CN207633847U - A kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus - Google Patents
A kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus Download PDFInfo
- Publication number
- CN207633847U CN207633847U CN201721792846.9U CN201721792846U CN207633847U CN 207633847 U CN207633847 U CN 207633847U CN 201721792846 U CN201721792846 U CN 201721792846U CN 207633847 U CN207633847 U CN 207633847U
- Authority
- CN
- China
- Prior art keywords
- steel beam
- chimney
- hydraulic
- hanging apparatus
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of chimney steel beam hydraulics to promote high-altitude integral slipping hanging apparatus and method.Device includes:Support steel beam, slideway, car stop, weight shifter, fixed anchor plate, hydraulic lifting jack, prestress wire;Construction method is realized by hanging apparatus.The utility model is directed to the steel beam lifting construction that bayonet joint is designed as between large and medium-sized Chimney in Fossil Power Plant concrete outer tube wall inner layers platform girder steel both ends end and concrete tube wall, it efficiently solves in construction because chimney inner space is small, girder steel element size is big, span is big, weight is big and the technical barrier of the direct vertical lifting of axial location can not be designed from girder steel.There is the utility model device to make simple, at low cost, convenient to assemble and disassemble, environmentally protective and energy repeated recycling utilize, the advantage that construction method is easy to operate, safe and reliable.
Description
Technical field
The utility model belongs to technical field of building construction, is mainly used in the concrete chimney outer tube wall of thermal power plant
The lifting construction of each main girder steel of layer platform in portion.The utility model discloses a kind of chimney internal platform girder steels to be carried using hydraulic synchronization
It rises and hanging apparatus in place is installed in the sliding of high-altitude integral level.
Background technology
The chimney design height in large and medium-sized thermal power plant is generally more meters of height of 210-240, belongs to towering structure, in coagulation
Inside the chimney outer tube wall of soil structure, it is typically designed with steel construction(Or glass fibre reinforced plastic structure)The smoke evacuation inner cylinder of material, due to chimney
Height is high, and inner space is narrow, and each layer platform steel beam lifting difficulty of construction is big, and operating risk coefficient is high, belongs to high-risk operations project.
Previous chimney inner layers platform girder steel mostly uses greatly hoist engine and is lifted with steel wire rope, but for being designed as two-tube suspension
The chimney of formula smoke evacuation inner cylinder(Or the large-scale chimney that Generator Set is mating), internal platform girder steel, usually with following spy
Point:Installation site is high(Upper platform steel girder erection absolute altitude meter height about more than 200), member profile size it is big, from great(What is had is single
Girder steel dead weight reaches more than 40 tons), the connection type between girder steel and concrete chimney outer tube wall is that girder steel two ends are located at coagulation
It the annular concrete bracket top surface of native inner wall of stack protrusion and is horizontally inserted into the reserving hole of outer tube wall, for this structure
When the main girder steel of platform is lifted using traditional hoist engine with steel wire rope, difficulty of construction and the dangerous bigger of safety wind need to seek
New technological means solves problem encountered, the labor intensity for reducing construction worker's working at height and the safety that faces
Risk, it is ensured that steel beam lifting operation process efficient quick, safe and reliable.
Utility model content
The utility model aim is intended to provide a kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus.
Specifically, chimney steel beam hydraulic promotes high-altitude integral slipping hanging apparatus, include mainly:Support steel beam, slideway, again
Object shifter, car stop, fixed anchor plate, hydraulic lifting jack and prestress wire, support steel beam are box structure, quantity
It it is two, arranged in parallel in the horizontal plane, the flange plate up and down of every support steel beam is provided with vertically communicated strip
A horizontal slide, hydraulic lifting jack and fixation are respectively installed in hole, support steel beam top surface along strip hole both sides position
It is fixedly connected at the top of support plate, weight shifter is installed in fixed anchor plate bottom, and weight shifter is arranged in slideway, in level
It is slided along slideway level under the action of tractive force, prestress wire upper end passes through strip hole and hydraulic lifting jack
Connection
Further, the slideway is the horizontally U-shaped sliding slot that channel steel makes.
Further, two support steel beams setting is first in chimney concrete outer tube wall cylinder(Or chimney top dust stratification
Platform)It top surface and is mutually parallel, horizontal axis of the support steel beam horizontal axis perpendicular to the main girder steel of chimney platform.
Further, the two ends of the slideway are additionally provided with the car stop of limit on-slip.
