CN105839850B - Precompressed construction method is poured into a mould after basement top-down method shaft - Google Patents

Precompressed construction method is poured into a mould after basement top-down method shaft Download PDF

Info

Publication number
CN105839850B
CN105839850B CN201610175190.XA CN201610175190A CN105839850B CN 105839850 B CN105839850 B CN 105839850B CN 201610175190 A CN201610175190 A CN 201610175190A CN 105839850 B CN105839850 B CN 105839850B
Authority
CN
China
Prior art keywords
concrete
shaft
poured
stigma
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610175190.XA
Other languages
Chinese (zh)
Other versions
CN105839850A (en
Inventor
郎正则
郑胜春
黄万里
傅伟俊
卞安亮
倪捷红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENZHOU CONSTRUCTION GROUP CO Ltd
Original Assignee
WENZHOU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENZHOU CONSTRUCTION GROUP CO Ltd filed Critical WENZHOU CONSTRUCTION GROUP CO Ltd
Priority to CN201610175190.XA priority Critical patent/CN105839850B/en
Publication of CN105839850A publication Critical patent/CN105839850A/en
Application granted granted Critical
Publication of CN105839850B publication Critical patent/CN105839850B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
    • E04G13/028Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor for columns' capital
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/06Solidifying concrete, e.g. by application of vacuum before hardening
    • E04G21/08Internal vibrators, e.g. needle vibrators
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

Precompressed construction method is poured into a mould after basement top-down method shaft, belongs to construction engineering technical field.It first completes one layer of Beam-Slab Construction, then basement negative one layer beam slab of constructing, finally the negative one layer shaft of construction connection negative one layer beam slab and one layer of beam slab, and its construction technology is as follows:Pouring hole indwelling, stigma and shaft treatment of construction joints, shaft formwork erection, Screw arbor with nut at both-ends are tightened precompressed, shaft concreting, form removal and maintenance and reject stigma horn mouth.The construction method of the present invention is greatly facilitated pours the constructing operation smash, enable concrete that basement negative one layer post is directly transported to from one layer of top board, while transport directly start to pour to smash operation, it is time saving and energy saving, avoid concrete first to be hung on negative one layer beam slab with tower crane, substantially increase shaft and pour the speed of application smash, saved the construction period, with very strong popularizing action, it is adaptable to using the secondary engineering for pouring pound column body of basement top-down method.

Description

Precompressed construction method is poured into a mould after basement top-down method shaft
Technical field
The invention belongs to construction engineering technical field, and in particular to a kind of both to have facilitated site operation, and new and old concrete can be improved Precompressed construction method is poured into a mould after the basement top-down method shaft of seam degree of compaction.
Background technology
After solving basement top-down method shaft at present, the conventional construction method of pouring concrete has four kinds, respectively bell mouth pressure Note method, method of repeatedly vibrating, sleeve pipe casting method, filling method, wherein bell mouth drape process are most popular methods, but the method Most significant three have the disadvantage:
1)In traditional bell mouth drape process, funnel hang plate inclination angle is that, between 20 ° to 30 °, inclination angle arranges too small, can go out Existing following two problems:One is to cause bell mouth oral area excessive, and at later stage funnel to be rejected, concrete volume is more;Two when being to pour concrete Effect of closely knit played of the structure counter-force that hang plate is provided to new and old concrete contact surface be not scientific and reasonable;
2)Have the disadvantage that during traditional bell mouth drape process formwork:One is the precompressed measure for not having hang plate to concrete; Two is that the setting of bell mouth size does not have theoretical foundation to there is larger subjective arbitrariness;
3)The concrete of traditional bell mouth drape process pours the method for smashing and there is certain defect, because of the presence of post core position lattice column And the setting of column tie-bar, pour concrete when smashing to newly pouring be difficult to vibrate it is fully closely knit.
The content of the invention
For the above-mentioned problems in the prior art, it is an object of the invention to using pouring after basement top-down method shaft Note precompressed construction had both facilitated site operation, and poured into a mould precompressed after improving the basement top-down method shaft of new and old concrete seam degree of compaction Construction method.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that first complete one layer of beam slab and apply Work, then basement negative one layer beam slab of constructing, finally construction connect the negative one layer shaft of negative one layer beam slab and one layer of beam slab, its construction Technique is as follows:Pouring hole indwelling, stigma and shaft treatment of construction joints, shaft formwork erection, Screw arbor with nut at both-ends are tightened precompressed, shaft and are mixed Solidifying soil is poured, form removal and maintenance and reject stigma horn mouth.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that Specific construction technique is as follows:
1)Pouring hole indwelling:Beam slab and stigma are poured by design requirement, for later stage shaft concreting, stigma and beam When board concrete is poured, on the Square consisting of two isosceles right-angled triangles of frame column position, pre-buried PVC sleeve pipes are used as reserved pouring hole;
2)Stigma and shaft treatment of construction joints:Capital face dabbing, post bottom surface concrete pick the pan bottom shape hole of concave up of chisel, Before casting and compacting of concrete, 30min pours a small amount of clear water into template simultaneously, and template, lattice column and reinforcing bar abundant moistening is poured mixed Before solidifying soil, one layer of stone mortar is first laid at post bottom surface;
3)Shaft formwork erection:In step 1)Funnel pressure injection entrance is installed in the stigma bottom poured, funnel pressure injection entrance by Two funnel hang plates are separately fixed at and pour the template top of shaft concrete and obtain, and it is past that funnel pressure injection entry bottom is located at stigma bottom surface At lower 300mm, funnel pressure injection access opening top is located at stigma bottom surface up 200mm;
4)Screw arbor with nut at both-ends tightens precompressed:In step 3)Screw arbor with nut at both-ends is set on the funnel hang plate of installation, is tightened to drawing spiral shell Bar, using Screw arbor with nut at both-ends precompressed before concrete initial set, makes concrete push up power upwards, makes after-pouring concrete effective with top stigma seam crossing It is closely knit;
5)Shaft casting and compacting of concrete:, in 170-200mm, concrete segmentation is poured, is mixed to pour concrete slump control when smashing The primary height that pours of solidifying soil is less than 600mm, and under being carried out after each concrete vibrating poured in height is closely knit again One-time-concreting, concreting to from stigma lower surface 280-320mm when stop pouring, 1 h of interval, so that concrete itself is heavy Drop, is further continued for pouring remaining position concrete before concrete initial set;As bell mouth top is higher by 200mm than stigma bottom surface, profit With concrete gravity and the principle of internal and external pressure balance, by new-old concrete junction vibration compacting, the generation of handing-over seam is reduced;
