CN207553575U - A kind of scaffold easy to assemble - Google Patents
A kind of scaffold easy to assemble Download PDFInfo
- Publication number
- CN207553575U CN207553575U CN201721349899.3U CN201721349899U CN207553575U CN 207553575 U CN207553575 U CN 207553575U CN 201721349899 U CN201721349899 U CN 201721349899U CN 207553575 U CN207553575 U CN 207553575U
- Authority
- CN
- China
- Prior art keywords
- shank
- grafting
- steel tube
- connecting rod
- scaffold
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of scaffolds easy to assemble, including the first shank and the second shank, there are two first shank is set altogether, there are two second shank is set altogether, first shank and the second shank lower end are socketed with grafting pedestal, the grafting pedestal upper end is equipped with grafting spacing ring, the grafting spacing ring side end face is equipped with connecting rod, steel tube fastener there are two being respectively mounted on first shank and the second shank, it is connected between first shank by running through the stock of steel tube fastener, it is connected between first shank and the second shank by running through the quarter butt of steel tube fastener, it is connected between the quarter butt by hanger plate.The utility model can be mounted and dismounted easily, by the way that stock and quarter butt are fixed on inside steel tube fastener, equipment is assembled, and can be facilitated by the grafting pedestal of shank end and equipment is fixed, the installation of equipment is made more to stablize, is safer.
Description
Technical field
The utility model is related to construction equipment technical field, specially a kind of scaffold easy to assemble.
Background technology
Scaffold is to ensure each work progress is smoothed out and is set up workbench, and different types of engineering is applied
Work selects the scaffold of different purposes, and bridge support frame is in the majority using bowl buckle scaffold, also has using door-type scaffold, main
Body structure construction floor scaffolding is in the majority using fastener scaffold, it should be noted that the smooth heavily fortified point of ground in steel tube fastener scaffold building
It is real, pedestal and backing plate are set, and have reliable drainage measure, prevent ponding from impregnating ground, but present scaffold is being installed
When with dismounting, a large amount of time is usually wasted, the handling for making equipment are inconvenient, so, it is now desired to it is a kind of easy-to-dismount
Scaffold, with the efficiency of lifting construction.
Utility model content
The purpose of this utility model is to provide a kind of scaffolds easy to assemble, and having easily to be dismounted, and side
Just the advantages of scaffold main body being fixed, solve existing equipment handling when it is not very convenient, and load and unload after
The problem of unstable.
To achieve the above object, the utility model provides following technical solution:A kind of scaffold easy to assemble is inserted including first
Extension bar and the second shank, there are two first shank is set altogether, there are two second shank is set altogether, described first inserts
Extension bar and the second shank lower end are socketed with grafting pedestal, and the grafting pedestal upper end is equipped with grafting spacing ring, described to insert
It connects spacing ring side end face and connecting rod is installed, be respectively mounted on first shank and the second shank there are two steel tube fastener,
It is connected by running through the stock of steel tube fastener between first shank, led between first shank and the second shank
The quarter butt crossed through steel tube fastener connects, and is connected between the quarter butt by hanger plate.
Preferably, the grafting spacing ring top is equipped with rubber panel.
Preferably, there are four the connecting rod is set altogether, and four connecting rods are circumferentially distributed with the axis of grafting spacing ring.
Preferably, the connecting rod side end face is connected by mounting rod, and connecting rod middle position offers inserting groove.
Preferably, the connecting rod end is equipped with connecting pole, and the connecting pole end is equipped with grafting iron fibre.
Preferably, the hanger plate both ends are mounted on symmetrical hook, and it is in pair to link up with the axis of hanger plate
Claim distribution.
Compared with prior art, the beneficial effects of the utility model are as follows:
1st, the utility model is by setting grafting pedestal, has achieved the effect that facilitate equipment is fixed, by that will insert
Connect pedestal place on the ground, beat rubber panel by using blunts such as hammers, grafting pedestal be inserted into ground, pass through by
Grafting iron fibre and inserting column are inserted into soil, and the scaffold of entire upper end is facilitated to be fixed, then by the first shank and second
Shank passes through grafting spacing ring, is inserted into inserting groove, then the scaffold main body of upper end is installed, can enable a device to
When handling, a large amount of time is saved, and can more stablize, make more safe when construction and stablized.
2nd, the utility model is by setting steel tube fastener, has reached to facilitate and equipment is fixed, and can be as needed
The effect of the adjustment of pole length is carried out, first by the way that the first shank and the second shank are passed through inside grafting spacing ring, is inserted
Inserting groove upper end is connected to, is fixed, then steel tube fastener is snapped into the first shank and the second shank upper end, further according to need
The length of quarter butt and stock is adjusted, finally, hanger plate is hung on quarter butt, you can construct, is buckled by steel pipe
Part can easily carry out the length of control quarter butt and stock, facilitate the different size of construction area of selection, can it is various not
Same construction site is used, and the adaptability for making equipment is stronger.
3rd, the utility model has achieved the effect that the platform of construction can be built, has passed through first by setting hanger plate
The length of different quarter butts and stock is adjusted, reselection uses hanger plate how long, and hanger plate is connected to quarter butt by linking up with
Upper end, you can hanger plate is installed, by selecting different hanger plates, different size of platform can be built, it can
The adaptability for making equipment is stronger, can be used in different construction sites.
Description of the drawings
Fig. 1 is the main structure diagram of the utility model;
Fig. 2 is the overlooking the structure diagram of the utility model;
Fig. 3 is the grafting pedestal main structure diagram of the utility model.
In figure:1- grafting pedestals;2- connection-pegs;3- steel tube fasteners;4- quarter butts;5- stocks;6- hanger plates;The first grafting of 7-
Bar;The second shanks of 8-;9- is linked up with;10- inserting columns;11- mounting rods;12- connecting rods;13- rubber panels;14- grafting limits
Ring;15- inserting grooves;16- grafting iron is fine.
Specific embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out
It clearly and completely describes, it is clear that the described embodiments are only a part of the embodiments of the utility model rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work
All other embodiments obtained shall fall within the protection scope of the present invention.
It please refers to Fig.1 to 3, a kind of embodiment provided by the utility model:A kind of scaffold easy to assemble, including the first grafting
7 and second shank 8 of bar, there are two the first shank 7 is set altogether, there are two the second shank 8 is set altogether, the first shank 7 and
Two shanks, 8 lower end is socketed with grafting pedestal 1, by the way that grafting pedestal 1 is placed on the ground, by using blunts such as hammers
Rubber panel 13 is beaten, grafting pedestal 1 is inserted into ground, by the way that grafting iron fibre 16 and inserting column 10 are inserted into soil, side
Just the scaffold of entire upper end is fixed, then the first shank 7 and the second shank 8 are passed through grafting spacing ring 14, is inserted into
In inserting groove 15, then the scaffold main body of upper end installed, 1 upper end of grafting pedestal is equipped with grafting spacing ring 14, grafting
14 top of spacing ring is equipped with rubber panel 13, and 14 side end face of grafting spacing ring is equipped with connecting rod 12, and connecting rod 12 is equipped with altogether
Four, and four connecting rods 12 are circumferentially distributed with the axis of grafting spacing ring 14,12 side end face of connecting rod passes through mounting rod 11
Connection, and 11 middle position of connecting rod offers inserting groove 15,12 end of connecting rod is equipped with connecting pole 10,10 end of connecting pole
End is equipped with grafting iron fibre 16, is respectively mounted on the first shank 7 and the second shank 8 there are two steel tube fastener 3, pass through first by
First shank 7 and the second shank 8 are passed through inside grafting spacing ring 14, are plugged into 15 upper end of inserting groove, are fixed, then will
Steel tube fastener 3 snaps into 8 upper end of the first shank 7 and the second shank, further according to needing to be adjusted quarter butt 4 and stock 5
Finally, hanger plate 6 is hung on quarter butt 4 for length, you can construct, by running through steel tube fastener between the first shank 7
3 stock 5 connects, and is connected between the first shank 7 and the second shank 8 by running through the quarter butt 4 of steel tube fastener 3, quarter butt 4 it
Between connected by hanger plate 6,6 both ends of hanger plate are mounted on symmetrical hook 9, and link up with 9 and be in the axis of hanger plate 6
Symmetrical, the length first by adjusting different quarter butt 4 and stock 5, reselection uses hanger plate how long 6, passes through extension
Hanger plate 6 is connected to 4 upper end of quarter butt by hook 9, you can installs hanger plate 6.
Operation principle:In utility model works, user first by grafting pedestal 1 place on the ground, by using
The blunts such as hammer beat rubber panel 13, and grafting pedestal 1 is inserted into ground, by the way that grafting iron fibre 16 and inserting column 10 are inserted into
In soil, the scaffold of entire upper end is facilitated to be fixed, then the first shank 7 and the second shank 8 are limited across grafting
Ring 14 is inserted into inserting groove 15, then the scaffold main body of upper end is installed, then steel tube fastener 3 is snapped into the first grafting
7 and second shank of bar, 8 upper end, further according to needing the length for being adjusted quarter butt 4 and stock 5, finally, hanger plate 6 is hung over
On quarter butt 4, the length first by adjusting different quarter butt 4 and stock 5, reselection uses hanger plate how long 6, passes through hook
Hanger plate 6 is connected to 4 upper end of quarter butt by 9, you can and hanger plate 6 is installed, is then constructed, so far, whole equipment
Workflow is completed.
It is obvious to a person skilled in the art that the utility model is not limited to the details of above-mentioned exemplary embodiment, and
And in the case of the spirit or essential attributes without departing substantially from the utility model, it can realize that this practicality is new in other specific forms
Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this practicality is new
The range of type is indicated by the appended claims rather than the foregoing description, it is intended that by containing in the equivalent requirements of the claims is fallen
All changes in justice and range are embraced therein.Any reference numeral in claim should not be considered as limitation
Involved claim.
Claims (6)
1. a kind of scaffold easy to assemble, including the first shank(7)With the second shank(8), it is characterised in that:Described first inserts
Extension bar(7)There are two setting altogether, second shank(8)There are two setting altogether, first shank(7)With the second shank
(8)Lower end is socketed with grafting pedestal(1), the grafting pedestal(1)Upper end is equipped with grafting spacing ring(14), the grafting limit
Position ring(14)Side end face is equipped with connecting rod(12), first shank(7)With the second shank(8)On be respectively mounted there are two
Steel tube fastener(3), first shank(7)Between by running through steel tube fastener(3)Stock(5)Connection, described first inserts
Extension bar(7)With the second shank(8)Between by running through steel tube fastener(3)Quarter butt(4)Connection, the quarter butt(4)Between lead to
Cross hanger plate(6)Connection.
2. a kind of scaffold easy to assemble according to claim 1, it is characterised in that:The grafting spacing ring(14)Pacify on top
Equipped with rubber panel(13).
3. a kind of scaffold easy to assemble according to claim 1, it is characterised in that:The connecting rod(12)It is equipped with four altogether
It is a, and four connecting rods(12)With grafting spacing ring(14)Axis be circumferentially distributed.
4. a kind of scaffold easy to assemble according to claim 1, it is characterised in that:The connecting rod(12)Side end face passes through
Mounting rod(11)Connection, and connecting rod(11)Middle position offers inserting groove(15).
5. a kind of scaffold easy to assemble according to claim 1, it is characterised in that:The connecting rod(12)End is equipped with
Connecting pole(10), the connecting pole(10)End is equipped with grafting iron fibre(16).
6. a kind of scaffold easy to assemble according to claim 1, it is characterised in that:The hanger plate(6)Both ends are respectively mounted
There is symmetrical hook(9), and link up with(9)With hanger plate(6)Axis be symmetric.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721349899.3U CN207553575U (en) | 2017-10-17 | 2017-10-17 | A kind of scaffold easy to assemble |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721349899.3U CN207553575U (en) | 2017-10-17 | 2017-10-17 | A kind of scaffold easy to assemble |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207553575U true CN207553575U (en) | 2018-06-29 |
Family
ID=62674363
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721349899.3U Expired - Fee Related CN207553575U (en) | 2017-10-17 | 2017-10-17 | A kind of scaffold easy to assemble |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207553575U (en) |
-
2017
- 2017-10-17 CN CN201721349899.3U patent/CN207553575U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103104092B (en) | Support composite structure of beam and slab | |
CN104389419B (en) | Encorbelment and prop up mould structure for mounting platform and a constructional method | |
CN206053274U (en) | The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose | |
CN211899558U (en) | Handling frame encorbelments | |
CN206320918U (en) | Air conditioner support for multi-storey building | |
CN208168317U (en) | A kind of lower extension platform of high-altitude construction | |
CN204282803U (en) | To encorbelment formwork structure for mounting platform | |
CN207553575U (en) | A kind of scaffold easy to assemble | |
CN206554500U (en) | Steel structure concrete, which is poured, uses adjustable transverse support bar | |
CN219528334U (en) | Scaffold for building construction | |
CN208586899U (en) | A kind of support frame with oblique jacking | |
CN208347296U (en) | A kind of belt lacing rod piece | |
CN105152039A (en) | Slope building tower crane ultralong attachment device and slope building inverted sequence construction method | |
CN214462346U (en) | Assembled scaffold for housing construction engineering | |
CN206467990U (en) | Adjustable truss independence support system | |
CN105133770B (en) | The roof structure of underpass entrance | |
CN205829097U (en) | A kind of temporary cable hanging hook assembly | |
CN202509750U (en) | Height-adjustable type scaffold | |
CN213234385U (en) | Support arrangement for steel house building | |
CN206220322U (en) | A kind of pre-stress floor | |
CN204876557U (en) | U -shaped steel construction template | |
CN209779976U (en) | Fixing device of large plate artificial stone curtain wall | |
CN109610663A (en) | A kind of rock wool-steel plywood | |
CN216201123U (en) | Warm grillage that rolls over that leads to of building | |
CN212897468U (en) | Detachable scaffold for building site |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190412 Address after: 301600 Northwest corner of Happy Village, Caigongzhuang Town, Jinghai District, Tianjin Patentee after: Tianjin Zhiyi Metal Products Co.,Ltd. Address before: No. 414, Wolong Village, Taocheng Town, Yongchun County, Quanzhou City, Fujian Province, 362000 Patentee before: Lin Zhengyu |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180629 Termination date: 20211017 |