CN207617069U - Pipeline shaper - Google Patents

Pipeline shaper Download PDF

Info

Publication number
CN207617069U
CN207617069U CN201721393463.4U CN201721393463U CN207617069U CN 207617069 U CN207617069 U CN 207617069U CN 201721393463 U CN201721393463 U CN 201721393463U CN 207617069 U CN207617069 U CN 207617069U
Authority
CN
China
Prior art keywords
core
group
pipeline
prepreg tape
wall layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721393463.4U
Other languages
Chinese (zh)
Inventor
王强
王晓融
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Senbaide Electromechanical Technology Co Ltd
Original Assignee
Fuzhou Senbaide Electromechanical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou Senbaide Electromechanical Technology Co Ltd filed Critical Fuzhou Senbaide Electromechanical Technology Co Ltd
Priority to CN201721393463.4U priority Critical patent/CN207617069U/en
Application granted granted Critical
Publication of CN207617069U publication Critical patent/CN207617069U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Extrusion Moulding Of Plastics Or The Like (AREA)

Abstract

The utility model is related to a kind of pipeline shapers, it is characterised in that:Including rack and the rotation core model that is located in rack, the steel band that the rotation core model includes core and is spirally wound on core, the steel band is inputted by core first end spiral winding, is exported by core second end and is passed through the centre bore of core to core first end;The first extruder that the first plastic material is squeezed out toward steel strip surface is equipped with above the core first end, to form the inner wall layer of pipeline;The stage casing of the core is equipped with the integrated charging tray toward spiral winding multilayer prepreg tape in inner wall layer, to form the fiber composite of pipeline;It is equipped with above the core second end toward the second extruder for squeezing out the second plastic material on fiber composite, to form the protective layer of pipeline;It is additionally provided with prepreg tape on the stage casing of core and imports composite structure, pipe cutting machine and tubing bracket are equipped with successively in core output end.The pipeline shaper reasonable design is conducive to production and obtains the good pipeline of intensity.

Description

Pipeline shaper
Technical field:
The utility model is related to a kind of pipeline shapers.
Background technology:
For large-diameter pipeline(Diameter is in 500mm or more)Production, presently, there are following problem, 1, pipeline strength Difference, 2, the pipeline circularity of production, cylindricity it is poor, 3, low production efficiency.
Invention content:
The purpose of this utility model is to provide a kind of pipeline shaper, which is conducive to give birth to Production obtains the good pipeline of intensity.
The utility model pipeline shaper, it is characterised in that:Including rack and the rotation core model being located in rack, the rotation Core mould includes core and the steel band that is spirally wound on core, and the steel band is inputted by core first end spiral winding, by turning Core second end exports and passes through the centre bore of core to core first end;It is equipped with toward steel strip surface and squeezes above the core first end The first extruder for going out the first plastic material, to form the inner wall layer of pipeline;The stage casing of the core is equipped with toward in inner wall layer The integrated charging tray of spiral winding multilayer prepreg tape, to form the fiber composite of pipeline;It is equipped with above the core second end past The second extruder that the second plastic material is squeezed out on fiber composite, to form the protective layer of pipeline;On the stage casing of core also Composite structure is imported equipped with prepreg tape, pipe cutting machine and tubing bracket are equipped with successively in core output end.
Further, above-mentioned core first end turns to turn to guide wheel and third to guide wheel, second equipped with steel band first turns guide Wheel, the core second end are turned equipped with the 4th to guide wheel.
Further, above-mentioned integrated charging tray is integrated box type kink comprising parallel multiple charging trays side by side, each charging tray On be wound with prepreg tape, the prepreg tape on adjacent charging tray misplaces successively to be spirally wound on the prepreg tape of last layer.
Further, have 20-180 charging tray, i.e. fiber composite pre- by 20-180 layers in above-mentioned integrated box type kink Leaching band is built up.
Further, above-mentioned prepreg tape import composite structure include four groups of hand adjustment pressing plates being located in core outlet and Two groups of Electronic control pressing plates between being located at four groups of hand adjustment pressing plates.
Further, above-mentioned four groups of hand adjustment pressing plates include two groups of inclined plates and two groups of arc pressuring plates, are first group oblique respectively Pressing plate, second group of inclined plate, first group of arc pressuring plate and second group of arc pressuring plate;First group of inclined plate and second group of inclined plate point Not tangent with inner wall layer, first group of arc pressuring plate and second group of arc pressuring plate are disposed adjacent;Two groups of Electronic control pressing plates are respectively First group of Electronic control arc pressuring plate and second group of Electronic control arc pressuring plate, wherein first group of inclined plate and second group of inclined plate Between be equipped with first group of Electronic control arc pressuring plate, second group of Electronic control arc pressuring plate is located at second group of inclined plate and the Between two groups of arc pressuring plates.
Further, the first prepreg tape, second group of inclined plate are imported between inclined plate and inner wall layer for above-mentioned first group The second prepreg tape is imported between inner wall layer.
Further, the pan feeding side of above-mentioned first group of Electronic control arc pressuring plate and second group of Electronic control arc pressuring plate is set There are more spines arranged side by side, and which is provided with the electric heater with temperature controller;First group of inclined plate and second group it is oblique The pan feeding side of pressing plate is equipped with plough and perms, and the plough is permed including perming and setting close to the stainless steel heat conduction of inner wall layer surface Primary heater above stainless steel heat conduction is permed, the stainless steel heat conduction, which perms to be equipped between primary heater, to be continued The prepreg tape of importing, above-mentioned stainless steel heat conduction are permed including stainless steel upper sheet space and are connected on stainless steel upper sheet space lower surface Lower encioser, plug is equipped with secondary heater between lower encioser and upper sheet space, and upper sheet space protracts close to the side of inner wall layer equipped with arc Piece, the lower encioser are in and the mutually matched arcwall face of inner wall layer surface close to the side of inner wall layer.
The working method of the utility model pipeline shaper, it is characterised in that:The pipeline shaper includes rack and sets Rotation core model in rack, the steel band that the rotation core model includes core and is spirally wound on core, the steel band is by turning Core first end spiral winding inputs, and is exported by core second end and passes through the centre bore of core to core first end;The core The first extruder that the first plastic material is squeezed out toward steel strip surface is equipped with above first end, to form the inner wall layer of pipeline;It is described The stage casing of core is equipped with the integrated charging tray toward spiral winding multilayer prepreg tape in inner wall layer, to form the fiber composite of pipeline Layer;It is equipped with above the core second end toward the second extruder for squeezing out the second plastic material on fiber composite, to form pipe The protective layer in road;It is additionally provided with prepreg tape on the stage casing of core and imports composite structure, is cut successively equipped with tubing in core output end Cutting mill and tubing bracket;When work, steel band is inputted from the first end spiral winding of core, is then twined from the second end spiral of core Around output, the centre bore for then passing through core arrives core first end again, and iterative cycles form the internal model of pipeline successively, by turning The first extruder is equipped with above core first end, to squeeze out the inner wall layer that the first plastic material forms pipeline;Existed by integrated charging tray The fiber composite being made of multilayer prepreg tape is laid in the inner wall layer of pipeline;It is equipped with second finally by core second end top Extruder, to squeeze out the protective layer that the second plastic material forms pipeline;Pipeline is exported finally by tubing bracket, is cut by tubing Cutting mill cuts off pipeline.
Further, above-mentioned integrated charging tray is integrated box type kink comprising parallel multiple charging trays side by side, each charging tray On be wound with prepreg tape, the prepreg tape on adjacent charging tray misplaces successively to be spirally wound on the prepreg tape of last layer;When work, The first charging tray near core first end lays first layer prepreg tape in inner wall layer, then near the of core second end Two charging trays misplace on first layer prepreg tape lays second layer prepreg tape.
The pipeline strength of the utility model manufacture is good, and circularity, cylindricity are met the requirements, and production efficiency is high.
Description of the drawings:
Fig. 1 is the profile construction schematic diagram of the pipeline of production;
Fig. 2 is the main view organigram of the utility model;
Fig. 3 is the A-A profile construction schematic diagrames of Fig. 2;
Fig. 4 is the organigram that prepreg tape imports composite structure;
Fig. 5 is the organigram of spine.
Specific implementation mode:
The utility model is described in more detail with reference to the accompanying drawings and detailed description.
The utility model pipeline shaper includes rack 1 and the rotation core model 2 that is located in rack 1, the packet of rotation core model 2 The steel band 4 for including core 3 and being spirally wound on core, the steel band 4 is inputted by 301 spiral winding of core first end, by core Second end 302 exports and across the centre bore 303 of core to core first end;It is equipped with above the core first end toward steel band table Face squeezes out the first extruder 5 of the first plastic material, to form the inner wall layer A1 of pipeline A;The stage casing of the core is equipped with past The integrated charging tray 6 of spiral winding multilayer prepreg tape in inner wall layer, to form the fiber composite A2 of pipeline;The core second end Top is equipped with toward the second extruder 7 for squeezing out the second plastic material on fiber composite, to form the protective layer A3 of pipeline;Turning It is additionally provided with prepreg tape on the stage casing of core and imports composite structure 8, pipe cutting machine 9 and tubing bracket are equipped with successively in core output end 10。
Prepreg tape is pre-processed before input integrates charging tray 6, i.e., is equipped with multiple band machine B in the delivery end of integrated charging tray 6, To merge one section of prepreg tape in the width direction of prepreg tape, the prepreg tape of 90 degree of intersections is formed, the width of prepreg tape is 40- 80mm wide.Above-mentioned first plastic material is the plastic materials such as PE, PPV, PVC, and the second plastic material is the modelings such as PP, PE, PPV, PVC Property material, protective layer A3 be the hollow protective layer of honeycomb, be by between the second extruder 7 and fiber composite A2 be equipped with bee Nest board making equipment.
Tubing bracket 10 is made of multigroup idler wheel being obliquely installed, multigroup idler wheel driving duct products spiral shell being obliquely installed Rotating is into output.Supersonic reflectoscope is equipped between cutting machine 9 and core second end 302, to realize quality testing.
The spiral winding speed of prepreg tape is 5-16 meters per minute.The inner wall layer A1 thickness of pipeline A is 3-5mm, and every layer pre- The thickness for soaking band is 0.5-0.6mm.
Further, in order to realize that the reciprocation cycle of steel band 4 uses, above-mentioned core first end turns guide equipped with steel band first Wheel 11, second, which is turned, to turn to guide wheel 12 and third to guide wheel 13, and the core second end is turned equipped with the 4th to guide wheel 14.
It further, will not be since it is desired that being connected prepreg tape and causing to rotate in order to make the input of prepreg tape constant Core model 2 is shut down, and above-mentioned integrated charging tray 6 is integrated box type kink comprising parallel multiple charging trays 601 side by side, each charging tray 601 On be wound with prepreg tape 15, the prepreg tape 15 on adjacent charging tray misplaces be spirally wound on the prepreg tape of last layer successively.
Further, in order to enable pipeline to reach the parameter requests such as better intensity, rigidity, above-mentioned integrated box type kink It is interior that there is 20-180 charging tray, i.e. fiber composite to be built up by 20-180 layers of prepreg tape.
Further, for reasonable design, it includes four be located in core outlet that above-mentioned prepreg tape, which imports composite structure 8, Group hand adjustment pressing plate 16 and interval are located at two groups of Electronic control pressing plates 17 between four groups of hand adjustment pressing plates.
Further, above-mentioned four groups of hand adjustment pressing plates 16 include two groups of inclined plates and two groups of arc pressuring plates, are first group respectively 1601, second groups of inclined plates 1602 of inclined plate, first group of arc pressuring plate 1603 and second group of arc pressuring plate 1604;First group baroclines Plate 1601 and second group of inclined plate 1602 are tangent with inner wall layer respectively, first group of arc pressuring plate 1603 and second group of arc pressuring plate 1604 are disposed adjacent;Two groups of Electronic control pressing plates 17 are first group of Electronic control arc pressuring plate 1701 and second group of electronic control respectively Arc pressuring plate 1702 processed, wherein being equipped with first group of electronic control between first group of inclined plate 1601 and second group of inclined plate 1602 Arc pressuring plate 1701 processed, second group of Electronic control arc pressuring plate 1702 are located at second group of inclined plate 1602 and second group of arc pressuring plate Between 1604;The first prepreg tape 1501, second group of inclined plate are imported between above-mentioned first group of inclined plate 1601 and inner wall layer The second prepreg tape 1502 is imported between 1602 and inner wall layer.
Further, in order to make the prepreg tape of importing have good bonding strength each other, above-mentioned first group electronic The pan feeding side for controlling arc pressuring plate 1701 and second group of Electronic control arc pressuring plate 1702 is equipped with more spines 18 arranged side by side; The pan feeding side of first group of inclined plate 1601 and second group of inclined plate 1602 is equipped with plough and perms 20, and the plough perms 20 Include perming close to the stainless steel heat conduction of inner wall layer surface and 21 and being located at stainless steel heat conduction and perm the primary heater 22 of top, institute It states stainless steel heat conduction and perms and be equipped with the prepreg tape 15 of lasting importing between 21 and primary heater 22, above-mentioned stainless steel heat conduction is scalded First 21 include stainless steel upper sheet space 2101 and the lower encioser 2102 that is connected on stainless steel upper sheet space lower surface, lower encioser 2102 with Plug is equipped with secondary heater 23 between upper sheet space 2101, and upper sheet space is equipped with arc extension piece 24 close to the side of inner wall layer, described Lower encioser is in and the mutually matched arcwall face of inner wall layer surface 25 close to the side of inner wall layer.Above-mentioned spine 18 and arc extension piece Position between 24 and it is equipped with third heater 26 close to the surface of mold core, which can penetrate 1601, On 1602.
How many layers of prepreg tape is inputted on the stage casing of core, i.e., being equipped with how many groups of prepreg tapes along core length direction imports Composite structure 8.
The utility model prepreg tape importing composite structure is permed by stainless steel heat conduction, arc extension piece and heater are set Meter, makes the prepreg tape of importing integrally comprehensively be melted, and imports and be located at the prepreg tape of inner wall layer surface before ensuring It can also be in molten state, so that the prepreg tape newly imported is preferably combined, avoid the occurrence of delamination and conjugation difference etc. and ask Topic;It is pierced into the prepreg tape covered on inner wall layer surface by the tip of grilling, and grilling can be in such a way that spiral be advanced pre- Leaching belt surface scrapes digging, is conducive to puncture the bubble generated during prepreg tape covers, plays scavenging action, and be conducive to avoid this A little bubbles are present in tube wall, and the later stage is caused to generate the hidden danger to crack using process.Digging is scraped by grilling, is also improved new The contact area of prepreg tape for being entangled to prepreg tape and covering before, increases frictional force, makes switching performance between layers, multiple Intensity is closed to significantly improve.It is proved by repetition test, using the pipeline of the structure, its physical property increases 2-3 times.
In order to prevent since prepreg tape is when importing, combustion phenomena occurs with heater contacts, and makes whole 6 quilt of integrated charging tray It ignites, is equipped between integrated charging tray 6 and rotation core model 2 and fire wall 26 is isolated, which, which is equipped with, is burning The importing of prepreg tape is isolated when phenomenon.
The working method of the utility model pipeline shaper, the pipeline shaper include rack and the rotation that is located in rack Core mould, the steel band that the rotation core model includes core and is spirally wound on core, the steel band is by core first end spiral Winding input is exported by core second end and passes through the centre bore of core to core first end;It is set above the core first end There is past steel strip surface to squeeze out the first extruder of the first plastic material, to form the inner wall layer of pipeline;On the stage casing of the core Equipped with the integrated charging tray toward spiral winding multilayer prepreg tape in inner wall layer, to form the fiber composite of pipeline;The core It is equipped with above two ends toward the second extruder for squeezing out the second plastic material on fiber composite, to form the protective layer of pipeline; It is additionally provided with prepreg tape on the stage casing of core and imports composite structure, is equipped with pipe cutting machine successively in core output end and tubing drags Frame;When work, steel band is inputted from the first end spiral winding of core, is then exported from the second end spiral winding of core, then Centre bore across core arrives core first end again, and iterative cycles form the internal model of pipeline successively, by core first end Side is equipped with the first extruder, to squeeze out the inner wall layer that the first plastic material forms pipeline;By integrate charging tray pipeline inner wall The fiber composite being made of multilayer prepreg tape is laid on layer;It is equipped with the second extruder finally by core second end top, with Squeeze out the protective layer that the second plastic material forms pipeline;Pipeline is exported finally by tubing bracket, by pipe cutting machine to pipe Road is cut off.
Further, above-mentioned integrated charging tray is integrated box type kink comprising parallel multiple charging trays side by side, each charging tray On be wound with prepreg tape, the prepreg tape on adjacent charging tray misplaces successively to be spirally wound on the prepreg tape of last layer;When work, The first charging tray near core first end lays first layer prepreg tape in inner wall layer, then near the of core second end Two charging trays misplace on first layer prepreg tape lays second layer prepreg tape.
The pipeline strength of the utility model manufacture is good, and circularity, cylindricity are met the requirements, and production efficiency is high.
The above is only the preferred embodiment of the present invention, it is all done according to present utility model application the scope of the claims it is equal Deng variation and modification, it should all belong to the covering scope of the utility model.

Claims (8)

1. a kind of pipeline shaper, it is characterised in that:Including rack and the rotation core model being located in rack, the rotation core model packet The steel band for including core and being spirally wound on core, the steel band is inputted by core first end spiral winding, by core second end It exports and passes through the centre bore of core to core first end;It is equipped with above the core first end toward steel strip surface and squeezes out the first modeling First extruder of property material, to form the inner wall layer of pipeline;The stage casing of the core is equipped with toward spiral winding in inner wall layer The integrated charging tray of multilayer prepreg tape, to form the fiber composite of pipeline;It is equipped with toward fiber composite above the core second end The second extruder that the second plastic material is squeezed out on layer, to form the protective layer of pipeline;Preimpregnation is additionally provided on the stage casing of core Band imports composite structure, and pipe cutting machine and tubing bracket are equipped with successively in core output end.
2. pipeline shaper according to claim 1, it is characterised in that:The core first end equipped with steel band first turn to Guide wheel, second, which are turned, turns to guide wheel and third to guide wheel, and the core second end is turned equipped with the 4th to guide wheel.
3. pipeline shaper according to claim 1, it is characterised in that:The integrated charging tray is integrated box type kink, Including parallel multiple charging trays side by side, it is wound with prepreg tape on each charging tray, the prepreg tape on adjacent charging tray misplaces spiral shell successively Rotation is wrapped on the prepreg tape of last layer.
4. pipeline shaper according to claim 3, it is characterised in that:There are 20-180 in the integrated box type kink Charging tray, i.e. fiber composite are built up by 20-180 layers of prepreg tape.
5. pipeline shaper according to claim 1, it is characterised in that:It includes being located at that the prepreg tape, which imports composite structure, Four groups of hand adjustment pressing plates and interval in core outlet are located at two groups of Electronic control pressing plates between four groups of hand adjustment pressing plates.
6. pipeline shaper according to claim 5, it is characterised in that:Four groups of hand adjustment pressing plates include two groups of inclined plates It is first group of inclined plate, second group of inclined plate respectively with two groups of arc pressuring plates, first group of arc pressuring plate and second group of arc pressure Plate;First group of inclined plate and second group of inclined plate are tangent with inner wall layer respectively, first group of arc pressuring plate and second group of arc pressuring plate It is disposed adjacent;Two groups of Electronic control pressing plates are first group of Electronic control arc pressuring plate and second group of Electronic control arc pressure respectively Plate, wherein first group of Electronic control arc pressuring plate is equipped between first group of inclined plate and second group of inclined plate, second group of electricity Dynamic control arc pressuring plate is located between second group of inclined plate and second group of arc pressuring plate.
7. pipeline shaper according to claim 6, it is characterised in that:Described first group is led between inclined plate and inner wall layer Enter the first prepreg tape, described second group imports the second prepreg tape between inclined plate and inner wall layer.
8. pipeline shaper according to claim 7, it is characterised in that:First group of Electronic control arc pressuring plate and The pan feeding side of two groups of Electronic control arc pressuring plates is equipped with more spines arranged side by side, and which is provided with the electrical heating with temperature controller Device;The pan feeding side of first group of inclined plate and second group of inclined plate is equipped with plough and perms, and the plough is permed including close The stainless steel heat conduction of inner wall layer surface perm and be located at stainless steel heat conduction perm top primary heater, the stainless steel heat conduction It perms and is equipped with the prepreg tape of lasting importing between primary heater, above-mentioned stainless steel heat conduction is permed including stainless steel upper sheet space With the lower encioser being connected on stainless steel upper sheet space lower surface, plug is equipped with secondary heater, upper plate between lower encioser and upper sheet space Piece is equipped with arc extension piece close to the side of inner wall layer, and the lower encioser is in mutual with inner wall layer surface close to the side of inner wall layer The arcwall face of cooperation.
CN201721393463.4U 2017-10-26 2017-10-26 Pipeline shaper Active CN207617069U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721393463.4U CN207617069U (en) 2017-10-26 2017-10-26 Pipeline shaper

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721393463.4U CN207617069U (en) 2017-10-26 2017-10-26 Pipeline shaper

Publications (1)

Publication Number Publication Date
CN207617069U true CN207617069U (en) 2018-07-17

Family

ID=62826994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721393463.4U Active CN207617069U (en) 2017-10-26 2017-10-26 Pipeline shaper

Country Status (1)

Country Link
CN (1) CN207617069U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107825684A (en) * 2017-10-26 2018-03-23 福州森百德机电科技有限公司 Pipeline shaper and its method of work
CN114193805A (en) * 2021-12-10 2022-03-18 永高股份有限公司 Forming equipment of continuous fiber reinforced composite pipe

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107825684A (en) * 2017-10-26 2018-03-23 福州森百德机电科技有限公司 Pipeline shaper and its method of work
CN114193805A (en) * 2021-12-10 2022-03-18 永高股份有限公司 Forming equipment of continuous fiber reinforced composite pipe
WO2023103108A1 (en) * 2021-12-10 2023-06-15 公元股份有限公司 Forming device for continuous fiber reinforced composite pipe

Similar Documents

Publication Publication Date Title
CN207617069U (en) Pipeline shaper
CN102749693B (en) Environment-protection, rat-proof and ant-proof optical cable and processing technology thereof
CN103722717B (en) A kind of PEI sticking plaster production equipment and process
CN104172469B (en) The processing method and its device of a kind of double-deck paper substrates of cigarette filter
CN205751701U (en) A kind of cable produces equipment
CN107825684A (en) Pipeline shaper and its method of work
CN106531297B (en) Heatproof Compression-resistincable cable and its production equipment and production technology
CN107863491A (en) A kind of online shaping equipment of electrodes of lithium-ion batteries
CN206457432U (en) high strength detonating tube production line
CN204354470U (en) A kind of Self-crimping type sleeve shaped device
CN107139441A (en) Prepreg tape imports set composite and its method of work
CN208946762U (en) Paper suction pipe molding machine with ultrasonic wave complex function
CN203937147U (en) A kind of chemical blowing extruder
CN107127918A (en) A kind of plasticity machines heater with quick cooling function
CN206127719U (en) A gyro wheel for preparing drench membrane paper
CN102104999A (en) Far infrared heating plate and manufacturing method thereof
CN205414210U (en) Aluminum honeycomb panel continuous production line
CN202399436U (en) Air drying preheating water channel for wire cables
CN205522563U (en) Improved generation slot wedge strip shaping processingequipment
CN205432078U (en) Tobacco is drying device for throwing
CN110367586A (en) A kind of cigarette carbon rod package molding apparatus and method of not burning
CN206579182U (en) A kind of fragrant device of horizontal system
CN206643521U (en) Hot attemperator after trolley type water-cooling wall
CN205959682U (en) Lian lalian moves back wire and cable integration production facility
CN202399435U (en) Preheating water channel for wire cables

Legal Events

Date Code Title Description
GR01 Patent grant