CN207458381U - Precast shear wall lining teaching training apparatus - Google Patents

Precast shear wall lining teaching training apparatus Download PDF

Info

Publication number
CN207458381U
CN207458381U CN201721143302.XU CN201721143302U CN207458381U CN 207458381 U CN207458381 U CN 207458381U CN 201721143302 U CN201721143302 U CN 201721143302U CN 207458381 U CN207458381 U CN 207458381U
Authority
CN
China
Prior art keywords
steel reinforcement
wall body
reinforcement net
precast shear
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721143302.XU
Other languages
Chinese (zh)
Inventor
杜国平
龙照华
蒋晓燕
戚甘红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Taixue Technology Group Co., Ltd
Original Assignee
Zhejiang Taixue Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Taixue Technology Co Ltd filed Critical Zhejiang Taixue Technology Co Ltd
Priority to CN201721143302.XU priority Critical patent/CN207458381U/en
Application granted granted Critical
Publication of CN207458381U publication Critical patent/CN207458381U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of precast shear wall lining teaching training apparatus, including wall body steel reinforcement net, temporary support embedded nut, grout sleeve, installation lifting hanging piece, rigid plastics foam and fiber cloth mortar;The wall body steel reinforcement net is rectangular to arrange and leaves door opening shape opening, 1 upper end of wall body steel reinforcement net is equipped with installation lifting hanging piece, wall body framework of steel reinforcement net surface is equipped with temporary support embedded nut, the wall body steel reinforcement net lower end is equipped with grout sleeve, and grout hole and extravasating hole are provided on grout sleeve;Rigid plastics foam is wrapped in outside wall body steel reinforcement net, and fiber cloth mortar is enclosed on the outside of rigid plastics foam.The beneficial effects of the utility model are:During education activities development, it can be used using this teaching training apparatus as the teaching aid of precast shear wall lining, be conducive to grasp of the student to professional knowledge.