6)Form removal and maintenance:After concreting is finished, mould is removed again when concrete strength reaches every square millimeter of 1N Plate, and ensure that form removal process center pillar corner angle are injury-free, using plastic sheeting parcel maintenance after form removable, seam crossing adopts glue Band sealing;
7)Reject stigma horn mouth:After concrete strength reaches 75%, artificial rejecting stigma bell mouth any excess concrete, and It is tentatively smooth with post surface, then concrete surface fine chipping is carried out by artificial stone with textures cut with an axe technique with axe, finally by four, pillar External corner angle grinder wears into the external corner of Founder, and construction is completed.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that step 1)Middle PVC sleeve pipes are straight Footpath size is 140-160mm, preferably 150mm.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that step 2)Middle stone mortar paving If thickness is 50-100mm.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that step 3)Described in funnel pressure Inlet is inclined to be fixed on by funnel hang plate in 45 ° and pours the template top of shaft concrete and obtain, and funnel pressure injection entrance pours height For 500mm, width is 500mm, and length is the post length of side in bell mouth place face.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that step 4)Described in draw spiral shell Bar two ends are set with funnel hang plate junction and use cleat, are padded by cleat.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that step 5)Middle puddling method For:Inserted soon using immersion vibrator and pulled out slowly, insert that point is evenly distributed, pointwise movement is carried out in order, movement is asked away from for 300- 400mm;Vibrate last layer when should insert lower-layer concrete face 50mm, to eliminate the seam of two interlayers.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that every vibrating time of concrete For 30-45s, shaken after per interval 10-20min again.
Precompressed construction method is poured into a mould after described basement top-down method shaft, it is characterised in that step 5)In pour coagulation when smashing The native slump is 180mm.
By using above-mentioned technology, compared with prior art, beneficial effects of the present invention are as follows:
1)Job site concrete is marched into the arena slump control between 170mm to 200mm by the present invention, and preferably 180mm is prevented Concrete slump is excessive, segregation phenomenon occurs and affects concrete strength, while it also avoid that concrete slump is too small is difficult to vibration compacting, Honeycomb or hole phenomenon are easily caused, the present invention also extends every vibrating time of concrete, and both collective effects improve which and mix Solidifying soil vibration compacting;
2)Casting concrete front pillar formwork erection of the present invention is simultaneously reinforced, and detailed inspection is done in the setting to tie, Screw arbor with nut at both-ends, And in Screw arbor with nut at both-ends and hang plate junction, cleat is set, it is limited prevent casting process in spillage, swollen mould, quick-fried mould etc. occur existing As improving construction quality;
3)The present invention is the secondary form erection plan for pouring the design of pound column body of basement top-down method, has very strong reality concurrently operable Property and scientific basis, in combination with the scheme of smashing of pouring for summarizing out from practical construction experience, both complementary result energy After Reliable guarantee form removal, shaft hands over seam crossing to pour dense and avoid the occurrence of shaft casting pounding quality common fault with stigma, with very strong Popularizing action, it is adaptable to using the secondary engineering for pouring pound column body of basement top-down method;
2)As basement top-down method is first to complete one layer of beam slab, basement negative one layer beam slab of constructing afterwards, negative one layer shaft Finally construct, thus pour concrete when smashing negative one layer shaft how to transport from one layer of beam slab negative one layer close pour pound column body Construction Difficulties, the present invention pour the way for smashing hole to be provided by arranging one layer of beam slab upper prop corner, greatly facilitate and pour applying of smashing Work is operated so that concrete directly can be transported to basement negative one layer post from one layer of top board, directly start while transport Pour and smash operation, it is time saving and energy saving, it is to avoid concrete is first hung on negative one layer beam slab with tower crane, then by hand haulage to post side, most The awkward situation smash is poured by adjustable shelf relay afterwards, shaft is substantially increased and is poured the speed of application smash, saved the construction period.
Description of the drawings
Fig. 1 is the constructing structure schematic diagram of the present invention;
Fig. 2 is the construction flow chart of the present invention.
In figure:1- funnel hang plates, 2- cleats, 3- Screw arbor with nut at both-ends, 4- templates, pouring concrete after 5-, 6- stigmas bottom surface, 7- funnel pressure injection entrances, 8- stigmas, 9- pouring out concrete buckets.
Specific embodiment
The description entered is made to the present invention below in conjunction with Figure of description, but protection scope of the present invention is not limited in This:
Fig. 1 is the constructing structure schematic diagram of the present invention, as shown in figure 1, the bottom surface of stigma 8 referred to as stigma bottom surface 6, and newly Old concrete seam crossing, funnel pressure injection entrance 7 are arranged on shaft, and funnel pressure injection entrance 7 is inclined and mounted on post by funnel hang plate 1 4 top of template of body, angle of inclination are that 45 °, i.e. funnel pressure injection entrance 7 are equilateral triangle structure, and 7 bottom of funnel pressure injection entrance At stigma bottom surface 6 down 300mm, at the top of funnel pressure injection entrance 7 at stigma bottom surface 6 up 200mm, the funnel pressure injection Entrance 7 pours height for 500mm, and width is 500mm, and length is the post length of side in bell mouth place face;Funnel hang plate 1 includes two It is individual, it is symmetricly set at the top of two side templates 4, and two funnel hang plates 1 is connected by Screw arbor with nut at both-ends 3, in order that after-pouring coagulation Soil 5 is effectively closely knit with 6 seam crossing of stigma bottom surface of top stigma 8, and the present invention is in Screw arbor with nut at both-ends 3 and 1 junction of funnel hang plate Cleat 2 is set, is padded by cleat 2, then when tightening Screw arbor with nut at both-ends 3, using Screw arbor with nut at both-ends precompressed before concrete initial set, make concrete Power is pushed up upwards, and the purpose closely knit so as to reach seam, the concrete of funnel pressure injection entrance 7 are fed by pouring out concrete bucket 9.
As shown in Fig. 2 precompressed construction method is poured into a mould after the basement top-down method shaft of the present invention, it is first to complete one layer of beam Plate, basement negative one layer beam slab of constructing afterwards, negative one layer shaft finally construct, and shaft construction is using pouring after basement top-down method shaft Note preloading method, its concrete construction method are as follows:
1)Pouring hole indwelling
Stigma 8 and beam slab are poured into a mould by design requirement, the rear pouring concrete 5 for ease of later stage shaft is poured, stigma 8 and beam When board concrete is poured, on the Square consisting of two isosceles right-angled triangles of frame column position, pre-buried PVC sleeve pipes are used as reserved pouring hole, the diameter chi of PVC sleeve pipes It is very little for 140-160mm, preferably 150mm;
2)Stigma 8 and shaft treatment of construction joints
The top surface for first pouring the stigma 8 being poured in carries out dabbing according to a conventional method, and post bottom surface concrete picks the pot of concave up of chisel Laitance is driven out of when pouring so as to the rear pouring concrete 5 of shaft by bottom shape hole;Lattice column, reinforcing bar and template 4 are built, while mixed Solidifying soil is poured to be smash front 30min and pours a small amount of clear water into template 4, by template 4, lattice column and the abundant moistening of reinforcing bar, in stigma bottom surface 6 (That is post bottom New-old concrete joint surface)One layer of stone mortar is laid first, laying depth is controlled in 50mm -100mm, to eliminate " rotten " phenomenon;
3)Shaft formwork erection
Column template is installed should be installed and be reinforced by arrangement and method for construction requirement, and the setting to tie, Screw arbor with nut at both-ends is done in detail Check, the phenomenons such as spillage, swollen mould, quick-fried mould in preventing casting process, occur, 8 bottom of the stigma installation funnel pressure injection for formerly pouring concrete enters Mouth 7, funnel pressure injection entrance 7 are that 45 ° of funnel hang plates 1 are constituted installed in the top of template 4 by inclination angle, 7 bottom of funnel pressure injection entrance Portion is higher by stigma bottom surface 6 at the top of funnel pressure injection entrance 7 at stigma bottom surface 6 down 300mm, and the height being higher by is 200mm, therefore Bell mouth pours height for 500mm, and width is 500mm, and length is the post length of side in bell mouth place face;
The present invention is conducive to pouring the carrying out for smashing operation by arranging the post length of side of the bell mouth length for bell mouth place face, Way is to take the bell mouth length in post opposite sides indwelling isometric with the cylinder length of side which is located, and is set up in another both sides Auxiliary funnel mouth, its length are 500mm, pour when smashing big bell mouth mainly to pour and smash position, and little bell mouth is vibrated position for auxiliary.
4)Screw arbor with nut at both-ends tightens precompressed
Screw arbor with nut at both-ends 3 is set on funnel hang plate 1, and in Screw arbor with nut at both-ends 3 and 1 junction cleat of funnel hang plate 2 pad, and tighten Screw arbor with nut at both-ends 3, using the precompressed before concrete initial set of Screw arbor with nut at both-ends 3, make concrete push up power upwards, make rear pouring concrete 5 and Top stigma bottom surface 6 is effectively closely knit;
5)Shaft casting and compacting of concrete
