- CN207538078U CN207538078U CN201721533293.5U CN201721533293U CN207538078U CN 207538078 U CN207538078 U CN 207538078U CN 201721533293 U CN201721533293 U CN 201721533293U CN 207538078 U CN207538078 U CN 207538078U
- Authority
- CN
- China
- Prior art keywords
- stent
- pipe gallery
- plate device
- sliding plate
- device open
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model is related to underground pipe gallery construction equipment technology field, more particularly to a kind of pipe gallery early tears sliding plate device open.It includes multiple assembled panels, stent group, connector and walking mechanism;Assembled panel is connect with stent group by connector;Walking mechanism is mounted on stent group lower end;Stent group includes left socle, right support and middle stent, and left socle, middle stent and right support are laterally set successively;Assembled panel and stent group be by connection when concrete is poured into a mould, and is formed whole, during form removal, is developed according to concrete strength, first removed, assembled panel and stent on mobile left and right stent, finally remove, it is mobile in stent and combinations thereof panel.The purpose of this utility model is that requiring difference to striking time according to concrete different parts, a kind of pipe gallery is provided and early tears sliding plate device open, reduces equipment cost, improve plate device applicability and utilization rate, realization becomes more meticulous construction, promotes working efficiency, effectively reduces construction cost.
Description
Technical field
The utility model is related to underground pipe gallery construction equipment technology field, more particularly to a kind of pipe gallery early tears cunning open
Shifting formwork panel assembly.
Background technology
Underground pipe gallery can provide enough spaces, install concentratedly various city planting ductworks are in good order, can avoid disperseing
The Excavation Problems repeatedly on ground during pipelining are carried out, therefore, underground pipe gallery is just largely used in new city construction.
Many underground pipe gallery construction are that open cut pours at the construction field (site) at present, and open cut piping lane concrete structure scene is poured
The wooden model system constructed and mostly supported using full framing is built, system scaffold dismounting is cumbersome, needs largely manually, and construct
Quality is unstable, while template circulation cycle times are few, and the system is both uneconomical or not environmentally, and quality difficulty control have safely it is hidden
Suffer from, it is difficult to meet the requirement of industrialized production.A small amount of piping lane employs rail-road road tunnel trolley form, is laid with track movement, but
The system mostly does stent using shaped steel, and the unfavorable installation of structure bulky, cost are higher, and trolley is all integral type fixed dimension,
A kind of piping lane of specification is only adapted to pour, section is poor for applicability, causes equipment recycling rate of waterused not high, therefore, the platform of the type
Vehicle does not find broad application, in addition, the trolley does not make full use of the difference of side wall and top plate striking time, carries out differentiation
Construction, template can only use assembling simultaneously to remove simultaneously, and template utilization rate is low, and construction technology has the space of optimization.
Utility model content
The purpose of this utility model is to provide a kind of pipe galleries early to tear sliding plate device open, is made with solving existing template
The problem of valency is high, section adaptability is low, utilization ratio of device is low, working procedure is not reasonable, construction cost is high.
The purpose of this utility model is realized by following technical proposals:
A kind of pipe gallery early tears sliding plate device open, including multiple assembled panels, stent group, connector and vehicle with walking machine
Structure;The assembled panel is connect with the stent group by the connector;The walking mechanism is mounted under the stent group
End;The stent group includes left socle, right support and middle stent, and the left socle, the middle stent and the right support are successively
Laterally setting.
Further, the stent group is there are two more than, more than two stent group longitudinal arrangements.
Further, the assembled panel is equipped with ribs.
Further, the ribs on the adjacent assembled panel is bolted.
Further, the stent group includes upright bar, horizon bar and terminal pad;The upright bar and the horizon bar pass through institute
State terminal pad connection.
Further, adjustable base is set between the stent group and the walking mechanism.
Further, it is connected between the left socle and the middle stent by silk braid, the middle stent and the right branch
It is connected between frame by the silk braid.
Further, it is connected between the adjacent stent group by the silk braid.
Further, it is equipped with end segment diagonal brace positioned at the stent group at both ends.
Further, the walking mechanism is industry braking universal wheel.
The utility model has the following advantages that compared with prior art:
1. the stent group that the utility model is set using assembled panel and branch, stent group include left socle, right support and
Middle stent, the left socle, the middle stent and the right support are laterally set successively;It will to striking time using different parts
The difference asked removes assembled panel and mobile stent group in work progress, realizes construction fine-grained management, shorten combination in batches
Panel and stent group single cycle time improve assembled panel and stent group utilization rate;It and can be big according to piping lane section span
Small situation sets different middle stents, coordinates with fixed-size left socle, right support, can meet the pipe of different large spans
Corridor pouring construction, device utilization rate is high, reduces construction cost.
2. pipe gallery described in the utility model early tears sliding plate device open, equipped with the walking below stent group
Mechanism;When needing to remove assembled panel, stent group can realize the movement of all directions by portion by walking mechanism section by section, keep away
Exempted from the repeated disassembled and assembled of conventional stent, reduced the workload of form removable, reduce piping lane construction human cost and the time into
This.
3. stent group described in the utility model includes upright bar, horizon bar and terminal pad;The upright bar and the horizon bar lead to
The terminal pad connection is crossed, the stent group uses socket joint type disk button steel pipe support, portable construction, high capacity, stability
It is good, low cost.
4. stent group described in the utility model is there are two more than, more than two stent group longitudinal arrangements;Stent it is horizontal,
Branch, merogenesis setting have been carried out on longitudinal direction, can be as needed, by portion section by section, installed and removed, convenient for site operation.
Description of the drawings
Fig. 1 early tears sliding plate device cross-sectional configuration figure open for pipe gallery described in the utility model;
Fig. 2 is stent group cross-sectional configuration figure described in the utility model;
Fig. 3 early tears sliding plate device longitudinal plane structure figure open for pipe gallery described in the utility model;
In figure:Stent in 1- assembled panels, 2- ribs, 3- stents group, 301- left socles, 302-, 303- right supports,
304 upright bars, 305- horizon bars, 306- terminal pads, 4- silk braids, 5- adjustable bases, 6- walking mechanisms, 7- connectors, 8- end segments are oblique
Support.
Specific embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described
Embodiment is the utility model part of the embodiment, instead of all the embodiments.Based on the embodiment in the utility model, sheet
Field those of ordinary skill all other embodiments obtained without making creative work, belong to this practicality
Novel protected range.
In the description of the present invention, it should be noted that term " center ", " upper ", " under ", " left side ", " right side ", " perpendicular
Directly ", " level ", " interior ", " " it is based on orientation shown in the drawings or position relationship to wait the orientation of instructions or position relationship, is only outside
The utility model must have specific with the device or element for simplifying description rather than instruction or hint meaning for ease of description
Orientation, with specific azimuth configuration and operation, therefore it is not intended that limitation to the utility model.In addition, term " the
One ", " second ", " third " description purpose is only used for, and it is not intended that instruction or hint relative importance.
The purpose of this utility model is realized by following technical proposals:
Referring to Fig. 1, Fig. 2, a kind of pipe gallery early tears sliding plate device open, including multiple assembled panels 1, stent group 3,
Connector 7 and walking mechanism 6;Assembled panel 1 is connect with stent group 3 by connector 7;Walking mechanism 6 is mounted under stent group 3
End;Stent group 3 includes left socle 301, right support 303 and middle stent 302, left socle 301, middle stent 302 and right support 303
Laterally setting successively;The utility model template uses assembled panel 1, and assembled panel 1 is standard element, has and makes precision height,
The advantages that piece is tight, good integrity, while stent group 3 is set using branch, stent group 3 includes left socle 301, right support
303 and middle stent 302, the laterally setting successively of left socle 301, middle stent 302 and right support 303;Using different parts to form removal
The difference of time requirement removes assembled panel 1 and mobile stent group 3 in work progress, realizes construction fine-grained management in batches,
Shorten the 3 single cycle time of assembled panel 1 and stent group, improve 3 utilization rate of assembled panel 1 and stent group;It and can be according to pipe
Corridor section span size cases, set different middle stents 302, coordinate with fixed-size left socle 301, right support 303,
The piping lane pouring construction of different large spans can be met, device utilization rate is high, reduces construction cost.
Referring to Fig. 3, stent group 3 is there are two more than, more than two 3 longitudinal arrangements of stent group;Stent is enterprising in horizontal stroke, longitudinal direction
The merogenesis setting of Hang Liao branches, can be as needed, by portion section by section, is installed and is removed, convenient for site operation.
Referring to Fig. 1, assembled panel 1 is equipped with ribs 2;Ribs 2 on adjacent assembled panel 1 is bolted;
Assembled panel 1 is equipped with ribs 2, can improve the rigidity of assembled panel 1, avoids the bending of assembled panel 1 in work progress, becomes
Shape;Ribs 2 on adjacent assembled panel 1 is bolted;It is assembled, and by ribs convenient for the dismounting of assembled panel 1
2 connect into an entirety, improve 1 integrally-built stability of assembled panel.
Referring to Fig. 2, stent group 3 includes upright bar 304, horizon bar 305 and terminal pad 306;Upright bar 304 and horizon bar 305 are logical
Terminal pad 306 is crossed to connect;Stent group 3 uses socket joint type disk button steel pipe support, and portable construction, high capacity, stability are good, make
Valency is low.
Referring to Fig. 1, adjustable base 5 is set between stent group 3 and walking mechanism 6;Adjustable base 5 is used for adjusting bracket group 3
Height, the piping lane pouring construction of different height can be met, device utilization rate is high, reduces construction cost.
It referring to Fig. 2, Fig. 3, is connected between left socle 301 and middle stent 302 by silk braid 4, middle stent 302 and right support
It is connected between 303 by silk braid 4;It is connected between adjacent stent group 3 by silk braid 4;During casting concrete, select silk braid 4 will
The stent of each branch links into an integrated entity, and can have enough rigidity and stability.
Referring to Fig. 3, the stent group 3 positioned at both ends is equipped with end segment diagonal brace 8;End segment diagonal brace 8 is set, it is ensured that is set
There is enough rigidity in the assembled panel 1 that this pipe gallery early tears sliding plate device both ends open, improve the stability of device entirety.
Referring to Fig. 1, walking mechanism 6 is industry braking universal wheel so that stent group 3 section by section can be arbitrary with all directions by portion
It is mobile, improve the flexibility of stent group 3.
Specific works step:
Wherein, the span of left socle 301, the cross section of right support 303 and vertical section is no more than 2m;According to《Concrete
Structure construction specification》The regulation of GB50666-2011:" as harden structure span≤2m, reach design strength in concrete strength
50% when can form removal;When harden structure span is 2~8 and 8m, reach the 75% of design strength in concrete strength
With can form removal when 100% ", the property of concrete is made full use of, when concrete roof intensity reaches design strength
When 50%, you can remove span section by section less than the assembled panel 1 on the left socle 301 of 2m, right support 303, during dismounting, first unclamp
Left socle 301, right support 303 and middle stent 302 and the connection with adjacent stent group 3, it is rear to lower left socle 301, right support 303
Following adjustable base 5 removes left socle 301, the top plate bottom assembled panel 1 on right support 303, then 6 water of logical walking mechanism
The dynamic dismounting left socle 301 of translation, the side wall assembled panel 1 of 303 side of right support, and moved with left socle 301, right support 303
It is in place to subsequent cycle section, when finally concrete reaches form removal requirement in the middle part of the top plate, then the combinatorial surface in removing on stent 302
Plate 1, and subsequent cycle section is moved to middle stent 302, the left socle 301 in place with early period and right support 302 connect positioning.
Finally it should be noted that:The above various embodiments is only to illustrate the technical solution of the utility model rather than it is limited
System;Although the utility model is described in detail with reference to foregoing embodiments, those of ordinary skill in the art should
Understand:It can still modify to the technical solution recorded in foregoing embodiments either to which part or whole
Technical characteristic carries out equivalent replacement;And these modifications or replacement, this practicality that it does not separate the essence of the corresponding technical solution are new
The range of each embodiment technical solution of type.
Claims (10)
1. a kind of pipe gallery early tears sliding plate device open, it is characterised in that:Including multiple assembled panels, stent group, connector
And walking mechanism;The assembled panel is connect with the stent group by the connector;The walking mechanism is mounted on described
Stent group lower end;The stent group includes left socle, right support and middle stent, the left socle, the middle stent, the right branch
Frame is laterally set successively.
2. pipe gallery according to claim 1 early tears sliding plate device open, it is characterised in that:There are two the stent groups
More than, more than two stent group longitudinal arrangements.
3. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The assembled panel
It is equipped with ribs.
4. pipe gallery according to claim 3 early tears sliding plate device open, it is characterised in that:The adjacent assembled panel
On the ribs be bolted.
5. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The stent group packet
Include upright bar, horizon bar and terminal pad;The upright bar is connected with the horizon bar by the terminal pad.
6. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The stent group with
Adjustable base is set between the walking mechanism.
7. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The left socle and
It is connected by silk braid between the middle stent, is connected between the middle stent and the right support by the silk braid.
8. pipe gallery according to claim 7 early tears sliding plate device open, it is characterised in that:The adjacent stent group
Between connected by the silk braid.
9. pipe gallery according to claim 2 early tears sliding plate device open, it is characterised in that:The branch positioned at both ends
Frame group is equipped with end segment diagonal brace.
10. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The walking mechanism
Universal wheel is braked for industry.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721533293.5U CN207538078U (en) | 2017-11-16 | 2017-11-16 | A kind of pipe gallery early tears sliding plate device open |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721533293.5U CN207538078U (en) | 2017-11-16 | 2017-11-16 | A kind of pipe gallery early tears sliding plate device open |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207538078U true CN207538078U (en) | 2018-06-26 |
Family
ID=62613834
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721533293.5U Active CN207538078U (en) | 2017-11-16 | 2017-11-16 | A kind of pipe gallery early tears sliding plate device open |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207538078U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112458936A (en) * | 2020-11-30 | 2021-03-09 | 中铁十六局集团地铁工程有限公司 | Construction method for integrally translating box culvert full-hall support |
CN112878362A (en) * | 2021-01-07 | 2021-06-01 | 中国二十冶集团有限公司 | Comprehensive pipe gallery slip form device and construction method |
CN113089511A (en) * | 2021-03-18 | 2021-07-09 | 湖北正鑫铝模科技有限公司 | Water diversion hole supporting aluminum mold and assembling method |
-
2017
- 2017-11-16 CN CN201721533293.5U patent/CN207538078U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112458936A (en) * | 2020-11-30 | 2021-03-09 | 中铁十六局集团地铁工程有限公司 | Construction method for integrally translating box culvert full-hall support |
CN112878362A (en) * | 2021-01-07 | 2021-06-01 | 中国二十冶集团有限公司 | Comprehensive pipe gallery slip form device and construction method |
CN113089511A (en) * | 2021-03-18 | 2021-07-09 | 湖北正鑫铝模科技有限公司 | Water diversion hole supporting aluminum mold and assembling method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207538078U (en) | A kind of pipe gallery early tears sliding plate device open | |
CN104806011B (en) | Raft board post poured band formwork for placing | |
CN105401599A (en) | Open trench tunnel main structure tall side wall unilateral vertical mold and construction process thereof | |
CN103215894B (en) | Portable interim prestressed stretch-draw anchor block | |
CN110374321A (en) | A kind of assembled waffle beam superstructure gang form and construction method | |
CN204298742U (en) | For the supporting and protection structure of Bridge High-pier construction | |
CN207920632U (en) | Formwork jumbo for pipe gallery of constructing | |
CN203531923U (en) | Moving framework for tunnel groove construction | |
CN202090932U (en) | Universal template device for tunnel construction | |
CN109610509A (en) | A kind of the adjustable die system and construction method of pipe gallery automatic control section | |
CN106150525A (en) | A kind of rock anchorage beam construction trolley and construction method thereof | |
CN205840892U (en) | Ditch mould bases is surveyed in self-propelled tunnel | |
CN209603182U (en) | A kind of adjustable die system of pipe gallery automatic control section | |
CN208088804U (en) | A kind of aerial device of interior decoration | |
CN207512790U (en) | A kind of trapezoidal bottom plate rear pouring tape and special-shaped steel plate for sealing water anti-leakage structure | |
CN207583391U (en) | One kind two serves as a contrast plug steel end mould | |
CN109356618A (en) | A kind of simple integral movable type square type tunnel frame and its construction method | |
CN105113536A (en) | Movable sidewall formwork erecting system for underground structure and construction method of system | |
CN206111212U (en) | Rock -anchored beam construction trolley car | |
CN108150198A (en) | For the formwork jumbo for pipe gallery of constructing | |
CN208594729U (en) | A kind of scaffold for building convenient for assembled adjusting height | |
CN207795270U (en) | A kind of portable cart | |
CN206707301U (en) | Adjustable height reinforcing bar colligation frame | |
CN216198149U (en) | Utility tunnel construction trolley | |
CN206110644U (en) | A stencil assembly for clear water concrete construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |