CN110118089B - Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof - Google Patents

Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof Download PDF

Info

Publication number
CN110118089B
CN110118089B CN201910432285.9A CN201910432285A CN110118089B CN 110118089 B CN110118089 B CN 110118089B CN 201910432285 A CN201910432285 A CN 201910432285A CN 110118089 B CN110118089 B CN 110118089B
Authority
CN
China
Prior art keywords
coal gangue
self
frp
layer
compacting concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910432285.9A
Other languages
Chinese (zh)
Other versions
CN110118089A (en
Inventor
赵红超
刘洪林
王宏志
李国栋
刘洋
万威
康海通
张炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xukuang Group Xinjiang Saier Energy Co ltd
Original Assignee
Xinjiang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang University filed Critical Xinjiang University
Priority to CN201910432285.9A priority Critical patent/CN110118089B/en
Publication of CN110118089A publication Critical patent/CN110118089A/en
Application granted granted Critical
Publication of CN110118089B publication Critical patent/CN110118089B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a mining FRP grid-coal gangue-self-compacting concrete regeneration top plate and a construction method thereof. The method comprises the following steps: laying a first layer of FRP grids along the bottom plate of the goaf after top-layering mining; filling the crushed coal gangue; then laying a second layer of FRP grid; continuously filling coal gangue; after filling, the gap of the coal gangue is filled by adopting self-compacting concrete at one time. The invention has the beneficial effects that: according to the invention, the lightweight high-strength corrosion-resistant FRP grid is adopted, so that the transverse deformation of the coal gangue material can be effectively restrained, the shear strength and the elastic modulus of the coal gangue discrete material are improved, and the self-compacting concrete is used for filling the gaps of the coal gangue discrete material, so that the non-uniform settlement of the discrete aggregate can be effectively inhibited. The construction process is simple, the construction speed is high, and the formed regenerated top plate is good in stability.

Description

Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof
Technical Field
The invention relates to the technical field of coal mining, in particular to a mining FRP grid-coal gangue-self-compacting concrete regenerated roof and a construction method thereof.
Background
When a thick coal seam is exploited in a layered mode, a top plate formed by naturally cementing a rock stratum collapsed in an upper layer for a certain time is called a regenerated top plate. The formation of the regenerated roof includes both compaction and cementing of the fractured rock formation. To reduce the time required for natural cementation, yellow mud or water glass is generally used as the cementing material. To improve the stability of the regenerated roof, a layer of metal or plastic mesh is usually laid along the upper layered roof. Because the metal net is easy to corrode and the plastic net is not enough in strength, the regenerated top plate formed by the method has the characteristics of being not enough in stability and poor in bonding property between broken rock bodies. In the process of lower-layer mining, the traditional anchor rod supporting technology cannot effectively control the stability of the regenerated top plate due to the fact that the traditional anchor rod supporting technology cannot be anchored to a stable rock stratum, and therefore the safety and high-efficiency production of coal mines are threatened. Meanwhile, in the process of mining the coal seam in the extremely close range, the disturbance of the mining of the upper coal seam on the bottom plate also causes the support of the lower roadway to have no stable and reliable anchoring area. In order to ensure that the anchor rod can be anchored to a stable rock stratum, a regenerated top plate with simple construction process and high reliability needs to be developed, and the current situations of high difficulty and insufficient stability of the existing layered mining support are changed.
Disclosure of Invention
The invention aims to provide a mining FRP grid-coal gangue-self-compacting concrete regenerated top plate to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: the upper end of the upper layer is an overlying rock stratum, the lower end of the upper layer is a reserved area rock stratum, the lower end of the reserved area rock stratum is a lower layer, an anchor rod is arranged between the reserved area rock stratums, an FRP grid is arranged at the bottom of the upper layer, artificial filling coal gangue is arranged at the upper end of the FRP grid, a second layer of the FRP grid is arranged at the upper end of the artificial filling coal gangue, a second layer of the artificial filling coal gangue is arranged at the upper end of the FRP grid, the artificial filling coal gangue is filled to the bottom of the overlying rock stratum, the FRP grid is provided with meshes, the overlying rock stratum forms naturally stacked caving rocks under the action of mine pressure, and self-compacting concrete is filled between the naturally stacked caving rocks and the artificial filling coal gangue.
Preferably, the maximum diameter of the meshes of the FRP grid is smaller than the average diameter of the artificial filling coal gangue.
Preferably, the self-compacting concrete can be prepared by mixing sand, gravel, cement and water, and also can be prepared by mixing coal gangue, sand, cement and water.
Preferably, the artificial filling coal gangue can be coal gangue directly crushed underground or coal gangue transported underground from the ground through a vertical feeding system, and the diameter range of the artificial filling coal gangue can be more than 200 mm.
Preferably, the distance between the two FRP grids is half of the thickness of the upper layer.
Preferably, the self-compacting concrete is integrally cast once after the artificial filling coal gangue is completely filled with the upper layer.
Preferably, the FRP grids may be erected in two or three layers according to an actual mining height.
A construction method of a mining FRP grid-coal gangue-self-compacting concrete regenerated top plate specifically comprises the following steps:
the method comprises the following steps: the FRP grids are laid along the bottom of the upper layer, and then a first layer of the artificial filling coal gangue is laid above the FRP grids.
Step two: and after the first layer of the artificial filling coal gangue is paved, paving a second layer of the FRP grid.
Step three: and after the second layer of FRP grids is paved, filling a second layer of the artificial filling coal gangue above the second layer of FRP grids until the second layer of the FRP grids contacts the overburden.
Step four: and after all the artificial filling coal gangue is filled, injecting the self-compacting concrete to form the final mining FRP grid-coal gangue-self-compacting concrete regeneration top plate.
The invention has the advantages of
According to the invention, the lightweight high-strength corrosion-resistant FRP grid is adopted, so that the transverse deformation of the coal gangue material can be effectively restrained, the shear strength and the elastic modulus of the coal gangue discrete material are improved, and the self-compacting concrete is used for filling the gaps of the coal gangue discrete material, so that the non-uniform settlement of the discrete aggregate can be effectively inhibited. The construction process is simple, the construction speed is high, and the formed regenerated top plate is good in stability.
Drawings
FIG. 1 is a schematic diagram of a process for stratified mining of a thick coal seam in accordance with the present invention;
FIG. 2 is a regenerated top plate formed by the natural caving method of the present invention;
FIG. 3 is a schematic structural view of an FRP grid-coal gangue-self-compacting concrete recycled roof according to the present invention;
FIG. 4 is a schematic diagram of the FRP grid-coal gangue-self-compacting concrete recycled roof construction of the invention.
Reference numerals
1-upper layering, 2-reserved area rock stratum, 3-lower layering, 4-overlying rock stratum, 5-naturally stacked collapsed rock, 6-anchor rod, 7-artificial filling coal gangue, 8-FRP grid, 9-mesh and 10-self-compacting concrete.
Detailed Description
The following are specific embodiments of the present invention and are further described with reference to the drawings, but the present invention is not limited to these embodiments.
Examples
As shown in fig. 1-4, a mining FRP grating-coal gangue-self-compacting concrete regenerated top plate comprises an upper layer 1, wherein the upper end of the upper layer 1 is an overlying rock stratum 4, the lower end of the upper layer 1 is a reserved zone rock stratum 2, the lower end of the reserved zone rock stratum 2 is a lower layer 3, an anchor rod 6 is arranged between the reserved zone rock stratums 2, an FRP grating 8 is arranged at the bottom of the upper layer 1, an artificial filling coal gangue 7 is arranged at the upper end of the FRP grating 8, a second layer of the FRP grating 8 is arranged at the upper end of the artificial filling coal gangue 7, the artificial filling coal gangue 7 is filled to the bottom of the overlying rock stratum 4, the FRP grating 8 is provided with meshes 9, the overlying rock stratum 4 forms naturally-piled caving rocks 5 under the action of mine pressure, and self-compacting concrete 10 is filled between the naturally-piled caving rocks 5 and the artificial filling coal gangue 7.
Preferably, the diameter of the maximum meshes 9 of the FRP grid 8 is smaller than the average diameter of the artificial filling coal gangue 7.
Preferably, the self-compacting concrete 10 is formed by mixing sand, gravel, cement and water, or by mixing coal gangue, sand, cement and water.
Preferably, the artificial filling coal gangue 7 can be coal gangue directly crushed underground or coal gangue transported underground from the ground through a vertical feeding system, and the diameter range of the artificial filling coal gangue can be more than 200 mm.
Preferably, the distance between the two FRP grid layers 8 is half of the thickness of the upper layer 1.
Preferably, the self-compacting concrete 10 is integrally cast once after the coal gangue 7 is completely filled and layered.
Preferably, the FRP grating 8 may be constructed in two or three layers depending on the actual mining height.
A construction method of a mining FRP grid-coal gangue-self-compacting concrete regenerated top plate specifically comprises the following steps:
the method comprises the following steps: the FRP grid 8 is laid along the bottom of the upper layer 1, and then a first layer of artificial filling coal gangue 7 is laid above the FRP grid 8.
Step two: and after the first layer of the artificial filling coal gangue 7 is paved, paving a second layer of FRP grid 8.
Step three: and after the second layer of FRP grid 8 is paved, filling a second layer of artificial filling coal gangue 7 above the second layer of FRP grid 8 until the second layer of artificial filling coal gangue contacts the overburden 4.
Step four: after all the artificial filling of the coal gangue 7 is completed, the self-compacting concrete 10 is injected to form the final mining FRP grid-coal gangue-self-compacting concrete regenerated top plate.
In the stratified mining of the thick coal seam, an upper stratum is usually mined firstly, and then a lower stratum is mined, so that a reserved area rock stratum with a certain thickness is usually reserved between the upper stratum and the lower stratum in order to ensure the safety and stability of the lower stratum. After the upper strata is mined, the overlying strata form naturally-accumulated collapsed rocks under the action of the mine pressure. Over time, the naturally piled up caving rock will further compact and consolidate, eventually forming a regenerated roof. When the lower layer is mined, the anchor rod cannot be anchored to a stable overlying rock layer due to length limitation, so that potential safety hazards are brought.
The FRP grid is obtained by a glass Fiber Reinforced Plastic (FRP) with light weight and high strength through a pultrusion process, and the diameter of the maximum mesh of the FRP grid is smaller than the average diameter of the artificial filling coal gangue. The artificial filling coal gangue can be directly crushed coal gangue underground or coal gangue transported underground from the ground through a vertical feeding system. Different from coal gangue used in traditional gangue filling, the diameter range of the coal gangue can be larger than 200 mm, and the FRP grid improves the shear strength and the elastic modulus of the coal gangue manually filled by limiting the lateral movement of the coal gangue manually filled. The FRP grids are laid along the bottom of the upper layer, then a first layer of artificial filling coal gangue is laid above the FRP grids, and then a second layer of FRP grids is laid, wherein the longitudinal distance between the two layers of FRP grids is one meter. And then, filling the artificial coal gangue above the second layer of FRP grid until the artificial coal gangue contacts the overburden. And after the artificial filling of the coal gangue is finished, injecting self-compacting concrete to form the final mining FRP grid-coal gangue-self-compacting concrete regenerated top plate.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (2)

