CN101311482B - Bolt reinforced structure for steel column foot - Google Patents

Bolt reinforced structure for steel column foot Download PDF

Info

Publication number
CN101311482B
CN101311482B CN2007102007132A CN200710200713A CN101311482B CN 101311482 B CN101311482 B CN 101311482B CN 2007102007132 A CN2007102007132 A CN 2007102007132A CN 200710200713 A CN200710200713 A CN 200710200713A CN 101311482 B CN101311482 B CN 101311482B
Authority
CN
China
Prior art keywords
newly
suspension column
column base
increased
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2007102007132A
Other languages
Chinese (zh)
Other versions
CN101311482A (en
Inventor
常建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2007102007132A priority Critical patent/CN101311482B/en
Publication of CN101311482A publication Critical patent/CN101311482A/en
Application granted granted Critical
Publication of CN101311482B publication Critical patent/CN101311482B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a reinforcing structure of a column base bolt of a steel column which includes a holding down bolt (1), original column base reinforcing steel bars (5) and a column base foundation (8); newly added column base vertical reinforcing steel bars (6) at the most external side and the original column base reinforcing steel bars (5) in the four corners of the column base foundation are connected by adopting a welding mode; the other newly added column base vertical reinforcing steel bars are anchored in the column base foundation (8) by drilling and using epoxy resin mortars; the column base foundation (8) and the original column base reinforcing steel bars (5), the newly added column base vertical reinforcing steel bars (6) at the most external side, newly added column base reinforcing steel bars (9) at the top side and newly added transverse column base reinforcing steel bars (10) are coated by concreting (7). The concreting (7) is 100mm higher than the newly added column base reinforcing steel bars (9) at the top side. The diameters of the newly added reinforcing steel bars are 16 to 20mm and the space between the newly added reinforcing steel bars is 150mm. The grade of the concreting (7) is higher than C20. The reinforcing structure is suitable for carrying out reinforcement when the intensity of the holding down bolt of the steel column is not enough.

Description

Bolt reinforced structure for steel column foot
Technical field
The present invention relates to a kind of bolt reinforced structure for steel column foot of steel building, use this structure can realize the reinforcement of coupled columns foot bolt simply and effectively.
Background technology
Steel building is because its quick construction, build is light and handy, be applied in the building structure in recent years increasingly extensively, particularly be applied in the factory building structure more, and as the member of the final power transmission of steel structure system, the safety of steel column foot just more seems particularly important, sometimes because design, artificial deviation appears in the construction, or the construction finish after building increased extra load again, and when finding these problems, steel column foot has often been constructed and has been finished, this moment is because the suspension column bolt strength is not enough, its strength deficiency is with the opposing pressure that post was transmitted, might occur the suspension column bolt in the use and be broken the situation that destruction is taken place, and then threaten the safety of total, at this moment just must give the reinforcement processing by the coupled columns foot bolt.For the not enough reinforcement measure of suspension column bolt strength, usually all be on the reinforced concrete foundation under the suspension column, to hole, bury additionally foot bolt underground with epoxy resin mortar, need set up the rigidity outrigger in addition, could will increase bolt tension force like this newly and pass to the original boots beam of suspension column, thereby play the effect of reinforcement by this rigidity outrigger.Adopt this method to waste time and energy, newly-increased reinforcement bolt and rigidity outrigger need special toward contact, also seem very uneconomical when bringing difficulty to reinforcement work.
Figure 1 shows that traditional reinforced structure schematic diagram, promptly increase the steel work suspension column full-page proof behind the stone bolt.Wherein, (1) is original stone bolt, (2) stone bolt for increasing, and (3) are the boots beam on original suspension column, and (8) are heel foundation, and (4) rigidity outrigger for increasing, this outrigger are to be convenient to the pulling force on the newly-increased bolt is passed to original boots beam.As can be seen from the figure, the stone bolt of increase and rigidity outrigger need special, are unfavorable for gathering materials on the spot the whole reinforcement process not only complexity but also economic inadequately that seems.
Summary of the invention
The technical problem to be solved in the present invention is: at traditional reinforced structure not only complexity but also sub-economic weak point when solution suspension column bolt strength is not enough, propose a kind of new steel column foot reinforced structure, the reinforcement during with realization coupled columns foot bolt strength deficiency.
The present invention constitutes like this: it comprises stone bolt (1), original suspension column reinforcing bar (5), heel foundation (8), newly-increased outermost suspension column vertical reinforcement (6) is connected with original suspension column reinforcing bar (5) employing welding manner in four angles of heel foundation, all the other newly-increased suspension column vertical reinforcements adopt boring and are anchored in the heel foundation (8) with epoxy resin mortar, and concreting (7) is with heel foundation (8) and original suspension column reinforcing bar (5), newly-increased outermost suspension column vertical reinforcement (6), newly-increased top side suspension column reinforcing bar (9), newly-increased horizontal suspension column reinforcing bar (10) parcel.
Concreting (7) is higher than newly-increased top side suspension column reinforcing bar (9) 100mm.
The diameter of described newly-increased reinforcing bar is 16~20mm, and spacing is 150mm.
The grade of concreting (7) is higher than C20.
In above structure, newly-increased reinforcing bar, newly placed concrete form one with suspension column, make anchor into the basis interior newly add reinforcing bar and original stone bolt co-operation, thereby remedied the problem of original stone bolt insufficient strength, easy and finished reinforcement work effectively.
The present invention reinforces when being applicable to steel column stone bolt insufficient strength, some members need special drawback when having avoided adopting traditional reinforcing mode, the reinforcement work that only need use in the engineering reinforcing bar commonly used and concrete just can finish stone bolt, simple, economical, be convenient to operation.
Description of drawings
Fig. 1 is traditional steel column foot reinforced structure schematic diagram;
Fig. 2 is a structural representation of the present invention.
The specific embodiment
Embodiments of the invention: as shown in Figure 2, can carry out as follows when adopting coupled columns foot bolt reinforcement of the present invention:
The first, the concrete at four angles of heel foundation 8 is destroyed, expose original suspension column reinforcing bar 5, exposed length should guarantee the weld length requirement, promptly the length of welded lap is 100mm, and with the concrete hacking of basic side;
Second, set up the suspension column reinforcing bar, reinforcing bar adopts the double-layer double-direction configuration, and bar space is 150mm, and diameter d is 16~20mm, for increasing adhesion stress, reinforcing bar should adopt figuratum II grade reinforcing steel, and newly-increased outermost suspension column vertical reinforcement 6 is connected with original suspension column reinforcing bar 5 employing welding manners in four angles of patten, and the length of welded lap is 100mm, the suspension column vertical reinforcement that all the other newly add should adopt boring and be anchored in the original base with epoxy resin mortar, and the degree of depth in hole is 20d;
The 3rd, concreting 7, concrete grade should not be lower than C20, and the height of young concrete is that suspension column stiffener height and position of living in increases 100mm.As can be seen, concreting 7 is wrapped to form one with heel foundation 8 and original suspension column reinforcing bar 5, newly-increased outermost suspension column vertical reinforcement 6, newly-increased top side suspension column reinforcing bar 9, newly-increased horizontal suspension column reinforcing bar 10, make to anchor into and newly add reinforcing bar and original stone bolt co-operation in the basis, thereby remedied the problem of original stone bolt insufficient strength, easy and finished reinforcement work effectively.

Claims (4)

1. steel column foot reinforced structure, it comprises stone bolt (1), original suspension column reinforcing bar (5), heel foundation (8), it is characterized in that: newly-increased outermost suspension column vertical reinforcement (6) is connected with original suspension column reinforcing bar (5) employing welding manner in four angles of heel foundation, all the other newly-increased suspension column vertical reinforcements adopt boring and are anchored in the heel foundation (8) with epoxy resin mortar, and concreting (7) is with heel foundation (8) and original suspension column reinforcing bar (5), newly-increased outermost suspension column vertical reinforcement (6), newly-increased top side suspension column reinforcing bar (9), newly-increased horizontal suspension column reinforcing bar (10) parcel.
2. steel column foot reinforced structure according to claim 1 is characterized in that: concreting (7) is higher than newly-increased top side suspension column reinforcing bar (9) 100mm.
3. steel column foot reinforced structure according to claim 1, it is characterized in that: the diameter of described newly-increased outermost suspension column vertical reinforcement (6), all the other newly-increased suspension column vertical reinforcements, newly-increased top side suspension column reinforcing bar (9) and newly-increased horizontal suspension column reinforcing bar (10) is 16~20mm, and spacing is 150mm.
4. steel column foot reinforced structure according to claim 1 is characterized in that: the grade of concreting (7) is higher than C20.
CN2007102007132A 2007-05-25 2007-05-25 Bolt reinforced structure for steel column foot Expired - Fee Related CN101311482B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007102007132A CN101311482B (en) 2007-05-25 2007-05-25 Bolt reinforced structure for steel column foot

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007102007132A CN101311482B (en) 2007-05-25 2007-05-25 Bolt reinforced structure for steel column foot

Publications (2)

Publication Number Publication Date
CN101311482A CN101311482A (en) 2008-11-26
CN101311482B true CN101311482B (en) 2010-06-23

Family

ID=40100299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007102007132A Expired - Fee Related CN101311482B (en) 2007-05-25 2007-05-25 Bolt reinforced structure for steel column foot

Country Status (1)

Country Link
CN (1) CN101311482B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174176A (en) * 2011-12-26 2013-06-26 贵阳铝镁设计研究院有限公司 Heightening method and structure of high cup opening prefabricated column foundation cup opening
CN102979320B (en) * 2012-12-29 2016-04-06 上海市建筑科学研究院(集团)有限公司 The method of serious damaged reinforced concrete frame structure reinforced by outsourcing steel bushing
CN103266664A (en) * 2013-06-03 2013-08-28 南京万德游乐设备有限公司 Footing connecting structure
CN103498572B (en) * 2013-10-12 2016-05-04 北京筑福国际工程技术有限责任公司 The construction method of the additional clamping plate beam of stone structure and clamping plate post ruggedized construction
CN105297796B (en) * 2014-07-21 2017-02-15 五冶集团上海有限公司 Rapid reinforcing and transforming method for drum type flying shears

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2661701B1 (en) * 1990-05-02 1996-05-15 Pomagalski Sa FORMWORK AND MASSIF FOR ANCHORING A PYLON; PROCESS FOR MAKING A FOUNDATION.
CN2644575Y (en) * 2003-07-01 2004-09-29 浙江中南建设集团有限公司 Portal frame pedestal footing without shear key
CN2861328Y (en) * 2005-12-19 2007-01-24 上海市第二建筑有限公司 Subsectional embedded structure of concrete steel column in reverse construction engineering

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2661701B1 (en) * 1990-05-02 1996-05-15 Pomagalski Sa FORMWORK AND MASSIF FOR ANCHORING A PYLON; PROCESS FOR MAKING A FOUNDATION.
CN2644575Y (en) * 2003-07-01 2004-09-29 浙江中南建设集团有限公司 Portal frame pedestal footing without shear key
CN2861328Y (en) * 2005-12-19 2007-01-24 上海市第二建筑有限公司 Subsectional embedded structure of concrete steel column in reverse construction engineering

Also Published As

Publication number Publication date
CN101311482A (en) 2008-11-26

Similar Documents

Publication Publication Date Title
CN106894523B (en) Connecting joint of rectangular steel pipe concrete column and steel reinforced concrete beam
CN100567659C (en) The base configuration of iron tower
CN104790424B (en) The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof
CN203452204U (en) Connecting node of prefabricated hollow steel-reinforced concrete column and steel girder
CN101311482B (en) Bolt reinforced structure for steel column foot
CN102071747A (en) Joint of square steel tube concrete column and reinforced concrete floor and production method thereof
KR101673287B1 (en) Methods of increasing the sectional resisting force for negative moment acting at the end part of beam in case of repair or remodeling
CN109441016B (en) Assembled concrete structure column steel tube sleeve joint and manufacturing method thereof
CN109578011B (en) Supporting structure in municipal tunnel and construction method thereof
CN209838429U (en) Back anchor shield constructs lining cutting supporting construction
CN110424529B (en) Prefabricated cantilever beam balcony and construction method
CN201254731Y (en) Steel cross beam type dismountable stupa base
CN111140248A (en) Bias tunnel structure applying prestress to pilot tunnel and construction method thereof
CN207211389U (en) A kind of assembled architecture is encorbelmented outrigger anchor hoop
CN103924676B (en) Prestressing force connects beams of concrete concrete-filled circular steel tube column node
CN206360399U (en) The existing reinforced concrete coupling beam bracing means of one species " doubly-linked beam "
CN102912928B (en) Structural member for restraining grouting anchoring connection by using two ends of steel bar and connection method
CN211142788U (en) Semi-assembled combined pier
CN101105077A (en) Method for connecting reinforced concrete structures
CN103498573B (en) Set up the existing frame strengthening method of band frame bracing members
CN215329312U (en) Steel construction of usefulness is consolidated to pier stand
CN211286292U (en) Prefabricated cavity slab rib roof beam steel bar connection built-up member of assembled
CN210288522U (en) Dam foundation rock mass reinforced structure based on prefabricated hollow pile
CN208533863U (en) A kind of prefabricated girder of armored concrete
JP2013032682A (en) Construction pile and construction pile constructing method using the same

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER NAME: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

CP03 Change of name, title or address

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100623

Termination date: 20150525

EXPY Termination of patent right or utility model