Description

Precast shear wall lining teaching training apparatus
Technical field
The utility model is related to a kind of teaching training apparatus, more particularly to a kind of precast shear wall lining practice teaching to fill It puts.
Background technology
Pre-cast building has had the development course of nearly 30 years in China, recent years under the support energetically of national policy, The assembled architecture in China has obtained tremendous development.However college student and building industry worker to the understanding of assembled architecture and Understanding is not deep, traces it to its cause and is a lack of suitable teaching training apparatus.Precast shear wall lining is assembled architecture One of main member is arranged in inside assembled architecture, is played separate room, is born the effects that load of floor.However, on the market Few to the related introduction data of precast shear wall lining, therefore, Building class college students and architectural industrialization worker are to pre- The understanding of shear wall lining processed is not deep enough, also has the teacher of many schools or student to go to precast shear wall lining Production process was viewed and emulated by factory, but architectural discipline is the very strong specialty of a practicality, and many professional skills need to put into practice behaviour Work can cultivate, and prefabricated components manufacturer manufacture precast shear wall lining it is very heavy, it is few then 1~2 ton, at most 4~8 tons, it is contemplated that the safe operation of student, such bulky precast shear wall lining are not used to teaching and are operated with practice. Therefore, it is badly in need of grinding the precast shear wall lining teaching training apparatus for creating a kind of lightweight, learns for architectural speciality student pre- The manufacturing process and installation process of shear wall lining processed.
Utility model content
It the purpose of the utility model is to overcome deficiency of the prior art, provides a kind of rational in infrastructure, facilitates the pre- of teaching Shear wall lining teaching training apparatus processed.
Precast shear wall lining teaching training apparatus, including wall body steel reinforcement net, temporary support embedded nut, grouting Sleeve, installation lifting hanging piece, rigid plastics foam and fiber cloth mortar;The wall body steel reinforcement net is rectangular to arrange and leaves Door opening shape opening, wall body steel reinforcement net upper end are equipped with installation lifting hanging piece, and wall body framework of steel reinforcement net surface is equipped with temporary support Embedded nut, the wall body steel reinforcement net lower end are equipped with grout sleeve, grout hole and extravasating hole are provided on grout sleeve;Firmly Matter plastic foam is wrapped in outside wall body steel reinforcement net, and fiber cloth mortar is enclosed on the outside of rigid plastics foam.
As preferred:It is pre-buried that the wall body steel reinforcement net is equipped with temporary support reinforcing in the lower section both sides of door opening shape opening Nut.
As preferred:The wall body framework of steel reinforcement is equipped with pre-buried wire box on the net.
The beneficial effects of the utility model are:Education activities development during, can using this teaching training apparatus as The teaching aid of precast shear wall lining uses, and professional teachers control is in kind, and (precast shear wall lining practice teaching fills Put) and atlas (15G365-2) explained, be conducive to grasp of the student to professional knowledge.At the same time, this practice teaching fills It puts and replaces concrete with rigid plastics foam, greatly alleviate in the band door opening precast shear wall of dead load, 3m*3m or so Wallboard, total weight about 110kg are only the 1/10 of comparable size concrete prefabricated stairs weight, and student can be by small-sized lifting Equipment completes installation and dismounting, breaks through the operative skill of student comprehensively, and ensure that the security of entire practice teaching.
Description of the drawings
Fig. 1 precast shear wall lining teaching training apparatus front views
Fig. 2 precast shear wall lining teaching training apparatus top views
Fig. 3 precast shear wall lining teaching training apparatus bottom views
Fig. 4 precast shear wall lining teaching training apparatus right views
Fig. 5 precast shear wall lining teaching training apparatus wall body framework of steel reinforcement figures
Fig. 6 precast shear wall lining teaching training apparatus wall body framework of steel reinforcement 1-1 sectional views
Fig. 7 precast shear wall lining teaching training apparatus wall body framework of steel reinforcement 2-2 sectional views
Fig. 8 precast shear wall lining teaching training apparatus wall body framework of steel reinforcement 3-3 sectional views
Fig. 9 precast shear wall lining teaching training apparatus wall body framework of steel reinforcement 4-4 sectional views
Figure 10 precast shear wall lining teaching training apparatus wall body framework of steel reinforcement 5-5 sectional views
Figure 11 precast shear wall lining teaching training apparatus wall body framework of steel reinforcement 6-6 sectional views
Reference sign:1. wall body steel reinforcement net;2. temporary support embedded nut;3. temporary support reinforces pre-buried spiral shell It is female;4. grout sleeve;5. pre-buried wire box, 6. installation lifting hanging pieces, 7. rigid plastics foams;8. fiber cloth mortar.
Specific embodiment