Further, overturn-preventing hook is additionally provided in the fixed anchor plate.In slipping, weight shifter passes through solid
Determine bearing plate support and hydraulic lifting jack, hydraulic lifting jack puies forward chimney platform girder steel entirety by prestress wire
Along the slideway of support steel beam into line slip, the horizontal power of sliding is to pass through chain block(Or hoist engine)Horizontal drag is fixed
Support plate provides.
The hanging apparatus integral level sliding is to pass through chain block(Or hoist engine)Pull hydraulic lifting jack bottom
The fixed anchor plate in portion is realized to drive weight shifter along slideway horizontal sliding.
The beneficial effects of the utility model are:
In conclusion a kind of chimney steel beam hydraulic provided by the utility model promotes high-altitude integral slipping hanging apparatus, it is
It is designed between large and medium-sized thermal power plant concrete chimney outer tube wall internal platform girder steel both ends end and concrete tube wall
Construct for the steel beam lifting of bayonet joint, efficiently solve in construction because chimney inner space is small, steel beam structure size is big,
Span is big, weight is big and the direct vertical lifting of axial location construction technology problem in place can not be designed from girder steel, this practicality is new
Type have device make it is simple, at low cost, convenient to assemble and disassemble, environmentally protective and can repeated recycling utilize, construction method is easy to operate,
Safe and reliable advantage.
Description of the drawings
Fig. 1 is hydraulic pressure lift high-altitude integral slipping hanging apparatus assembling schematic diagram;
Fig. 2 is the vertical view that support steel beam, slideway, car stop three fit together;
Fig. 3 is the side view of hydraulic pressure lift high-altitude integral slide device;
Fig. 4 is the demonstration graph that chimney steel beam hydraulic promotes high-altitude integral level sliding construction step.
Reference numeral is as follows:
1. support steel beam;2. slideway;3. car stop;4. weight shifter;5. fixed anchor plate;6. hydraulic lifting jack;
7. prestress wire;8. strip hole;9. polyfluortetraethylene plate;10. overturn-preventing is linked up with.
Specific implementation mode
Specific embodiment of the present utility model is illustrated below in conjunction with the accompanying drawings:
As shown in Figure 1 to Figure 3, chimney steel beam hydraulic promotion high-altitude integral slide device includes mainly:Support steel beam 1 is slided
Road 2, car stop 3, weight shift unit 4, fixed anchor plate 5, hydraulic lifting jack 6, prestress wire 7.
Support steel beam 1 is box type structure girder, and totally two, the cylinder head in chimney concrete outer tube wall is arranged by left and right horizontal
(Or chimney top dust stratification platform)It top surface and is mutually parallel, level of the support steel beam horizontal axis perpendicular to the main girder steel of chimney platform
Axis;Flange plate is provided with vertically communicated strip hole to every support steel beam up and down, and the length satisfaction of strip hole is not small
In the distance for waiting for that hoisting steel beam needs horizontal sliding.
1 top surface of support steel beam is disposed with two U-shaped horizontal slides 2 made of channel steel, and two horizontal slides 2 are along support
The 8 both sides horizontal parallel arrangement of strip hole of 1 top flange plate of girder steel, 2 two ends of slideway are equipped with car stop 3.
6 bottom of hydraulic lifting jack is fixedly connected with 5 top surface of fixed anchor plate, if 5 bottom of fixed anchor plate is equipped with
Dry weight shifter 4, weight shift unit 4 is placed in U-shaped slideway 2.
The length of prestress wire 7 should meet maximum lifting height, and the radical of prestress wire 7 should meet maximum and hang
Fill the promotion requirement of load;7 upper end of prestress wire passes vertically through the strip hole 8 and hydraulic pressure of track support steel beam 1
Lifting jack 6 is connected, and 7 lower end of prestress wire passes through bottom anchorage and girder steel end top flange plate phase to be lifted
Even.
Overturn-preventing hook 10 is used for overturn-preventing;One layer of polyfluortetraethylene plate 9 of elongated paving in U-shaped slideway, for reducing cunning
Horizontal frictional resistance during shifting between the idler wheel and slideway of weight shifter.
As shown in figure 4, chimney steel beam hydraulic, which promotes high-altitude integral sliding construction method, specifically includes following steps:
Step 1, assembling hydraulic pressure lift high-altitude integral slipping hanging apparatus.
It is in the venue that support steel beam 1, slideway 2, car stop 3 is assembled integral according to design drawing, it is lifted by crane and is pacified with hoist engine
It is attached to the first top of chimney concrete outer tube wall cylinder, or is arranged in the dust stratification platform girder steel top surface of top inside chimney.By hydraulic pressure
After lifting jack 6, fixed anchor plate 5,4 three of weight shifter assemble in the venue, pacified with hoist engine integral lifting
It is attached on the U-shaped slideway 2 of track support steel beam top surface two.Track is passed through to support from bottom to top 7 upper end of prestress wire
The strip hole 8 of girder steel 1 is attached with hydraulic lifting jack 6.Hydraulic lifting jack 6 passes through hydraulic oil pipe and hydraulic pressure
Driving pumping plant is attached.
Step 2, prestress wire lower end is connect with hoisting steel beam is waited for.
By zero meter face inside girder steel horizontal transport to be lifted to chimney, by the lower end of the two groups of prestress wires in left and right
Head is connect with the hoisting point position of hoisting steel beam two ends is waited for respectively by bottom anchorage.
Step 3, vertical lifting girder steel.
Start hydraulic power unit driving hydraulic lifting jack work, it is flat that chimney to be lifted is promoted by prestress wire
Platform girder steel slowly rises, until girder steel bottom surface absolute altitude is higher by concrete chimney outer barrel wall circular bracket top surface at design installed height mark
When 30 ~ 50mm of absolute altitude, stops girder steel and promoted.
Step 4, high-altitude integral level slides girder steel.
With two chain blocks(Or hoist engine)Synchronize the hold-down support of horizontal drag hydraulic lifting jack in the same direction bottom
Plate, to drive slideway horizontal sliding of the weight shifter along support steel beam top surface.In slipping, weight shifter support solid
Determine support plate and hydraulic lifting jack, hydraulic lifting jack proposes girder steel integral level displacement by prestress wire,
Up to girder steel horizontal sliding to design position.
Step 5, steel girder erection is in place.
Hydraulic power unit drives hydraulic lifting jack oil cylinder flexible, drive prestress wire carry girder steel decline 30 ~
50mm, until girder steel is in place on the annular bracket built-in fitting of installation site.
Step 6, the reversed horizontal sliding of hanging apparatus is resetted.
Wait for that steel girder erection is in place, after the fully relaxed unloading of steel strand wires, by prestress wire lower end and girder steel junction
Disintegrate and detach, drives the flexible drive prestress wire of hydraulic lifting jack oil cylinder to decline falling by hydraulic power unit and reset;
Reversed Level Promoting hydraulic lifting jack, makes hanging apparatus(Including:Weight shifter, fixed anchor plate, hydraulic pressure lift are very heavy
Top and steel strand wires)Horizontal slide reverse shuffle along support steel beam top surface is to initial starting slip locations.
Step 7, action of the step 2 to step 6 is repeated, lower layers platform steel is successively lifted by top-down sequence
Beam.
Repeat the above steps 2 to step 6 action, by top-down sequence successively by remaining each same axis of layer platform
The girder steel sliding and lifting installation of position is in place.For the girder steel of lighter in weight, also can allow to lift by crane within the scope of load, by lower layer
More girders of platform are connected by steel wire rope while being lifted by crane, slide installation up and down, to accelerate to lift speed, improve construction work
Effect.
Step 8, sliding and lifting device is removed, next engineering is remained and re-uses.
After the completion of steel beam lifting, prestress wire, hydraulic lifting jack, hold-down support are removed successively with hoist engine
Plate, weight shifter, support steel beam, keep the slide device of dismantling, remain next engineering and re-use.
The above is preferred embodiments of the present invention, it is noted that for the ordinary skill of the art
For personnel, under the premise of not departing from principle described in the utility model, it can also make several improvements and retouch, these improvement
The scope of protection of the utility model is also should be regarded as with retouching.
Claims (5)
1. a kind of chimney steel beam hydraulic promotes high-altitude integral slipping hanging apparatus, which is characterized in that the chimney steel beam hydraulic carries
Increasing empty integral slipping hanging apparatus includes:Support steel beam, slideway, car stop, weight shifter, fixed anchor plate, hydraulic pressure lift
Jack, prestress wire, slideway are located at support steel beam top flange plate top surface, hydraulic lifting jack and fixed anchor plate top
Portion is fixedly connected, and weight shifter is installed in fixed anchor plate bottom, and weight shifter is arranged in the sliding slot of slideway, prestress steel
The upper end of twisted wire passes through the strip hole of support steel beam to be connect with hydraulic lifting jack from bottom to top.
2. chimney steel beam hydraulic as described in claim 1 promotes high-altitude integral slipping hanging apparatus, which is characterized in that described
Support steel beam is box structure, and flange plate is equipped with vertically communicated strip hole, support steel beam quantity to support steel beam up and down
It it is two, setting is in chimney concrete outer tube wall cylinder head or chimney top dust stratification layer platform top surface, and two support steel beams are in level
Be mutually parallel on face and its horizontal axis perpendicular to the main girder steel of chimney platform horizontal axis.
3. chimney steel beam hydraulic as described in claim 1 promotes high-altitude integral slipping hanging apparatus, which is characterized in that the cunning
Road is the U-shaped horizontal sliding track that channel steel makes, and two slideways are along the two sides of the top flange plate strip hole of support steel beam
The elongated parallel arrangement of edge, the position of slideway two ends are additionally provided with the car stop of limit on-slip.
4. chimney steel beam hydraulic as described in claim 1 promotes high-altitude integral slipping hanging apparatus, which is characterized in that described solid
Determine to be additionally provided with the overturn-preventing hook for preventing hydraulic lifting jack from toppling on support plate.
5. chimney steel beam hydraulic as described in claim 1 promotes high-altitude integral slipping hanging apparatus, which is characterized in that described heavy
The traction end of object shifter is chain block or hoist engine.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721792846.9U CN207633847U (en) | 2017-12-20 | 2017-12-20 | A kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721792846.9U CN207633847U (en) | 2017-12-20 | 2017-12-20 | A kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207633847U true CN207633847U (en) | 2018-07-20 |
Family
ID=62853151
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721792846.9U Active CN207633847U (en) | 2017-12-20 | 2017-12-20 | A kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207633847U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107842246A (en) * | 2017-12-20 | 2018-03-27 | 西北电力建设第四工程有限公司 | A kind of chimney steel beam hydraulic lifting high-altitude integral slipping hanging apparatus and method |
CN109989588A (en) * | 2019-03-15 | 2019-07-09 | 上海建工七建集团有限公司 | The installation of steel vestibule is promoted and high-altitude translation device and its installation method with whole |
-
2017
- 2017-12-20 CN CN201721792846.9U patent/CN207633847U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107842246A (en) * | 2017-12-20 | 2018-03-27 | 西北电力建设第四工程有限公司 | A kind of chimney steel beam hydraulic lifting high-altitude integral slipping hanging apparatus and method |
CN109989588A (en) * | 2019-03-15 | 2019-07-09 | 上海建工七建集团有限公司 | The installation of steel vestibule is promoted and high-altitude translation device and its installation method with whole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107013038B (en) | A kind of steel structure slipping of building roof lighting Zhongting changes column construction method | |
CN201411900Y (en) | Hydraulic die lifter for chimneys | |
CN204199721U (en) | A kind of erecting device for factory building construction high and medium structure | |
CN103726421A (en) | Height and span adjustable track paver for metro construction | |
CN207633847U (en) | A kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus | |
CN110685433A (en) | Chimney construction device and construction method applying hydraulic lifting and rollover technology | |
CN107842246A (en) | A kind of chimney steel beam hydraulic lifting high-altitude integral slipping hanging apparatus and method | |
CN211286601U (en) | Chimney construction device applying hydraulic lifting and rollover technology | |
CN104192735A (en) | Small-size crane | |
CN101566005B (en) | Chimney hydraulic mould lifting device | |
CN103173230B (en) | Transporting and constructing method and device for coke-oven checker bricks | |
CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
CN203684019U (en) | Height and span adjustable track laying machine for subway construction | |
CN211007590U (en) | Construction platform for overhanging steel structure | |
CN204983692U (en) | Concrete panel's hoist device | |
CN201507112U (en) | Sliding template system | |
CN104401887B (en) | A kind of micro lifter | |
CN201362556Y (en) | Earthwork overhead hoist | |
CN202347884U (en) | Overhaul platform for water turbine | |
CN206523054U (en) | Thermal Equipment Quick overhaul umbrella shape movable platform | |
CN205617771U (en) | Construction operation platform and pipe -line transportation integrated device in high residential building elevartor shaft | |
CN214573768U (en) | Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot | |
CN210763974U (en) | Be suitable for reverse construction method to get soil mouthful and pass suspension type electric hoist for material | |
CN208980193U (en) | The curtain wall hanging apparatus of anticollision | |
CN203256222U (en) | Transportation and construction device for coke oven checker bricks |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 710065 12010, 12011, floor 20, building D, city gate, Tangyan South Road, hi tech Zone, Xi'an City, Shaanxi Province Patentee after: China energy construction northwest City Construction Co.,Ltd. Address before: 710038 Textile Road, Baqiao District, Xi'an, Shaanxi Province, No. 1198 Patentee before: NORTHWEST POWER CONSTRUCTION NO.4 Co.,Ltd. |
|
CP03 | Change of name, title or address |