CN207525777U - Prefabricated utility tunnel multidimension degree directional installation car - Google Patents
Prefabricated utility tunnel multidimension degree directional installation car Download PDFInfo
- Publication number
- CN207525777U CN207525777U CN201720937731.8U CN201720937731U CN207525777U CN 207525777 U CN207525777 U CN 207525777U CN 201720937731 U CN201720937731 U CN 201720937731U CN 207525777 U CN207525777 U CN 207525777U
- Authority
- CN
- China
- Prior art keywords
- chassis
- oil cylinder
- longitudinal
- pipe gallery
- dragging track
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009434 installation Methods 0.000 title claims abstract description 27
- 230000007246 mechanism Effects 0.000 claims abstract description 15
- 239000000758 substrate Substances 0.000 claims description 22
- 229910000831 Steel Inorganic materials 0.000 claims description 20
- 239000010959 steel Substances 0.000 claims description 20
- 239000003638 chemical reducing agent Substances 0.000 claims description 9
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 9
- 239000011324 bead Substances 0.000 claims description 3
- 239000003921 oil Substances 0.000 description 30
- 238000010276 construction Methods 0.000 description 9
- 239000000203 mixture Substances 0.000 description 8
- 238000000034 method Methods 0.000 description 7
- 238000010586 diagram Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 6
- 238000003032 molecular docking Methods 0.000 description 5
- 230000006835 compression Effects 0.000 description 3
- 238000007906 compression Methods 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 238000003466 welding Methods 0.000 description 3
- 239000002390 adhesive tape Substances 0.000 description 2
- 230000008901 benefit Effects 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000002457 bidirectional effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 210000000988 bone and bone Anatomy 0.000 description 1
- 230000003139 buffering effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 238000012954 risk control Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000007569 slipcasting Methods 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
- 239000010729 system oil Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model provides a prefabricated utility tunnel multidimension degree directional installation car, includes transaxle, steering axle, chassis, the system of transversely sliding, the system of vertically sliding, vertical lift system, front end hydro-cylinder, inside hydro-cylinder, counter weight and clamping mechanism, clamping mechanism welds on the chassis through two L shape shoulder arms, and clamping mechanism is connected by two pendulum axle hydro-cylinders, two guide arms, two flexible hydro-cylinders and grabs the mechanism of inserting and constitute, clamping mechanism goes up and down through setting up the pendulum axle hydro-cylinder control clamping mechanism on the shoulder arm to it carries out counterpoint clamp tightly to grab the mechanism by two flexible hydro-cylinders control.
Description
Technical field
The utility model is related to piping lane construction instrument, especially a kind of prefabricated pipe gallery various dimensions orientation installation vehicle.
Background technology
At present, with the continuous advantage of national policy, China's pipe gallery engineering construction has been enter into the outbreak period, various regions according to
The actual features of engineering consider that the factors such as cost, duration, environment are generally required using prefabricated pipe gallery technique.According to entering corridor
The type and quantity of pipeline, pipe gallery is mainly in the majority with three cabins at this stage, also has five cabins, six cabin structures individually, this causes
It is all increasing often to save prefabricated pipe gallery volume and weight, in order to ensure construction safety, generally requires in the construction process
The setting of foundation pit side thickeies temporary construction sidewalk, is installed section by section using large-scale crane or gantry crane.
Existing method technical disadvantages:
1st, the assembled docking of lift-on/lift-off type, generally require twice, three times more than, influenced by personnel's skilled operation degree, installation effect
Rate is relatively low.
2nd, it needs to put into a large amount of operating personnel, carries out the collaboration combined operation of not timing, external demand is kept at any time in foundation pit
Unimpeded contact, ensures the correct transmission of command signal, and practice of construction task difficulty is larger.
3rd, provide equipment interim erect-position place, according to gantry crane, it is also necessary to be laid with track, construction cost is caused to increase
Add, be unfavorable for the popularization of technique.
If the 4, foundation depth is larger, it is still necessary to consider in hoisting process, the safety and stability of internal support of foundation pit is protected, is unfavorable for
Risk control.
5th, lifting operation is larger by external environment influence, such as incoming road, place size, hoisting height, whether has obstacle
Object etc. is must take into consideration before operation.
Utility model content
The purpose of this utility model is that for these problems, a kind of prefabricated pipe gallery various dimensions orientation installation is developed
Vehicle, solution exist in the prior art that prefabricated pipe gallery installation effectiveness is low, environmental requirement is high, risk requirement is high and human input is big
Problem.
A kind of prefabricated pipe gallery various dimensions orientation installation vehicle, including drive axle, steeraxle, chassis, horizontal sliding system,
Straight skidding system, vertical lift system, front end oil cylinder, internal oil cylinder, counterweight and clamp system, the chassis front end installation
There is front end oil cylinder, vertical lift system, straight skidding system and horizontal sliding system from top to bottom carried successively on chassis,
Chassis both sides are equipped with clamp system, and middle part is equipped with oil cylinder inside multi-section in chassis, and tray bottom front and rear ends are axially symmetric
Steeraxle and drive axle are provided with, chassis back segment is provided with counterweight;The clamp system is welded on bottom by two L-shaped shoulder arms
On disk, the clamp system is made of two balance staff oil cylinders, two guide rods, two telescopic oil cylinder connection Zhua Cha mechanisms, the folder
Tight mechanism controls clamp system to lift by the balance staff oil cylinder being set on shoulder arm, and controls Zhua Cha mechanisms by two telescopic oil cylinders
Carry out contraposition clamping.
Moreover, the chassis by two lateral shaped steel as main joist, more crossbeams are as false keel, before the main joist
End is provided with front end oil cylinder pedestal, and main joist top is provided with false keel steel plate, is prefabricated with to install lateral cunning on the steel plate
The connection keyhole of shifting system;In the middle part of the main joist internal oil cylinder pedestal is also formed with positioned at two false keel both ends.
Moreover, the steeraxle includes front axle bracket, steering cylinder, spindle general assembly, steering link, axis pin, tire, it is described
Preceding bridge is installed in chassis forepart, and steering cylinder is fixed in the middle part of preceding bridge, and steering cylinder both ends are controlled by steering link and axis pin
Tire turns to.
Moreover, the drive axle includes rear axle, driving motor, bead seat, bearing block and sprocket wheel, the rear axle is fixedly mounted with
In chassis rear portion, driving motor is installed at the top of rear axle, rear pars basilaris pontis is provided with bearing block, driving is rotatably installed in bearing block
Axis, driving motor control tire, wheel hub to rotate by the sprocket wheel being set in drive shaft.
Moreover, the horizontal sliding system includes horizontal drive motor, transversal deceleration machine, lateral dragging track, assembled
Wheel and head substrate, the transverse direction dragging track is installed on the connection keyhole on false keel steel plate, on lateral dragging track
Driving transversal deceleration machine by horizontal drive motor, transversely dragging track moves to control fabricated vehicle wheel and head substrate.
Moreover, the straight skidding system is assembled by vertical drive motor, longitudinal deceleration machine, longitudinal dragging track, longitudinal direction
Formula wheel and longitudinal head substrate composition, the longitudinal direction dragging track is set in horizontal sliding system, on longitudinal dragging track
Longitudinal deceleration machine is driven by vertical drive motor longitudinal fabricated vehicle wheel and longitudinal head substrate to be controlled to slide along longitudinal direction
Track moves.
Moreover, the vertical lift system is by vertical lift driving motor, vertical lift speed reducer and vertical top substrate
Composition, the vertical lift driving motor are installed in straight skidding system, and vertical rise is driven by being vertically moved up or down driving motor
It drops speed reducer and then vertical top substrate is made to lift above and below.
The advantages of the utility model and economic effect are:
1st, the utility model orients the vertical lift system for installing vehicle, straight skidding system, transverse direction by using various dimensions
Sliding system by piping lane body construction and concrete cushion, realizes the multidimensional longitudinally, laterally, vertical of prefabricated pipe gallery
Degree orientation installment work, it is easy to operate, it can be completed using remote control, hand-operating device, mechanization installation effectiveness is high, no
Additional place is occupied, safe, with traditional lifting form ratio, economic effect is more preferably.
2nd, the utility model substitutes the steel strand tension in traditional technology, realizes pre- by using dedicated clamping device
Tensioner work between pipe gallery processed, compression factor accurately control, and improve construction quality.
3rd, the utility model personnel depaly is few, in same working face operation, links up smooth, reduction human cost.
Description of the drawings
Fig. 1 is the front view of the utility model;
Fig. 2 is the rearview of Fig. 1;
Fig. 3 is the structure diagram of the utility model drive axle;
Fig. 4 is the structure diagram of the utility model steeraxle;
Fig. 5 is the vertical view of Fig. 4;
Fig. 6 is the structure diagram on the utility model chassis;
Fig. 7 is the side view of the utility model horizontal sliding system;
Fig. 8 is the rearview of Fig. 7;
Fig. 9 is the utility model straight skidding system side view;
Figure 10 is the rearview of Fig. 9;
Figure 11 is the structure diagram of the utility model vertical lift system;
Figure 12 is the structure diagram of the utility model clamp system;
Figure 13 is the utility model pipe gallery tensioner operating diagram.
In figure:1-drive axle, 2-steeraxle, 3-chassis, 4-horizontal sliding, 5-straight skidding of system system 6-
7-front end of vertical lift system oil cylinder 8-inside oil cylinder 9-counterweight, 10-clamp system 11- prefabricated integrated pipes to be installed
Corridor 12- installation is complete prefabricated pipe galleries
Specific embodiment
For that can further appreciate that the contents, features and effects of the utility model, the following examples are hereby given, and coordinates attached drawing
Detailed description are as follows.It should be noted that the present embodiment is descriptive, it is not limited, it is impossible to thus limit this practicality
Novel protection domain.
A kind of prefabricated pipe gallery various dimensions orientation installation vehicle, including drive axle 1, steeraxle 2, chassis 3, horizontal sliding system
System 4, straight skidding system 5, vertical lift system 6, front end oil cylinder 7, internal oil cylinder 8, counterweight 9 and clamp system 10, it is described
Chassis front end is equipped with front end oil cylinder, from top to bottom carried successively on chassis vertical lift system, straight skidding system and
Horizontal sliding system, chassis both sides are equipped with clamp system, and middle part is equipped with oil cylinder inside multi-section in chassis, before tray bottom,
Both ends are axially symmetrically arranged with steeraxle and drive axle afterwards, and chassis back segment is provided with counterweight.
Moreover, the chassis by two lateral shaped steel as main joist, more crossbeams are as false keel, before the main joist
End is provided with front end oil cylinder pedestal, and main joist top is provided with false keel steel plate, is prefabricated with to install lateral cunning on the steel plate
The connection keyhole of shifting system;In the middle part of the main joist internal oil cylinder pedestal is also formed with positioned at two false keel both ends.
Moreover, the steeraxle includes front axle bracket, steering cylinder, spindle general assembly, steering link, axis pin, tire, it is described
Preceding bridge is installed in chassis forepart, and steering cylinder is fixed in the middle part of preceding bridge, and steering cylinder both ends are controlled by steering link and axis pin
Tire turns to.
Moreover, the drive axle includes rear axle, driving motor, bead seat, bearing block and sprocket wheel, the rear axle is fixedly mounted with
In chassis rear portion, driving motor is installed at the top of rear axle, rear pars basilaris pontis is provided with bearing block, driving is rotatably installed in bearing block
Axis, driving motor control tire, wheel hub to rotate by the sprocket wheel being set in drive shaft.
Moreover, the horizontal sliding system includes horizontal drive motor, transversal deceleration machine, lateral dragging track, assembled
Wheel and head substrate, the transverse direction dragging track is installed on the connection keyhole on false keel steel plate, on lateral dragging track
Driving transversal deceleration machine by horizontal drive motor, transversely dragging track moves to control fabricated vehicle wheel and head substrate.
Moreover, the straight skidding system is assembled by vertical drive motor, longitudinal deceleration machine, longitudinal dragging track, longitudinal direction
Formula wheel and longitudinal head substrate composition, the longitudinal direction dragging track is set in horizontal sliding system, on longitudinal dragging track
Longitudinal deceleration machine is driven by vertical drive motor longitudinal fabricated vehicle wheel and longitudinal head substrate to be controlled to slide along longitudinal direction
Track moves.
Moreover, the vertical lift system is by vertical lift driving motor, vertical lift speed reducer and vertical top substrate
Composition, the vertical lift driving motor are installed in straight skidding system, and vertical rise is driven by being vertically moved up or down driving motor
It drops speed reducer and then vertical top substrate is made to lift above and below.
Moreover, the clamp system is welded on by two L-shaped shoulder arms on chassis, the clamp system is by two balance staff oil
Cylinder, two guide rods, two telescopic oil cylinder connection Zhua Cha mechanisms compositions, the clamp system are oily by the balance staff being set on shoulder arm
Cylinder control clamp system lifting, and Zhua Cha mechanisms is controlled to carry out contraposition clamping by two telescopic oil cylinders.
Embodiment 1:
(1) wherein described drive axle 1 is by large-scale driving motor 1-1, wheel hub 1-2, bearing block 1-3, sprocket wheel 1-4, tire 1-
5 grade parts form, and the large size driving motor 1-1 power is at least up to 4KW, the preferred YVF2-131M1-6 of model.
(2) wherein described steeraxle 2 by front axle bracket 2-1, steering cylinder 2-2, spindle general assembly 2-3, steering link 2-4,
The parts such as axis pin 2-5, tire 2-6 form, it is desirable that all welding must be continuous, weld seam 6~8mm, the steering cylinder 2-2
Cylinder diameter preferred 63mm, piston rod 35mm form the bidirectional buffering band of left and right ± 50mm, and piston rod connection uses monaural spherical hinge,
Use is threadedly coupled between piston rod and hinge, and oil cylinder fundamental mode is engineering hydraulic cylinder SHG.
(3) wherein described chassis 3 is made of parts such as the steel plates, gusset, shaped steel of plurality of specifications, the chassis and top
Device, driving device are bolted by bolt hole, are specifically described, and chassis is by the shaped steel of two long 8.5m as main dragon
Bone 3-5 laterally coordinates the steel plate of plurality of specifications, gusset welding to form, weld seam is high by five 1.6m shaped steel as false keel 3-3
8~10mm is spent, it is continuous to weld, after the completion of welding, it is desirable that surface evenness≤5mm on longitudinal beam profiled bar;It is set in middle part false keel both sides
The pedestal 3-2 of four internal oil cylinders 8 is put, makes form, as shown in the figure;In the pedestal 3- of the front end of longeron setting front end oil cylinder 7
4, make form as shown in the figure;The pedestal of large-scale driving motor 1-1, horizontal drive motor 4-1 are set in shown position, reserve bolt
Hole site, quantity make as illustrated, meet subject to fixed requirement;It reserves on the false keel steel plate 3-1 of front end and well laterally slides
The connection keyhole of track 4-3.
(4) wherein described horizontal sliding system 4 is by horizontal drive motor 4-1, transversal deceleration machine 4-2, lateral dragging track
4-3, fabricated vehicle wheel 4-4 and head substrate 4-5 compositions, the horizontal sliding system 4 form ± 180mm movings range.
(5) wherein described straight skidding system 5 is by vertical drive motor 5-1, longitudinal deceleration machine 5-2, longitudinal dragging track
5-3, fabricated vehicle wheel 5-4 and head substrate 5-5 compositions, the straight skidding system 5 form 500mm movings range.
(6) wherein described vertical lift system 6 is by vertical lift driving motor 6-1, vertical lift speed reducer 6-2 and top
Substrate 6-3 is formed, and the vertical lift system 6 forms 620mm movings range.
(7) wherein described front end oil cylinder 7 can form the displacement distance of 1100mm.
(8) wherein described interior oil cylinder 8 can form the displacement distance of 300mm.
(9) according to every prefabricated pipe gallery weight of section, 9 size of required counterweight is obtained by conversion for wherein described counterweight 9,
The block or steel material of armored concrete making may be selected in the counterweight 9.
(10) wherein described clamp system 10 is welded on by two shoulder arm L-shaped on chassis 3, and the clamp system 10 is by two
A balance staff oil cylinder 10-1, two guide rod 10-2, two telescopic oil cylinder 10-3 connection Zhua Cha mechanisms compositions.The flexible model of clamp system
1260~1590mm is enclosed, meets piping lane docking and waterproof adhesive tape compression requirement.
The operating procedure of the utility model coordinates prefabricated pipe gallery assembly to describe:
(1) in the thin sand in one layer of concrete cushion upper berth, it is desirable that thickness≤5mm in order to control bed course flatness, is scraped using wood
Thick stick strikes off;Then along pipe gallery design centre line, by the prefabricated rough compact Layout of pipe gallery standard knot on bed course.
(2) regarding site space size and sidewalk situation, various dimensions orientation installation vehicle can voluntarily drive into pipe gallery or use
It is in place that QUY-200 crawler cranes enter foundation pit, in prefabricated pipe gallery standard knot, completes installation vehicle debugging efforts.
As shown in Figure 1, start various dimensions orientation installation vehicle using remote controler, in the effect of large-scale driving driving motor 1-1
Under, installation vehicle starts to advance, and tire 1-5 is travelled on completed pipe gallery, passes through front end oil cylinder 7 to be installed prefabricated
Pipe gallery standard knot when the head substrate 6-3 alignment criteria section centers of vertical lift system 6, stops advancing.
(3) it as shown in Figure 1, hydraulic power control front end oil cylinder 7 stretches out supporting leg, falls on pipe gallery bed course;Then liquid
The internal oil cylinder 8 of pressure power control stretches out rear support leg, falls on mounted pipe gallery bottom plate;Before and after control hydraulic cylinder adjustment
Height of landing leg, it is ensured that installation vehicle longitudinal direction vehicle body is consistent with the piping lane gradient.
(4) when the pipe gallery is double storehouses or more cabins, two various dimensions orientation installation vehicles can be used according to calculating
It is installed, controlled using Digiplex synchronous interaction or controls two installation vehicles respectively.
(5) as shown in Figure 1, first profit horizontal sliding system 4 adjusts prefabricated pipe gallery and is laterally aligned to, side is concordant;In profit
Alignment is moved up and down with vertical lift system 6, top surface, bottom surface are concordant;Finally prefabricated integrated pipe is carried out using straight skidding system 5
The assembled docking of corridor, the movement speed speed in three directions are adjustable;After concordant up and down, to prefabricated pipe gallery mark
Quasi- section carries out the assembled docking in longitudinal direction, observes the gap up and down between lateral tube section, stops longitudinal direction when gap reaches 50mm or so
Sliding system 5 accurately measures bell and spigot gap, and control errors are docked to the clamping of two seals adhesive tape in ± 1mm, continuation assembly,
Slide unit is stopped.This method can ensure that prefabricated pipe gallery disposably completes assembled docking.
As shown in Figure 12,13, using various dimensions orient clamp system 10 on installation vehicle to the two prefabricated pipe galleries of section into
Row tensioner, it is ensured that two seals item reaches design compression ratio example, ensures sealing effect, finally in the hole position reserved using perforation
Bolt fastens, and carries out the processes such as follow-up filleting slip casting and waterproof test.
Claims (7)
1. a kind of prefabricated pipe gallery various dimensions orientation installation vehicle, including drive axle, steeraxle, chassis, horizontal sliding system, is indulged
It is equipped with to sliding system, vertical lift system, front end oil cylinder, internal oil cylinder, counterweight and clamp system, the chassis front end
Front end oil cylinder from top to bottom carries vertical lift system, straight skidding system and horizontal sliding system, bottom on chassis successively
Disk both sides are equipped with clamp system, and middle part is equipped with oil cylinder inside multi-section in chassis, and tray bottom front and rear ends are axially and symmetrically set
Steeraxle and drive axle are equipped with, chassis back segment is provided with counterweight;It is characterized in that:The clamp system passes through two L-shaped shoulders
Arm is welded on chassis, and clamp system is made of balance staff oil cylinder, guide rod, two telescopic oil cylinders and Zhua Cha mechanisms;It is provided with
In the balance staff oil cylinder control clamp system lifting on shoulder arm, clamp system is controlled to be determined along guide rod by a telescopic oil cylinder
Position, another oil cylinder control Zhua Cha mechanisms are clamped.
2. a kind of prefabricated pipe gallery various dimensions orientation installation vehicle according to claim 1, it is characterised in that:The chassis
By two lateral shaped steel as main joist, more crossbeams are provided with front end oil cylinder pedestal as false keel, the main joist front end,
Main joist top is provided with false keel steel plate, and the connection keyhole for installing horizontal sliding system is prefabricated on the steel plate;It is described
In the middle part of main joist internal oil cylinder pedestal is also formed with positioned at two false keel both ends.
3. a kind of prefabricated pipe gallery various dimensions orientation installation vehicle according to claim 1, it is characterised in that:The steering
Bridge includes front axle bracket, steering cylinder, spindle general assembly, steering link, axis pin, tire, and the preceding bridge is installed in chassis forepart, preceding
Steering cylinder is fixed in the middle part of bridge, steering cylinder both ends control tire to turn to by steering link and axis pin.
4. a kind of prefabricated pipe gallery various dimensions orientation installation vehicle according to claim 1, it is characterised in that:The driving
Bridge includes rear axle, driving motor, bead seat, bearing block and sprocket wheel, and the rear axle is installed in chassis rear portion, pacifies at the top of rear axle
Equipped with driving motor, rear pars basilaris pontis is provided with bearing block, drive shaft is rotatably installed in bearing block, driving motor is by being set to
Sprocket wheel control tire in drive shaft, wheel hub rotation.
5. a kind of prefabricated pipe gallery various dimensions orientation installation vehicle according to claim 2, it is characterised in that:The transverse direction
Sliding system includes horizontal drive motor, transversal deceleration machine, lateral dragging track, fabricated vehicle wheel and head substrate, the horizontal stroke
On the connection keyhole being installed on false keel steel plate to dragging track, horizontal stroke is driven by horizontal drive motor on lateral dragging track
To speed reducer and then control the transversely dragging track movement of fabricated vehicle wheel and head substrate.
6. a kind of prefabricated pipe gallery various dimensions orientation installation vehicle according to claim 1, it is characterised in that:The longitudinal direction
Sliding system is by vertical drive motor, longitudinal deceleration machine, longitudinal dragging track, longitudinal fabricated vehicle wheel and longitudinal head substrate group
Into the longitudinal direction dragging track is set in horizontal sliding system, is driven and indulged by vertical drive motor on longitudinal dragging track
To speed reducer and then control longitudinal fabricated vehicle wheel and the dragging track movement along longitudinal direction of longitudinal head substrate.
7. a kind of prefabricated pipe gallery various dimensions orientation installation vehicle according to claim 1, it is characterised in that:It is described vertical
Jacking system is made of vertical lift driving motor, vertical lift speed reducer and vertical top substrate, the vertical lift driving
Motor is installed in straight skidding system, vertical lift speed reducer is driven to make vertical top by being vertically moved up or down driving motor
Substrate lifts above and below.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720937731.8U CN207525777U (en) | 2017-07-31 | 2017-07-31 | Prefabricated utility tunnel multidimension degree directional installation car |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720937731.8U CN207525777U (en) | 2017-07-31 | 2017-07-31 | Prefabricated utility tunnel multidimension degree directional installation car |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207525777U true CN207525777U (en) | 2018-06-22 |
Family
ID=62576038
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720937731.8U Active CN207525777U (en) | 2017-07-31 | 2017-07-31 | Prefabricated utility tunnel multidimension degree directional installation car |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207525777U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109295999A (en) * | 2018-10-10 | 2019-02-01 | 中铁工程机械研究设计院有限公司 | Prefabricated assembled pipe gallery fitting machine and its construction method |
CN109811797A (en) * | 2019-04-04 | 2019-05-28 | 安徽精工电缆桥架有限公司 | A kind of rectangular piping lane support construction and its operating method convenient for adjusting |
CN109928160A (en) * | 2019-04-11 | 2019-06-25 | 中国建筑土木建设有限公司 | Large-tonnage pipe gallery transporting and erecting all-in-one machine and using method |
CN111254974A (en) * | 2020-01-03 | 2020-06-09 | 中铁工程机械研究设计院有限公司 | Floor transportation and installation method in pipe gallery construction |
CN111270704A (en) * | 2020-01-03 | 2020-06-12 | 中铁工程机械研究设计院有限公司 | Adjusting mechanism of mounting vehicle |
CN111287775A (en) * | 2020-01-03 | 2020-06-16 | 中铁工程机械研究设计院有限公司 | Integrated installation vehicle for tunnel construction |
-
2017
- 2017-07-31 CN CN201720937731.8U patent/CN207525777U/en active Active
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109295999A (en) * | 2018-10-10 | 2019-02-01 | 中铁工程机械研究设计院有限公司 | Prefabricated assembled pipe gallery fitting machine and its construction method |
CN109295999B (en) * | 2018-10-10 | 2024-05-28 | 中铁科工集团装备工程有限公司 | Prefabricated assembled comprehensive pipe rack mounting machine and construction method thereof |
CN109811797A (en) * | 2019-04-04 | 2019-05-28 | 安徽精工电缆桥架有限公司 | A kind of rectangular piping lane support construction and its operating method convenient for adjusting |
CN109928160A (en) * | 2019-04-11 | 2019-06-25 | 中国建筑土木建设有限公司 | Large-tonnage pipe gallery transporting and erecting all-in-one machine and using method |
CN109928160B (en) * | 2019-04-11 | 2024-05-24 | 中国建筑土木建设有限公司 | Large-tonnage pipe gallery and transportation frame integrated machine and use method |
CN111254974A (en) * | 2020-01-03 | 2020-06-09 | 中铁工程机械研究设计院有限公司 | Floor transportation and installation method in pipe gallery construction |
CN111270704A (en) * | 2020-01-03 | 2020-06-12 | 中铁工程机械研究设计院有限公司 | Adjusting mechanism of mounting vehicle |
CN111287775A (en) * | 2020-01-03 | 2020-06-16 | 中铁工程机械研究设计院有限公司 | Integrated installation vehicle for tunnel construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207525777U (en) | Prefabricated utility tunnel multidimension degree directional installation car | |
CN104234079B (en) | A kind of subway station Y type cast steel combines steel pipe column construction method | |
CN202899040U (en) | Crossing tunnel box girder transporting and mounting all-in-one machine | |
CN103123016B (en) | Construction method for laying gas pipelines along bridge | |
CN101974913A (en) | Parallel construction method of bridge deepwater foundation bored pile and cofferdam | |
CN106917360A (en) | Lift leg formula frame plate machine and its frame plate method | |
CN101736703A (en) | 3000t special bridge girder erection machine for integrally erecting 120m-span double-layer four-line steel beam bridge for highway and railway | |
WO2023279741A1 (en) | New-energy rail transport device having double travelling systems, and use method | |
CN205591131U (en) | Whole superelevation of multispan case roof beam is jacking construction system in turn | |
CN109235291A (en) | Railroad bridge changes girder system system, packaging technology and changes beam process | |
CN204960871U (en) | Ground installation device of preventer group | |
CN201883104U (en) | Trolley device for mounting steelmaking converter backing ring and converter housing | |
CN101967798B (en) | Highway double-guide-beam bridge erecting machine and turning method | |
CN108643941B (en) | Gantry type arch installs trolley | |
CN100567134C (en) | Double-track four-crane conveyor | |
CN103806374B (en) | The overall track erection supplying system of assembly type steel bridge on highway and erection push technique | |
CN105839548B (en) | Section assembling box beam erection construction technology based on down-type bridge-erecting machine | |
CN108004930A (en) | The construction method of vertical shift bowstring arch bridge | |
CN207919265U (en) | Suitable for covering rail plate-type ballastless track plate paver on steel truss girder bridge | |
CN207267963U (en) | A kind of mobile stent of servicing bridges bridge floor edge of a wing bottom surface Pipe installing | |
CN206737521U (en) | Multi-storied garage with steel structure | |
CN202325303U (en) | Front hydraulic energy storage workover rig | |
CN206033160U (en) | Bank ship CNG loading and unloading gas bizhong meets butt joint system of valve group usefulness soon | |
CN213269911U (en) | Multifunctional two-lining trolley construction equipment for long and wide tunnel | |
CN106978929A (en) | The steel structures coating of the multi-storied garage of parallelization Transport Vehicle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |