CN207526101U - A kind of sliding formwork overlay film health preserving equipment - Google Patents
A kind of sliding formwork overlay film health preserving equipment Download PDFInfo
- Publication number
- CN207526101U CN207526101U CN201721468228.9U CN201721468228U CN207526101U CN 207526101 U CN207526101 U CN 207526101U CN 201721468228 U CN201721468228 U CN 201721468228U CN 207526101 U CN207526101 U CN 207526101U
- Authority
- CN
- China
- Prior art keywords
- inner template
- wall
- door frame
- overlay film
- exterior sheathing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model provides a kind of sliding formwork overlay film health preserving equipment, including door frame, lifting device for hoisting frame is housed on the door frame, exterior sheathing is arranged in the door frame, vertically sliding is equipped with inner template on the exterior sheathing inner wall, and exterior sheathing setting is stretched out in the inner template bottom end, and the inner template is equipped with plastic film, the door frame bottom end is arranged with fixing device, and the fixing device is connected on the outer wall of inner template.Exterior sheathing is symmetrically arranged in the door frame equipped with lifting device, inner template in sliding connection, plastic film is sticked on inner template inner wall on exterior sheathing inner wall.In this way, film can not only be pasted on the wall poured, moreover it is possible to reduce the resistance of hoisting frame, so as to reduce cost, facilitate construction.In addition, in order to avoid inner template is detached from door frame, the fixing device for fixing inner template is also equipped on door frame.
Description
Technical field
The utility model is related to the realm of building construction, more particularly to a kind of sliding formwork overlay film health preserving equipment.
Background technology
Sliding formwork is a kind of after fixed-size typified form is put up, and using lifting device, is Xiang Shanged while pouring
The construction method of traction.After casting concrete, in order to ensure that concrete can gradually harden under suitable temperature and humidity,
Ensure that the intensity of concrete wall is continuously increased, need to conserve the concrete poured.
At present, notification number is that the Chinese utility patent of CN104806063A discloses a kind of silo sliding formwork overlay film curing means
And construction method, the curing means include hoisting frame, hydraulic jack, supporting rod, combined steel formwork, hanger, the hanger
For " L " font, described hanger one end is hinged on using pivoting support in the hole of combined steel formwork back cord, the hanger other end
Plastic film on hanger and double-sided adhesive tape are laid on the wall of silo library by idler wheel, and the plastic film is bonded on the wall of silo library
Form the concrete curing space of overlay film closing.
Although this silo sliding formwork overlay film curing means and construction method can while sliding formwork using door frame below
Film-sticking tool pastes plastic film on concrete wall, is conserved;But in addition this method for adhering film is needed on door frame
Install film-sticking tool additional, the outer wall of the building of construction is bigger, and cost is higher.
Utility model content
The purpose of this utility model is to provide a kind of sliding formwork overlay film health preserving equipment, and it is thin that plastics are pasted on inner template inner wall
Film can not only complete the work of overlay film, and simple in structure while sliding formwork, of low cost.
The above-mentioned technical purpose of the utility model technical scheme is that:A kind of sliding formwork overlay film health
Device is equipped with the lifting device for hoisting frame including door frame, on the door frame, exterior sheathing is arranged in the door frame,
Vertically sliding is equipped with inner template on the exterior sheathing inner wall, and exterior sheathing setting is stretched out in the inner template bottom end, described
Inner template inner wall is equipped with plastic film, and the door frame bottom end is arranged with fixing device, and the fixing device is connected to internal model
On the outer wall of plate.
By using above-mentioned technical proposal, exterior sheathing is symmetrically arranged in the door frame equipped with lifting device, in exterior sheathing
The interior upper inner template of slip at wall connection, plastic film is sticked on inner template inner wall.In this way, in the gap between inner template
After having poured concrete, moving door frame drives exterior sheathing to move up, and inner template stays in origin-location, at the beginning for the treatment of the concrete in inner template
After step condensation, inner template is removed, plastic film is stayed on wall;Stick plastic film again in inner template, then by
Template is attached on the inner wall for the exterior sheathing being located above and is continuing with again.In this way, it can not only be pasted on the wall poured
Upper film, moreover it is possible to reduce the resistance of hoisting frame, so as to reduce cost, facilitate construction.In addition, in order to avoid inner template is detached from door
Frame is also equipped with the fixing device for fixing inner template on door frame.
Further, the door frame includes the montant that both sides are vertically arranged, and it is vertical that the fixing device includes montant bottom end
The sliding bar of setting, horizontal on the sliding bar to be equipped with fixed link, the fixed boom end is connected on the outer wall of inner template.
By using above-mentioned technical proposal, sliding bar in setting is slid below the montant of door frame, is set sliding boom end
Fixed link is put, inner template is resisted using fixed link;In addition, when pulling up door frame, sliding bar slides downwards with respect to door frame,
The inner template connected in fixed link and fixed link is avoided to block the door frame of rising.
Further, screw hole is horizontally opened on the sliding bar, the fixed link is threaded in screw hole.
By using above-mentioned technical proposal, the thickness of the wall of the concrete poured every time is different from, in order to make internal model
Plate can follow exterior sheathing to move together, adjust the distance between two inner templates, screw hole is horizontally opened on sliding bar, will be solid
Fixed pole is threaded in screw hole, in this way, staff can rotate fixed link, adjusts internal model Board position, and by changing door
Connecting component between frame and exterior sheathing can coordinate inner template to change position;In addition, the fixed link being threadedly coupled can also be adjusted
Inner template and between the walls active force, so as to which staff be facilitated to construct.
Further, the montant bottom end is vertically provided with slip hole, and the sliding bar is slidably connected at slip hole
In.
By using above-mentioned technical proposal, sliding bar sliding is connected to slip hole using the slip hole opened in montant
In, staff is facilitated to adjust fixed link position, in this way, after exterior sheathing moves up, fixed link position can be adjusted, ensures to fix
Bar can steadily resist inner template, avoid inner template and generate gap between the walls and influence pouring for wall.
Further, the center of the inner template outer wall is provided with downwards fixing groove vertically, the fixing groove penetrate through to
Inner template bottom, the fixed link are inserted in fixing groove.
By using above-mentioned technical proposal, fixing groove is provided with vertically downwards in the center outer wall of inner template outer wall, by fixation
Bar is inserted in fixing groove, is oriented to the sliding of fixed link in the vertical direction;It is and fixing groove is vertical from the center of inner template
Bottom is reached, in this way, door frame, during moving up, fixed link can gradually be moved up from inner template bottom end, until inner template
Center coordinates the sliding of exterior sheathing, balances the stress of inner template, ensures that inner template can be against on wall always.
Further, the C-shaped setting of the fixing groove, end rotation of the fixed link far from sliding bar are equipped with T-shaped block,
The T-shaped block is stuck in fixing groove.
By using above-mentioned technical proposal, in order to enable fixed link that inner template to be driven to move, fixing groove is set C-shaped
Slot is provided with T-shaped block in fixed boom end rotation, and T-shaped block is stuck in fixing groove, so as to block inner template, and rotates the T of setting
Shape block can avoid the fixed link of rotation that inner template is driven to shift.
Further, guide pad is vertically equipped on the exterior sheathing inner wall, matches on the inner template outer wall and runs jointly
There is perforation to the guide groove of inner template bottom.
By using above-mentioned technical proposal, guide pad is symmetrically arranged on exterior sheathing inner wall and on inner template outer wall and is led
To slot, on the one hand, can direction staff's alignment guide slot and guide pad installation inner template, on the other hand, can increase in
Frictional force between template and exterior sheathing avoids exterior sheathing that inner template is driven to move together.
Further, lifting slot is provided on the inner template outer wall, hanging ring is housed in the lifting slot.
By using above-mentioned technical proposal, inner template is reused in construction in order to facilitate staff, in inner template
Hanging ring is provided on outer wall, inner template directly can be hung to top by staff using boom hoisting;In addition, in order to avoid prominent
The hanging ring gone out influences the connection of inner template and exterior sheathing, and lifting slot is provided on the outer wall of inner template, by hanging ring mounted in lifting
In slot.
In conclusion the utility model has the advantages that:
1. by sliding the inner template of setting in exterior sheathing, reduce frictional force when lifting device pulls flood structure;
2. by the plastic film set in inner template, overlay film health is carried out to wall.