1. A mining FRP grid-gangue-self-compacting concrete regeneration roof is characterized in that: the coal mine underground coal mine, self-compacting concrete (10) is injected between the naturally piled caving rock (5) and the artificially filled coal gangue (7), the maximum mesh (9) diameter of the FRP grid (8) is smaller than the average diameter of the artificially filled coal gangue (7), the self-compacting concrete (10) is formed by stirring sand, stone, cement and water or is formed by stirring coal gangue, sand, cement and water, the artificially filled coal gangue (7) is coal gangue directly crushed underground or is coal gangue transported underground from the ground through a vertical feeding system, the diameter range of the artificially filled coal gangue is larger than 200 mm, the distance between the two layers of the FRP grid (8) is half of the thickness of the upper layer (1), and after the artificially filled coal gangue (7) is completely filled with the upper layer, the integral pouring is completed in one step, and the FRP grid (8) is erected into two or three layers according to the actual mining height.
2. The construction method of the mining FRP grid-coal gangue-self-compacting concrete recycled roof as recited in claim 1, characterized in that: the method is implemented by the following steps:
the method comprises the following steps: the FRP grid (8) is laid along the bottom of the upper layer (1), and then a first layer of the artificial filling coal gangue (7) is laid above the FRP grid (8);
step two: after the first layer of the artificial filling coal gangue (7) is paved, a second layer of the FRP grid (8) is paved;
step three: after the second layer of FRP grids (8) is paved, filling a second layer of the artificial filling coal gangue (7) above the second layer of FRP grids (8) until the artificial filling coal gangue contacts the overburden (4);
step four: and after all the artificial filling coal gangue (7) is filled, injecting the self-compacting concrete (10) to form a final mining FRP grid-coal gangue-self-compacting concrete regeneration top plate.
CN201910432285.9A 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof Active CN110118089B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910432285.9A CN110118089B (en) 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910432285.9A CN110118089B (en) 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof

Publications (2)

Publication Number Publication Date
CN110118089A CN110118089A (en) 2019-08-13
CN110118089B true CN110118089B (en) 2021-09-07

Family

ID=67522963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910432285.9A Active CN110118089B (en) 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof

Country Status (1)

Country Link
CN (1) CN110118089B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112001086B (en) * 2020-08-26 2024-01-30 湖南科技大学 Method for determining components of leakage air crack cementing material based on regenerated roof layering characteristics
CN113638770B (en) * 2021-08-30 2023-07-18 烟台杰瑞石油装备技术有限公司 Goaf filling equipment and method and goaf filling structure
CN113898373B (en) * 2021-10-19 2023-10-13 辽宁工业大学 FRP-PVC film shell internally filled with self-compaction gangue concrete fireproof combined coal column and reinforcing method
CN114294008B (en) * 2022-01-13 2024-03-05 辽宁工业大学 FRP strip constraint and sprayed concrete and geogrid combined coal column reinforcement method
CN116480367B (en) * 2023-03-29 2024-07-09 国能经济技术研究院有限责任公司 Construction method of integral type leveling reinforcement structure of roadway floor

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH093745A (en) * 1995-06-19 1997-01-07 Toray Ind Inc Reinforcing fiber sheet and concrete structure
JP2002038655A (en) * 2000-07-31 2002-02-06 Nippon Steel Composite Co Ltd Strip composite frp lattice member, and concrete reinforcing method using strip composite frp lattice member
CN103291305A (en) * 2013-05-22 2013-09-11 贵州开磷(集团)有限责任公司 Quick and low-cost artificial fake roof construction method for ground mine
CN109595016A (en) * 2018-12-27 2019-04-09 中南大学 False top construction method is exploited to admission passage filling under one kind

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH093745A (en) * 1995-06-19 1997-01-07 Toray Ind Inc Reinforcing fiber sheet and concrete structure
JP2002038655A (en) * 2000-07-31 2002-02-06 Nippon Steel Composite Co Ltd Strip composite frp lattice member, and concrete reinforcing method using strip composite frp lattice member
CN103291305A (en) * 2013-05-22 2013-09-11 贵州开磷(集团)有限责任公司 Quick and low-cost artificial fake roof construction method for ground mine
CN109595016A (en) * 2018-12-27 2019-04-09 中南大学 False top construction method is exploited to admission passage filling under one kind

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
FRP锚网在煤矿中的应用;王厚东;《中国建材报》;20100909;第1-2页 *

Also Published As

Publication number Publication date
CN110118089A (en) 2019-08-13

Similar Documents

Publication Publication Date Title
CN110118089B (en) Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof
CN102155226B (en) Roadway backfill mining method for coal seams with medium-high thickness
CN105971606B (en) A kind of thick sandstone coal wall recovery method
CN111335943B (en) Point source type interval grouting loss reduction method by utilizing top plate collapse, crushing and swelling filling and directional drilling
CN109184694A (en) A kind of pre- anchor sublevel drilling stage open stope afterwards filling mining method of upper disk
CN102071941B (en) Fully mechanized mining gob-side entry retaining-based concrete block staggered joint longitudinal stacking wall forming method
CN111878117B (en) Construction method of artificial roof facility by downward approach filling method
CN110043311A (en) A kind of goaf grouting filling process for being suitble to stay lane
CN111734482A (en) Method for reducing damage by utilizing gangue cementation and bag grouting combined support
CN106321113B (en) A kind of lane space frame structure and its method for protecting support for being used to wear goaf
CN104594926A (en) Rapid composite roof roadway support method for high-stress water guiding karst cave group
CN103321234B (en) Constructing method of load-bearing structure built on high slope or geological complex area
CN111594168B (en) Pseudo-goaf-layer supporting and sinking-limiting stoping method formed by matching rock waste with rock waste
CN103147792A (en) Drift type coal mining filling method
CN103161467B (en) Horizontal moderately thick mine body compartment type filling mining method
CN112593939A (en) Method for mining 'three lower' coal seam by replacing all coal pillars through gangue double filling
CN110645018B (en) Mine underground strong dynamic pressure roadway prestress anchor-charging integrated supporting structure and method
CN206280090U (en) High-dipping surrounding rock of actual mining roadway stabilization supporting facility
CN117449900A (en) Method for controlling stope rock stratum movement and earth surface subsidence
CN114673527A (en) Method for reinforcing broken surrounding rock of progressive roadway and tunnel
CN108691559A (en) One kind helping hard and soft cooperative control method for gob side entry coal column
CN106761867A (en) High-dipping surrounding rock of actual mining roadway stabilization supporting facility and support process
CN103572680A (en) Road roadbed filling construction method of coal mine gob
CN102373955A (en) Steel wire rope cemented filling method used in open stope mining subsequent filling gob
CN109958456B (en) Advanced reinforcement construction method for building tunnel in stratum without self-stability capability

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231213

Address after: 834406 No. 396, Dielun South Street, Hestoluogai Town, Hoboksar Mongol Autonomous County, Tacheng Prefecture, Xinjiang Uygur Autonomous Region

Patentee after: Xukuang group Xinjiang Saier Energy Co.,Ltd.

Address before: No. 666, Shengli Road, Urumqi, Xinjiang Uygur Autonomous Region

Patentee before: XINJIANG University

TR01 Transfer of patent right