The utility model is described further with reference to embodiment.The explanation of following embodiments is only intended to help to manage Solve the utility model.It should be pointed out that for those skilled in the art, the utility model principle is not being departed from On the premise of, can also to the utility model, some improvement and modification can also be carried out, these improvement and modification also fall into the utility model In scope of the claims.
As shown in Figure 1 to 11, the precast shear wall lining teaching training apparatus of this example includes wall body framework of steel reinforcement 1 temporary support embedded nut 2 of net, temporary support reinforce embedded nut 3, grout sleeve 4, pre-buried wire box 5, installation lifting hanging piece 6, Rigid plastics foam 7, fiber cloth mortar 8.The wall body steel reinforcement net 1 is the stress core of entire precast shear wall lining Part, contexture is entirely by reference to precast concrete shear wall lining (15G365-2) atlas, moreover, vertically and horizontally steel Muscle must link securely, and built-in fitting is also needed with wall body framework of steel reinforcement firm welding, and the gap between wall body framework of steel reinforcement passes through hard Plastic foam 7 is clogged;The effect of the temporary support embedded nut 2 is to be fixed temporarily precast shear wall lining, and passes through branch Strut member adjust precast shear wall lining position, treat institute's grouting liquid intensity reach design (100% design strength) require with Afterwards, you can remove temporary support rod piece, temporary support embedded nut 4 is stayed in preburied component always;The temporary support is reinforced The main function of embedded nut 3 is the intensity for reinforcing precast shear wall lining doorway openings side, is avoided in structure hoisting process Middle damage, the mode of reinforcing can at hole fixation steel plate either template steel plate or the prior reserving hole of template, pass through spiral shell Bolt is fixed on temporary support and reinforces on embedded nut 3;The grout sleeve 4 is a kind of reinforcing bar link grout sleeve, grouting set Cylinder upper end and a bar connecting of precast shear wall lining are secured, and the reinforcing bar that next layer of Side fascia stretches out flooring is inserted into lower end On, grout hole and extravasating hole are provided on grout sleeve;The effect of the pre-buried wire box 5 is through electric wire, and real training is in the process The real training worn in terms of electric wire can be carried out;The installation lifting hanging piece 6 is for lifting by crane prefabricated components, in precast shear wall lining It is used in transfer and installation process, in order to ensure Hoisting Security, installation lifting hanging piece 6 must be reliable with wall body steel reinforcement net 1 Connection;The rigid plastics foam 7 is used to fill the gap between wall body steel reinforcement net 1, makes entire precast shear wall interior wall Plate possesses certain rigidity;The fiber cloth mortar package 8 steeps steel reinforcement net 1 and rigid plastics in the outer surface of entire component Foam 7 is rolled into a stress entirety, improves the intensity of entire component.
During real training, embedded nut 3 is reinforced by temporary support first, precast shear wall lining door opening bottom is added Gu afterwards then minor crane tool is rotated on installation lifting hanging piece 6 by the suspension hook hanging of minor crane tool, it will be pre- Shear wall lining processed is moved on real training installment work face, and the vertical range from installment work face about 1m adjusts prefabricated shearing The position of wallboard within the walls makes the reinforcing bar that lower wall body stretches out wall top accurately be directed at grout sleeve 4, slowly transfers in precast shear wall Wallboard, and temporary support rod piece is fixed on by temporary support embedded nut 3 on precast shear wall lining, temporary support bar The other end of part is fixed on flooring, it is ensured that entire precast shear wall lining is not subjected to displacement, and is then fallen by theodolite, line Etc. measuring instruments check precast shear wall lining installation site (plan-position and absolute altitude) whether meet design requirement.It is errorless The bolt on temporary support rod piece is fixed afterwards, and slurries are poured into grout sleeve 4 by pressure grouting equipment.During real training, The low-intensity such as lime white slurries may be employed instead of cement mortar, prefabricated outer wall panel dismounting to be facilitated to reinstall real training, reach The purpose of recycling.
The wall body steel reinforcement net is to carry the main member of the dead weight of precast shear wall lining and lifting load, and There is no concrete to bond framework of steel reinforcement, in manufacturing process, wall body steel reinforcement net is fabricated to truss structure, and is moulded using hard Strand foam fills gap, it is ensured that entire component possesses enough bearing capacity and non-deformability.The rigid plastics foam tool Standby certain intensity, main the reason is that quality the is very light, (practice teaching on the premise of entire element bearing capacity is of less demanding Device), the framework of steel reinforcement using rigid plastics foam filling precast shear wall lining can effectively mitigate the weight of structure.Institute It states plastering fiber cloth mortar and steel reinforcement net and rigid plastics foam is rolled into a stress for possessing some strength and rigidity It is whole.Fiber cloth has high intensity and high tenacity, and very light weight, is wrapped on the outside of rigid plastics foam and framework of steel reinforcement, Effectively raise the stress performance of entire component.
Following table is precast shear wall lining teaching training apparatus reinforcement summary in Figure of description:

Claims (3)

1. a kind of precast shear wall lining teaching training apparatus, it is characterised in that:Including wall body steel reinforcement net (1), temporarily Support embedded nut (2), grout sleeve (4), installation lifting hanging piece (6), rigid plastics foam (7) and fiber cloth mortar (8);Institute It states the rectangular arrangement of wall body steel reinforcement net (1) and leaves door opening shape opening, wall body steel reinforcement net (1) upper end is equipped with and installs Hanging piece (6), wall body steel reinforcement net (1) surface are equipped with temporary support embedded nut (2), the wall body steel reinforcement net (1) Lower end is equipped with grout sleeve (4), and grout sleeve is provided with grout hole and extravasating hole on (4);Rigid plastics foam (7) is wrapped in wall Outside body steel reinforcement net (1), fiber cloth mortar (8) is enclosed on the outside of rigid plastics foam (7).
2. precast shear wall lining teaching training apparatus according to claim 1, it is characterised in that:The wall body reinforcing bar Skeleton (1) is equipped with temporary support in the lower section both sides of door opening shape opening and reinforces embedded nut (3).
3. precast shear wall lining teaching training apparatus according to claim 1, it is characterised in that:The wall body reinforcing bar Skeleton (1) is equipped with pre-buried wire box (5).
CN201721143302.XU 2017-09-07 2017-09-07 Precast shear wall lining teaching training apparatus Active CN207458381U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721143302.XU CN207458381U (en) 2017-09-07 2017-09-07 Precast shear wall lining teaching training apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721143302.XU CN207458381U (en) 2017-09-07 2017-09-07 Precast shear wall lining teaching training apparatus

Publications (1)

Publication Number Publication Date
CN207458381U true CN207458381U (en) 2018-06-05

Family

ID=62282625

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721143302.XU Active CN207458381U (en) 2017-09-07 2017-09-07 Precast shear wall lining teaching training apparatus

Country Status (1)

Country Link
CN (1) CN207458381U (en)

Similar Documents

Publication Publication Date Title
CN102493603B (en) Prefabricated column of reserved concealed column channel, concealed column type complete assembled earthquake-resistant building and its method
CN106522382A (en) Fabricated concrete-filled steel tube column-H type steel beam self-resetting energy consumption connection joint
CN105155685B (en) A kind of assembled beam-column node and its construction method
CN106088327B (en) The production method of assembling frame column based on 3D printing
CN208023781U (en) A kind of assembled architecture wall and prefabricated concrete structure
CN207458381U (en) Precast shear wall lining teaching training apparatus
CN207718654U (en) Precast shear wall Side fascia teaching training apparatus
CN209514904U (en) Assembled architecture frame column grouting teaching training apparatus
CN102808511A (en) Method for constructing steel box column-concrete beam joint
CN202401667U (en) Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building
CN204940608U (en) The prefabrication and lifting body of wall of fabricated structure
CN204940585U (en) The precast wall body of assembled-type house
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN207794401U (en) A kind of composite floor
CN207567939U (en) A kind of cast-in-situ concrete columns hinged structures
CN206800964U (en) A kind of builder's jack bottom plate closes protector
CN205976447U (en) Scaffold frame of connecting with straight screw sleeve links wall spare
CN106193540B (en) A kind of GRC components
CN207663599U (en) Precast stair teaching training apparatus
CN207690339U (en) Truss bars superimposed sheet teaching training apparatus
CN107401215A (en) Assembled architecture and construction process
CN209297537U (en) Assembled architecture shear wall grouting teaching training apparatus
CN106351245A (en) Tower crane foundation base and construction method thereof
CN207526118U (en) For pre-buried and closure unwrapping wire hole unwrapping wire punch die
CN105951987A (en) Sub-frame post-cast joint with external permanent aluminum plate outer mold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 310020 B1047, building 1, 343 triumphal road, Zhejiang, Hangzhou

Patentee after: Zhejiang Taixue Technology Group Co., Ltd

Address before: 310020 B1047, building 1, 343 triumphal road, Zhejiang, Hangzhou

Patentee before: ZHEJIANG TAIXUE TECHNOLOGY Co.,Ltd.