CN207718654U - Precast shear wall Side fascia teaching training apparatus - Google Patents
Precast shear wall Side fascia teaching training apparatus Download PDFInfo
- Publication number
- CN207718654U CN207718654U CN201721142902.4U CN201721142902U CN207718654U CN 207718654 U CN207718654 U CN 207718654U CN 201721142902 U CN201721142902 U CN 201721142902U CN 207718654 U CN207718654 U CN 207718654U
- Authority
- CN
- China
- Prior art keywords
- steel reinforcement
- wall body
- side fascia
- reinforcement net
- precast shear
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Finishing Walls (AREA)
Abstract
The utility model is related to a kind of precast shear wall Side fascia teaching training apparatus, including exterior wall light-weight decorative face layer, polyphenylene heat insulation slab, wall body steel reinforcement net, temporary support embedded nut, grout sleeve, pre-buried wire box, installation lifting hanging piece, rigid plastics foam, fiber cloth mortar and strength adhesive, the wall body steel reinforcement net upper end connection installation lifting hanging piece, the wall body framework of steel reinforcement net surface is equipped with temporary support embedded nut, the wall body steel reinforcement net lower end is equipped with grout sleeve, grout sleeve is equipped with grout hole and extravasating hole, the wall body steel reinforcement net is wrapped with rigid plastics foam, it is enclosed with fiber cloth mortar on the outside of rigid plastics foam and side is covered with polyphenylene heat insulation slab wherein.The utility model has the beneficial effects that:During education activities are carried out, this teaching training apparatus can be used as the teaching aid of precast shear wall Side fascia, be conducive to grasp of the student to professional knowledge.
Description
Technical field
The utility model is a kind of teaching training apparatus, specifically a kind of precast shear wall Side fascia practice teaching dress
It sets.
Background technology
Pre-cast building has had nearly 30 years development courses in China, recent years under the support energetically of national policy,
The assembled architecture in China has obtained tremendous development.However college student and building industry worker to the understanding of assembled architecture and
Understanding is not deep, traces it to its cause and is a lack of suitable teaching training apparatus.Precast shear wall Side fascia is assembled architecture
One of main member is arranged in assembled architecture all around, the effects that playing load-bearing, heat preservation individual, go along with sb. to guard him, decorate.Prefabricated
During the processing of shear wall Side fascia, thermal insulation material and architectural surface are effectively just fixed on precast shear wall exterior wall
The outside of plate.However, it is few to the related introduction data of precast shear wall Side fascia on the market, therefore, Building class college students
It is not deep enough to the understanding of precast shear wall Side fascia with architectural industrialization worker, before also having the teacher or student of many schools
Production process was viewed and emulated by factory toward precast shear wall Side fascia, but architectural discipline is a very strong profession of practicality, perhaps
Multi-specialized technical ability, which needs to put into practice, to be operated and can cultivate, and the precast shear wall Side fascia of prefabricated components manufacturer manufacture is very
Heaviness, few then 1~2 ton, at most 4~8 tons, it is contemplated that the safe operation of student, such bulky precast shear wall Side fascia without
Method is for imparting knowledge to students and putting into practice operation.Therefore, it is badly in need of grinding creating a kind of precast shear wall Side fascia teaching training apparatus of lightweight, supplies
Architectural speciality student learns the manufacturing process and installation process of precast shear wall Side fascia.
Utility model content
It the purpose of the utility model is to overcome deficiency in the prior art, provides a kind of reasonable for structure, facilitates the pre- of teaching
Shear wall Side fascia teaching training apparatus processed.
Precast shear wall Side fascia teaching training apparatus, including exterior wall light-weight decorative face layer, polyphenylene heat insulation slab, wall body reinforcing bar
Skeleton, temporary support embedded nut, grout sleeve, pre-buried wire box, installation lifting hanging piece, rigid plastics foam, fiber cloth sand
Slurry and strength adhesive, the wall body steel reinforcement net upper end connection installation lifting hanging piece, the wall body framework of steel reinforcement net surface
Equipped with temporary support embedded nut, the wall body steel reinforcement net lower end is equipped with grout sleeve, and grout sleeve is equipped with grout hole
And extravasating hole, the wall body steel reinforcement net are wrapped with rigid plastics foam, fiber are enclosed on the outside of rigid plastics foam
Cloth mortar and side is covered with polyphenylene heat insulation slab wherein is equipped with exterior wall light-weight decorative face layer on the outside of polyphenylene heat insulation slab.
As preferred:Pass through strength gluing between the fiber cloth mortar, polyphenylene heat insulation slab and exterior wall light-weight decorative face layer
Agent connects.
As preferred:The wall body framework of steel reinforcement is equipped with pre-buried wire box on the net.
The utility model has the beneficial effects that:It, can be by the conduct of this teaching training apparatus during education activities are carried out
The teaching aid of precast shear wall Side fascia uses, and professional teachers control is in kind, and (precast shear wall Side fascia practice teaching fills
Set) and atlas (15G365-1) explained, be conducive to grasp of the student to professional knowledge.At the same time, this practice teaching fills
Set and replace concrete with rigid plastics foam, greatly alleviate dead load, 3m*3m or so without window opening precast shear wall outside
Wallboard, total weight about 130kg, only the 1/10 of comparable size concrete prefabricated stairs weight, student can be by small-sized liftings
Equipment completes installation and dismounting, breaks through the operative skill of student comprehensively, and ensure that the safety of entire practice teaching.
Description of the drawings
Fig. 1 precast shear wall Side fascia teaching training apparatus front views
Fig. 2 precast shear wall Side fascia teaching training apparatus vertical views
Fig. 3 precast shear wall Side fascia teaching training apparatus upward views
Fig. 4 precast shear wall Side fascia teaching training apparatus right views
Fig. 5 precast shear wall Side fascia teaching training apparatus wall body steel reinforcement nets
Fig. 6 precast shear wall Side fascia teaching training apparatus wall body steel reinforcement net 1-1 sectional views
Fig. 7 precast shear wall Side fascia teaching training apparatus wall body steel reinforcement net 2-2 sectional views
Fig. 8 precast shear wall Side fascia teaching training apparatus wall body steel reinforcement net 3-3 sectional views
Fig. 9 precast shear wall Side fascia teaching training apparatus wall body steel reinforcement net 4-4 sectional views
Reference sign:1. exterior wall light-weight decorative face layer;2. polyphenylene heat insulation slab;3. wall body steel reinforcement net;4. interim
Support embedded nut;5. grout sleeve;6. pre-buried wire box, 7. installation lifting hanging pieces, 8 rigid plastics foams;9. fiber cloth mortar;
10. strength adhesive.
Specific implementation mode
The utility model is described further with reference to embodiment.The explanation of following embodiments is only intended to help to manage
Solve the utility model.It should be pointed out that for those skilled in the art, not departing from the utility model principle
Under the premise of, several improvements and modifications can be made to this utility model, these improvement and modification also fall into the utility model
In scope of the claims.
As shown in Figures 1 to 9, the precast shear wall Side fascia teaching training apparatus of this example includes exterior wall light-weight decorative face
Layer 1, wall body steel reinforcement net 3, temporary support embedded nut 4, grout sleeve 5, pre-buried wire box 6, is installed polyphenylene heat insulation slab 2
Hanging piece 7, rigid plastics foam 8, fiber cloth mortar 9, strength adhesive 10.The main work of exterior wall light-weight decorative face layer 1
It with its decoration function, is formed using lightweight decorating material, and is fixed on thermal insulation material by strength adhesive 10;It is described poly-
The main function of benzene thermal insulation board 2 is function of heat insulation, is pasted on precast shear wall Side fascia by strength adhesive 10;Institute
The stress core that wall body steel reinforcement net 3 is entire precast shear wall Side fascia is stated, contexture is entirely by reference to prefabricated
Concrete shear force wall Side fascia (15G365-1) atlas, moreover, vertically and horizontally reinforcing bar must link securely, built-in fitting also need with
Wall body framework of steel reinforcement firm welding, the gap between wall body framework of steel reinforcement are clogged by rigid plastics foam 8;The temporary support is pre-
The effect for burying nut 4 is to be fixed temporarily precast shear wall Side fascia, and adjust precast shear wall Side fascia by supporting bar
Position, after institute's grouting liquid intensity reaches design (100% design strength) requirement, you can remove temporary support rod piece, temporarily
Support embedded nut 4 stays in preburied component always;The grout sleeve 5 is a kind of reinforcing bar link grout sleeve, grouting set
Cylinder upper end and a bar connecting of precast shear wall Side fascia are secured, and the reinforcing bar that next layer of Side fascia stretches out flooring is inserted into lower end
On, grout hole and extravasating hole are provided on grout sleeve;The effect of the pre-buried wire box 6 is through electric wire, and real training is in the process
The real training in terms of wearing electric wire can be carried out;Installation lifting hanging piece 7 for lifting by crane prefabricated components, in prefabricated outer wall panel transfer and
It is used in installation process, in order to ensure Hoisting Security, installation lifting hanging piece 7 must be reliably connected with wall body steel reinforcement net 3;Institute
Rigid plastics foam 8 is stated for filling the gap between wall body steel reinforcement net 3, entire precast shear wall Side fascia is made to have one
Determine rigidity;Fiber cloth mortar package 9 is in the outer surface of entire component by steel reinforcement net 3 and rigid plastics foam 8, exterior wall
Light-weight decorative face layer 1, polyphenylene heat insulation slab 2 are rolled into a stress entirety, improve the intensity of entire component;The strength gluing
Agent 10 is for bonding polyphenylene heat insulation slab and exterior wall lightweight decorating material.
When real training, by the suspension hook hanging of minor crane tool on installation lifting hanging piece 7, minor crane is then rotated
Precast shear wall Side fascia is moved on real training installment work face by tool, then the vertical range from installment work face about 1m is adjusted
The position of whole precast shear wall Side fascia makes the reinforcing bar that lower wall body stretches out wall top precisely align grout sleeve 5, and slowly decentralization is pre-
Shear wall Side fascia processed, and temporary support rod piece is fixed on by temporary support embedded nut 4 on precast shear wall Side fascia,
The other end of temporary support rod piece is fixed on flooring, it is ensured that entire precast shear wall Side fascia is not subjected to displacement, then by
Whether the installation site (plan-position and absolute altitude) of the measuring instruments check precast shear wall Side fascia such as theodolite, line pendant, which meets, sets
Meter requires.Bolt after errorless on fixed temporary support rod piece, slurries are poured by pressure grouting equipment in grout sleeve 5.
During real training, the low-intensity slurries such as lime white may be used and replace cement mortar, to facilitate prefabricated outer wall panel dismounting to pacify again
Real training is filled, achievees the purpose that recycling.
The wall body steel reinforcement net is the main member for carrying the dead weight of precast shear wall Side fascia and lifting load, and
There is no concrete to bond framework of steel reinforcement, in manufacturing process, wall body steel reinforcement net is fabricated to truss structure, and mould using hard
Strand foam fills gap, it is ensured that entire component has enough bearing capacity and non-deformability.The rigid plastics foam tool
Standby certain intensity, main the reason is that quality is very light, (practice teaching under the premise of entire element bearing capacity is of less demanding
Device), the framework of steel reinforcement of precast shear wall Side fascia is filled using rigid plastics foam can effectively mitigate the weight of structure.Institute
Plastering fiber cloth mortar is stated to be rolled into steel reinforcement net and rigid plastics foam, polyphenylene heat insulation slab, exterior wall lightweight decorating material
The one stress entirety for having some strength and rigidity.Fiber cloth has high intensity and high tenacity, and very light weight, is wrapped in
On the outside of rigid plastics foam and framework of steel reinforcement, the stress performance of entire component is effectively raised.
Following table is precast shear wall Side fascia reinforcement summary in Figure of description:
Claims (3)
1. a kind of precast shear wall Side fascia teaching training apparatus, it is characterised in that:Including exterior wall light-weight decorative face layer (1), gather
Benzene thermal insulation board (2), wall body steel reinforcement net (3), temporary support embedded nut (4), grout sleeve (5), pre-buried wire box (6), peace
Load hanging piece (7), rigid plastics foam (8), fiber cloth mortar (9) and strength adhesive (10), the wall body framework of steel reinforcement
Net (3) upper end connection installation lifting hanging piece (7), wall body steel reinforcement net (3) surface are equipped with temporary support embedded nut
(4), wall body steel reinforcement net (3) lower end is equipped with grout sleeve (5), and grout sleeve (5) is equipped with grout hole and extravasating hole,
The wall body steel reinforcement net (3) is wrapped with rigid plastics foam (8), and rigid plastics foam is enclosed with fiber on the outside of (8)
Cloth mortar (9) and wherein side are covered with polyphenylene heat insulation slab (2), and exterior wall light-weight decorative is equipped on the outside of polyphenylene heat insulation slab (2)
Face layer (1).
2. precast shear wall Side fascia teaching training apparatus according to claim 1, it is characterised in that:The fiber cloth sand
It is connected by strength adhesive (10) between slurry (9), polyphenylene heat insulation slab (2) and exterior wall light-weight decorative face layer (1).
3. precast shear wall Side fascia teaching training apparatus according to claim 1, it is characterised in that:The wall body reinforcing bar
Skeleton (3) is equipped with pre-buried wire box (6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721142902.4U CN207718654U (en) | 2017-09-07 | 2017-09-07 | Precast shear wall Side fascia teaching training apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721142902.4U CN207718654U (en) | 2017-09-07 | 2017-09-07 | Precast shear wall Side fascia teaching training apparatus |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207718654U true CN207718654U (en) | 2018-08-10 |
Family
ID=63064180
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721142902.4U Active CN207718654U (en) | 2017-09-07 | 2017-09-07 | Precast shear wall Side fascia teaching training apparatus |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207718654U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112064882A (en) * | 2020-08-11 | 2020-12-11 | 周学兵 | Concrete prefabricated member |
-
2017
- 2017-09-07 CN CN201721142902.4U patent/CN207718654U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112064882A (en) * | 2020-08-11 | 2020-12-11 | 周学兵 | Concrete prefabricated member |
CN112064882B (en) * | 2020-08-11 | 2021-12-31 | 苏州旭杰绿建装配式设计有限公司 | Concrete prefabricated member |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105625570B (en) | A kind of prefabricated beam column attachment means and preparation method thereof | |
CN104563384B (en) | A kind of decoration integrated large scale prefabricated out-hung panel of structural thermal insulation and preparation method thereof | |
CN105155685B (en) | A kind of assembled beam-column node and its construction method | |
CN112854745A (en) | Construction process of assembled building aluminum alloy template | |
CN106499092A (en) | A kind of lightgage steel joist composite concrete wallboard hoisting structure and its installation method | |
CN107605177A (en) | The construction method of efficient precast floor slab and its independent support frame | |
CN208023710U (en) | A kind of connection structure of assembly concrete shear wall | |
CN105507470B (en) | A kind of periphery overlapping overall assembled floor and its construction method | |
CN108130837A (en) | A kind of prefabricated road plate and its construction method | |
CN206308842U (en) | A kind of lightgage steel joist composite concrete wallboard hoisting structure | |
CN104831844B (en) | The unidirectional double rope inverted cone-shaped cable curtain wall construction methods of arc | |
CN207718654U (en) | Precast shear wall Side fascia teaching training apparatus | |
CN207244452U (en) | A kind of suspension bridge vice saddle adjusting apparatus in place | |
CN206971769U (en) | A kind of rubber support installation positioning special purpose device | |
CN206329145U (en) | A kind of quick assembled type enclosure wall | |
CN108170978A (en) | A kind of tensile capacity analysis method of the pre-buried lifting anchor bolt of precast concrete | |
CN208777557U (en) | Exposed inversion reinforcing bar grout sleeve precast concrete column | |
CN110439175A (en) | Ceramsite Concrete plate and its processing method with shear-resistant membrane shell structure | |
CN207458381U (en) | Precast shear wall lining teaching training apparatus | |
CN209514904U (en) | Assembled architecture frame column grouting teaching training apparatus | |
CN209297537U (en) | Assembled architecture shear wall grouting teaching training apparatus | |
CN107476263A (en) | A kind of construction method of prestressed pier anchor cable | |
CN208889184U (en) | A kind of assembled architecture comprehensive practical traning model | |
CN208534069U (en) | The assembled support device of steel bar truss floor support plate composite floor system | |
CN209635721U (en) | A kind of clear-water concrete GRC plate lifting balancing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 310020 B1047, building 1, 343 triumphal road, Zhejiang, Hangzhou Patentee after: Zhejiang Taixue Technology Group Co., Ltd Address before: 310020 B1047, building 1, 343 triumphal road, Zhejiang, Hangzhou Patentee before: ZHEJIANG TAIXUE TECHNOLOGY Co.,Ltd. |