CN110118089A - A kind of mining FRP grid-gangue-self-compacting concrete mat and its construction method - Google Patents

A kind of mining FRP grid-gangue-self-compacting concrete mat and its construction method Download PDF

Info

Publication number
CN110118089A
CN110118089A CN201910432285.9A CN201910432285A CN110118089A CN 110118089 A CN110118089 A CN 110118089A CN 201910432285 A CN201910432285 A CN 201910432285A CN 110118089 A CN110118089 A CN 110118089A
Authority
CN
China
Prior art keywords
gangue
frp grid
self
compacting concrete
mining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910432285.9A
Other languages
Chinese (zh)
Other versions
CN110118089B (en
Inventor
赵红超
刘洪林
王宏志
李国栋
刘洋
万威
康海通
张炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xukuang Group Xinjiang Saier Energy Co ltd
Original Assignee
Xinjiang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang University filed Critical Xinjiang University
Priority to CN201910432285.9A priority Critical patent/CN110118089B/en
Publication of CN110118089A publication Critical patent/CN110118089A/en
Application granted granted Critical
Publication of CN110118089B publication Critical patent/CN110118089B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material

Abstract

The invention discloses a kind of mining FRP grid-gangue-self-compacting concrete mat and its construction methods, including FRP grid, gangue packing material, self-compacting concrete.The method of the present invention step includes: to be laid with first layer FRP grid along gob floor after mining top slice;Smashed gangue is filled;Then it is laid with second layer FRP grid;Continue to fill gangue;Self-compacting concrete one-time filling gangue gap is being used after the completion of filling.The beneficial effects of the present invention are: the present invention is by using the corrosion resistant FRP grid of high-strength light, the transversely deforming of granular media bastard coal stone material can effectively be constrained, improve the shear strength and elasticity modulus of gangue discrete material, and using the gap of self-compacting concrete filling gangue discrete material, the heterogeneity sedimentation of granular media aggregate can be effectively inhibited.Construction technology of the present invention is simple, speed of application is fast, and the mat stability of formation is good.

Description

A kind of mining FRP grid-gangue-self-compacting concrete mat and its construction Method
Technical field
The present invention relates to coal mining technology field, specially a kind of mining FRP grid-gangue-self-compacting concrete Mat and its construction method.
Background technique
When thick seam slicing system, top plate that rock stratum that higher slice is caving is formed by the naturally cementing of certain time Do mat.The formation of mat includes being caving the compacting and cementing two processes of rock stratum.It is cementing required to reduce nature Time, generally use yellow mud or waterglass as cementing material.For improve mat stability, usually along higher slice Top plate is laid with one layer of metal mesh or plastic wire.Since metal mesh easily corrodes, plastic wire intensity is inadequate, is formed using the above method Mat usually there is stability deficiency, the feature for cohering characteristic difference between fragmented rock body.In lower leaf recovery process In, the steady of mat cannot be efficiently controlled due to that can not anchor to stable rock stratum using traditional bolt support technology It is fixed, it is efficiently produced to safety of coal mines and brings threat.Meanwhile in ultra close distance coal seam recovery process, superjacent exploitation pair The disturbance of bottom plate bring, which also leads to the next roadway support, does not have reliable and stable anchorage zone.To ensure that anchor pole can anchor to surely Determine rock stratum, it is necessary to develop that a kind of construction technology is simple, mat of high reliablity, change existing separate zone production supporting difficulty Greatly, the insufficient status of stability.
Summary of the invention
The purpose of the present invention is to provide a kind of mining FRP grid-gangue-self-compacting concrete mats, with solution Certainly the problems mentioned above in the background art.
To achieve the above object, the invention provides the following technical scheme: a kind of mining FRP grid-gangue-self-compaction is mixed Solidifying soil mat, including higher slice, the higher slice upper end are overlying rock, and the higher slice lower end is trough rock stratum, Trough rock stratum lower end is lower leaf, and anchor pole is equipped between the trough rock stratum, and the higher slice bottom is equipped with FRP lattice Grid, FRP grid upper end are equipped with artificial filling gangue, and the artificial filling gangue upper end is equipped with FRP described in the second layer Grid, FRP grid upper end described in the second layer are equipped with and manually fill gangue described in the second layer, the artificial filling gangue filling To the overlying rock bottom, the FRP grid is equipped with mesh, and the overlying rock forms nature heap under action of underground Long-pending is caving rock, and being caving between rock and the artificial filling gangue for the natural packing is marked with self-compacting concrete.
Preferably, the diameter of the maximum mesh of the FRP grid is less than the average straight of the hand packing gangue Diameter.
Preferably, the self-compacting concrete can be stirred by sandstone, sand, cement and water, can also pass through coal Spoil, sand, cement and water stir.
Preferably, the hand packing gangue can be the gangue that underground directly crushes, and be also possible to logical from ground It crosses vertical feeding system to transport to the gangue of underground, the diameter range of the hand packing gangue can be greater than 200 mm.
Preferably, between two layers of FRP grid spacing be the higher slice thickness half.
Preferably, the self-compacting concrete waits for that the artificial filling gangue is completely filled with after higher slice, disposably One-piece casting is completed.
Preferably, the FRP grid can be set up two layers or three layers according to practical mining height.
A kind of construction method of mining FRP grid-gangue-self-compacting concrete mat specifically uses following step It is rapid to implement:
Step 1: the FRP grid is laid with along the higher slice bottom, and first layer institute is then laid with above the FRP grid State hand packing gangue.
Step 2: after the completion of the hand packing gangue described in the first layer is laid with, it is laid with FRP grid described in the second layer.
Step 3: after the completion of the FRP grid described in the second layer is laid with, the filling the in the top of the second layer FRP grid Two layers of hand packing gangue, until touching the overlying rock.
Step 4: it after all hand packing gangues are completed in filling, injects the self-compacting concrete and is formed most Whole mining FRP grid-gangue-self-compacting concrete mat.
Beneficial effects of the present invention
The present invention can effectively constrain the transverse direction of granular media bastard coal stone material by using the corrosion resistant FRP grid of high-strength light Deformation is improved the shear strength and elasticity modulus of gangue discrete material, and is dissipated using self-compacting concrete filling gangue The gap of body material can effectively inhibit the heterogeneity sedimentation of granular media aggregate.Construction technology of the present invention is simple, speed of application Fastly, the mat stability of formation is good.
Detailed description of the invention
Fig. 1 is thick seam slicing system process schematic representation of the invention;
Fig. 2 is the mat that spontaneous caving method of the invention is formed;
Fig. 3 is FRP grid-gangue-self-compacting concrete mat structural schematic diagram of the invention;
Fig. 4 is FRP grid-gangue-self-compacting concrete mat construction schematic diagram of the invention.
Appended drawing reference
1- higher slice, the trough 2- rock stratum, 3- lower leaf, 4- overlying rock, 5- natural packing are caving rock, 6- anchor pole, 7- Hand packing gangue, 8-FRP grid, 9- mesh, 10- self-compacting concrete.
Specific embodiment
Following is a specific embodiment of the present invention in conjunction with the accompanying drawings, technical scheme of the present invention will be further described, However, the present invention is not limited to these examples.
Embodiment
As shown in Figs 1-4, a kind of mining FRP grid-gangue-self-compacting concrete mat, including higher slice 1, 1 upper end of higher slice is overlying rock 4, and 1 lower end of higher slice is trough rock stratum 2, and 2 lower end of trough rock stratum is lower leaf 3, is reserved Anchor pole 6 is equipped between area rock stratum 2,1 bottom of higher slice is equipped with FRP grid 8, and 8 upper end of FRP grid is equipped with artificial filling gangue 7, Artificial filling 7 upper end of gangue is equipped with FRP grid 8 described in the second layer, and 8 upper end of second layer FRP grid is equipped with the second layer and manually fills out Gangue 7 is filled, artificial to fill the filling of gangue 7 to 4 bottom of overlying rock, FRP grid 8 is equipped with mesh 9, and overlying rock 4 is in mine Natural packing is formed under the effect of mountain pressure is caving rock 5, and natural packing is caving between rock 5 and artificial filling gangue 7 It is marked with self-compacting concrete 10.
Preferably, the diameter of the maximum mesh 9 of FRP grid 8 is less than the average diameter of hand packing gangue 7.
Preferably, self-compacting concrete 10 can be stirred by sandstone, sand, cement and water, can also pass through bastard coal Stone, sand, cement and water stir.
Preferably, hand packing gangue 7 can be the gangue that underground directly crushes, and be also possible to from ground by hanging down The gangue of material system transfer to underground is delivered directly, the diameter range of the hand packing gangue can be greater than 200 mm.
Preferably, between two layers of FRP grid 8 spacing be 1 thickness of higher slice half.
Preferably, it is disposable whole to pour after self-compacting concrete 10 is completely filled with higher slice to manually filling gangue 7 Build completion.
Preferably, FRP grid 8 can be set up two layers or three layers according to practical mining height.
A kind of construction method of mining FRP grid-gangue-self-compacting concrete mat specifically uses following step It is rapid to implement:
Step 1: FRP grid 8 is laid with along 1 bottom of higher slice, and first layer hand packing bastard coal is then laid with above FRP grid 8 Stone 7.
Step 2: after the completion of the laying of first layer hand packing gangue 7, it is laid with second layer FRP grid 8.
Step 3: after the completion of the laying of second layer FRP grid 8, second layer people is filled in the top of second layer FRP grid 8 Work fills gangue 7, until touching overlying rock 4.
Step 4: after whole hand packing gangues 7 are completed in filling, injection self-compacting concrete 10 forms final mine With FRP grid-gangue-self-compacting concrete mat.
Thick seam slicing system usually first exploits higher slice, then exploits lower leaf, for the safety and stability for ensuring lower leaf, It is stayed usually between higher slice and lower leaf and sets certain thickness trough rock stratum.After higher slice is exploited, overlying rock is in mine Natural packing is formed under the effect of mountain pressure is caving rock.As time goes by, natural packing is caving rock and will further press It is real and cementing, ultimately form mat.When exploiting lower leaf, anchor pole can not be anchored to stable upper due to length limitation Rock stratum, to bring security risk.
FRP grid of the invention passes through formed by extrusion and tension by the glass fibre reinforced composion (FRP) with high-strength light Technique obtains, and the diameter of the maximum mesh of FRP grid should be less than the average diameter of hand packing gangue.Hand packing coal Spoil can be the gangue that underground directly crushes, and be also possible to transport from ground by vertical feeding system to the bastard coal of underground Stone.Different from gangue used in traditional waste filling, gangue diameter range can be greater than 200 mm, and FRP grid passes through limit The lateral movement of hand packing gangue processed improves the shear strength and elasticity modulus of hand packing gangue.FRP grid is along upper It is layered bottom to be laid with, first layer hand packing gangue is then laid with above FRP grid, is then laid with second layer FRP grid, Wherein the longitudinal pitch of two layers of FRP grid is one meter.Full hand packing gangue is filled in the top of second layer FRP grid later Until touching overlying rock.After completing hand packing gangue, self-compacting concrete is injected, is formed final mining FRP grid-gangue-self-compacting concrete mat.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (8)

1. a kind of mining FRP grid-gangue-self-compacting concrete mat, it is characterised in that: including higher slice (1), institute Stating higher slice (1) upper end is overlying rock (4), and higher slice (1) lower end is trough rock stratum (2), the trough rock stratum (2) lower end is lower leaf (3), is equipped with anchor pole (6) between the trough rock stratum (2), higher slice (1) bottom is equipped with FRP Grid (8), FRP grid (8) upper end are equipped with artificial filling gangue (7), and artificial filling gangue (7) upper end is equipped with FRP grid (8) described in the second layer, FRP grid (8) upper end described in the second layer are equipped with described in the second layer and manually fill gangue (7), To the overlying rock (4) bottom, the FRP grid (8) is equipped with mesh (9), described for artificial filling gangue (7) filling What overlying rock (4) formed natural packing under action of underground is caving rock (5), and the natural packing is caving rock (5) self-compacting concrete (10) are marked between the artificial filling gangue (7).
2. mining FRP grid-gangue-self-compacting concrete mat according to claim 1, it is characterised in that: The diameter of the maximum mesh (9) of the FRP grid (8) is less than the average diameter of the hand packing gangue (7).
3. mining FRP grid-gangue-self-compacting concrete mat according to claim 1, it is characterised in that: The self-compacting concrete (10) can be stirred by sandstone, sand, cement and water, can also pass through gangue, sand, water Mud and water stir.
4. mining FRP grid-gangue-self-compacting concrete mat according to claim 1, it is characterised in that: The hand packing gangue (7) can be the gangue that underground directly crushes, and be also possible to pass through vertical feeding system from ground System is transported to the gangue of underground, and the diameter range of the hand packing gangue can be greater than 200mm.
5. mining FRP grid-gangue-self-compacting concrete mat according to claim 1, it is characterised in that: Spacing is the half of the higher slice (1) thickness between two layers of FRP grid (8).
6. mining FRP grid-gangue-self-compacting concrete mat according to claim 1, it is characterised in that: After the self-compacting concrete (10) is completely filled with higher slice to the artificial filling gangue (7), disposable one-piece casting It completes.
7. mining FRP grid-gangue-self-compacting concrete mat according to claim 1, it is characterised in that: The FRP grid (8) can set up two layers or three layers according to practical mining height.
8. according to claim 1 to the grid-gangue-self-compacting concrete mat of mining FRP described in 7 any one Construction method, it is characterised in that: specifically implemented using following steps:
Step 1: the FRP grid (8) is laid with along the higher slice (1) bottom, is then laid with above the FRP grid (8) Hand packing gangue (7) described in first layer.
Step 2: after the completion of the hand packing gangue (7) described in the first layer is laid with, it is laid with FRP grid (8) described in the second layer.
Step 3: it after the completion of the FRP grid (8) described in the second layer is laid with, is filled in the top of the second layer FRP grid (8) Hand packing gangue (7) described in the second layer, until touching the overlying rock (4).
Step 4: after all hand packing gangues (7) are completed in filling, the self-compacting concrete (10) formation is injected Final mining FRP grid-gangue-self-compacting concrete mat.
CN201910432285.9A 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof Active CN110118089B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910432285.9A CN110118089B (en) 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910432285.9A CN110118089B (en) 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof

Publications (2)

Publication Number Publication Date
CN110118089A true CN110118089A (en) 2019-08-13
CN110118089B CN110118089B (en) 2021-09-07

Family

ID=67522963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910432285.9A Active CN110118089B (en) 2019-05-23 2019-05-23 Mining FRP grid-coal gangue-self-compacting concrete regenerated top plate and construction method thereof

Country Status (1)

Country Link
CN (1) CN110118089B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112001086A (en) * 2020-08-26 2020-11-27 湖南科技大学 Method for determining components of air leakage crack cementing material based on layering characteristics of regenerated top plate
CN113638770A (en) * 2021-08-30 2021-11-12 烟台杰瑞石油装备技术有限公司 Goaf filling equipment and method and goaf filling structure
CN113898373A (en) * 2021-10-19 2022-01-07 辽宁工业大学 FRP-PVC membrane shell filled with self-compacting coal gangue concrete fireproof combined coal pillar and reinforcing method
CN114294008A (en) * 2022-01-13 2022-04-08 辽宁工业大学 FRP strip constraint, sprayed concrete and geogrid combined coal pillar reinforcing method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH093745A (en) * 1995-06-19 1997-01-07 Toray Ind Inc Reinforcing fiber sheet and concrete structure
JP2002038655A (en) * 2000-07-31 2002-02-06 Nippon Steel Composite Co Ltd Strip composite frp lattice member, and concrete reinforcing method using strip composite frp lattice member
CN103291305A (en) * 2013-05-22 2013-09-11 贵州开磷(集团)有限责任公司 Quick and low-cost artificial fake roof construction method for ground mine
CN109595016A (en) * 2018-12-27 2019-04-09 中南大学 False top construction method is exploited to admission passage filling under one kind

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH093745A (en) * 1995-06-19 1997-01-07 Toray Ind Inc Reinforcing fiber sheet and concrete structure
JP2002038655A (en) * 2000-07-31 2002-02-06 Nippon Steel Composite Co Ltd Strip composite frp lattice member, and concrete reinforcing method using strip composite frp lattice member
CN103291305A (en) * 2013-05-22 2013-09-11 贵州开磷(集团)有限责任公司 Quick and low-cost artificial fake roof construction method for ground mine
CN109595016A (en) * 2018-12-27 2019-04-09 中南大学 False top construction method is exploited to admission passage filling under one kind

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王厚东: "FRP锚网在煤矿中的应用", 《中国建材报》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112001086A (en) * 2020-08-26 2020-11-27 湖南科技大学 Method for determining components of air leakage crack cementing material based on layering characteristics of regenerated top plate
CN112001086B (en) * 2020-08-26 2024-01-30 湖南科技大学 Method for determining components of leakage air crack cementing material based on regenerated roof layering characteristics
CN113638770A (en) * 2021-08-30 2021-11-12 烟台杰瑞石油装备技术有限公司 Goaf filling equipment and method and goaf filling structure
CN113638770B (en) * 2021-08-30 2023-07-18 烟台杰瑞石油装备技术有限公司 Goaf filling equipment and method and goaf filling structure
CN113898373A (en) * 2021-10-19 2022-01-07 辽宁工业大学 FRP-PVC membrane shell filled with self-compacting coal gangue concrete fireproof combined coal pillar and reinforcing method
CN113898373B (en) * 2021-10-19 2023-10-13 辽宁工业大学 FRP-PVC film shell internally filled with self-compaction gangue concrete fireproof combined coal column and reinforcing method
CN114294008A (en) * 2022-01-13 2022-04-08 辽宁工业大学 FRP strip constraint, sprayed concrete and geogrid combined coal pillar reinforcing method
CN114294008B (en) * 2022-01-13 2024-03-05 辽宁工业大学 FRP strip constraint and sprayed concrete and geogrid combined coal column reinforcement method

Also Published As

Publication number Publication date
CN110118089B (en) 2021-09-07

Similar Documents

Publication Publication Date Title
CN110118089A (en) A kind of mining FRP grid-gangue-self-compacting concrete mat and its construction method
CN102155226B (en) Roadway backfill mining method for coal seams with medium-high thickness
CN106884676A (en) A kind of well work subsidence area administering method of neighbouring opencut
CN110043311A (en) A kind of goaf grouting filling process for being suitble to stay lane
CN105240047A (en) Filling reinforcement method for managing underground mined area of open-pit mine
CN108119144A (en) A kind of different restoring and fastening methods based on the classification of shaft wall fracture degree
CN104763434B (en) A kind of without coal column double lanes driving method
CN207177964U (en) A kind of abandoned mine goaf grouting fills structure
CN106958446B (en) A kind of strata movement of steeply-inclined seam mining and the control method of subsidence
CN102678121A (en) Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN111878117B (en) Construction method of artificial roof facility by downward approach filling method
CN109184694A (en) A kind of pre- anchor sublevel drilling stage open stope afterwards filling mining method of upper disk
CN109826665A (en) A kind of spoil and high-water material mixed filling method
CN107893658A (en) Big thick ore body stage open stope afterwards filling mining methods in pole under strong ground pressure ring border
CN103939137B (en) The drift-sand barnyard placement method of western desertification mining area shallow buried coal seam
CN108035769B (en) A kind of modified filling coal mining method of microorganism
CN108930543A (en) A kind of big cross section gob side entry driving coupling supporting structure and construction method
CN105927243B (en) A kind of underground country rock tomography suspension device and method for protecting support
CN103147792A (en) Drift type coal mining filling method
CN109812269A (en) It is a kind of suitable for second mining working face without pillar mining method
CN104453900A (en) Filling mining method of near-horizontal ore body
CN104762956B (en) Method for forming pile based on construction waste recycled aggregate
CN105971605A (en) A non-waste mining method for underground mines
CN109899070A (en) Gently inclined medium thick orebody based on spheroid Ore drawing structure is without the solid waste method of mining by the way of filling
CN106088107B (en) A kind of tailings impoundment is in the method in Caving Method with Large Space production mine surface subsidence hole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231213

Address after: 834406 No. 396, Dielun South Street, Hestoluogai Town, Hoboksar Mongol Autonomous County, Tacheng Prefecture, Xinjiang Uygur Autonomous Region

Patentee after: Xukuang group Xinjiang Saier Energy Co.,Ltd.

Address before: No. 666, Shengli Road, Urumqi, Xinjiang Uygur Autonomous Region

Patentee before: XINJIANG University