Description of the drawings
Fig. 1 is the overall structure diagram that a kind of sliding formwork of the utility model covers mould health preserving equipment;
Fig. 2 is the section view explosive view in A-A directions in Fig. 1;
Fig. 3 is the enlarged drawing of part B in Fig. 2;
Fig. 4 is the overall structure diagram of inner template.
In figure, 1, door frame;11st, lifting device;12nd, montant;2nd, exterior sheathing;21st, guide pad;3rd, inner template;31st, it is oriented to
Slot;32nd, fixing groove;33rd, slot is lifted by crane;331st, hanging ring;4th, plastic film;5th, slip hole;51st, sliding bar;52nd, fixed link;521、T
Shape block.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:A kind of sliding formwork overlay film health preserving equipment, as shown in Figure 1, including be in "ON" font setting door frame 1, in door
Workbench has been built around frame 1(It is not shown in figure), include vertical equipped with lifting device 11, lifting device 11 in door frame 1
The supporting rod and hydraulic jack of setting;The montant that door frame 1 includes horizontally disposed two cross bars and cross bar both ends are vertically arranged
12, the exterior sheathing 2 being mutually parallel is symmetrically connected between two montants 12, the building that exterior sheathing 2 is built as needed carries out
Equipped with inner template 3 on 2 inner wall of exterior sheathing, plastic film 4 is posted on 3 inner wall of inner template for selection.In this way, utilizing template
Plastic film 4 can be covered on wall, can not only accelerate pad pasting speed by casting concrete, moreover it is possible to reduce needed for maintenance
Cost.
In order to reduce the frictional force between template and concrete, so as to which lifting device 11 be facilitated to pull door frame 1, such as Fig. 1 and
Shown in Fig. 4, guide pad 21 is fixed on 2 inner wall of exterior sheathing, guide groove 31 is equipped with, and lead on 3 outer wall of inner template
It is vertically opened up to block 21 and guide groove 31.It is connected in exterior sheathing 2 in this way, inner template 3 can slide, and exterior sheathing 2
It is fixed on door frame 1, when pulling door frame 1, exterior sheathing 2 moves up, and inner template 3 is parked in initial position, in this way, passing through inner template 3
With the slide lines of exterior sheathing 2, avoid template and concrete is in direct contact sliding, can not only reduce frictional force, moreover it is possible to
Template is avoided to destroy wall construction in drawing process.In addition, guide pad 21 and guide groove 31 are set in dovetail shaped, so as to disappear
Except the gap before inner template 3 and exterior sheathing 2, so as to ensure that inner template 3 can be against on wall by exterior sheathing 2.
Be detached from exterior sheathing 2 in order to avoid inner template 3 is skidded off from the lower section of door frame 1, and influence the progress of construction, such as Fig. 2 and
Shown in Fig. 3, sliding bar 51 is connected with vertically downwards in the end of montant 12, fixed link is connected in the end horizontal of sliding bar 51
52, the fixing groove 32 of the C-shaped setting in section is provided with vertically downwards from 3 center of inner template on 3 outer wall of inner template, in fixation
End of the bar 52 far from sliding bar 51 is connected with T-shaped block 521, and T-shaped block 521 is stuck in fixing groove 32 and slides.In this way, pass through connection
Fixed link 52 in fixing groove 32 holds inner template 3, and the fixing groove 32 for only reaching center can be blocked by T-shaped block 521
Firmly, so as to which inner template 3 be avoided to slip away fixed link 52.Fixed link 52 is against in inner template 3, and center is moved to from 3 bottom end of inner template,
The exterior sheathing 2 abutted outside inner template 3 is coordinated to balance the stress of inner template 3 during this, inner template 3 is avoided and produces between the walls
Raw gap.
After T-shaped block 521 is moved to 3 center of inner template, in order to avoid the inner template 3 of 52 end of fixed link connection is blocked
Door frame 1 moves up, as shown in Fig. 2, being provided with slip hole 5 vertically in montant 12, sliding bar 51 is slidably connected in slip hole 5,
In this way, slide the sliding that the sliding bar 51 set can not only avoid inner template 3 from blocking door frame 1, moreover it is possible to according to the length of inner template 3
Degree adjusts the position of sliding bar 51, so as to facilitate the displacement of door frame 1.
After 3 use of inner template, inner template 3, as shown in Figures 2 and 3, T-shaped block are dismantled in order to facilitate staff
521 are rotatably connected on the width of 52 end of fixed link and T-shaped block 521 less than the width that fixing groove 32 is open;In sliding bar 51
End horizontal is provided with screw hole, and screw thread is equipped on 52 outer wall of fixed link, and fixed link 52 is rotatably connected on sliding bar 51
Bottom end.In this way, rotation T-shaped block 521 makes the length direction of T-shaped block 521 be parallel to the length direction of fixing groove 32, then turn fixation
T-shaped block 521 is pulled out fixing groove 32 by bar 52, can take out inner template 3.
After inner template 3 is taken, inner template 3 can be hung in order to facilitate staff to top, as shown in the figure, in inner template
Lifting slot 33 is provided on 3 outer walls, need to be only fixed on and hung using boom hoisting equipped with hanging ring 331, staff in slot 33 is lifted by crane
Ring 331 can hang inner template 3 to top;And the setting for lifting by crane slot 33 can avoid prominent hanging ring 331 from influencing inner template 3
Sliding with exterior sheathing 2 connects.
The above is only the preferred embodiment of the utility model, and the scope of protection of the utility model is not limited merely to
Above-described embodiment, all technical solutions belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to
Go out, for those skilled in the art, several improvement under the premise of the utility model principle is not departed from and
Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.
Claims (8)
1. a kind of sliding formwork overlay film health preserving equipment, including door frame(1), the door frame(1)It is upper to be equipped with for hoisting frame(1)Promotion
Device(11), the door frame(1)Inside it is arranged with exterior sheathing(2), it is characterised in that:The exterior sheathing(2)Between be bonded in it
Wall is vertically slid equipped with inner template(3), and the inner template(3)Exterior sheathing is stretched out in bottom end(2)Setting, the inner template
(3)Inner wall is equipped with plastic film(4), the door frame(1)Bottom end is arranged with fixing device, and the fixing device is connected to interior
Template(3)Outer wall on.
2. a kind of sliding formwork overlay film health preserving equipment according to claim 1, it is characterised in that:The door frame(1)Including both sides
The montant being vertically arranged(12), the fixing device include montant(12)The sliding bar that bottom end is clamped vertically(51), the slip
Bar(51)It is upper horizontal equipped with fixed link(52), the fixed link(52)End is connected to inner template(3)Outer wall on.
3. a kind of sliding formwork overlay film health preserving equipment according to claim 2, it is characterised in that:The sliding bar(51)Upper level
It is provided with screw hole, the fixed link(52)It is threaded in screw hole.
4. a kind of sliding formwork overlay film health preserving equipment according to claim 3, it is characterised in that:The montant(12)Bottom end is along perpendicular
Nogata is to being provided with slip hole(5), the sliding bar(51)It is slidably connected at slip hole(5)In.
5. a kind of sliding formwork overlay film health preserving equipment according to claim 4, it is characterised in that:The inner template(3)Outer wall
Center is provided with downwards fixing groove vertically(32), the fixing groove(32)It penetrates through to inner template(3)Bottom, the fixed link
(52)It is inserted in fixing groove(32)In.
6. a kind of sliding formwork overlay film health preserving equipment according to claim 5, it is characterised in that:The fixing groove(32)It is C-shaped
Setting, the fixed link(52)Far from sliding bar(51)End rotation be equipped with T-shaped block(521), the T-shaped block(521)It is stuck in
Fixing groove(32)In.
7. a kind of sliding formwork overlay film health preserving equipment according to claim 1, it is characterised in that:The exterior sheathing(2)On inner wall
Vertically it is equipped with guide pad(21), the inner template(3)Cooperation is provided with perforation to inner template on outer wall(3)The guiding of bottom
Slot(31).
8. a kind of sliding formwork overlay film health preserving equipment according to claim 1, it is characterised in that:The inner template(3)On outer wall
It is provided with lifting slot(33), the lifting slot(33)In be equipped with hanging ring(331).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721468228.9U CN207526101U (en) | 2017-11-06 | 2017-11-06 | A kind of sliding formwork overlay film health preserving equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721468228.9U CN207526101U (en) | 2017-11-06 | 2017-11-06 | A kind of sliding formwork overlay film health preserving equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207526101U true CN207526101U (en) | 2018-06-22 |
Family
ID=62572462
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721468228.9U Expired - Fee Related CN207526101U (en) | 2017-11-06 | 2017-11-06 | A kind of sliding formwork overlay film health preserving equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207526101U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560907A (en) * | 2018-06-26 | 2018-09-21 | 苏州中材建设有限公司 | Clinker warehouse cylinder slip form construction device |
CN108691413A (en) * | 2018-07-05 | 2018-10-23 | 中水电第十工程局(郑州)有限公司 | A kind of surge tower unilateral side reducing synovial membrane constructing device |
CN110821149A (en) * | 2018-08-08 | 2020-02-21 | 李宜君 | Mold taking device and mold taking method applied to house slip form forming device |
-
2017
- 2017-11-06 CN CN201721468228.9U patent/CN207526101U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560907A (en) * | 2018-06-26 | 2018-09-21 | 苏州中材建设有限公司 | Clinker warehouse cylinder slip form construction device |
CN108560907B (en) * | 2018-06-26 | 2024-03-26 | 苏州中材建设有限公司 | Clinker storehouse barrel slipform construction device |
CN108691413A (en) * | 2018-07-05 | 2018-10-23 | 中水电第十工程局(郑州)有限公司 | A kind of surge tower unilateral side reducing synovial membrane constructing device |
CN108691413B (en) * | 2018-07-05 | 2024-05-10 | 中电建十一局工程有限公司 | Single-side reducing sliding film construction device of pressure regulating tower |
CN110821149A (en) * | 2018-08-08 | 2020-02-21 | 李宜君 | Mold taking device and mold taking method applied to house slip form forming device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207526101U (en) | A kind of sliding formwork overlay film health preserving equipment | |
CN207130622U (en) | A kind of flower basket type anticollision barrier construction formwork | |
CN205936645U (en) | A full liquid die plate system for culvert is pour | |
CN206521108U (en) | A kind of concrete curing membrane rolls up unwinding device | |
CN208054796U (en) | A kind of cement block boom hoisting | |
CN104806063B (en) | Silo slip form covering film maintenance device and construction method | |
CN205935643U (en) | Outer wall is from climbing die carrier | |
CN204492173U (en) | Elevator shaft integral lifting template operation platform | |
CN108726358A (en) | A kind of towering concrete structure main reinforcement batch hanging apparatus and method | |
CN108222500A (en) | A kind of Core Walls Structure outrigger wall-attachment electric hydaulic climbing frame | |
CN208815562U (en) | A kind of capping beam rapid construction device | |
CN204236784U (en) | A kind of adjustable for height moving type security mooring gear | |
CN207276008U (en) | A kind of elevator counterweight | |
CN208907273U (en) | A kind of assembled architecture prefabricated component convenient for positioning lifting | |
CN207877181U (en) | A kind of automatic brick laying machine system | |
CN208532052U (en) | A kind of material lift device of the building safety with anti-collision effect | |
CN208057118U (en) | A kind of subway construction engineering construction vertical shaft | |
CN207277831U (en) | A kind of floor aluminum alloy pattern plate splices supporting structure | |
CN206180488U (en) | Cable pit moving die carrier | |
CN206233116U (en) | Construction moving platform car on the outside of a kind of bridge-collision-avoidance wall | |
CN220976227U (en) | Hoisting equipment for binding tubular piles | |
CN214658779U (en) | Building climbing equipment | |
CN221142692U (en) | Aqueduct pouring construction template | |
CN220080002U (en) | Piling device | |
CN218264923U (en) | Clear water self-compaction concrete form with location structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 300400 Liutan East, Beichen District, Tianjin Patentee after: Tianjin Jianggong City Construction Development Co., Ltd. Address before: 300400 Liutan East, Beichen District, Tianjin Patentee before: Tianjin Erjian Water & Electrical Installation Engineering Limited |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180622 Termination date: 20191106 |