creative work, wherein:

图1是本实用新型工字型预应力钢筋混凝土板桩接桩结构一较佳实施例的结构示意图;Fig. 1 is the structural representation of a preferred embodiment of the I-shaped prestressed reinforced concrete sheet pile connection pile structure of the present invention;

图2是图1所示的工字型预应力钢筋混凝土板桩接桩结构的局部结构放大示意图;Fig. 2 is the enlarged schematic view of the partial structure of the I-shaped prestressed reinforced concrete sheet pile connection structure shown in Fig. 1;

图3是图1所示的工字型预应力钢筋混凝土板桩接桩结构的局部结构示意图;Fig. 3 is the local structure schematic diagram of the I-shaped prestressed reinforced concrete sheet pile connection structure shown in Fig. 1;

图4是图1所示的工字型预应力钢筋混凝土板桩接桩结构的局部结构示意图;Fig. 4 is the local structure schematic diagram of the I-shaped prestressed reinforced concrete sheet pile connection structure shown in Fig. 1;

附图中各部件的标记如下:1、第一节桩,2、第二节桩,3、第一预埋钢板,4、第二预埋钢板,5、螺帽,6、第一钢筋,7、第二钢筋,8、波纹管,9、高强度结构胶。The marks of each part in the accompanying drawings are as follows: 1. The first section pile, 2. The second section pile, 3. The first pre-embedded steel plate, 4. The second pre-embedded steel plate, 5. Nut, 6. The first steel bar, 7. The second steel bar, 8. Bellows, 9. High-strength structural adhesive.

具体实施方式Detailed ways

下面将对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅是本实用新型的一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本实用新型保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, not all of them. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

请参阅图1,一种工字型预应力钢筋混凝土板桩接桩结构,包括第一节桩1和第二节桩2,第一节桩1的尾部设有第一预埋钢板3,第二节桩2的前端部设有第二预埋钢板4,第一预埋钢板3上设有多个螺帽5,螺帽5上下两端分别螺纹连接有第一钢筋6和第二钢筋7,第二预埋板4上设有与第一预埋板3的螺帽5相对应的波纹管8,第二钢筋7的下端对应插入波纹管8内使第一节桩1的尾部与第二节桩2的前端部对接,并且将第一预埋钢板3和第二预埋钢板4两者固定连接,螺帽5为特制超长高强度螺帽,第一钢筋6和第二钢筋7为高强度钢筋。Please refer to Fig. 1, an I-shaped prestressed reinforced concrete sheet pile connection structure, including the first section pile 1 and the second section pile 2, the tail of the first section pile 1 is provided with the first pre-embedded steel plate 3, the second section pile The front end of the two-section pile 2 is provided with a second pre-embedded steel plate 4, and the first pre-embedded steel plate 3 is provided with a plurality of nuts 5, and the upper and lower ends of the nut 5 are respectively threaded with a first steel bar 6 and a second steel bar 7 The second pre-embedded plate 4 is provided with a corrugated tube 8 corresponding to the nut 5 of the first pre-embedded plate 3, and the lower end of the second steel bar 7 is correspondingly inserted into the corrugated tube 8 so that the afterbody of the first section pile 1 is aligned with the second The front end of the two-section pile 2 is docked, and the first embedded steel plate 3 and the second embedded steel plate 4 are fixedly connected. The nut 5 is a special super-long high-strength nut. The first steel bar 6 and the second steel bar 7 For high-strength steel.

另外,螺帽5的一部分与第一钢筋6螺纹连接,其余部分与第二钢筋7螺纹连接。In addition, a part of the nut 5 is screwed to the first steel bar 6 , and the rest is screwed to the second steel bar 7 .

另外,第一钢筋6进入螺帽5深度为螺帽5长度的一半,第二钢筋7进入螺帽5深度为螺帽5长度的一半 In addition, the depth of the first steel bar 6 entering the nut 5 is half the length of the nut 5 , and the depth of the second steel bar 7 entering the nut 5 is half the length of the nut 5 .

另外,第一预埋钢板3和第二预埋钢板4之间通过焊接固定,螺帽5焊接连接在第一预埋钢板3上。In addition, the first embedded steel plate 3 and the second embedded steel plate 4 are fixed by welding, and the nut 5 is connected to the first embedded steel plate 3 by welding.

另外,波纹管8为中空结构并且内填充有高强结构胶9。In addition, the bellows 8 is hollow and filled with high-strength structural glue 9 .

另外,第一预埋钢板3和第二预埋钢板4为工字型结构的钢板,螺帽5和波纹管8的数量为2个或者更多。In addition, the first embedded steel plate 3 and the second embedded steel plate 4 are steel plates with an I-shaped structure, and the number of nuts 5 and bellows 8 is 2 or more.

另外,螺帽5和波纹管8的数量为5个。In addition, the number of nuts 5 and bellows 8 is five.

本实用新型工字型预应力钢筋混凝土板桩接桩结构具体原理如下:第一节桩1成形前在其尾部设置第一预埋钢板3、多个特制超长高强度螺帽5、第一钢筋6,第一预埋钢板4上设具有与螺帽对应的开孔,螺帽5的一端与第一预埋钢板4的开孔边缘焊接连接,另一端与第一钢筋6螺纹连接,连接深度为螺帽5的一半;第一钢筋6的长度至少满足其规范要求的锚固长度。第二节桩2成形前在其头部设置第二预埋钢板4和高强波纹管8;波纹管8内为中空,便于后期填充高强浆料;施工时,现将第二节桩2垂直施入土体内,第二节桩2露出地面的部分不低于1m,并用固定装置将其固定;在第一节桩和1第二节桩2对接前,第二节桩2端部的波纹管8内填充高强度结构胶9;将第一节桩1吊起前,将第二钢筋7拧入第一节桩1内的特制超长高强度螺帽6内,拧入深度为螺帽6长度的一半;第一节桩1起吊后,与第二节桩2端部对中,将第一节桩1尾部的第二钢筋7插入波纹管8内,第一节桩1和第二节桩2对接完成后,通过焊接第一预埋钢筋3和第二预埋钢筋4使第一节桩1和第二节桩2连接为一体。The specific principle of the I-shaped prestressed reinforced concrete sheet pile connection structure of the utility model is as follows: the first pre-embedded steel plate 3, a plurality of special super-long high-strength nuts 5, the first Reinforcing bar 6, the first pre-embedded steel plate 4 is provided with an opening corresponding to the nut, one end of the nut 5 is welded to the edge of the opening of the first pre-embedded steel plate 4, and the other end is threadedly connected to the first steel bar 6. The depth is half of the nut 5; the length of the first steel bar 6 at least meets the anchorage length required by its specification. Before the second section pile 2 is formed, a second pre-embedded steel plate 4 and a high-strength corrugated pipe 8 are arranged on its head; the bellows 8 is hollow, which is convenient for later filling of high-strength slurry; In the soil body, the part of the second section pile 2 exposed to the ground is not less than 1m, and it is fixed with a fixing device; before the first section pile and the second section pile 2 are docked, the bellows at the end of the second section pile 2 8 is filled with high-strength structural glue 9; before lifting the first section pile 1, the second steel bar 7 is screwed into the special super-long high-strength nut 6 in the first section pile 1, and the screwing depth is 6 half of the length; after the first section pile 1 is hoisted, it is centered with the end of the second section pile 2, and the second steel bar 7 at the end of the first section pile 1 is inserted into the bellows 8, and the first section pile 1 and the second section After the docking of the piles 2 is completed, the first section pile 1 and the second section pile 2 are connected as one by welding the first pre-embedded steel bar 3 and the second pre-embedded steel bar 4 .

区别于现有技术,本实用新型工字型预应力钢筋混凝土板桩接桩结构,能够保证管桩对接结构稳定,成本低,施工便捷。Different from the prior art, the utility model has an I-shaped prestressed reinforced concrete sheet pile connection structure, which can ensure the stability of the pipe pile connection structure, low cost and convenient construction.

以上所述仅为本实用新型的实施例,并非因此限制本实用新型的专利范围,凡是利用本实用新型说明书内容所作的等效结构或等效流程变换,或直接或间接运用在其它相关的技术领域,均同理包括在本实用新型的专利保护范围内。The above descriptions are only examples of the present utility model, and are not intended to limit the patent scope of the present utility model. Any equivalent structure or equivalent process transformation made by using the content of the utility model description, or directly or indirectly used in other related technologies Fields are all included in the scope of patent protection of the utility model in the same way.

Claims (7)

1.一种工字型预应力钢筋混凝土板桩接桩结构,其特征在于,包括第一节桩和第二节桩,所述第一节桩的尾部设有第一预埋钢板,所述第二节桩的前端部设有第二预埋钢板,所述第一预埋钢板上设有多个螺帽,所述螺帽上下两端分别螺纹连接有第一钢筋和第二钢筋,所述第二预埋板上设有与第一预埋板的螺帽相对应的波纹管,所述第二钢筋的下端对应插入波纹管内使第一节桩的尾部与第二节桩的前端部对接,并且将第一预埋钢板和第二预埋钢板两者固定连接。1. a kind of I-shaped prestressed reinforced concrete sheet pile connection pile structure, it is characterized in that, comprise the first section pile and the second section pile, the afterbody of described first section pile is provided with the first pre-embedded steel plate, described The front end of the second section pile is provided with a second pre-embedded steel plate, the first pre-embedded steel plate is provided with a plurality of nuts, and the upper and lower ends of the nuts are respectively threaded with a first steel bar and a second steel bar, so The second pre-embedded plate is provided with a corrugated tube corresponding to the nut of the first pre-embedded plate, and the lower end of the second steel bar is correspondingly inserted into the corrugated tube so that the tail of the first section pile is aligned with the front end of the second section pile. butt joint, and fixedly connect the first embedded steel plate and the second embedded steel plate. 2.根据权利要求1所述的工字型预应力钢筋混凝土板桩接桩结构,其特征在于,所述螺帽的一部分与第一钢筋螺纹连接,其余部分与第二钢筋螺纹连接。2. The H-shaped prestressed reinforced concrete sheet pile connection structure according to claim 1, characterized in that, a part of the nut is threaded with the first steel bar, and the rest is threaded with the second steel bar. 3.根据权利要求2所述的工字型预应力钢筋混凝土板桩接桩结构,其特征在于,所述第一钢筋进入螺帽深度为螺帽长度的一半,所述第二钢筋进入螺帽深度为螺帽长度的一半 3. The H-shaped prestressed reinforced concrete sheet pile connection structure according to claim 2, characterized in that, the depth of the first reinforcement entering the nut is half the length of the nut, and the second reinforcement enters the nut The depth is half the length of the nut . 4.根据权利要求1-3任一所述的工字型预应力钢筋混凝土板桩接桩结构,其特征在于,所述第一预埋钢板和第二预埋钢板之间通过焊接固定,所述螺帽下端端部与第一预埋钢板的开孔边缘焊接。4. The I-shaped prestressed reinforced concrete sheet pile connection structure according to any one of claims 1-3, characterized in that, the first pre-embedded steel plate and the second pre-embedded steel plate are fixed by welding, and the The lower end of the nut is welded to the opening edge of the first embedded steel plate. 5.根据权利要求4所述的工字型预应力钢筋混凝土板桩接桩结构,其特征在于,所述波纹管为中空结构并且内填充有高强结构胶。5. The I-shaped prestressed reinforced concrete sheet pile connection structure according to claim 4, characterized in that, the bellows is a hollow structure filled with high-strength structural glue. 6.根据权利要求5所述的工字型预应力钢筋混凝土板桩接桩结构,其特征在于,所述第一预埋钢板和第二预埋钢板为工字型结构的钢板,所述螺帽和波纹管的数量为2个或者更多。6. The I-shaped prestressed reinforced concrete sheet pile connection structure according to claim 5, wherein the first embedded steel plate and the second embedded steel plate are steel plates of an I-shaped structure, and the screw The number of caps and bellows is 2 or more. 7.根据权利要求6所述的工字型预应力钢筋混凝土板桩接桩结构,其特征在于,所述螺帽和波纹管的数量为5个。7. The I-shaped prestressed reinforced concrete sheet pile connection structure according to claim 6, wherein the number of said nuts and bellows is five.
CN201721828391.1U 2017-12-25 2017-12-25 I-shaped prestressed concrete slabs staking pilework Active CN207727555U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721828391.1U CN207727555U (en) 2017-12-25 2017-12-25 I-shaped prestressed concrete slabs staking pilework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721828391.1U CN207727555U (en) 2017-12-25 2017-12-25 I-shaped prestressed concrete slabs staking pilework

Publications (1)

Publication Number Publication Date
CN207727555U true CN207727555U (en) 2018-08-14

Family

ID=63086384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721828391.1U Active CN207727555U (en) 2017-12-25 2017-12-25 I-shaped prestressed concrete slabs staking pilework

Country Status (1)

Country Link
CN (1) CN207727555U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882019A (en) * 2017-12-25 2018-04-06 江苏鼎达建筑新技术有限公司 I-shaped prestressed concrete slabses staking pilework

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882019A (en) * 2017-12-25 2018-04-06 江苏鼎达建筑新技术有限公司 I-shaped prestressed concrete slabses staking pilework

Similar Documents

Publication Publication Date Title
CN104358207A (en) Rapid steel trestle construction structure and construction method
CN103924505A (en) Prefabricated steel-concrete combination T beam with corrugated steel web and construction method
CN110593485A (en) Main material damage-free detachable steel-concrete combined beam
CN205907604U (en) Steel bridge segmental hoisting counterpoint fixing device
CN102839678A (en) Structure for improving rigidity and stability of foundation pit steel support
CN111188457A (en) Edge sealing beam structure of super high-rise steel structure building and construction method
CN203222738U (en) Steel pipe latticed column temporary buttress supporting device
CN209669688U (en) A kind of half assembled thin-wall piers
CN103469735A (en) Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN110318344A (en) A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method
CN207727555U (en) I-shaped prestressed concrete slabs staking pilework
CN202124933U (en) Connecting structure for steel bar truss floor deck and concrete wall column
CN105421251B (en) Plate-girder jacking supporting mechanism, plate-girder jacking supporting tool
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN211922288U (en) Grouting sleeve connection assembly type reinforced concrete central anti-collision guardrail
CN214461277U (en) Quick plugging mechanism for overhanging I-steel reserved hole
CN105604342A (en) Comprehensive reinforcing method for T-shaped beam of reinforced concrete frame
CN107882019A (en) I-shaped prestressed concrete slabses staking pilework
CN205294673U (en) Change basic connection structure
CN208293762U (en) A kind of connection structure in steel building
CN103195079B (en) Installing type template, installing type template group and complete installing type plate device
CN204728493U (en) A kind of concrete beam and girder steel sidepiece have just connect dry type syndeton
CN104481162A (en) Reinforcing structure applicable to punching-resistant stand column and construction method thereof
CN209620242U (en) Strenthening member for basement structure
CN204097885U (en) For the combined steel board fixing structure of ring road bridge anti-collision wall construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 213015 Jiangsu province Changzhou City Zhonglou District Mushu Road No. 10

Patentee after: JIANGSU DINGDA HIGH-TECH CONSTRUCTION Co.,Ltd.

Country or region after: China

Patentee after: Joint Inspection (Jiangsu) Technology Co.,Ltd.

Address before: 213015 Jiangsu province Changzhou City Zhonglou District Mushu Road No. 10

Patentee before: JIANGSU DINGDA HIGH-TECH CONSTRUCTION Co.,Ltd.

Country or region before: China

Patentee before: CHANGZHOU ARCHITECTUAL RESEARCH INSTITUTE GROUP Co.,Ltd.

CP03 Change of name, title or address