CN207556493U - Landslide displacement monitoring device and early warning system - Google Patents

Landslide displacement monitoring device and early warning system Download PDF

Info

Publication number
CN207556493U
CN207556493U CN201721436235.0U CN201721436235U CN207556493U CN 207556493 U CN207556493 U CN 207556493U CN 201721436235 U CN201721436235 U CN 201721436235U CN 207556493 U CN207556493 U CN 207556493U
Authority
CN
China
Prior art keywords
landslide
displacement
monitoring
stake
monitoring device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721436235.0U
Other languages
Chinese (zh)
Inventor
倪卫达
单治钢
王敬勇
孙淼军
徐文刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201721436235.0U priority Critical patent/CN207556493U/en
Application granted granted Critical
Publication of CN207556493U publication Critical patent/CN207556493U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Emergency Alarm Devices (AREA)

Abstract

The utility model is related to a kind of landslide displacement monitoring device and early warning systems, particularly belong to a kind of landslide trailing edge displacement monitoring device and early warning system based on displacement sensor for pull rope.The purpose of this utility model is to provide a kind of landslide displacement monitoring device and early warning system, to realize the real-time monitoring of landslide trailing edge displacement and early warning, so as to ensure the people's lives and property safety in the coverage of landslide.The technical solution of the utility model is:A kind of landslide displacement monitoring device, it is characterised in that:With the reference stake and monitoring stake being anchored in respectively on landslide;It is equipped with wherein on reference stake for real-time monitoring criteria stake with the displacement monitoring module of monitoring stake relative displacement, by displacement monitoring module acquisition relative displacement information and the information sending module being sent out and the power supply module powered for displacement monitoring module and information sending module.The utility model is suitable for monitoring and warning technical field.

Description

Landslide displacement monitoring device and early warning system
Technical field
The utility model is related to a kind of landslide displacement monitoring device and early warning systems, particularly belong to a kind of based on drawstring displacement The landslide trailing edge displacement monitoring device and early warning system of sensor, suitable for monitoring and warning technical field.
Background technology
Landslide is one of most commonly seen and important geological disaster, and serious danger is formed to the security of the lives and property of the mankind Evil.The displacement monitoring on landslide and the early-warning and predicting based on displacement are the important means of Landslide Hazards prevention and research.Due to The structure type on landslide, origin mechanism and evolutionary process are different, therefore the monitoring method of landslide displacement is varied, at present Main method has:Landslide displacement monitoring method, the landslide displacement monitoring method based on distribution type fiber-optic based on GPS monitoring piers With the landslide displacement monitoring method based on photosignal etc..
However above-mentioned landslide displacement monitoring method is had some disadvantages during practice and deficiency:
1st, the landslide displacement monitoring method based on GPS monitoring piers:This method the degree of automation is low, and hand labor intensity is big, Real-time monitoring is can not achieve, and is difficult under the severe weather conditions such as rain, mist to carry out monitoring;
2nd, the landslide displacement monitoring method based on distribution type fiber-optic:The cost of distribution type fiber-optic is higher, monitors the amount of displacement Journey is smaller, buries during distribution type fiber-optic and later stage use, and distribution type fiber-optic is easier to break, the operability of this method compared with Difference;
3rd, the landslide displacement monitoring method based on photosignal:The cost of this method equipment is higher, automatic at landslide scene It is easily stolen, destroyed in monitoring process, and it is similarly subjected to the limitation of the severe weather conditions such as rain, mist.
Invention content
The technical problems to be solved in the utility model is:In view of the above problems, a kind of landslide displacement monitoring is provided Device and early warning system, to realize the real-time monitoring of landslide trailing edge displacement and early warning, so as to ensure the people in the coverage of landslide The security of the lives and property.
Technical solution is used by the utility model:A kind of landslide displacement monitoring device, it is characterised in that:With respectively The reference stake and monitoring stake being anchored on landslide;
It is equipped with wherein on reference stake and is used for the displacement monitoring module of real-time monitoring criteria stake and monitoring stake relative displacement, passes through The information sending module and be displacement monitoring module and information that displacement monitoring module obtains relative displacement information and is sent out The power supply module of sending module power supply.
The reference stake includes reference stake stent and base platform, and base platform is pivotally mounted to benchmark through rotary joint Stake cradle top, installs the displacement monitoring module, information sending module and power supply module in the base platform.
Band is useful for obtaining the angle dial of its rotation angle on the rotary joint.
Levelling rod is housed on the reference stake stent.
The power supply module includes solar panels and the accumulator being connect with solar panels circuit, and solar panels are through supporting rod It is installed in the base platform, wherein solar panels are rotatably connected with supporting rod, supporting rod and the rotatable phase of base platform Even.
The displacement monitoring module has displacement sensor for pull rope, drawing of the drawstring through its end of the displacement sensor for pull rope Rope socket ring cooperation anchor bolt is fixed at the top of the monitoring stake.
Levelling rod is housed in the monitoring stake.
The reference stake is anchored in the rear lateral stabilization rock mass of landslide;The monitoring stake is anchored in the rear of landslide and breaks away In slopes.
A kind of landslide displacement early warning system, it is characterised in that:With the landslide displacement monitoring dress described in above-mentioned any one The landslide monitoring base station put and communicated with the information sending module in landslide displacement monitoring device is equipped in landslide monitoring base station pre- Alert broadcast.
The beneficial effects of the utility model are:The utility model has the advantages of simple structure, sets and uses, is self-powered, have compared with Good sustainability and operability;The utility model it is with strong applicability, cannot be only used for the monitoring and warning on all kinds of landslides, It can be used for the monitoring and warning of all kinds of engineering slopes, foundation pit highwall and Dangerous Rock Body etc.;The utility model uses drawstring displacement sensing Device realizes contact physical monitoring, not by the wind, the interference of temperature, visibility and other weather conditions, the accuracy of monitoring data It is higher with reliability;The utility model realizes the combination of remote monitoring and live early warning by information transmitting system, landslide Displacement monitoring data can be used to long-range monitoring and scientific research, and available for the early warning and forecast of landslide phenomenon.
Description of the drawings
Fig. 1 is the arrangement schematic diagram that the reference stake of embodiment is connect with monitoring stake.
Fig. 2 is the schematic cross-section of reference stake in embodiment.
Fig. 3 is the schematic cross-section of monitoring stake in embodiment.
Fig. 4 is the stereogram of reference stake in embodiment.
Fig. 5 is the pile crown partial enlarged view of monitoring stake in embodiment.
Specific embodiment
The present embodiment is a kind of landslide displacement early warning system, has landslide displacement monitoring device and is filled with landslide displacement monitoring The landslide monitoring base station of information sending module communication in putting, early warning broadcast is equipped in landslide monitoring base station.
As shown in Figure 1 to 4, landslide displacement monitoring device has the base being anchored in the 19 lateral stabilization rock mass of rear of landslide Quasi- stake and the monitoring stake being anchored in the 19 inside slip mass of rear of landslide.
Monitoring stake has monitoring stake stent 18, is equipped with to adjust and ensure that the monitoring stake stent erects on monitoring stake stent 18 Straight levelling rod 8.
Reference stake includes reference stake stent 7 and base platform 5, is equipped with to adjust and ensure the base on reference stake stent 7 The vertical levelling rod 8 of quasi- stake stent;Base platform 5 is pivotally mounted to 7 top of reference stake stent through rotary joint 6, and rotation connects Band is useful for obtaining the angle dial of its rotation angle on first 6.
Displacement monitoring module, information sending module and power supply module are installed, displacement monitoring module is used in base platform 5 Real-time monitoring criteria stake and monitoring stake relative displacement, information sending module obtain relative displacement information simultaneously by displacement monitoring module It is sent out and (is sent to landslide monitoring base station), power supply module is used to power for displacement monitoring module and information sending module.
Power supply module includes solar panels 1 and the accumulator 9 being connect with solar panels circuit, and solar panels 1 are through supporting rod 3 It is installed in base platform 5, wherein solar panels 1 are rotatably connected through solar panels rotary joint 2 with 3 top of supporting rod, 1 bottom end of supporting rod is rotatably connected through supporting rod rotary joint 4 with base platform 5.
Displacement monitoring module has displacement sensor for pull rope 14 and data processing single chip 13, the drawing of displacement sensor for pull rope Drawstring joint ring 17 of the rope 15 through its end coordinates anchor bolt 16 to be fixed on 18 top (such as Fig. 5) of monitoring stake stent;Drawstring position Displacement sensor 14 exports the relative displacement information of the monitoring stake of acquisition and reference stake with digital signal form;
Data processing microcontroller 13 is according to the following formula:
The displacement information value of acquisition is decomposed into horizontal displacement value and vertical displacement value.
In formula, dhHorizontal displacement value (mm) for the rear that comes down;dvVertical displacement value (mm) for the rear that comes down;S is drawstring The displacement information value (mm) that displacement sensor obtains;Come down the flat of earth's surface on the basis of α between piled anchor solid point and monitoring stake anchor point Equal inclination angle is obtained on the angle dial by rotary joint 6.
Information sending module includes signal projector 12 and signal transmitting antenna 10, and signal transmitting antenna 10 emits through signal Antenna rotary joint 11 is rotationally connected with 5 middle part of base platform, and signal projector 12 is coordinated regularly to send out displacement information It send to landslide monitoring base station;Signal projector 12 can be with preset critical, when the displacement information value of acquisition is more than preset threshold During value, warning information is sent immediately and starts the early warning broadcast of landslide monitoring base station, so as to notify the resident in the zone of influence of landslide It withdraws in time.
The installation of the present embodiment and application method are as follows:
1st, monitoring point is selected:According to the geologic survey of early period, determine landslide 19 boundary of rear, select representative prison Measuring point;
2nd, reference stake and monitoring stake anchoring:Reference stake and monitoring stake are anchored in landslide 19 lateral stabilization rock mass of rear respectively In interior and landslide 19 inside slip mass of rear, reference stake and monitoring stake are adjusted, and ensure reference stake and monitoring stake by levelling rod 8 Vertically, then using the stake of cement mortar fixed reference and monitoring stake;Ensure the line of reference stake and monitoring stake and the main cunning side that comes down To consistent;
3rd, equipment adjusts:The base platform 5 on reference stake is adjusted, makes the inclination angle of base platform 5 and being averaged for landslide earth's surface Inclination angle is consistent;Adjustment solar panels 1 make direct sunlight solar panels;Signal transmitting antenna 10 is adjusted, is allowed to be pointed generally in landslide Monitoring base station;Then drawstring joint ring 17 is fixed on 18 top of monitoring stake stent by anchor bolt 16;
4th, inclination angle measures:Its rotation angle α is obtained by the angle dial on rotary joint 6, as reference stake anchors The mean obliquity for the earth's surface that comes down between point and monitoring stake anchor point;
5th, Initialize installation:The monitoring data of displacement sensor for pull rope 14 are initialized, setting landslide inclination value, displacement are preset Critical value and access time spacing value.
Complete above-mentioned installation and using after step, the utility model enters auto-real-time monitoring and early warning work shape State.

Claims (9)

1. a kind of landslide displacement monitoring device, it is characterised in that:With the reference stake and monitoring stake being anchored in respectively on landslide;
It is equipped with wherein on reference stake for the displacement monitoring module of real-time monitoring criteria stake and monitoring stake relative displacement, passes through displacement The information sending module and sent for displacement monitoring module and information that monitoring modular obtains relative displacement information and is sent out The power supply module of module for power supply.
2. landslide displacement monitoring device according to claim 1, it is characterised in that:The reference stake includes reference stake stent (7) it is pivotally mounted at the top of reference stake stent (7) through rotary joint (6) with base platform (5), base platform (5), the pedestal The displacement monitoring module, information sending module and power supply module are installed on platform.
3. landslide displacement monitoring device according to claim 2, it is characterised in that:With useful on the rotary joint (6) In the angle dial for obtaining its rotation angle.
4. the landslide displacement monitoring device according to Claims 2 or 3, it is characterised in that:It is filled on the reference stake stent (7) There is levelling rod (8).
5. the landslide displacement monitoring device according to Claims 2 or 3, it is characterised in that:The power supply module includes the sun Energy plate (1) and the accumulator (9) being connect with solar panels circuit, solar panels (1) are installed on the pedestal through supporting rod (3) and put down On platform (5), wherein solar panels (1) are rotatably connected with supporting rod (3), supporting rod (3) and base platform (5) rotatable phase Even.
6. landslide displacement monitoring device according to claim 1, it is characterised in that:The displacement monitoring module has drawstring Displacement sensor (14), drawstring joint ring (17) cooperation anchor bolt of the drawstring (15) through its end of the displacement sensor for pull rope (16) it is fixed at the top of the monitoring stake.
7. the landslide displacement monitoring device according to claim 1 or 6, it is characterised in that:Level is housed in the monitoring stake Ruler (8).
8. landslide displacement monitoring device according to claim 1, it is characterised in that:The reference stake is anchored in landslide rear (19) in lateral stabilization rock mass;The monitoring stake is anchored on the inside of landslide rear (19) in slip mass.
9. a kind of landslide displacement early warning system, it is characterised in that:With the landslide displacement described in claim 1~8 any one Monitoring device and the landslide monitoring base station to communicate with the information sending module in landslide displacement monitoring device, in landslide monitoring base station It is broadcasted equipped with early warning.
CN201721436235.0U 2017-11-01 2017-11-01 Landslide displacement monitoring device and early warning system Active CN207556493U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721436235.0U CN207556493U (en) 2017-11-01 2017-11-01 Landslide displacement monitoring device and early warning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721436235.0U CN207556493U (en) 2017-11-01 2017-11-01 Landslide displacement monitoring device and early warning system

Publications (1)

Publication Number Publication Date
CN207556493U true CN207556493U (en) 2018-06-29

Family

ID=62681167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721436235.0U Active CN207556493U (en) 2017-11-01 2017-11-01 Landslide displacement monitoring device and early warning system

Country Status (1)

Country Link
CN (1) CN207556493U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109141319A (en) * 2018-10-26 2019-01-04 兰州理工大学 A kind of landslide surface displacement the whole series monitoring device and its monitoring method
CN110491094A (en) * 2019-08-23 2019-11-22 贵州大学 A kind of prior-warning device for mountain landslide supervision
CN110533886A (en) * 2019-09-27 2019-12-03 南昌大学 A kind of monitoring of full coverage type slope of highway and early warning system
CN111189437A (en) * 2020-01-13 2020-05-22 内蒙古广纳信息科技有限公司 Strip mine side slope deformation detection device and method
CN111649661A (en) * 2020-06-08 2020-09-11 中国葛洲坝集团第一工程有限公司 Stay wire sensor for dangerous rock monitoring and monitoring system
CN111735419A (en) * 2020-08-06 2020-10-02 北京大成国测科技有限公司 Slope horizontal displacement monitoring system and method thereof
CN113465523A (en) * 2021-05-14 2021-10-01 中国地质大学(武汉) Landslide underwater net type three-dimensional deformation monitoring system and method
CN114076580A (en) * 2020-08-21 2022-02-22 南京凡澄自动化有限公司 Device and method for monitoring road surface excavation position
CN115790536A (en) * 2023-02-13 2023-03-14 河北地质大学 Geological exploration sloping field angle accurate measurement device

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109141319B (en) * 2018-10-26 2023-08-15 兰州理工大学 Landslide surface displacement whole set monitoring device and monitoring method thereof
CN109141319A (en) * 2018-10-26 2019-01-04 兰州理工大学 A kind of landslide surface displacement the whole series monitoring device and its monitoring method
CN110491094A (en) * 2019-08-23 2019-11-22 贵州大学 A kind of prior-warning device for mountain landslide supervision
CN110533886A (en) * 2019-09-27 2019-12-03 南昌大学 A kind of monitoring of full coverage type slope of highway and early warning system
CN111189437A (en) * 2020-01-13 2020-05-22 内蒙古广纳信息科技有限公司 Strip mine side slope deformation detection device and method
CN111189437B (en) * 2020-01-13 2022-02-18 江苏恒旺数字科技有限责任公司 Strip mine side slope deformation detection device and method
CN111649661A (en) * 2020-06-08 2020-09-11 中国葛洲坝集团第一工程有限公司 Stay wire sensor for dangerous rock monitoring and monitoring system
CN111735419A (en) * 2020-08-06 2020-10-02 北京大成国测科技有限公司 Slope horizontal displacement monitoring system and method thereof
CN114076580A (en) * 2020-08-21 2022-02-22 南京凡澄自动化有限公司 Device and method for monitoring road surface excavation position
CN114076580B (en) * 2020-08-21 2023-11-21 南京凡澄自动化有限公司 Device and method for monitoring pavement excavation position
CN113465523A (en) * 2021-05-14 2021-10-01 中国地质大学(武汉) Landslide underwater net type three-dimensional deformation monitoring system and method
CN115790536B (en) * 2023-02-13 2023-04-11 河北地质大学 Geological exploration sloping field angle accurate measurement device
CN115790536A (en) * 2023-02-13 2023-03-14 河北地质大学 Geological exploration sloping field angle accurate measurement device

Similar Documents

Publication Publication Date Title
CN207556493U (en) Landslide displacement monitoring device and early warning system
Rahardjo et al. Effect of antecedent rainfall on pore‐water pressure distribution characteristics in residual soil slopes under tropical rainfall
CN209312199U (en) A kind of device monitoring geological disaster
CN112393711B (en) Pole tower settlement and inclination monitoring system based on Beidou positioning and monitoring method thereof
CN107067656A (en) A kind of geological disaster monitoring system
CN108344347A (en) A kind of landslide depth displacement real-time measurement apparatus and measurement method
CN108877177A (en) A kind of fixed wireless inclination monitoring early warning system
CN102043163B (en) Swing type sensing apparatus for debris flow and method for sensing debris flow using thereof
CN110319881A (en) Building deformation and Blast Vibration Monitoring System and method for based on millimetre-wave radar
CN215679597U (en) Landslide disaster monitoring device
CN112301991B (en) Deformation automatic monitoring and early warning method capable of being used for high-fill and soft foundation engineering
CN103914950A (en) Landslide and debris-flow pre-warning system based on 4G network
CN109523743A (en) A kind of landslide comprehensive monitoring prior-warning device
CN111754732A (en) Data acquisition device for monitoring mountain torrent disasters
CN207799866U (en) A kind of strike-slip fault High Cut Slope safety monitoring system based on high and cold mountain area
CN207182625U (en) A kind of debris flow early-warning system
CN107784793A (en) Mountain landslide supervision sensor
CN106225883B (en) Flood beacon
CN218765513U (en) Water level measuring device capable of being flexibly arranged
CN115060154A (en) Soil property side slope deformation monitoring device based on GNSS satellite positioning technology
CN207409113U (en) A kind of landslide and debris flow early-warning detection device
CN206863931U (en) Electric pole and Iron tower incline alarm
CN214149165U (en) Monitoring device for slope stability
Xiao et al. Application and analysis on geological hazard monitoring and early warning system based on Internet of Things
CN112504333B (en) Tunnel vertical settlement and arch wall compressive stress monitor and cloud monitoring and early warning system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant