CN207554109U - Gold mine Bottom of Stope cuts tunnel filling Concrete false bottom - Google Patents
Gold mine Bottom of Stope cuts tunnel filling Concrete false bottom Download PDFInfo
- Publication number
- CN207554109U CN207554109U CN201721785071.2U CN201721785071U CN207554109U CN 207554109 U CN207554109 U CN 207554109U CN 201721785071 U CN201721785071 U CN 201721785071U CN 207554109 U CN207554109 U CN 207554109U
- Authority
- CN
- China
- Prior art keywords
- stope
- reinforced liner
- gold mine
- false bottom
- plastic film
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- PCHJSUWPFVWCPO-UHFFFAOYSA-N gold Chemical compound [Au] PCHJSUWPFVWCPO-UHFFFAOYSA-N 0.000 title claims abstract description 9
- 239000010931 gold Substances 0.000 title claims abstract description 9
- 229910052737 gold Inorganic materials 0.000 title claims abstract description 9
- 239000002985 plastic film Substances 0.000 claims abstract description 9
- 229920006255 plastic film Polymers 0.000 claims abstract description 9
- 239000011449 brick Substances 0.000 claims abstract description 5
- 230000002787 reinforcement Effects 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 5
- 239000010959 steel Substances 0.000 claims description 5
- 238000010276 construction Methods 0.000 abstract description 6
- 238000000034 method Methods 0.000 abstract description 5
- 238000005520 cutting process Methods 0.000 abstract description 4
- 239000011435 rock Substances 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 description 4
- 238000005065 mining Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 229910052500 inorganic mineral Inorganic materials 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011707 mineral Substances 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Abstract
The utility model is a kind of gold mine Bottom of Stope cutting tunnel filling Concrete false bottom, it includes blotter(1), blotter(1)Upper surface is covered with plastic film(2), plastic film(2)Upper surface is equipped with reinforced liner(3), in reinforced liner(3)On built concrete cushion by laying bricks or stones(4).The utility model is applied to oper cylinler shallow hole shrinkage method Bottom of Stope as Concrete false bottom and cuts roadway construction, and certain supporting role can be played to upper lower burrs country rock, improves Stope safty, reduces the occurrence probability of roof fall accident.And it can press with more effectively controlling.
Description
Technical field
The utility model is related to a kind of gold mine Bottom of Stope to cut tunnel filling Concrete false bottom, is mainly used for bottomless
Column shallow hole shrinkage method stope.
Background technology
In gold mine mining, when carrying out back production using oper cylinler shallow hole shrinkage method, after a large amount of ore removals of stope, due to spine
Loss there are, still there are part ore, causing stope quadratic loss larger in stope the problem of.In back production waste fill ore deposit
During the corresponding bottom mineral building in room, it must stop back production when back production is to stope sill 4-5 meters away from top stage casing and set fore-set to stay, this
Sample can cause once to lose, the primary loss up to 10% or so.
Utility model content
The utility model is so the technical issues of solving is to provide a kind of gold mine Bottom of Stope cutting tunnel filling coagulation
Native vacation bottom, to reduce mining loss ratio and press with controlling.
The technical solution of the utility model is as follows:
Gold mine Bottom of Stope cuts tunnel filling Concrete false bottom, it is characterised in that it includes blotter, rubble pad
Layer upper surface is covered with plastic film, and plastic film upper surface is equipped with reinforced liner, has built concrete mats by laying bricks or stones on reinforced liner
Layer.
The reinforced liner includes bar-mat reinforcement, and the rail as rinforcement bar is fixed on bar-mat reinforcement, and two of rail are outer
End has been respectively fixedly connected with round steel.
The utility model has the positive effect that:
First, the utility model is applied as Concrete false bottom applied to oper cylinler shallow hole shrinkage method Bottom of Stope cutting tunnel
Work can play upper lower burrs country rock certain supporting role, improve Stope safty, and the generation for reducing roof fall accident is several
Rate.And it can press with more effectively controlling.
2nd, mining loss ratio is reduced, reduces ore resources waste, improves Economic Effects in Mine Enterprices.
3rd, reduce barren rock freight volume, reduce labor intensity.
Description of the drawings
Fig. 1 is the structure diagram of the utility model.
Fig. 2 is the structure diagram of the reinforced liner of the utility model, the overlook direction which is Fig. 1.
Specific embodiment
The utility model is further illustrated with reference to the accompanying drawings and examples.
Such as Fig. 1, the embodiment of the utility model includes blotter 1, and 1 upper surface of blotter is covered with plastic film 2, moulds
2 upper surface of material film is equipped with reinforced liner 3, has built concrete cushion 4 by laying bricks or stones on reinforced liner 3.
Such as Fig. 2, the reinforced liner 3 includes bar-mat reinforcement 31, the rail 32 as rinforcement bar is fixed on bar-mat reinforcement 31,
Two outer ends of rail 32 are fixedly connected with round steel 33 respectively.
Round steel 33 welds, the reinforcing bar of bar-mat reinforcement 31 is crisscross for being inserted into upper lower burrs between bar-mat reinforcement 31 and rail 32
It is tied up using iron wire at place.
The construction procedure of the utility model is as follows:
Preparation:After adopting quasi- engineering construction, Xian Duiqie chooses ore deposit in lane, chooses to design height;Simultaneously under stope one
Stubble big gun cloth eye.It caunches again to disk on ore removal Chuan Chuqie lanes.
Before construction ore removal wears Concrete false bottom, by design and construction reinforced liner 3, rail 32(The discarded rail of interception
Road)It is both needed to weld between round steel 33, rail 32 and bar-mat reinforcement 31.
Construction:Concrete false bottom carries out successively according to bottom-up sequence.First, in the rubble pad for cutting lane laying 200mm
Layer 1;2nd, plastic film 2 is laid on blotter 1;3rd, reinforced liner 3 is laid on plastic film 2;4th, in reinforced liner
Construct on 3 the concrete cushion 4 of 1m, at the same each ore removal of constructing wear and ore removal wear between concrete slope, reinforced liner 3 need to build by laying bricks or stones
In concrete.Rubble lumpiness is not greater than 50 × 50 ㎜ 2.
Maintenance:Curing period is five to seven days after Concrete false bottom is constructed, after Concrete false bottom intensity reaches requirement
It can dig up mine.
Claims (2)
1. gold mine Bottom of Stope cuts tunnel filling Concrete false bottom, it is characterised in that it includes blotter(1), rubble pad
Layer(1)Upper surface is covered with plastic film(2), plastic film(2)Upper surface is equipped with reinforced liner(3), in reinforced liner(3)On
Concrete cushion is built by laying bricks or stones(4).
2. gold mine Bottom of Stope as described in claim 1 cuts tunnel filling Concrete false bottom, it is characterised in that:Described
Reinforced liner(3)Including bar-mat reinforcement(31), bar-mat reinforcement(31)On be fixed with rail as rinforcement bar(32), rail(32)Two
A outer end is fixedly connected with round steel respectively(33).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721785071.2U CN207554109U (en) | 2017-12-20 | 2017-12-20 | Gold mine Bottom of Stope cuts tunnel filling Concrete false bottom |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721785071.2U CN207554109U (en) | 2017-12-20 | 2017-12-20 | Gold mine Bottom of Stope cuts tunnel filling Concrete false bottom |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207554109U true CN207554109U (en) | 2018-06-29 |
Family
ID=62663705
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721785071.2U Expired - Fee Related CN207554109U (en) | 2017-12-20 | 2017-12-20 | Gold mine Bottom of Stope cuts tunnel filling Concrete false bottom |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207554109U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114776373A (en) * | 2022-06-20 | 2022-07-22 | 长春黄金研究院有限公司 | Artificial false bottom for thin-vein stope and manufacturing method |
-
2017
- 2017-12-20 CN CN201721785071.2U patent/CN207554109U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114776373A (en) * | 2022-06-20 | 2022-07-22 | 长春黄金研究院有限公司 | Artificial false bottom for thin-vein stope and manufacturing method |
CN114776373B (en) * | 2022-06-20 | 2022-10-11 | 长春黄金研究院有限公司 | Artificial false bottom for thin-vein stope and manufacturing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105839850B (en) | Precompressed construction method is poured into a mould after basement top-down method shaft | |
CN104632220B (en) | Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope | |
CN110118089B (en) | Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof | |
CN109595029B (en) | Goaf partial stowage supporting structure and its construction method under the conditions of tight roof | |
CN111878117B (en) | Construction method of artificial roof facility by downward approach filling method | |
CN107805987A (en) | The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section | |
CN113914860B (en) | Roof-cutting gob-side entry retaining method for non-compact solid filling working face | |
CN106499405A (en) | Tunnel lining structure | |
CN106089207B (en) | Super high seam working face gob side entry driving thin coal pillar stays equipment, method | |
CN107288684A (en) | The segmented filling process and method in a kind of excessively complicated empty lane of high working face comprehensive coal face | |
CN104358202B (en) | Road surface structare layer and its paving method | |
CN206707726U (en) | A kind of gob side entry retaining roadside support system | |
CN207554109U (en) | Gold mine Bottom of Stope cuts tunnel filling Concrete false bottom | |
CN104747191A (en) | Construction method for connecting structure of shaft and shaft station | |
CN106759464A (en) | A kind of hypogee and its construction method | |
CN109252873B (en) | Design and construction method for multiple cross mountain road and railway tunnels | |
CN104695315B (en) | Frame structure of deep foundation pit under existing railway and layered jacking method for construction of frame structure | |
CN108691559A (en) | One kind helping hard and soft cooperative control method for gob side entry coal column | |
CN105840234B (en) | A kind of pile pillar filling template and its application method | |
CN105909290B (en) | The apparatus and method that controlroof sinks in a kind of filling mining of pillar part | |
CN207452609U (en) | A kind of hassock layer Foam lightweight soil road structure in deep soft foundation section | |
CN114109490A (en) | Construction process for key layer of artificial false roof of prefabricated reinforced concrete slab | |
CN114352350A (en) | Artificial false roof construction and recovery method | |
CN110541729A (en) | artificial false bottom and manufacturing method thereof | |
CN104564136A (en) | Artificial false bottom and manufacturing method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180629 |