CN207608831U - A kind of New operation device of bridge construction - Google Patents

A kind of New operation device of bridge construction Download PDF

Info

Publication number
CN207608831U
CN207608831U CN201721664578.2U CN201721664578U CN207608831U CN 207608831 U CN207608831 U CN 207608831U CN 201721664578 U CN201721664578 U CN 201721664578U CN 207608831 U CN207608831 U CN 207608831U
Authority
CN
China
Prior art keywords
pulleys
operation console
support
driving
bridge construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721664578.2U
Other languages
Chinese (zh)
Inventor
蒲燚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan College of Architectural Technology
Original Assignee
Sichuan College of Architectural Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan College of Architectural Technology filed Critical Sichuan College of Architectural Technology
Priority to CN201721664578.2U priority Critical patent/CN207608831U/en
Application granted granted Critical
Publication of CN207608831U publication Critical patent/CN207608831U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Transmission Devices (AREA)

Abstract

The utility model discloses a kind of New operation devices of bridge construction, including operating mechanism, the supporting mechanism for driving operating mechanism vertical motion;The operating mechanism includes operation console, is used to support the supporting rack of operation console and for driving operation console to do the driving mechanism of transverse movement on supporting rack;The operation console is slidably mounted on supporting rack.The utility model can effectively realize the transverse shifting of operation console;Working efficiency is effectively raised, construction cost is reduced;It is simple in structure, highly practical.

Description

A kind of New operation device of bridge construction
Technical field
The utility model is related to technical field of bridge construction, are a kind of novel operating dresses of bridge construction specifically It sets.
Background technology
Bridge construction(Bridge construction), refer to building the process of bridge according to design content;It refers mainly to The contents such as bridge Construction Technology and construction organization, construction management, construction quality.Bridge construction belongs to working at height, to ensure to apply Working medium amount, it would be desirable to operation console is built on bridge pavement to realize the construction to bridge pavement upper end column, due to this Operation console service life is short, and turnaround speed is fast, but we need to spend when building operation console a large amount of manpower and materials, and at This is higher, therefore general unit in charge of construction is all that directly hanging basket is placed on model of the column to construct, and there are a large amount of security risks. With the continuous development of technology, people have devised various operation consoles, these operation consoles pass through hydraulic system or pure Mechanical system realizes the lifting of construction worker, to achieve the purpose that construction, but due to the diversity of bridge construction, this A little operation consoles need left and right to move back and forth, and existing operation console is all otherwise operating personnel oneself get off to move, otherwise cries Another people carries out, and drastically influences bridge construction efficiency.Simultaneously because the operating surface of operation console is excessive so that grasping The construction personnel made on platform is excessive, occurs load caused by construction personnel when serious and is more than the maximum lotus that operation console can bear Load value, there are larger security risks.
Utility model content
The purpose of this utility model is to provide a kind of New operation devices of bridge construction, can effectively realize behaviour Make the transverse shifting of platform;Working efficiency is effectively raised, construction cost is reduced;It is simple in structure, highly practical.
The utility model is achieved through the following technical solutions:A kind of New operation device of bridge construction, including operation Mechanism, the supporting mechanism for driving operating mechanism vertical motion;The operating mechanism includes operation console, is used to support operation console Supporting rack and for driving operation console to do the driving mechanism of transverse movement on supporting rack;The operation console is slidably mounted on On supporting rack.
Operation principle:Before use, operating device to be moved to the position constructed, construction personnel enters and stands It stands in operation console, control supporting mechanism driving operation console moves upwards, and after reaching designated position, control supporting mechanism stops driving It is dynamic;Construction personnel can construct;After the completion of construction personnel is capable of the construction surface of construction operation;Construction personnel controls driving Mechanism makes operation console do transverse movement on supporting rack, and after being moved to construction area, control driving mechanism stops driving;It applies Worker person is constructing.
The effective transverse shifting for realizing operation console, provides working efficiency, accelerates construction progress, and reduces construction cost; It is safe.
Further, in order to preferably realize the utility model, the driving mechanism is including being mounted on operation console lateral two The A pulleys of side, the driving motor for driving A pulley rotations, respectively symmetrically be mounted on supporting rack on B pulleys and C pulleys with And the hawser being connect respectively with A pulleys, B pulleys and C pulleys.
Further, in order to preferably realize that the utility model, the bottom of the operation console are equipped with D pulleys;The branch Support is provided with the sliding slot being used cooperatively with D pulleys.
Further, in order to preferably realize the utility model, support frame as described above is including two cross bars and mounted on cross Bar both sides free end and the connecting plate for connecting two cross bars;The sliding slot is arranged on cross bar;The B pulleys and C pulleys peace On connecting plate, the A pulleys are identical with the distance of B pulley distance transverse rods.
Further, in order to preferably realize that the utility model, the cross bar are provided with buffering close to the side of operation console Portion.
Further, in order to preferably realize the utility model, two slide bars, the cunning are provided between the connecting plate Bar is symmetrically mounted on side of the connecting plate far from cross bar, and the operation console is socketed with slide bar;The operation console passes through linear bearing Seat is socketed with slide bar.
Further, in order to preferably realize the utility model, the supporting mechanism includes support foot rest, is mounted on support Vertical drive on tripod and for driving operation console vertical motion.
Further, in order to preferably realize that the utility model, the driving device include the hydraulic pressure being connect with operation console Pump, the hydraulic cylinder are connect with hydraulic system.
Further, in order to preferably realize that the utility model, the support foot rest include support plate, connect with support plate And symmetrically arranged support column;The hydraulic pump installation is on the supporting plate.
Further, in order to preferably realize that the utility model, both sides of the support column far from support plate are additionally provided with It is used to support the support portion of supporting rack, cushion pad is arranged close to the side of operation console in the support portion.
The utility model compared with prior art, has the following advantages and advantageous effect:
(1)The utility model can effectively realize the transverse shifting of operation console;
(2)The utility model effectively raises working efficiency, reduces construction cost;
(3)The utility model is simple in structure, highly practical.
Description of the drawings
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is operation console and supporting rack connection relationship diagram in the utility model;
Fig. 3 is the plan view of operating mechanism in the utility model;
Wherein 1- operating mechanisms, 11- operation consoles, 111-D pulleys, 12-A pulleys, 13-B pulleys, 14-C pulleys, 15- are slided Bar, 10- supporting racks, 101- cross bars, 1011- sliding slots, 102- buffer parts, 103- connecting plates, 21- support columns, 22- support portions, 23- Support plate, 24- hydraulic pumps, 25- cushion pads.
Specific implementation mode
The embodiments of the present invention are described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning Same or similar element or element with the same or similar functions are indicated to same or similar label eventually.Below by ginseng The embodiment for examining attached drawing description is exemplary, it is intended to for explaining the utility model, and should not be understood as to the utility model Limitation.
In the description of the present invention, it should be understood that term "center", " longitudinal direction ", " transverse direction ", " length ", " width Degree ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside", " suitable The orientation or positional relationship of the instructions such as hour hands ", " counterclockwise " is to be based on the orientation or positional relationship shown in the drawings, merely to just In description the utility model and simplify description, specific side must be had by not indicating or implying the indicated device or element Position, with specific azimuth configuration and operation, therefore should not be understood as limiting the present invention.
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " Gu It is fixed " etc. terms shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can Can also be electrical connection to be mechanical connection;It can be directly connected, can also indirectly connected through an intermediary, Ke Yishi Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood as the case may be Concrete meaning in the present invention.
The utility model is described in further detail with reference to embodiment, but the embodiment of the utility model is not It is limited to this.
Embodiment 1:
The utility model is achieved through the following technical solutions, as shown in Figure 1-Figure 3 shown in, a kind of bridge construction it is novel Operating device, including operating mechanism 1, the supporting mechanism for driving 1 vertical motion of operating mechanism;The operating mechanism 1 includes Operation console 11, the supporting rack 10 for being used to support operation console 11 and for driving operation console 11 to do transverse movement on supporting rack 10 Driving mechanism;The operation console 11 is slidably mounted on supporting rack 10.
It should be noted that by above-mentioned improvement, operation principle:It needs to carry out before use, operating device is moved to The position of construction, construction personnel enter and stand in operation console 11, and control supporting mechanism driving operating mechanism 1 moves upwards, After reaching designated position, control supporting mechanism stops driving;Construction personnel can construct;When construction personnel can construct work After the completion of the construction surface of industry;Construction personnel controls driving mechanism and operation console 11 is made to do transverse movement on supporting rack 10, works as shifting After moving construction area, control driving mechanism stops driving;Construction personnel is constructing.
The effective transverse shifting for realizing operation console 11, provides working efficiency, accelerates construction progress, reduction is constructed into This;It is safe.
The other parts of the present embodiment are same as the previously described embodiments, and so it will not be repeated.
Embodiment 2:
The present embodiment advanced optimizes on the basis of the above embodiments, as shown in Figure 1-Figure 3, the driving mechanism packet It includes the A pulleys 12 mounted on 11 both lateral sides of operation console, the driving motor for driving the rotation of A pulleys 12, respectively symmetrically install B pulleys 13 and C pulleys 14 on supporting rack 10 and the hawser being connect respectively with A pulleys 12, B pulleys 13 and C pulleys 14.
The output shaft of the A pulleys 12 and driving motor is coaxial, when needing progress operation console 11 mobile to lateral right side, Two driving motors coaxial with A pulleys 12 of control rotate forward, and the A pulleys 12 in left side will tighten hawser, winding Hawser on right side A pulleys 12 will be reduced, to which real operation platform 11 moves to the right;Conversely, two driving motors of control Reversion, to which real operation platform 11 moves to the left.
The bottom of the operation console 11 is equipped with D pulleys 111;Support frame as described above 10 is provided with to be used cooperatively with D pulleys 111 Sliding slot 1011.
D pulleys 111 are connect by pillar with the bottom of operation console 11, the D pulleys 111 sliding in sliding slot 1011;D is slided Wheel 111 effectively limits operation console 11, and operation console 11 is avoided to be moved forward and backward.
Support frame as described above 10 includes two cross bars 101 and mounted on 101 both sides free end of cross bar and by two cross bars The connecting plate 103 of 101 connections;The sliding slot 1011 is arranged on cross bar 101;The B pulleys 13 and C pulleys 14 are mounted on connection On plate 103, the A pulleys 12 are identical with the distance of 13 distance transverse rod 101 of B pulleys.
Cross bar 101 is mounted between connecting plate 103, and cross bar 101 runs through operation console 11;So that operation console 11 can only be along cross bar 101 length directions are moved;It effectively avoids in motion process simultaneously, operation console 11 is turned on one's side from supporting rack 10.
The cross bar 101 is provided with buffer part 102 close to the side of operation console 11.Buffer part 102 effectively avoids operating Platform 11 is hit close to the side of connecting plate 103 and connecting plate 103, influences the service life of the present apparatus.
Two slide bars 15 are provided between the connecting plate 103, the slide bar 15 is symmetrically mounted on connecting plate 103 far from horizontal The side of bar 101, the operation console 11 are socketed with slide bar 15;The operation console 11 is socketed by linear bearing seat and slide bar 15.
Linear bearing seat is effectively realized with slide bar 15 and is moved along a straight line.
The other parts of the present embodiment are same as the previously described embodiments, and so it will not be repeated.
Embodiment 3:
The present embodiment advanced optimizes on the basis of the above embodiments, as shown in Figure 1-Figure 3, the supporting mechanism packet Include support foot rest, the vertical drive on support foot rest and for driving 11 vertical motion of operation console.
The driving device includes the hydraulic pump 24 being connect with operation console 11, and the hydraulic cylinder is connect with hydraulic system.
The support foot rest includes support plate 23, connect with support plate 23 and symmetrically arranged support column 21;The hydraulic pressure Pump 24 is mounted in support plate 23.
Both sides of the support column 21 far from support plate 23 are additionally provided with the support portion 22 for being used to support supporting rack 10, described Cushion pad 25 is arranged close to the side of operation console 11 in support portion 22.
Cushion pad 25 effectively avoids the hard contact of supporting rack 10 and support portion 22.
The other parts of the present embodiment are same as the previously described embodiments, and so it will not be repeated.
Embodiment 4:
The present embodiment is the most preferred embodiment of the utility model, as shown in Figure 1-Figure 3, a kind of novel behaviour of bridge construction Make device, including operating mechanism 1, the supporting mechanism for driving 1 vertical motion of operating mechanism;The operating mechanism 1 includes behaviour Make platform 11, be used to support the supporting rack 10 of operation console 11 and for driving operation console 11 to do transverse movement on supporting rack 10 Driving mechanism;The operation console 11 is slidably mounted on supporting rack 10.
Operation principle:Before use, operating device to be moved to the position constructed, construction personnel enters and stands It stands in operation console 11, control supporting mechanism driving operating mechanism 1 moves upwards, and after reaching designated position, controls supporting mechanism Stop driving, construction personnel can construct;After the completion of construction personnel is capable of the construction surface of construction operation;Construction personnel controls Driving mechanism makes operation console 11 do transverse movement on supporting rack 10, and after being moved to construction area, control driving mechanism is stopped Only drive;Construction personnel is constructing.
The effective transverse shifting for realizing operation console 11, provides working efficiency, accelerates construction progress, reduction is constructed into This;It is safe.
The driving mechanism includes mounted on the A pulleys 12 of 11 both lateral sides of operation console, for driving A pulleys 12 to rotate Driving motor, respectively symmetrically be mounted on supporting rack 10 on B pulleys 13 and C pulleys 14 and respectively with A pulleys 12, B pulleys 13 The hawser connected with C pulleys 14.
The bottom of the operation console 11 is equipped with D pulleys 111;Support frame as described above 10 is provided with to be used cooperatively with D pulleys 111 Sliding slot 1011.
Support frame as described above 10 includes two cross bars 101 and mounted on 101 both sides free end of cross bar and by two cross bars The connecting plate 103 of 101 connections;The sliding slot 1011 is arranged on cross bar 101;The B pulleys 13 and C pulleys 14 are mounted on connection On plate 103, the A pulleys 12 are identical with the distance of 13 distance transverse rod 101 of B pulleys.
The cross bar 101 is provided with buffer part 102 close to the side of operation console 11.
Two slide bars 15 are provided between the connecting plate 103, the slide bar 15 is symmetrically mounted on connecting plate 103 far from horizontal The side of bar 101, the operation console 11 are socketed with slide bar 15;The operation console 11 is socketed by linear bearing seat and slide bar 15.
The supporting mechanism includes support foot rest, on support foot rest and for driving 11 vertical motion of operation console Vertical drive.
Include the hydraulic pump 24 being connect with operation console 11 into the driving device, the hydraulic pump 24 connects with hydraulic system It connects.
The support foot rest includes support plate 23, connect with support plate 23 and symmetrically arranged support column 21;The hydraulic pressure Pump 24 is mounted in support plate 23.
Both sides of the support column 21 far from support plate 23 are additionally provided with the support portion 22 for being used to support supporting rack 10, described Cushion pad 25 is arranged close to the side of operation console 11 in support portion 22.
It should be noted that by above-mentioned improvement, the driving motor is clockwise and anticlockwise motor.
The other parts of the present embodiment are same as the previously described embodiments, and so it will not be repeated.
The above is only the preferred embodiment of the utility model, not does limit in any form to the utility model System, any simple modification made by the above technical examples according to the technical essence of the present invention, equivalent variations, each falls within Within the scope of protection of the utility model.

Claims (10)

1. a kind of New operation device of bridge construction, it is characterised in that:Including operating mechanism(1), for driving operation machine Structure(1)The supporting mechanism of vertical motion;The operating mechanism(1)Including operation console(11), be used to support operation console(11)Branch Support(10)And for driving operation console(11)In supporting rack(10)On do the driving mechanism of transverse movement;The operation console (11)It is slidably mounted on supporting rack(10)On.
2. a kind of New operation device of bridge construction according to claim 1, it is characterised in that:The driving mechanism Including being mounted on operation console(11)The A pulleys of both lateral sides(12), for driving A pulleys(12)The driving motor of rotation, difference It is symmetrically mounted on supporting rack(10)On B pulleys(13)With C pulleys(14)And respectively with A pulleys(12), B pulleys(13)And C Pulley(14)The hawser of connection.
3. a kind of New operation device of bridge construction according to claim 2, it is characterised in that:The operation console (11)Bottom D pulleys are installed(111);Support frame as described above(10)It is provided with and D pulleys(111)The sliding slot being used cooperatively (1011).
4. a kind of New operation device of bridge construction according to claim 3, it is characterised in that:Support frame as described above (10)Including two cross bars(101)And it is mounted on cross bar(101)Both sides free end and by two cross bars(101)The company of connection Fishplate bar(103);The sliding slot(1011)It is arranged in cross bar(101)On;The B pulleys(13)With C pulleys(14)Mounted on connection Plate(103)On, the A pulleys(12)With B pulleys(13)Distance transverse rod(101)Distance it is identical.
5. a kind of New operation device of bridge construction according to claim 4, it is characterised in that:The cross bar (101)Close to operation console(11)Side be provided with buffer part(102).
6. a kind of New operation device of bridge construction according to claim 5, it is characterised in that:The connecting plate (103)Between be provided with two slide bars(15), the slide bar(15)It is symmetrically mounted on connecting plate(103)Far from cross bar(101)'s Side, the operation console(11)With slide bar(15)Socket;The operation console(11)Pass through linear bearing seat and slide bar(15)Socket.
7. according to a kind of New operation device of bridge construction of claim 1-6 any one of them, it is characterised in that:It is described Supporting mechanism includes support foot rest, on support foot rest and for driving operation console(11)The vertical driving of vertical motion fills It sets.
8. a kind of New operation device of bridge construction according to claim 7, it is characterised in that:The driving device Including with operation console(11)The hydraulic pump of connection(24), the hydraulic pump(24)It is connect with hydraulic system.
9. a kind of New operation device of bridge construction according to claim 8, it is characterised in that:The support foot rest Including support plate(23)With support plate(23)Connection and symmetrically arranged support column(21);The hydraulic pump(24)Mounted on branch Fagging(23)On.
10. a kind of New operation device of bridge construction according to claim 9, it is characterised in that:The support column (21)Far from support plate(23)Both sides be additionally provided with and be used to support supporting rack(10)Support portion(22), the support portion(22) Close to operation console(11)Side be arranged cushion pad(25).
CN201721664578.2U 2017-12-04 2017-12-04 A kind of New operation device of bridge construction Expired - Fee Related CN207608831U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721664578.2U CN207608831U (en) 2017-12-04 2017-12-04 A kind of New operation device of bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721664578.2U CN207608831U (en) 2017-12-04 2017-12-04 A kind of New operation device of bridge construction

Publications (1)

Publication Number Publication Date
CN207608831U true CN207608831U (en) 2018-07-13

Family

ID=62796395

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721664578.2U Expired - Fee Related CN207608831U (en) 2017-12-04 2017-12-04 A kind of New operation device of bridge construction

Country Status (1)

Country Link
CN (1) CN207608831U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029583A (en) * 2019-05-16 2019-07-19 袁奥 A kind of cross-line bridge standardized construction system and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029583A (en) * 2019-05-16 2019-07-19 袁奥 A kind of cross-line bridge standardized construction system and its construction method
CN110029583B (en) * 2019-05-16 2021-03-30 袁奥 Standardized construction system for overpass bridge and construction method thereof

Similar Documents

Publication Publication Date Title
CN205346760U (en) Hoist overhauls uses elevating platform
CN201182732Y (en) Self-body massage bed
CN104944328A (en) Vehicle-mounted insulating lift platform
CN207608831U (en) A kind of New operation device of bridge construction
CN204897083U (en) Directly drive elevator steering mechanism
CN208341593U (en) A kind of auxiliary construction device of electric railway construction
CN108529472A (en) A kind of lifting means for construction
CN104724493B (en) Heavy retractor device
CN207458247U (en) A kind of mobile cashing machine
CN109967547A (en) A kind of crane end carriage automation pressurizing unit
CN202248940U (en) Turnover device for unitized curtain wall
CN105923586B (en) It is a kind of for building from steady support meanss
CN213532480U (en) Movable supporting platform for elevator maintenance
CN104386581B (en) One kind sliding hoisting running device
CN209259612U (en) A kind of feeding device for construction
CN204624669U (en) Heavy retractor device
CN110700604B (en) Assembly type laminated slab mounting trolley and using method thereof
CN205312938U (en) Crane equipped with travelable counterweight unit
CN211178154U (en) Rotary target drone
CN113371606A (en) Double-lifting container crane and working method thereof
CN202554816U (en) Running machine convenient to fold up
CN106629470A (en) Lifting type level gage overhaul device
CN207175268U (en) A kind of heavy module assembling/disassembling machine
CN206825415U (en) A kind of carrying roller catching robot
CN215857209U (en) Bridge detects moving platform's perpendicular arm connection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180713

Termination date: 20201204

CF01 Termination of patent right due to non-payment of annual fee