CN207523885U - Ships and light boats mooring trial test workbench - Google Patents

Ships and light boats mooring trial test workbench Download PDF

Info

Publication number
CN207523885U
CN207523885U CN201721518759.4U CN201721518759U CN207523885U CN 207523885 U CN207523885 U CN 207523885U CN 201721518759 U CN201721518759 U CN 201721518759U CN 207523885 U CN207523885 U CN 207523885U
Authority
CN
China
Prior art keywords
ships
main frame
light boats
trial test
suspension arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721518759.4U
Other languages
Chinese (zh)
Inventor
冯诚普
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Xingye Boat Co Ltd
Original Assignee
Jiangsu Xingye Boat Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Xingye Boat Co Ltd filed Critical Jiangsu Xingye Boat Co Ltd
Priority to CN201721518759.4U priority Critical patent/CN207523885U/en
Application granted granted Critical
Publication of CN207523885U publication Critical patent/CN207523885U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forklifts And Lifting Vehicles (AREA)

Abstract

Ships and light boats mooring trial test workbench provided by the utility model includes being fixed on the fixed column on harbour bank, suspension arm, main frame, two columns, lifting platform and the buffer stopper to buffer ships and light boats shock.One end of suspension arm is sheathed on fixed column, and the other end is bent towards harbour side wall.The other end of suspension arm is fixed in the top surface of main frame, and the first side of main frame is resisted against harbour side wall.Two columns are fixedly installed on the top surface of main frame and are adjacent to second side respectively, and each column vertically has multiple location holes.Lifting platform includes two locating sleeves and the falsework being fixedly installed between two locating sleeves, each locating sleeve has the locking part to coordinate with location hole, locating sleeve can be sheathed on column up or down, and falsework has the mounting portion to install test equipment.Buffer stopper is set in the second side of main frame.The working efficiency of mooring trial test can be promoted by the utility model, reduces testing cost.

Description

Ships and light boats mooring trial test workbench
Technical field
The utility model is related to ships and light boats testing field, more particularly to a kind of ships and light boats mooring trial test workbench.
Background technology
Mooring trial test refers to tie all experiments done when being docked in harbour after launching a ship, including compartment test and wheel Integralities and the functional trials such as machine, host, mechanical equipment, electrical, piping.
In existing ships and light boats mooring trial test, since harbour is generally fixed concreting, cushion pad and all kinds of biographies The test equipments such as sensor can only be fixed on a certain fixed position of harbour, and due to ships and light boats size and the difference of water level height, it surveys Examination often directly can not be carried out effectively, it is necessary to the position of test equipment be adjusted repeatedly, this greatly affected mooring examination The efficiency tested.
Invention content
For above-mentioned technical problem, the utility model provides a kind of position adjustable and easy to operate ships and light boats mooring trial test work Make platform.
The ships and light boats mooring trial test workbench of the utility model includes being fixed on the fixed column on harbour bank, suspension arm, main frame Frame, two columns, lifting platform and the buffer stopper to buffer ships and light boats shock.One end of suspension arm is sheathed on fixed column, suspension arm The other end towards harbour side wall bend.Main frame has top surface, first side and second side, and top surface is located at what is be oppositely arranged Between first side and second side, the other end of suspension arm is fixed in the top surface of main frame, the first side of main frame against In harbour side wall.Two columns are fixedly installed on the top surface of main frame and are adjacent to second side respectively, and each column is along vertically Direction has multiple location holes.Lifting platform includes two locating sleeves corresponding with two columns and is fixedly installed on two Falsework between locating sleeve, each locating sleeve have the locking part to coordinate with location hole, two locating sleeves point It can not be sheathed on up or down on two columns, falsework has the mounting portion to install test equipment.Buffer stopper is set In in the second side of main frame.
Preferably, ships and light boats mooring trial test workbench further includes cushion block, cushion block is set between suspension arm and harbour bank, and Cushion block is between fixed column and harbour side wall.Further, in the vertical direction, the distance between suspension arm and harbour bank Equal to the height of cushion block.
Preferably, suspension arm is welded and fixed with main frame.
Preferably, two columns are respectively metal circular tube.Further, two columns, which are respectively welded, is fixed on main frame On.
Preferably, buffer stopper is removably hung on main frame.
Preferably, locking part includes locking hole corresponding with location hole and the fixation to be arranged in locking hole and location hole Pin.
Preferably, ships and light boats mooring trial test workbench further includes lift-pull handle, lift-pull handle is fixedly installed on the top of lifting platform Portion.
Compared with prior art, the connection that the ships and light boats mooring trial test workbench of the utility model passes through suspension arm and fixed column Preliminary installation can be completed, convenient for mostly being installed and being debugged, while the design of lifting platform is so that the work of test equipment It is highly adjustable.Therefore, the working efficiency of mooring trial test can be promoted well by the utility model, reduce the survey of mooring trial test Try cost.
Description of the drawings
Fig. 1 is the side schematic view of the ships and light boats mooring trial test workbench of one embodiment of the utility model.
Fig. 2 is the front schematic view of the ships and light boats mooring trial test workbench part of one embodiment of the utility model.
Specific embodiment
To make have further understanding to the purpose of this utility model, construction, feature and its function, hereby coordinate embodiment Detailed description are as follows.
Incorporated by reference to referring to Fig. 1 and Fig. 2, Fig. 1 is the side of the ships and light boats mooring trial test workbench 100 of one embodiment of the utility model Face schematic diagram, Fig. 2 are the front schematic view of 100 part of ships and light boats mooring trial test workbench of one embodiment of the utility model.Ships and light boats Mooring trial test workbench 100 includes being fixed on the fixed column 1 on harbour bank 101, suspension arm 2,3, two columns 4 of main frame, rise Drop platform 5 and the buffer stopper 6 to buffer ships and light boats shock.
One end 21 of suspension arm 2 is sheathed on fixed column 1, and the other end 22 of suspension arm 2 is bent towards harbour side wall 102.
Main frame 3 has top surface 30, first side 31 and second side 32, and top surface 30 is located at the first side being oppositely arranged Between 31 and second side 32, the other end 22 of suspension arm 2, the first side 21 of main frame 3 are fixed in the top surface 30 of main frame 3 It is resisted against harbour side wall 102.In practical applications, suspension arm 2 is welded and fixed with main frame 3.
Two columns 4 are fixedly installed on the top surface 30 of main frame 3 and are adjacent to second side 32 respectively, each 4 edge of column Vertical direction G has multiple location holes 41.
Lifting platform 5 includes and two columns, 4 corresponding two locating sleeves 51 and is fixedly installed on two positioning sleeves Falsework 52 between pipe 51, each locating sleeve 51 have the locking part 53 to coordinate with location hole 41, two positioning sleeves Pipe 51 can be sheathed on two columns 4 up or down respectively, and falsework 52 has the mounting portion to install test equipment 103 54.In practical applications, two columns 4 are respectively metal circular tube.Two columns 4, which can be respectively welded, to be fixed on main frame 3. In one embodiment, locking part 53 includes locking hole corresponding with location hole and the fixation to be arranged in locking hole and location hole Pin.
Buffer stopper 6 is set in the second side 32 of main frame 3.In practical applications, buffer stopper 6 is removably hung on On main frame 3.
In one embodiment, ships and light boats mooring trial test workbench 100 further includes cushion block 7, and cushion block 7 is set to suspension arm 2 and code Between head bank 101, and cushion block 7 is between fixed column 1 and harbour side wall 102.Preferably, on vertical direction G, suspension arm The distance between 2 and harbour bank 101 are equal to the height of cushion block 7.Can suspension arm be adjusted by the cushion block 7 of different height in this way 2 height further adjusts the height of the buffer stopper 6 being set on main frame 3 and lifting platform 5 versatile and flexiblely.
In one embodiment, ships and light boats mooring trial test workbench 100 further includes lift-pull handle 8, and lift-pull handle 8 is fixedly installed on The top of lifting platform 5, to facilitate adjustment and handling lifting platform 5.
Preliminary peace can be completed by the connection of suspension arm and fixed column in the ships and light boats mooring trial test workbench of the utility model Dress, convenient for mostly being installed and being debugged, while the design of lifting platform is so that the working depth of test equipment is adjustable.Therefore, The working efficiency of mooring trial test can be promoted well by the utility model, reduce the testing cost of mooring trial test.
The utility model is described by above-mentioned related embodiment, however above-described embodiment is only to implement the utility model Example.It must be noted that the embodiment disclosed is not limiting as the scope of the utility model.On the contrary, not departing from this That is made in the spirit and scope of utility model changes and retouches, and belongs to the scope of patent protection of the utility model.

Claims (9)

1. a kind of ships and light boats mooring trial test workbench, it is characterised in that including:
It is fixed on the fixed column on harbour bank;
Suspension arm, one end of the suspension arm are sheathed on the fixed column, and the other end of the suspension arm is bent towards harbour side wall;
Main frame, the main frame have top surface, first side and second side, which is located at the first side being oppositely arranged Between the second side, the other end of the suspension arm is fixed in the top surface of the main frame, the first side of the main frame against In harbour side wall;
Two columns, two columns are fixedly installed on the top surface of the main frame and are adjacent to the second side, Mei Geli respectively Column vertically has multiple location holes;
Lifting platform, the lifting platform include two locating sleeves corresponding with two columns and are fixedly installed on this two calmly Falsework between the casing of position, each locating sleeve have the locking part to coordinate with location hole, two locating sleeves point It can not be sheathed on up or down on two columns, which has the mounting portion to install test equipment;And
To buffer the buffer stopper of ships and light boats shock, which is set in the second side of the main frame.
2. ships and light boats mooring trial test workbench as described in claim 1, it is characterised in that further include cushion block, which is set to this Between suspension arm and harbour bank, and the cushion block is located between the fixed column and harbour side wall.
3. ships and light boats mooring trial test workbench as claimed in claim 2, which is characterized in that in the vertical direction, the suspension arm with The distance between harbour bank is equal to the height of the cushion block.
4. ships and light boats mooring trial test workbench as described in claim 1, which is characterized in that the suspension arm and main frame welding are solid It is fixed.
5. ships and light boats mooring trial test workbench as described in claim 1, which is characterized in that two columns are respectively round metal Pipe.
6. ships and light boats mooring trial test workbench as claimed in claim 5, which is characterized in that two columns, which are respectively welded, to be fixed on On the main frame.
7. ships and light boats mooring trial test workbench as described in claim 1, which is characterized in that the buffer stopper removably hang on this On main frame.
8. ships and light boats mooring trial test workbench as described in claim 1, which is characterized in that the locking part includes corresponding with location hole Locking hole and fixed pin to be arranged in the locking hole and location hole.
9. ships and light boats mooring trial test workbench as described in claim 1, it is characterised in that further include lift-pull handle, the lift-pull handle It is fixedly installed on the top of the lifting platform.
CN201721518759.4U 2017-11-13 2017-11-13 Ships and light boats mooring trial test workbench Active CN207523885U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721518759.4U CN207523885U (en) 2017-11-13 2017-11-13 Ships and light boats mooring trial test workbench

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721518759.4U CN207523885U (en) 2017-11-13 2017-11-13 Ships and light boats mooring trial test workbench

Publications (1)

Publication Number Publication Date
CN207523885U true CN207523885U (en) 2018-06-22

Family

ID=62582386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721518759.4U Active CN207523885U (en) 2017-11-13 2017-11-13 Ships and light boats mooring trial test workbench

Country Status (1)

Country Link
CN (1) CN207523885U (en)

Similar Documents

Publication Publication Date Title
CN101726449B (en) Non-destructive test equipment
CN105588698A (en) Seabed pipeline simulation impact test system
CN104554628A (en) Observation bracket for acoustic Doppler current profiler
JP2015021320A (en) Gps antenna device for construction machinery
CN204098090U (en) The displacement observation device of pile body is protected in a kind of static loading test
CN106891126B (en) A kind of positioning device of elevator lower beam casing multi-angle welding
CN207523885U (en) Ships and light boats mooring trial test workbench
CN205619882U (en) Header board crossbeam automatic checkout device
CN103267515A (en) Alignment device for ship staff gauge number assembling work
CN103693175B (en) A kind of anticollision device, collision-prevention device being applied to boats and ships protection and be equipped with the boats and ships of this anticollision device, collision-prevention device
CN203976268U (en) Leg structure and there is the construction machinery and equipment of this leg structure
CN205021189U (en) Angle steel drilling machine
KR20150025134A (en) Load testing apparatus for lifting lug
CN107031789B (en) The cross spacing method of hatch board
CN110043772B (en) Four-point leveling system and method for underwater landing platform
CN209841058U (en) Electric field check out test set under water
KR20140062985A (en) Tubular storage stanchion for drilling unit
CN207466902U (en) A kind of adjustable suspended type ultra-short baseline energy converter erecting device
CN104003296B (en) The aerial counterpart bracket of a kind of removable large diameter pipeline
CN203780778U (en) Underwater detector bracket
CN203375120U (en) Fixing device for measuring apparatus
CN204421897U (en) A kind of building vertical column testing apparatus for verticality
CN110824580A (en) Model geophysical prospecting test device between inclined hole holes
CN201573763U (en) Support tool for embarkation and connection of dock
CN104359469A (en) Suspension wire device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant