CN207538078U CN201721533293.5U CN201721533293U CN207538078U CN 207538078 U CN207538078 U CN 207538078U CN 201721533293 U CN201721533293 U CN 201721533293U CN 207538078 U CN207538078 U CN 207538078U
Authority
CN
China
Prior art keywords
stent
pipe gallery
plate device
sliding plate
device open
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721533293.5U
Other languages
Chinese (zh)
Inventor
元华梁
薛志文
尹红亮
刘昂
张先武
李金荣
宗玉峰
盛三湘
顾金柱
王孟
王北华
徐杰梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Communications Infrastructure Maintenance Group Co Ltd
Original Assignee
China Communications Infrastructure Maintenance Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Communications Infrastructure Maintenance Group Co Ltd filed Critical China Communications Infrastructure Maintenance Group Co Ltd
Priority to CN201721533293.5U priority Critical patent/CN207538078U/en
Application granted granted Critical
Publication of CN207538078U publication Critical patent/CN207538078U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to underground pipe gallery construction equipment technology field, more particularly to a kind of pipe gallery early tears sliding plate device open.It includes multiple assembled panels, stent group, connector and walking mechanism;Assembled panel is connect with stent group by connector;Walking mechanism is mounted on stent group lower end;Stent group includes left socle, right support and middle stent, and left socle, middle stent and right support are laterally set successively;Assembled panel and stent group be by connection when concrete is poured into a mould, and is formed whole, during form removal, is developed according to concrete strength, first removed, assembled panel and stent on mobile left and right stent, finally remove, it is mobile in stent and combinations thereof panel.The purpose of this utility model is that requiring difference to striking time according to concrete different parts, a kind of pipe gallery is provided and early tears sliding plate device open, reduces equipment cost, improve plate device applicability and utilization rate, realization becomes more meticulous construction, promotes working efficiency, effectively reduces construction cost.

Description

A kind of pipe gallery early tears sliding plate device open
Technical field
The utility model is related to underground pipe gallery construction equipment technology field, more particularly to a kind of pipe gallery early tears cunning open Shifting formwork panel assembly.
Background technology
Underground pipe gallery can provide enough spaces, install concentratedly various city planting ductworks are in good order, can avoid disperseing The Excavation Problems repeatedly on ground during pipelining are carried out, therefore, underground pipe gallery is just largely used in new city construction.
Many underground pipe gallery construction are that open cut pours at the construction field (site) at present, and open cut piping lane concrete structure scene is poured The wooden model system constructed and mostly supported using full framing is built, system scaffold dismounting is cumbersome, needs largely manually, and construct Quality is unstable, while template circulation cycle times are few, and the system is both uneconomical or not environmentally, and quality difficulty control have safely it is hidden Suffer from, it is difficult to meet the requirement of industrialized production.A small amount of piping lane employs rail-road road tunnel trolley form, is laid with track movement, but The system mostly does stent using shaped steel, and the unfavorable installation of structure bulky, cost are higher, and trolley is all integral type fixed dimension, A kind of piping lane of specification is only adapted to pour, section is poor for applicability, causes equipment recycling rate of waterused not high, therefore, the platform of the type Vehicle does not find broad application, in addition, the trolley does not make full use of the difference of side wall and top plate striking time, carries out differentiation Construction, template can only use assembling simultaneously to remove simultaneously, and template utilization rate is low, and construction technology has the space of optimization.
Utility model content
The purpose of this utility model is to provide a kind of pipe galleries early to tear sliding plate device open, is made with solving existing template The problem of valency is high, section adaptability is low, utilization ratio of device is low, working procedure is not reasonable, construction cost is high.
The purpose of this utility model is realized by following technical proposals:
A kind of pipe gallery early tears sliding plate device open, including multiple assembled panels, stent group, connector and vehicle with walking machine Structure;The assembled panel is connect with the stent group by the connector;The walking mechanism is mounted under the stent group End;The stent group includes left socle, right support and middle stent, and the left socle, the middle stent and the right support are successively Laterally setting.
Further, the stent group is there are two more than, more than two stent group longitudinal arrangements.
Further, the assembled panel is equipped with ribs.
Further, the ribs on the adjacent assembled panel is bolted.
Further, the stent group includes upright bar, horizon bar and terminal pad;The upright bar and the horizon bar pass through institute State terminal pad connection.
Further, adjustable base is set between the stent group and the walking mechanism.
Further, it is connected between the left socle and the middle stent by silk braid, the middle stent and the right branch It is connected between frame by the silk braid.
Further, it is connected between the adjacent stent group by the silk braid.
Further, it is equipped with end segment diagonal brace positioned at the stent group at both ends.
Further, the walking mechanism is industry braking universal wheel.
The utility model has the following advantages that compared with prior art:
1. the stent group that the utility model is set using assembled panel and branch, stent group include left socle, right support and Middle stent, the left socle, the middle stent and the right support are laterally set successively;It will to striking time using different parts The difference asked removes assembled panel and mobile stent group in work progress, realizes construction fine-grained management, shorten combination in batches Panel and stent group single cycle time improve assembled panel and stent group utilization rate;It and can be big according to piping lane section span Small situation sets different middle stents, coordinates with fixed-size left socle, right support, can meet the pipe of different large spans Corridor pouring construction, device utilization rate is high, reduces construction cost.
2. pipe gallery described in the utility model early tears sliding plate device open, equipped with the walking below stent group Mechanism;When needing to remove assembled panel, stent group can realize the movement of all directions by portion by walking mechanism section by section, keep away Exempted from the repeated disassembled and assembled of conventional stent, reduced the workload of form removable, reduce piping lane construction human cost and the time into This.
3. stent group described in the utility model includes upright bar, horizon bar and terminal pad;The upright bar and the horizon bar lead to The terminal pad connection is crossed, the stent group uses socket joint type disk button steel pipe support, portable construction, high capacity, stability It is good, low cost.
4. stent group described in the utility model is there are two more than, more than two stent group longitudinal arrangements;Stent it is horizontal, Branch, merogenesis setting have been carried out on longitudinal direction, can be as needed, by portion section by section, installed and removed, convenient for site operation.
Description of the drawings
Fig. 1 early tears sliding plate device cross-sectional configuration figure open for pipe gallery described in the utility model;
Fig. 2 is stent group cross-sectional configuration figure described in the utility model;
Fig. 3 early tears sliding plate device longitudinal plane structure figure open for pipe gallery described in the utility model;
In figure:Stent in 1- assembled panels, 2- ribs, 3- stents group, 301- left socles, 302-, 303- right supports, 304 upright bars, 305- horizon bars, 306- terminal pads, 4- silk braids, 5- adjustable bases, 6- walking mechanisms, 7- connectors, 8- end segments are oblique Support.
Specific embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described Embodiment is the utility model part of the embodiment, instead of all the embodiments.Based on the embodiment in the utility model, sheet Field those of ordinary skill all other embodiments obtained without making creative work, belong to this practicality Novel protected range.