Due to concrete slump it is excessive, it may appear that segregation phenomenon, concrete strength can be affected, and concrete slump is too small, then be difficult to shake Puddling reality, easily causes honeycomb or hole phenomenon, the present invention at the construction field (site) will control concrete march into the arena the slump in 170mm extremely 200mm, pours the preferred 180mm of concrete slump when smashing, and the primary height that pours of concrete is less than 600mm, and at each Pour the concrete vibrating in height it is closely knit after can be poured next time, concreting to from stigma lower surface about Stop pouring during 300mm, 1 h of interval, so that concrete settlement, is further continued for pouring remaining position coagulation before concrete initial set Soil, as 7 top of funnel pressure injection entrance is higher by 200mm than stigma 8, using concrete gravity and the principle of internal and external pressure balance, By new-old concrete junction vibration compacting, the generation of handing-over seam, volume of concrete summation on two funnel pressure injection entrances 7 are reduced More than the shaft volume of concrete between 7 bottom surface of stigma bottom surface 6 and funnel pressure injection entrance;
The present invention is smash when shaking, and smashes and shake between two lattice columns, while on the outside of template 4 aiding in smashing shaking, concrete is per point Vibrating time control is shaken after 30 to 45s, 10 to 20min again;Final step concreting, concrete is from bell mouth Adjacent both sides blanking, and vibrate in the same side, when vibrating, vibrating spear need to insert 50mm in casting concrete in advance.Pour to stigma Behind bottom surface, top laitance is cleared up, then casting concrete exceed New-old concrete joint surface at least 100mm again, observation is separately Both sides, after concrete flowing comes, in the concrete of both sides teeming below.
The present invention is affected due to lattice column occupy-place, causes indirectly reinforcing bar to configure overstocked situation, therefore vibrating head when vibrating Diameter is excessive to be unfavorable for concrete vibration compacting, there is portion 50mm vibrating heads and is difficult to insertion and vibrate, therefore project management department should match somebody with somebody simultaneously Standby 30mm minor diameter vibrating heads, smash operation for coordinating to pour, it is ensured that concrete pours the density smash.Pour when smashing, the slightly larger place in space is used The insertion of 50mm vibrating heads is vibrated, and 30mm vibrations are then used at the position of vibrating that cannot insert 50mm shock clubs intensive for reinforcing bar instead Rod, two kinds of specification vibrating heads are used in combination, it is ensured that what each was told somebody what one's real intentions are vibrate, and position fully can be vibrated, and obtain quality of vibrating Ensure;
6 )Form removal and maintenance
Concreting finish after when concrete strength reaches every square millimeter of 1N form removal again, and ensure form removal Cheng Zhongzhu corner angle are injury-free, and template 4 adopts rubber belt sealing using plastic sheeting parcel maintenance, seam crossing after removing;
Reject stigma horn mouth
After concrete strength reaches 75%, any excess concrete at 8 outside funnel pressure injection entrance 7 of stigma is rejected, to avoid the old and new There is crack in concrete joint surface, forbids using machineries such as pneumatic picks when picking chisel, all using manually picking chisel and preliminary with post surface It is smooth, then concrete surface fine chipping is carried out by artificial stone with textures cut with an axe technique with axe, finally by four external corner angle grinders of pillar Wear into the external corner of Founder.
Embodiment 1:
Wenzhou build Business Building engineering basement post it is secondary pour smash employ this engineering method construction.Engineering is located at Wenzhou City Lucheng District, 57208.1 ㎡ of overall floorage, wherein 35315.3 ㎡, 21892.8 ㎡ of underground on the ground.The long 81m in foundation ditch north-south, east West is to wide 98m, foundation ditch girth 358m, 7938 ㎡ of excavation area, cutting depth about 12.7-13.6 rice, three layers of basement, using this After engineering method operation, both reduced and poured the generation for smashing rear pillar crack and voids and pits, significantly improved new and old concrete seam crossing quality again, Once survive, reduce the trouble of later stage repairing, be the basis that project has established wound high grade project.
Embodiment 2:
Wenzhou Medical University's eye employs the construction of this engineering method depending on Guang Yijiao buildings reconstruction and extension project.Engineering is located at Wenzhou City Lucheng City Area, 49181.3 ㎡ of overall floorage.Superstructure is 22 layers of main building and 5 layers of annex.Basement be two layers, be integrally under Room.This engineering belongs to frame-shear structure, raft foundation, and basement has post core lattice column and needs the secondary pillar smash that pours to have 94 Root.Through the data acquisition to after-pouring post quality problems, once pour and smash qualification rate and be obviously improved, including voids and pits, crack, Swollen mould, rotten, the quality problems such as hole all significantly reduce, improve post casting pounding quality.

Claims (9)

1. precompressed construction method is poured into a mould after basement top-down method shaft, one layer of Beam-Slab Construction, then basement negative one of constructing first is completed Layer beam slab, finally construction connect the negative one layer shaft of negative one layer beam slab and one layer of beam slab, and its construction technology is as follows:Pouring hole is stayed Put, stigma and shaft treatment of construction joints, shaft formwork erection, Screw arbor with nut at both-ends are tightened precompressed, shaft concreting, form removal and supported Shield and rejecting stigma horn mouth, it is characterised in that Specific construction technique is as follows:
1)Pouring hole indwelling:Beam slab and stigma are poured by design requirement, in order to later stage shaft concreting, stigma and beam slab are mixed When solidifying soil is poured, on the Square consisting of two isosceles right-angled triangles of frame column position, pre-buried PVC sleeve pipes are used as reserved pouring hole;
2)Stigma and shaft treatment of construction joints:Capital face dabbing, post bottom surface concrete pick the pan bottom shape hole of concave up of chisel, while Before casting and compacting of concrete, 30min pours a small amount of clear water into template, by template, lattice column and reinforcing bar abundant moistening, casting concrete Before, one layer of stone mortar is first laid at post bottom surface;
3)Shaft formwork erection:In step 1)Funnel pressure injection entrance is installed in the stigma bottom poured, and funnel pressure injection entrance is by two Funnel hang plate is separately fixed at and pours the template top of shaft concrete and obtain, and funnel pressure injection entry bottom is located at stigma bottom surface down At 300mm, funnel pressure injection access opening top is located at stigma bottom surface up 200mm;
4)Screw arbor with nut at both-ends tightens precompressed:In step 3)Screw arbor with nut at both-ends is set on the funnel hang plate of installation, Screw arbor with nut at both-ends is tightened, profit With Screw arbor with nut at both-ends precompressed before concrete initial set, make concrete push up power upwards, make after-pouring concrete effectively closely knit with top stigma seam crossing;
5)Shaft casting and compacting of concrete:, in 170-200mm, concrete segmentation is poured, concrete to pour concrete slump control when smashing The primary height that pours is less than 600mm, and carries out again once after each concrete vibrating poured in height is closely knit Pour, concreting to from stigma lower surface 280-320mm when stop pouring, 1 h of interval so that concrete settlement, It is further continued for pouring remaining position concrete before concrete initial set;As bell mouth top is higher by 200mm than stigma bottom surface, using mixed Solidifying soil deadweight and the principle of internal and external pressure balance, by new-old concrete junction vibration compacting, reduce the generation of handing-over seam;
6)Form removal and maintenance:After concreting is finished, the form removal again when concrete strength reaches every square millimeter of 1N, and Ensure that form removal process center pillar corner angle are injury-free, using plastic sheeting parcel maintenance after form removable, seam crossing is close using adhesive tape Envelope;
7)Reject stigma horn mouth:It is after concrete strength reaches 75%, artificial to reject stigma bell mouth any excess concrete, and and post Surface is tentatively smooth, then carries out concrete surface fine chipping by artificial stone with textures cut with an axe technique with axe, finally by four external corners of pillar The external corner of Founder is worn into angle grinder, construction is completed.
2. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 1, it is characterised in that step 1) Middle PVC casing diameters size is 140-160mm.
3. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 1, it is characterised in that step 1) Middle PVC casing diameters size is 150mm.
4. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 1, it is characterised in that step 2) Middle stone mortar laying depth is 50-100mm.
5. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 1, it is characterised in that step 3) Described in funnel pressure injection entrance inclined to be fixed on by funnel hang plate in 45 ° and pour the template top of shaft concrete and obtain, funnel pressure injection Entrance pours height for 500mm, and width is 500mm, and length is the post length of side in bell mouth place face.
6. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 1, it is characterised in that step 4) Described in Screw arbor with nut at both-ends two ends and funnel hang plate junction be provided with cleat, padded by cleat.
7. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 1, it is characterised in that step 5) Middle puddling method is:Slowly pulled out using fast the inserting of immersion vibrator, insert evenly distributed, a pointwise movement, carry out in order, between movement Away from for 300-400mm;Vibrate last layer when should insert lower-layer concrete face 50mm, to eliminate the seam of two interlayers.
8. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 7, it is characterised in that concrete Every vibrating time is 30-45s, is shaken after per interval 10-20min again.
9. precompressed construction method is poured into a mould after basement top-down method shaft according to claim 1, it is characterised in that step 5) In to pour when smashing concrete slump be 180mm.
CN201610175190.XA 2016-03-25 2016-03-25 Precompressed construction method is poured into a mould after basement top-down method shaft Active CN105839850B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610175190.XA CN105839850B (en) 2016-03-25 2016-03-25 Precompressed construction method is poured into a mould after basement top-down method shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610175190.XA CN105839850B (en) 2016-03-25 2016-03-25 Precompressed construction method is poured into a mould after basement top-down method shaft

Publications (2)

Publication Number Publication Date
CN105839850A CN105839850A (en) 2016-08-10
CN105839850B true CN105839850B (en) 2017-03-29

Family

ID=56583274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610175190.XA Active CN105839850B (en) 2016-03-25 2016-03-25 Precompressed construction method is poured into a mould after basement top-down method shaft

Country Status (1)

Country Link
CN (1) CN105839850B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193706A (en) * 2017-12-20 2018-06-22 中煤建工集团有限公司 A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106245680A (en) * 2016-08-26 2016-12-21 中天建设集团有限公司 Construction method is watered after contrary sequence method shaft precompressed
CN106567543A (en) * 2016-10-26 2017-04-19 上海中锦建设集团股份有限公司 Slab-bottom structural concrete column reserved hole construction method
CN106836564B (en) * 2017-01-03 2020-04-14 深圳大学 Formwork supporting method for partition bearing wall in underground station
CN108277818A (en) * 2018-03-22 2018-07-13 中国电建市政建设集团有限公司 Basement top-down method Combined tower crane foundation structure and construction method
CN108612260A (en) * 2018-07-05 2018-10-02 江苏省苏中建设集团股份有限公司 A kind of constructional column top concrete pours once-molding construction process and its device
CN110130646A (en) * 2019-05-21 2019-08-16 杭州悦为科技有限公司 The Constructional Col-umn Construction method of device is poured based on tool-type intelligence compressional structure column
CN111733820A (en) * 2020-06-22 2020-10-02 上海建工四建集团有限公司 Reverse construction method waterproof grouting hole device and construction method
CN111719559A (en) * 2020-07-16 2020-09-29 湖南建工集团有限公司 Concrete conveying construction method for deep foundation pit by vertical synchronous full-reverse construction method
CN113090064A (en) * 2021-04-15 2021-07-09 中国建筑第二工程局有限公司 Roof panel column head and newly-built structural column folding construction system and construction method thereof
CN113756601B (en) * 2021-09-27 2023-07-14 山西五建集团有限公司 Frame column replacement reinforcement construction method
CN114197526B (en) * 2021-12-28 2023-03-21 中铁建工集团有限公司 Formwork system with vertical structure by reverse construction method and construction method
CN115387635B (en) * 2022-09-29 2023-07-25 中建八局第一建设有限公司 System for preventing concrete girderless floor basement from overload collapse

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU5586080A (en) * 1980-02-25 1981-09-03 Moore, C.D. Reconditioning structural piling
JPH06317016A (en) * 1991-03-15 1994-11-15 Okabe Co Ltd Formwork device for pillar
US5586080A (en) * 1995-06-26 1996-12-17 Micron Technology, Inc. Local word line phase driver
AU2006201409A1 (en) * 2005-04-12 2007-10-18 William George Ross Stump Former
CN2898153Y (en) * 2006-04-18 2007-05-09 上海市第二建筑有限公司 Concrete pouring tamping pole cap node by reversed construction
CN101139867B (en) * 2006-09-08 2010-09-08 上海市第七建筑有限公司 Pressure-grouting construction method for structure consolidation
CN101492918B (en) * 2008-01-24 2012-02-01 华东建筑设计研究院有限公司 Beam column node for base pit engineering of topdown construction method
CN203654760U (en) * 2013-12-30 2014-06-18 上海建工二建集团有限公司 Device for treating seam between vertical structure and horizontal structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193706A (en) * 2017-12-20 2018-06-22 中煤建工集团有限公司 A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure

Also Published As

Publication number Publication date
CN105839850A (en) 2016-08-10

Similar Documents

Publication Publication Date Title
CN105839850B (en) Precompressed construction method is poured into a mould after basement top-down method shaft
CN204401432U (en) A kind of measures of cracks on concrete pavement repairs structure
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
CN102003069B (en) Construction method and pouring device for framework masonry infill wall structure
CN107574762A (en) A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities
CN108385512A (en) One kind being based on bolted modular assembly formula Hollow High Pier splicing structure and its practice
CN109853832A (en) A kind of construction method of filling wall masonry and electrical pre-embedded pipe synchronous construction
CN105350777A (en) Device and method for one-time pouring molding of ultra-high concrete column
CN208167956U (en) A kind of basement inwall using reverse construction
CN105780976B (en) Compound concrete shear wall structure and its concreting method
CN103469806A (en) Construction method for replacing brick forming die with prefabricated concrete foundation bearing platform side die
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN102505709A (en) Concrete-formwork-precast foundation construction method
CN107859352A (en) Consolidation process construction at skyscraper different strength concrete bean column node
CN106522248A (en) Method for reinforcing soil slope and slope reinforcing device
CN104556766A (en) Construction method for building foundation bed employing recycled concrete
CN108005255A (en) A kind of construction method of wall
CN107524471A (en) A kind of tunnel end plugging construction method
CN107989049A (en) A kind of construction method of frame bank protection
CN110145124A (en) A kind of control shear wall level connects the reinforcement tools and its construction method of batch quality
CN108442724B (en) Earthen site crack repairing method
CN104594633B (en) The construction method and its formwork structure of umbrella shape space curved surface clear-water concrete
CN206233560U (en) Wall formwork erecting structure
CN110004787A (en) Pier storage yard road concrete surface construction method
CN206245730U (en) A kind of cast-in-place pitched roof double template structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant