CN206320918U - Air conditioner support for multi-storey building - Google Patents

Air conditioner support for multi-storey building Download PDF

Info

Publication number
CN206320918U
CN206320918U CN201621451872.0U CN201621451872U CN206320918U CN 206320918 U CN206320918 U CN 206320918U CN 201621451872 U CN201621451872 U CN 201621451872U CN 206320918 U CN206320918 U CN 206320918U
Authority
CN
China
Prior art keywords
air
vertical
support
building
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621451872.0U
Other languages
Chinese (zh)
Inventor
孟建城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiacheng Lifeng Equipment Manufacturing Co Ltd
Original Assignee
Beijing Jiacheng Lifeng Equipment Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiacheng Lifeng Equipment Manufacturing Co Ltd filed Critical Beijing Jiacheng Lifeng Equipment Manufacturing Co Ltd
Priority to CN201621451872.0U priority Critical patent/CN206320918U/en
Application granted granted Critical
Publication of CN206320918U publication Critical patent/CN206320918U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of air conditioner support for multi-storey building, its drip irrigation device is some air-conditioner mounting racks for including being used to take up air-conditioning, also include for the support frame of connecting building thing wall and the connector for connecting support frame and air-conditioner mounting rack, support frame as described above includes two vertical beams, it is connected to two crossbeams of vertical beam upper and lower ends and is welded on some connecting plates that vertical beam presses close to metope side, connector includes C-shaped neck, penetrate the jack a of two side walls of C-shaped neck and coordinate jack a pin, C-shaped neck is fastened on vertical beam and its back fixation is connected to air-conditioner mounting rack, vertical beam is spaced apart provided with some jack b coordinated with jack a from the top down.The utility model solves existing air-conditioning and installs the situation that individual installs air-conditioning that only considered, not in view of the popularity rate of current air-conditioning, is all independently installed during each household installation air conditioner support, causes the problem of many unnecessary human and material resources are wasted.

Description

Air conditioner support for multi-storey building
Technical field
The utility model is related to air conditioner mounting bracket, more particularly to a kind of air conditioner support for multi-storey building.
Background technology
Current air-conditioning is a kind of indispensable household electrical appliance, and the residential building newly built can be pre-designed outside air-conditioning in design The installation site of machine.But for old-fashioned building, when building, air-conditioning is not yet popularized, and sky is not often accounted on its outer wall The installation of outer machine is adjusted, is built for such, it is necessary to independent welding support on its external wall, for installing outdoor machine of air-conditioner.
For example, a kind of outdoor air conditioner support that Authorization Notice No. is announced by 204141755U Chinese patent, its technology Scheme is that air conditioner support is integrally made up of high-quality stainless steel, and stainless steel materials and the both sides bending stainless steel pipe of its both sides lead to The mode for crossing welding is attached, and bending stainless steel pipe in both sides is welded with small dimension stainless steel pipe by way of punching Connect in succession, hard plastic board is fixed on the top of bottom small dimension stainless steel pipe, the top of both sides stainless steel materials is hung provided with U types Hook and screw hole.
The technical scheme be it is the more commonly used at present reserved for building air-conditioning position is installed in the case of, use Pattern.Although the problem of this method can solve no air-conditioning backup land, fairly simple.But only considered individual and air-conditioning is installed Situation, not in view of the popularity rate of current air-conditioning, each household is required for installing such support, each household peace when installing air-conditioning All it is independently installed during dress air conditioner support, causes the waste of many unnecessary human and material resources.While this plain type framework knot Structure is in itself due to small with wall contact surface, and support degree is inadequate, it is easy to come off, and there is potential safety hazard.
Utility model content
The purpose of this utility model is to provide a kind of air conditioner support for multi-storey building, and it has easy for installation, peace The characteristics of good perfection.
Above-mentioned purpose of the present utility model technical scheme is that:A kind of sky for multi-storey building Adjust support, including for taking up some air-conditioner mounting racks of air-conditioning, also including the support frame for connecting building thing wall and Connector for connecting support frame and air-conditioner mounting rack, support frame as described above includes two vertical beams, level connection joints being vertically arranged In vertical beam upper and lower ends two crossbeams and be welded on some connecting plates that vertical beam presses close to metope side, connector include C-shaped Neck, the jack a for penetrating two side walls of C-shaped neck and the pin for coordinating jack a, C-shaped neck is fastened on vertical beam and it is carried on the back Portion is fixedly connected on air-conditioner mounting rack, and vertical beam is spaced apart provided with some jack b coordinated with jack a from the top down.
By using above-mentioned technical proposal, old-fashioned building is most at 6 layers or so, entire building close to 60 families other.If The all independently installed air conditioner support of every family, each household, it is necessary to installation personnel repeat 60 times transport air conditioner supports, climbing external wall, Drilling, air conditioner support and lifting air-conditioning are installed, many human and material resources can be so wasted, while the noise repeatedly constructed also shadow Ring the life of people.
After design is improved, the height for being first according to floor sets the height of support frame, and the height of support frame will be with floor Highly approach, when story height is higher, vertical beam is not readily transportable, vertical beam is done into segment processing, then Assembling.Air conditioner support Each part all transport to behind erecting bed, by two vertical beam rightings, make its keep vertical state, then by connecting plate and building wall Body is fixedly connected, and vertical beam is connected on wall.Connector can up and down be adjusted on vertical beam, and then air-conditioner mounting rack also may be used To be adjusted up and down on vertical beam, according to the position of other window of each household, air-conditioner mounting rack regulation is arrived into suitable installation site simultaneously Complete to install, air-conditioning can be subsequently directly placed into air-conditioner mounting rack.In such building, if 60 family buildings of 6 floor Room, it is once just to complete the installation task of other air-conditioner mounting rack of 5 families.
If floor is higher, can also be segmented in vertical direction, such as 5 families or 6 families other with an air conditioner support, So that the use of air conditioner support is more convenient.
Compared to existing mounting means, after design is improved, it can be pacified every time with the air-conditioning of a row in one building of installation The installation task shelved, entire building, which only needs to a limited number of time, can just install all air-conditioner mounting racks, it is not necessary to repeatedly Transport, repeatedly climbing, the significantly less waste of human and material resources, while connection of the vertical beam by connecting plate and building masonry wall Point is more, and connection area is big, and safety coefficient is high.
The utility model is further arranged to:Side and be connected to side lower section that air-conditioner mounting rack is surrounded including three faces Bottom surface, sideways including two semiclosed rectangular shaped rims setting up and down, it is vertical be connected at two frame right angle nodes two Root montant and the iron plate above and below being located on two frames, bottom surface are made up of several horizontally disposed cross bars, two neighboring horizontal stroke Space is left between bar.
By using above-mentioned technical proposal, the processing of air-conditioner mounting rack is more convenient, while being stayed between the adjacent crossbars of bottom surface There is space, can prevent from accumulating rainwater.
The utility model is further arranged to:Steel reinforcement rope is set in the vertical beam, and steel reinforcement rope lower end is connected with Grasp, grasp is hooked at the lower port of vertical beam, its upper end upwardly extend until stretch out at the top of the montant and with building top Portion is connected.
By using above-mentioned technical proposal, the cooperation of steel reinforcement rope and grasp can have a certain upgrade to whole support Power, reduces the stress of connecting plate so that the connection of support and wall is more firm, improves the security used.
The utility model is further arranged to:It is spaced apart on iron plate and is provided with some heat emission holes.
By using above-mentioned technical proposal, it is easy to air-conditioning heat dissipation.
The utility model is further arranged to:The vertical beam is manufactured using hollow square steel.
By using above-mentioned technical proposal, the weight of vertical beam is alleviated while vertical beam structural strength is ensured, is reduced The stress of connecting plate so that the connection of support and wall is more firm, improves the security used.
The utility model is further arranged to:Screw is offered on the connecting plate and by expansion bolt and building wall Body is connected.
By using above-mentioned technical proposal so that the connection of vertical beam and construction wall is more convenient, firm.
In summary, the utility model has the advantages that:Old-fashioned building majority is at 6 layers or so, and entire building connects Nearly 60 family other.If all independently installed air conditioner support of every family, each household, it is necessary to which installation personnel repeats 60 transport air-conditioning branch Frame, climbing external wall, drilling, installation air conditioner support and lifting air-conditioning, can so waste many human and material resources, while many The noise of secondary construction also influences the life of people.
After design is improved, the height for being first according to floor sets the height of support frame, and the height of support frame will be with floor Highly approach, when story height is higher, vertical beam is not readily transportable, vertical beam is done into segment processing, then Assembling.Air conditioner support Each part all transport to behind erecting bed, by two vertical beam rightings, make its keep vertical state, then by connecting plate and building wall Body is fixedly connected, and vertical beam is connected on wall.Connector can up and down be adjusted on vertical beam, and then air-conditioner mounting rack also may be used To be adjusted up and down on vertical beam, according to the position of other window of each household, air-conditioner mounting rack regulation is arrived into suitable installation site simultaneously Complete to install, air-conditioning can be subsequently directly placed into air-conditioner mounting rack.In such building, if 60 family buildings of 6 floor Room, it is once just to complete the installation task of other air-conditioner mounting rack of 5 families.
If floor is higher, can also be segmented in vertical direction, such as 5 families or 6 families other with an air conditioner support, So that the use of air conditioner support is more convenient.
Compared to existing mounting means, after design is improved, it can be pacified every time with the air-conditioning of a row in one building of installation The installation task shelved, entire building, which only needs to a limited number of time, can just install all air-conditioner mounting racks, it is not necessary to repeatedly Transport, repeatedly climbing, the significantly less waste of human and material resources, while connection of the vertical beam by connecting plate and building masonry wall Point is more, and connection area is big, and safety coefficient is high.
Brief description of the drawings
Fig. 1 is the overall structure diagram of the air conditioner support for multi-storey building;
Fig. 2 is to save the explosive view that iron plate is done for the air conditioner support of multi-storey building;
Fig. 3 is to show the enlarged drawing in the A portions for Fig. 2 that the structure of connector is done.
In figure, 1, support frame;10th, vertical beam;100th, jack b;11st, crossbeam;12nd, connecting plate;2nd, air-conditioner mounting rack;20th, side Frame;21st, montant;22nd, iron plate;220th, heat emission hole;23rd, cross bar;3rd, connector;30th, C-shaped neck;31st, jack a;32nd, pin;4、 Steel reinforcement rope;5th, grasp.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment 1:A kind of air conditioner support for multi-storey building, reference picture 1, Fig. 2, Fig. 3, including support frame 1, air-conditioning peace Shelve 2 and for connecting the connector 3 of support frame 1 and air-conditioner mounting rack 2.
Two vertical beams 10 that support frame 1 includes being vertically arranged, level connection joint is in two crossbeams 11 of the upper and lower ends of vertical beam 10 And equidistantly it is welded on some connecting plates 12 that vertical beam 10 presses close to metope side.Vertical beam 10 is made of hollow square steel, its Length highly determines according to building, and its top is close to roof, and bottom is close to ground.Screw is offered on connecting plate 12, is used Vertical beam 10 is connected by expansion bolt through screw with external wall.Crossbeam 11 is also made of hollow square steel, crossbeam 11 and vertical beam 10 welding.
Air-conditioner mounting rack 2 is cuboid framework formula structure, and it includes the side that three faces surround and is connected to below side Bottom surface, be connected to sideways including two semiclosed rectangular shaped rims 20 setting up and down, vertically at two right angle nodes of frame 20 Two montants 21 and the iron plate 22 above and below being located on two frames 20.Rectangular shaped rim 20, montant 21 use hollow square steel It is made, rectangular shaped rim 20, montant 21 and iron plate 22 are welded, iron plate 22 goes out to process necessarily by laser cutting or wire cutting The heat emission hole 220 of quantity, for air-conditioning heat dissipation.
Bottom surface is made up of several horizontally disposed cross bars 23, and cross bar 23 uses hollow square steel, and two ends are respectively welded at lower floor Space is left between the both sides of rectangular shaped rim 20, two neighboring cross bar 23, accumulation of raining is prevented.
Connector 3 includes C-shaped neck 30, the jack a31 for penetrating 30 two side walls of C-shaped neck and coordinates jack a31's Pin 32.
C-shaped neck 30 is made of channel-section steel, and it is welded on the two ends of rectangular shaped rim 20, if vertical beam 10 is offered from the top down The dry jack b100 coordinated with jack a31, when C-shaped neck 30 is fastened on vertical beam 10, pin 32 passes through jack a31 and jack B100, support frame 1 is fixed on by air-conditioner mounting rack 2.In order that must connect more firm, can be in jack a31 and jack b100 Air-conditioner mounting rack 2, is then connected on support frame 1 by middle setting internal thread by bolt.
In order that the connection of support frame 1 and external wall is more firm, steel reinforcement rope 4, steel are provided with vertical beam 10 Silk reinforcing cord 4 one end is connected with grasp 5, and grasp 5 is hooked at the lower port of vertical beam 10, and its upper end is upwardly extended until from perpendicular The top of bar 21 is stretched out and is fixed on by clip at the top of building.The whole support of 4 pairs of steel reinforcement rope has a certain upgrade power so that The connection of support and wall is more firm, reduces the stress of connecting plate 12, improves the security used.
This specific embodiment is only to explain of the present utility model, and it is not to limitation of the present utility model, ability Field technique personnel can make the modification without creative contribution to the present embodiment as needed after this specification is read, but As long as all being protected in right of the present utility model by Patent Law.

Claims (6)

1. a kind of air conditioner support for multi-storey building, including for taking up some air-conditioner mounting racks (2) of air-conditioning, its feature exists In:Also include for the support frame (1) of connecting building thing wall and for connecting support frame (1) and air-conditioner mounting rack (2) Connector (3), two vertical beams (10) that support frame as described above (1) includes being vertically arranged, level connection joint is in vertical beam (10) upper and lower ends Two crossbeams (11) and be welded on some connecting plates (12) that vertical beam (10) presses close to metope side, connector (3) include C-shaped Neck (30), the jack a (31) for penetrating (30) two side walls of C-shaped neck and the pin (32) for coordinating jack a (31), C-shaped card Groove (30) is fastened on vertical beam (10) and its back fixation is connected to air-conditioner mounting rack (2), and vertical beam (10) is spaced apart from the top down Provided with some jack b (100) coordinated with jack a (31).
2. the air conditioner support according to claim 1 for multi-storey building, it is characterised in that:Air-conditioner mounting rack (2) includes Side that three faces are surrounded and the bottom surface being connected to below side, sideways including two semiclosed rectangular shaped rims setting up and down (20), it is vertical be connected to two montants (21) at two frame (20) right angle nodes and be located above and below two frames (20) On iron plate (22), bottom surface is made up of several horizontally disposed cross bars (23), and space is left between two neighboring cross bar (23).
3. the air conditioner support according to claim 1 for multi-storey building, it is characterised in that:Set in the vertical beam (10) Steel reinforcement rope (4), steel reinforcement rope (4) lower end is connected with grasp (5), and grasp (5) is hooked in the lower port of vertical beam (10) Place, its upper end is upwardly extended until stretching out and being connected with top of building at the top of montant (21).
4. the air conditioner support according to claim 2 for multi-storey building, it is characterised in that:It is spaced and opens up on iron plate (22) There are some heat emission holes (220).
5. the air conditioner support according to claim 1 for multi-storey building, it is characterised in that:The vertical beam (10) is using empty Heart square steel is manufactured.
6. the air conditioner support according to claim 1 for multi-storey building, it is characterised in that:Opened on the connecting plate (12) It is connected provided with screw and by expansion bolt with building masonry wall.
CN201621451872.0U 2016-12-27 2016-12-27 Air conditioner support for multi-storey building Expired - Fee Related CN206320918U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621451872.0U CN206320918U (en) 2016-12-27 2016-12-27 Air conditioner support for multi-storey building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621451872.0U CN206320918U (en) 2016-12-27 2016-12-27 Air conditioner support for multi-storey building

Publications (1)

Publication Number Publication Date
CN206320918U true CN206320918U (en) 2017-07-11

Family

ID=59259136

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621451872.0U Expired - Fee Related CN206320918U (en) 2016-12-27 2016-12-27 Air conditioner support for multi-storey building

Country Status (1)

Country Link
CN (1) CN206320918U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107300227A (en) * 2017-08-08 2017-10-27 天津商业大学 The method for determining outdoor unit optimal mounting distance that Relative vertical is arranged in groove
CN108131744A (en) * 2017-12-22 2018-06-08 吴柳平 For the shelves of motor
CN111519754A (en) * 2020-05-08 2020-08-11 黄炳江 Detachable green terrace for multi-storey building and manufacturing method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107300227A (en) * 2017-08-08 2017-10-27 天津商业大学 The method for determining outdoor unit optimal mounting distance that Relative vertical is arranged in groove
CN108131744A (en) * 2017-12-22 2018-06-08 吴柳平 For the shelves of motor
CN111519754A (en) * 2020-05-08 2020-08-11 黄炳江 Detachable green terrace for multi-storey building and manufacturing method thereof

Similar Documents

Publication Publication Date Title
US9004443B2 (en) Early-stripping formwork system for concreting of constructions comprising beams, slab and columns
CN104358315B (en) A kind of prefabricated buildings and its installation method
CN101736893B (en) Overhanging type scaffold supporting system
CN205316525U (en) Novel outer quick -witted suspension support structure of air conditioner
CN203499229U (en) Operating platform for construction of elevator shaft
CN202324571U (en) Overhanging type double-row scaffold
CN208202603U (en) A kind of arch truss installa-tion moulding bed
CN105484502A (en) Combination installation method for steel structure roofing purlins and support bars of industrial factory building
CN206428956U (en) Driven hanging basket and its fixing device
CN101397844B (en) Construction method of special section steel concrete composite structure inclined wall mould base engineering
WO2019033477A1 (en) High tensile strength aseismatic connector and aseismatic bracket support
CN203296166U (en) Supporting structure of main module unit in module building
WO2017078567A1 (en) Connection joint of a column and a floor slab of a girderless building frame without a capital
CN206667718U (en) A kind of high-rise outdoor cradling platform of extension type
CN105401714A (en) Attachment type lifting scaffold and lifting method
CN103993735A (en) Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN107675794A (en) Prefabricated steel framework frame module room
CN206697773U (en) Suspension type station institute terminal D TU cabinet erecting devices
CN210399268U (en) Adjustable air conditioner mounting frame
CN104878867B (en) Integral structure of ceiling joist and double-deck operation platform and preparation method thereof
CN107060098A (en) A kind of high-altitude wire frame Steel Structure Installation method based on sliding platform
CN105986664A (en) Hanging basket and roof reverse-hanging plate work platform including same
CN205577383U (en) Attached lifting scaffold
CN209323800U (en) A kind of prefabricated three-hinged arch roof boarding
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170711

Termination date: 20181227

CF01 Termination of patent right due to non-payment of annual fee