CN207419519U - 一种排桩支护与扶臂式挡墙结合的结构体系 - Google Patents
一种排桩支护与扶臂式挡墙结合的结构体系 Download PDFInfo
- Publication number
- CN207419519U CN207419519U CN201721522521.9U CN201721522521U CN207419519U CN 207419519 U CN207419519 U CN 207419519U CN 201721522521 U CN201721522521 U CN 201721522521U CN 207419519 U CN207419519 U CN 207419519U
- Authority
- CN
- China
- Prior art keywords
- barricade
- arm
- helping
- support pile
- structural system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
本实用新型公开了一种排桩支护与扶臂式挡墙结合的结构体系,通过在支护排桩顶部设置扶臂挡墙,排桩与扶臂挡墙相结合从而确保边坡的稳定性及美观性;施工排桩支护体系;破除排桩桩头,绑扎冠梁钢筋,浇筑冠梁;开挖坑内土方,施工地下室主体结构;待地下室结构施工完毕后,基坑周边回土至冠梁顶面;绑扎扶臂挡墙钢筋,利用冠梁上部预留钢筋,让排桩与扶臂挡墙结合形成一个整体,浇筑扶臂挡墙;待达到强度后继续回填土方至设计标高。本实用新型解决了在地形起伏比较大的区域需要进行基坑开挖和边坡支护的工程,所提供的排桩支护与扶臂挡墙结合的结构体系,通过在桩顶设置扶臂挡墙,解决了以往传统单一结构体系的不足及缺陷。
Description
技术领域
本实用新型涉及建筑工程技术领域,具体而言,尤其涉及一种排桩支护与扶臂式挡墙结合的结构体系。
背景技术
随着我国经济的飞速发展,城市化进程的步伐加快,人们对居住环境的不断升级,及城市用地的大量减少,建筑工程项目在城市每个角落遍地开花,从城市中心向周边郊区发展,依山傍水的住宅也越来越多,因此边坡支护也显得尤为重要。再者地下空间的开发利用迅猛发展,基坑工程越来越普遍。在此复杂地形区域,结构设计正负零差距较大,有时需向下开挖,有时则需向上回填,因此需将基坑支护设计和边坡挡墙设计相结合显得尤为重要。传统设计情况存在以下两点弊端:①、单一采用排桩支护,后期需接桩,施工难度大,且与后期景观设计难以衔接;②、单一采用扶臂挡墙,需施工空间较大,且挡墙受力较大,不利于结构安全。如何解决在高差起伏较大的建筑场地,合理的考虑支护设计及挡墙设计是工程安全性的保证,是项目协调性与美观性的制约因素。
实用新型内容
实用新型目的:本实用新型针对高差起伏较大地形环境下,传统单一的支护结构或挡墙结构体系存在不足,提出了一种排桩支护与扶臂式挡墙结合的结构体系,解决了传统单一设计的不足。
一种排桩支护与扶臂式挡墙结合的结构体系,包括:单排支护桩结合扶臂式挡墙的结构体系与双排支护桩结合扶臂式挡墙的结构体系,单排支护桩结合扶臂挡墙的结构体系,包括支护桩1,所述支护桩1的上端与圈梁2连接;圈梁2的上部分别为后期回填土13及扶壁式挡墙11,圈梁2与扶壁挡墙11通过预留钢筋3连接形成整体;所述扶壁挡墙11上设置泄水孔12;支护桩1与结构外墙7之间为基坑回填土9,支护桩1与基础底板5之间为设置的基础换撑板6;基础底板5下部为基础垫层4,上部为结构顶板8两者通过结构外墙7连接。
对于双排支护桩结合扶臂式挡墙的结构体系,在单排支护桩结合扶臂式挡墙的结构体系的基础上,再增设一个支护桩1;两个支护桩1之间在圈梁2之间通过拉结梁板15联接。
有益效果:与现有技术相比,本实用新型提供的排桩支护与扶臂挡墙结合的结构体系,通过在桩顶设置扶臂挡墙,解决了以往传统单一结构体系的不足及缺陷。此结构不仅简单易操作,而且还具有节省工期及美观性。
附图说明
图1是单排支护桩结合扶臂式挡墙的结构体系示意图;
图2是双排支护桩结合扶臂式挡墙的结构体系示意图;
图中:1、支护桩;2、圈梁;3、预留钢筋;4、基础垫层;5、基础底板;6、基础换撑板;7、结构外墙;8、结构顶板;9、基坑回填土;10、场地整平标高;11、扶臂式挡墙;12、泄水孔;13、后期回填土;14、最终设计标高;15、拉结梁板。
具体实施方式
下面结合具体实施例,进一步详细的阐明本实用新型,应理解这些实施例仅用于说明本实用新型而不用于限制本实用新型的范围,在阅读了本实用新型之后,本领域技术人员对本实用新型的各种等价形式的修改均落于本申请所附权利要求所限定的范围。
如图1及图2所示,本实用新型提供了一种排桩支护结构与扶臂式挡墙相结合的结构体系,其中图1是单排支护桩结合扶臂式挡墙的结构体系,包括支护桩1,所述支护桩1的上端与圈梁2连接;圈梁2的上部分别为后期回填土13及扶壁式挡墙11,圈梁2与扶壁式挡墙11通过预留钢筋3连接形成整体;所述扶壁挡墙11上设置泄水孔12;支护桩1与结构外墙7之间为基坑回填土9,支护桩1与基础底板5之间为设置的基础换撑板6;基础底板5下部为基础垫层4,上部为结构顶板8两者通过结构外墙7连接。
对于双排支护桩结合扶臂式挡墙的结构体系,如图2;再增设一个支护桩1;两个支护桩1之间在圈梁2之间通过拉结梁板15联接。
本实用新型的这种将排桩支护与扶臂式挡墙相结合的结构体系可以解决传统设计形式下单一结构体系存在的不足及缺陷等问题。
具体实施步骤如下:现场地整平至标高10,施工支护桩1,待支护结构达到设计强度后,卸土破除围护桩桩头,绑扎冠梁2钢筋(或冠梁2及拉结梁板15钢筋),浇筑冠梁2;开挖坑内土方,按结构设计要求施工基础垫层4及基础底板5,并设置基础换撑板6;继续向上施工地下室结构外墙7及结构顶板8;待地下室外墙7及顶板8达到设计强度后,进行基坑回填9至现自然地面标高10,绑扎扶臂挡墙11钢筋,与预留钢筋3焊接形成整体,并设置泄水孔12,浇筑扶臂式挡墙11;待扶臂式挡墙达到强度后,进行墙后土体回填至最终设计标高14。
Claims (1)
1.一种排桩支护与扶臂式挡墙结合的结构体系,其特征在于:包括单排支护桩结合扶臂挡墙的结构体系与双排支护桩结合扶臂挡墙的结构体系,其中单排支护桩结合扶臂挡墙的结构体系包括支护桩(1),所述支护桩(1)的上端与圈梁(2)连接;圈梁(2)的上部分别为后期回填土(13)及扶壁挡墙(11),圈梁(2)与扶壁挡墙(11)通过预留钢筋(3)连接形成整体;所述扶壁挡墙(11)上设置泄水孔(12);支护桩(1)与结构外墙(7)之间为基坑回填土(9),支护桩(1)与基础底板(5)之间为设置的基础换撑板(6);基础底板(5)下部为基础垫层(4),上部为结构顶板(8)两者通过结构外墙(7)连接;
双排支护桩结合扶臂挡墙的结构体系,在单排支护桩结合扶臂挡墙的结构体系的基础上再增设一个支护桩(1);两个支护桩(1)之间在圈梁(2)之间通过拉结梁板(15)联接。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721522521.9U CN207419519U (zh) | 2017-11-15 | 2017-11-15 | 一种排桩支护与扶臂式挡墙结合的结构体系 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721522521.9U CN207419519U (zh) | 2017-11-15 | 2017-11-15 | 一种排桩支护与扶臂式挡墙结合的结构体系 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207419519U true CN207419519U (zh) | 2018-05-29 |
Family
ID=62306232
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721522521.9U Expired - Fee Related CN207419519U (zh) | 2017-11-15 | 2017-11-15 | 一种排桩支护与扶臂式挡墙结合的结构体系 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207419519U (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110144824A (zh) * | 2019-05-12 | 2019-08-20 | 中铁二十二局哈尔滨铁路建设集团有限责任公司 | 贝雷片单侧支模法 |
CN112962667A (zh) * | 2021-02-08 | 2021-06-15 | 中国建筑第八工程局有限公司 | 下沉庭院的外墙结构及其施工方法 |
CN113006084A (zh) * | 2021-03-08 | 2021-06-22 | 中铁十一局集团有限公司 | 一种无支撑基坑支档系统的施工方法及其动态设计方法 |
CN115182378A (zh) * | 2022-05-10 | 2022-10-14 | 中国建筑第八工程局有限公司 | 挡土墙构造及其施工方法 |
-
2017
- 2017-11-15 CN CN201721522521.9U patent/CN207419519U/zh not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110144824A (zh) * | 2019-05-12 | 2019-08-20 | 中铁二十二局哈尔滨铁路建设集团有限责任公司 | 贝雷片单侧支模法 |
CN112962667A (zh) * | 2021-02-08 | 2021-06-15 | 中国建筑第八工程局有限公司 | 下沉庭院的外墙结构及其施工方法 |
CN113006084A (zh) * | 2021-03-08 | 2021-06-22 | 中铁十一局集团有限公司 | 一种无支撑基坑支档系统的施工方法及其动态设计方法 |
CN115182378A (zh) * | 2022-05-10 | 2022-10-14 | 中国建筑第八工程局有限公司 | 挡土墙构造及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207419519U (zh) | 一种排桩支护与扶臂式挡墙结合的结构体系 | |
CN105041349B (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的暗挖施工方法 | |
CN101914925B (zh) | 利用优化复合预制拱墙作外墙的地下室 | |
CN105089061B (zh) | 一种超深基坑支护方法 | |
CN103031839B (zh) | 人工挖孔桩施工方法 | |
CN104989425B (zh) | 一种暗挖进洞支护结构及其支护方法 | |
CN105064397A (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法 | |
CN207987927U (zh) | 多级梯次基坑支护体系 | |
CN102182325A (zh) | 一种框架结构独立基础既有建筑物地下室增层方法 | |
CN108035361A (zh) | 一种超前支撑支护结构及其施工方法 | |
CN102162258B (zh) | 一种塔吊钢管混凝土高桩塔基结构及构建方法 | |
CN207063982U (zh) | 一种导洞内机械辅助止水暗挖车站结构 | |
CN103452120B (zh) | 一种用于基坑支护的高强预应力管桩的桩顶冠梁结构及其施工方法 | |
CN106703044A (zh) | 一种流塑状冲填土软弱地层放坡组合支护方法 | |
CN102864780A (zh) | 一种基坑支护结构及其支护方法 | |
CN109441456A (zh) | 一种软弱易滑地层的隧道进洞结构及其施工方法 | |
CN204825928U (zh) | 一种基坑支护 | |
CN203716156U (zh) | 一种深基坑内设坑中坑城门洞式出土施工结构 | |
CN105586985A (zh) | 一种地铁围护结构的修建方法及一种地铁围护结构 | |
CN203960896U (zh) | 斜柱桩基础 | |
CN104131566B (zh) | 一种地下室无水平支撑基坑的施工方法 | |
CN201991013U (zh) | 一种塔吊钢管混凝土高桩塔基结构 | |
CN109267575A (zh) | 软土区坑中坑基坑支护的施工方法 | |
CN109538236A (zh) | 一种隧道进洞结构及隧道进洞施工方法 | |
CN107476315A (zh) | 一种针对紧邻型基坑的预制式构件及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180529 Termination date: 20191115 |