In the description of the present invention, it should be noted that term " center ", " upper ", " under ", " left side ", " right side ", " perpendicular Directly ", " level ", " interior ", " " it is based on orientation shown in the drawings or position relationship to wait the orientation of instructions or position relationship, is only outside The utility model must have specific with the device or element for simplifying description rather than instruction or hint meaning for ease of description Orientation, with specific azimuth configuration and operation, therefore it is not intended that limitation to the utility model.In addition, term " the One ", " second ", " third " description purpose is only used for, and it is not intended that instruction or hint relative importance.
The purpose of this utility model is realized by following technical proposals:
Referring to Fig. 1, Fig. 2, a kind of pipe gallery early tears sliding plate device open, including multiple assembled panels 1, stent group 3, Connector 7 and walking mechanism 6;Assembled panel 1 is connect with stent group 3 by connector 7;Walking mechanism 6 is mounted under stent group 3 End;Stent group 3 includes left socle 301, right support 303 and middle stent 302, left socle 301, middle stent 302 and right support 303 Laterally setting successively;The utility model template uses assembled panel 1, and assembled panel 1 is standard element, has and makes precision height, The advantages that piece is tight, good integrity, while stent group 3 is set using branch, stent group 3 includes left socle 301, right support 303 and middle stent 302, the laterally setting successively of left socle 301, middle stent 302 and right support 303;Using different parts to form removal The difference of time requirement removes assembled panel 1 and mobile stent group 3 in work progress, realizes construction fine-grained management in batches, Shorten the 3 single cycle time of assembled panel 1 and stent group, improve 3 utilization rate of assembled panel 1 and stent group;It and can be according to pipe Corridor section span size cases, set different middle stents 302, coordinate with fixed-size left socle 301, right support 303, The piping lane pouring construction of different large spans can be met, device utilization rate is high, reduces construction cost.
Referring to Fig. 3, stent group 3 is there are two more than, more than two 3 longitudinal arrangements of stent group;Stent is enterprising in horizontal stroke, longitudinal direction The merogenesis setting of Hang Liao branches, can be as needed, by portion section by section, is installed and is removed, convenient for site operation.
Referring to Fig. 1, assembled panel 1 is equipped with ribs 2;Ribs 2 on adjacent assembled panel 1 is bolted; Assembled panel 1 is equipped with ribs 2, can improve the rigidity of assembled panel 1, avoids the bending of assembled panel 1 in work progress, becomes Shape;Ribs 2 on adjacent assembled panel 1 is bolted;It is assembled, and by ribs convenient for the dismounting of assembled panel 1 2 connect into an entirety, improve 1 integrally-built stability of assembled panel.
Referring to Fig. 2, stent group 3 includes upright bar 304, horizon bar 305 and terminal pad 306;Upright bar 304 and horizon bar 305 are logical Terminal pad 306 is crossed to connect;Stent group 3 uses socket joint type disk button steel pipe support, and portable construction, high capacity, stability are good, make Valency is low.
Referring to Fig. 1, adjustable base 5 is set between stent group 3 and walking mechanism 6;Adjustable base 5 is used for adjusting bracket group 3 Height, the piping lane pouring construction of different height can be met, device utilization rate is high, reduces construction cost.
It referring to Fig. 2, Fig. 3, is connected between left socle 301 and middle stent 302 by silk braid 4, middle stent 302 and right support It is connected between 303 by silk braid 4;It is connected between adjacent stent group 3 by silk braid 4;During casting concrete, select silk braid 4 will The stent of each branch links into an integrated entity, and can have enough rigidity and stability.
Referring to Fig. 3, the stent group 3 positioned at both ends is equipped with end segment diagonal brace 8;End segment diagonal brace 8 is set, it is ensured that is set There is enough rigidity in the assembled panel 1 that this pipe gallery early tears sliding plate device both ends open, improve the stability of device entirety.
Referring to Fig. 1, walking mechanism 6 is industry braking universal wheel so that stent group 3 section by section can be arbitrary with all directions by portion It is mobile, improve the flexibility of stent group 3.
Specific works step:
Wherein, the span of left socle 301, the cross section of right support 303 and vertical section is no more than 2m;According to《Concrete Structure construction specification》The regulation of GB50666-2011:" as harden structure span≤2m, reach design strength in concrete strength 50% when can form removal;When harden structure span is 2~8 and 8m, reach the 75% of design strength in concrete strength With can form removal when 100% ", the property of concrete is made full use of, when concrete roof intensity reaches design strength When 50%, you can remove span section by section less than the assembled panel 1 on the left socle 301 of 2m, right support 303, during dismounting, first unclamp Left socle 301, right support 303 and middle stent 302 and the connection with adjacent stent group 3, it is rear to lower left socle 301, right support 303 Following adjustable base 5 removes left socle 301, the top plate bottom assembled panel 1 on right support 303, then 6 water of logical walking mechanism The dynamic dismounting left socle 301 of translation, the side wall assembled panel 1 of 303 side of right support, and moved with left socle 301, right support 303 It is in place to subsequent cycle section, when finally concrete reaches form removal requirement in the middle part of the top plate, then the combinatorial surface in removing on stent 302 Plate 1, and subsequent cycle section is moved to middle stent 302, the left socle 301 in place with early period and right support 302 connect positioning.
Finally it should be noted that:The above various embodiments is only to illustrate the technical solution of the utility model rather than it is limited System;Although the utility model is described in detail with reference to foregoing embodiments, those of ordinary skill in the art should Understand:It can still modify to the technical solution recorded in foregoing embodiments either to which part or whole Technical characteristic carries out equivalent replacement;And these modifications or replacement, this practicality that it does not separate the essence of the corresponding technical solution are new The range of each embodiment technical solution of type.

Claims (10)

1. a kind of pipe gallery early tears sliding plate device open, it is characterised in that:Including multiple assembled panels, stent group, connector And walking mechanism;The assembled panel is connect with the stent group by the connector;The walking mechanism is mounted on described Stent group lower end;The stent group includes left socle, right support and middle stent, the left socle, the middle stent, the right branch Frame is laterally set successively.
2. pipe gallery according to claim 1 early tears sliding plate device open, it is characterised in that:There are two the stent groups More than, more than two stent group longitudinal arrangements.
3. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The assembled panel It is equipped with ribs.
4. pipe gallery according to claim 3 early tears sliding plate device open, it is characterised in that:The adjacent assembled panel On the ribs be bolted.
5. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The stent group packet Include upright bar, horizon bar and terminal pad;The upright bar is connected with the horizon bar by the terminal pad.
6. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The stent group with Adjustable base is set between the walking mechanism.
7. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The left socle and It is connected by silk braid between the middle stent, is connected between the middle stent and the right support by the silk braid.
8. pipe gallery according to claim 7 early tears sliding plate device open, it is characterised in that:The adjacent stent group Between connected by the silk braid.
9. pipe gallery according to claim 2 early tears sliding plate device open, it is characterised in that:The branch positioned at both ends Frame group is equipped with end segment diagonal brace.
10. pipe gallery according to claim 1 or 2 early tears sliding plate device open, it is characterised in that:The walking mechanism Universal wheel is braked for industry.
CN201721533293.5U 2017-11-16 2017-11-16 A kind of pipe gallery early tears sliding plate device open Active CN207538078U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721533293.5U CN207538078U (en) 2017-11-16 2017-11-16 A kind of pipe gallery early tears sliding plate device open

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721533293.5U CN207538078U (en) 2017-11-16 2017-11-16 A kind of pipe gallery early tears sliding plate device open

Publications (1)

Publication Number Publication Date
CN207538078U true CN207538078U (en) 2018-06-26

Family

ID=62613834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721533293.5U Active CN207538078U (en) 2017-11-16 2017-11-16 A kind of pipe gallery early tears sliding plate device open

Country Status (1)

Country Link
CN (1) CN207538078U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112458936A (en) * 2020-11-30 2021-03-09 中铁十六局集团地铁工程有限公司 Construction method for integrally translating box culvert full-hall support
CN112878362A (en) * 2021-01-07 2021-06-01 中国二十冶集团有限公司 Comprehensive pipe gallery slip form device and construction method
CN113089511A (en) * 2021-03-18 2021-07-09 湖北正鑫铝模科技有限公司 Water diversion hole supporting aluminum mold and assembling method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112458936A (en) * 2020-11-30 2021-03-09 中铁十六局集团地铁工程有限公司 Construction method for integrally translating box culvert full-hall support
CN112878362A (en) * 2021-01-07 2021-06-01 中国二十冶集团有限公司 Comprehensive pipe gallery slip form device and construction method
CN113089511A (en) * 2021-03-18 2021-07-09 湖北正鑫铝模科技有限公司 Water diversion hole supporting aluminum mold and assembling method

Similar Documents

Publication Publication Date Title
CN207538078U (en) A kind of pipe gallery early tears sliding plate device open
CN104806011B (en) Raft board post poured band formwork for placing
CN105401599A (en) Open trench tunnel main structure tall side wall unilateral vertical mold and construction process thereof
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN110374321A (en) A kind of assembled waffle beam superstructure gang form and construction method
CN204298742U (en) For the supporting and protection structure of Bridge High-pier construction
CN207920632U (en) Formwork jumbo for pipe gallery of constructing
CN203531923U (en) Moving framework for tunnel groove construction
CN202090932U (en) Universal template device for tunnel construction
CN109610509A (en) A kind of the adjustable die system and construction method of pipe gallery automatic control section
CN106150525A (en) A kind of rock anchorage beam construction trolley and construction method thereof
CN205840892U (en) Ditch mould bases is surveyed in self-propelled tunnel
CN209603182U (en) A kind of adjustable die system of pipe gallery automatic control section
CN208088804U (en) A kind of aerial device of interior decoration
CN207512790U (en) A kind of trapezoidal bottom plate rear pouring tape and special-shaped steel plate for sealing water anti-leakage structure
CN207583391U (en) One kind two serves as a contrast plug steel end mould
CN109356618A (en) A kind of simple integral movable type square type tunnel frame and its construction method
CN105113536A (en) Movable sidewall formwork erecting system for underground structure and construction method of system
CN206111212U (en) Rock -anchored beam construction trolley car
CN108150198A (en) For the formwork jumbo for pipe gallery of constructing
CN208594729U (en) A kind of scaffold for building convenient for assembled adjusting height
CN207795270U (en) A kind of portable cart
CN206707301U (en) Adjustable height reinforcing bar colligation frame
CN216198149U (en) Utility tunnel construction trolley
CN206110644U (en) A stencil assembly for clear water concrete construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant