CN207375632U - Thermal power generation unit tower boiler lifting machine arrangement - Google Patents

Thermal power generation unit tower boiler lifting machine arrangement Download PDF

Info

Publication number
CN207375632U
CN207375632U CN201721327560.3U CN201721327560U CN207375632U CN 207375632 U CN207375632 U CN 207375632U CN 201721327560 U CN201721327560 U CN 201721327560U CN 207375632 U CN207375632 U CN 207375632U
Authority
CN
China
Prior art keywords
tower crane
boiler
tower
crane
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721327560.3U
Other languages
Chinese (zh)
Inventor
张亭森
于景龙
庞继勇
梁宏刚
张尧
罗强
杨政
张庆敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO1 Electric Power Construction Co Ltd
Original Assignee
SEPCO1 Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO1 Electric Power Construction Co Ltd filed Critical SEPCO1 Electric Power Construction Co Ltd
Priority to CN201721327560.3U priority Critical patent/CN207375632U/en
Application granted granted Critical
Publication of CN207375632U publication Critical patent/CN207375632U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a kind of thermal power generation unit tower boiler lifting machine arrangements, tower crane I including being responsible for the major-minor steelframe installation of boiler and board roof hoisting, tower crane II, the tower crane I is arranged in boiler furnace close to the one side of stokehold, the tower crane II is arranged in outside Boiler Furnace, the one side after stove, the major-minor steelframe installation of boiler and the lifting of large girder are completed in tower crane I and the cooperation of tower crane II, III position of reserved tower crane on the right side of boiler, tower crane III is used to install the lifting work of remaining equipment of boiler, after tower crane I is dismantled using tower crane II, shifting is filled to III position of tower crane, form tower crane III, the mechanical arrangement structure of the utility model, avoid the defects of big beam slab or the lifting of other eminence large components are using crawler crane, and save a large amount of machinery expenses, construction cost is saved.

Description

Thermal power generation unit tower boiler lifting machine arrangement
Technical field
The utility model is related to Heavy Equipment-hoisting technical fields, and in particular to a kind of thermal power generation unit tower boiler is hung Fill mechanical arrangement structure.
Background technology
Electric power is the important energy source of the national economic development, and thermal power generation is China and many countries produce electric energy in the world Main method.Thermal power generation carries out capital equipment --- boiler, steam turbine and the generator of energy conversion, and it is big main to be referred to as three Machine, and boiler is then energy conversion most basic in three big hosts.Boiler plant quantity is more, weight is big, it is therefore desirable to match somebody with somebody Put special hoisting machinery.
Currently used lifting machine allocation plan is in a stove left side or the one large-scale derrick crane of the right arrangement of stove, the machinery It is responsible for boiler plant lifting, when later stage board roof hoisting calls in a giant caterpillar formula crane and carries out cooperation lifting temporarily again.
But with the fast development of China's power industry, the single-machine capacity of thermal power project is increasing, and boiler components are hung Fill that difficulty is also higher and higher, previous mechanical arrangements and Hoisting Program can not meet the installation requirements of current large sized unit.
The more conventional boiler height of thermal power generation unit tower boiler is high, weight of equipment is big, and the later stage is risen using giant caterpillar formula When heavy-duty machine coordinates large girder and the lifting of other eminence large components, crawler crane is in sling height, rate of load condensate and mechanical resistance It cannot be met the requirements in terms of bar, giant caterpillar formula crane can not be used.
Utility model content
The defects of in order to solve the prior art, the purpose of this utility model are to provide a kind of thermal power generation unit tower boiler Lifting machine arrangement.
A kind of thermal power generation unit tower boiler lifting machine arrangement of the utility model, it is major-minor including being responsible for boiler Steelframe is installed and tower crane I, the tower crane II of board roof hoisting, tower crane I and the cooperation of tower crane II complete the installation of boiler major-minor steelframe and The lifting of large girder, the tower crane I are arranged in boiler furnace and are arranged in Boiler Furnace close to the one side of stokehold, the tower crane II Outside, the one side after stove, III position of reserved tower crane on the right side of boiler, for installing boiler, remaining sets tower crane at III position of tower crane Standby lifting work.
Further, the tower crane I and tower crane II are detachable tower crane, and boiler is completed in tower crane I and the cooperation of tower crane II The lifting of major-minor steelframe, large girder, tower crane II can also complete the dismounting of tower crane I, and tower crane I is facilitated to be moved to III position of tower crane.
Further, the tower crane I and II same period of tower crane arrangement, are used cooperatively, and can facilitate the major-minor steelframe installation of boiler And the lifting of large girder, it avoids and carries out large girder and the lifting of other eminence large components using giant caterpillar formula crane, So as to which effectively overcome that crawler crane cannot meet the requirements in terms of sling height, rate of load condensate and mechanical resistance bar lacks It falls into.
Further, at III position of tower crane tower crane be tower crane I, i.e., tower crane III for tower crane I dismounting after assemble again and Into in this way, realizing the secondary use of tower crane I, saving machinery expenses, saved construction cost.
The advantageous effect of utility model:
1st, the thermal power generation unit tower boiler lifting machine arrangement and installation method of the utility model, using the same period The lifting of the major-minor steelframe of boiler and large girder is completed in tower crane I and tower crane II cooperation of arrangement, is avoided big in existing hanging method Plate-girder and other eminence large components must call in a defects of crawler crane is lifted temporarily when lifting, thus gram Crawler crane has been taken cannot be met the requirements in terms of sling height, rate of load condensate and mechanical resistance bar the problem of.
2nd, the utility model proposes targetedly big machinery arrangement side for the lifting of thermal power generation unit tower boiler Case, working region can meet the lifting demand of each component of tower boiler, using only two tower cranes, save substantial amounts of machinery Expense has saved construction cost.
Description of the drawings
The accompanying drawings which form a part of this application are used for providing further understanding of the present application, and the application's shows Meaning property embodiment and its explanation do not form the restriction to the application for explaining the application.
Fig. 1 is the utility model thermal power generation unit tower boiler lifting machine arrangement schematic diagram;
Wherein:1. tower crane I, 2. tower cranes II, 3. tower cranes III.
Specific embodiment
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.It is unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative It is also intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " bag Include " when, indicate existing characteristics, step, operation, device, component and/or combination thereof.
As background technology is introduced, in the prior art the more conventional boiler height of thermal power generation unit tower boiler it is high, Weight of equipment is big, when the later stage is lifted using giant caterpillar formula crane cooperation large girder and other eminence large components, crawler type Crane cannot be met the requirements in terms of sling height, rate of load condensate and mechanical resistance bar, can not use giant caterpillar formula crane, For this problem, present applicant proposes a kind of thermal power generation unit tower boiler lifting machine arrangement and hanging methods.
In a kind of exemplary embodiment of the application, the double reheat tower boiler that need to be lifted is arranged using side coal bunker, is hung Mechanical arrangement structure is filled as shown in Figure 1, a kind of thermal power generation unit tower boiler lifting machine arrangement, including being responsible for boiler The major-minor steel of boiler is completed in major-minor steelframe installation and tower crane I 1, the tower crane II 2 of board roof hoisting, tower crane I 1 and the cooperation of tower crane II 2 Frame is installed and the lifting of large girder, and the tower crane I 1 is arranged in boiler furnace close to the one side of stokehold, and the tower crane II 2 is arranged Outside Boiler Furnace, III 3 position of tower crane is reserved on the one side after stove, boiler right side, and tower crane is used to install at III position of tower crane The lifting work of remaining equipment of boiler.
In the present embodiment, according to the design feature of thermal power generation unit tower boiler, tower crane I 1 uses FHFZQ1700/ 150t tower cranes, tower crane II 2 use FZQ2200B tower cranes.
The tower crane I and II same period of tower crane arrangement, are used cooperatively, and can cover the major-minor steelframe of boiler and large girder peace comprehensively Region is filled, facilitates the major-minor steelframe installation of boiler and the lifting of large girder, avoids and carry out big plate using giant caterpillar formula crane The lifting of beam and other eminence large components, so as to effectively overcome crawler crane in sling height, rate of load condensate and machinery The defects of cannot being met the requirements in terms of anti-bar.
Tower crane III is moved to be filled on the right side of boiler after dismantling for tower crane I and formed at III position of tower crane, i.e., tower crane III is the two of tower crane I Secondary utilization for the lifting work of boiler surplus equipment, effectively saves substantial amounts of machinery expenses, has saved construction cost.
A kind of thermal power generation unit tower boiler hanging method, including:
Step 1:Tower crane I is laid close to stokehold one side in boiler furnace, tower crane II is laid in one side after the stove outside stove.
Step 2:Coordinate the major-minor steelframe of covering boiler and large girder installation region comprehensively using tower crane I, tower crane II, complete pot The installation of the major-minor steelframe of stove and the lifting of large girder.
Step 3:After completing board roof hoisting, tower crane I is removed using tower crane II, the shifting of tower crane I is attached at III position of tower crane, Tower crane I after movement is used as tower crane III, and tower crane III removes tower crane II after installation is complete.
Step 4:The lifting work of boiler surplus equipment is completed using tower crane III.
Wherein tower crane I uses FHFZQ1700/150t tower cranes, and tower crane II uses FZQ2200B tower cranes.
In specific implementation, tower crane I and tower crane II are arranged for the same period, when being lifted to major-minor steelframe and large girder, adopt It is used cooperatively with tower crane I and tower crane II, the installation site of tower crane I and tower crane II can cover major-minor steelframe and large girder area comprehensively Domain, and the lifting of its workpiece is completed, a crawler type need to be called in temporarily by solving lifting large girder or other eminence large components Crane the problem of lifting using crawler crane, meets the lifting of large-scale thermal power machine group tower boiler to crane The requirement of tool;III installation site of tower crane can cover the region of boiler other equipment comprehensively, complete the lifting of boiler surplus equipment, I secondary use of tower crane is realized, a large amount of machinery expenses is saved and saves construction cost.
It is above-mentioned although specific embodiments of the present invention are described with reference to the accompanying drawings, but not to this practicality newly The limitation of type protection domain, those skilled in the art should understand that, on the basis of the technical solution of the utility model, ability Field technique personnel need not make the creative labor the various modifications or changes that can be made still in the protection model of the utility model Within enclosing.

Claims (4)

1. a kind of thermal power generation unit tower boiler lifting machine arrangement, which is characterized in that including being responsible for the major-minor steel of boiler Frame is installed and tower crane I, the tower crane II of board roof hoisting, and the major-minor steelframe installation of boiler and big plate are completed in tower crane I and the cooperation of tower crane II The lifting of beam, the tower crane I are arranged in boiler furnace and are arranged in close to the one side of stokehold, the tower crane II outside Boiler Furnace, position The one side after stove, III position of reserved tower crane on the right side of boiler, tower crane is used to installing boiler remaining equipment at III position of tower crane Lift work.
A kind of 2. thermal power generation unit tower boiler lifting machine arrangement as described in claim 1, which is characterized in that institute It is detachable tower crane to state tower crane I and tower crane II.
A kind of 3. thermal power generation unit tower boiler lifting machine arrangement as described in claim 1, which is characterized in that institute State tower crane I and II same period of tower crane arrangement.
A kind of 4. thermal power generation unit tower boiler lifting machine arrangement as described in claim 1, which is characterized in that institute Tower crane III at III position of tower crane on the right side of boiler is stated to fill to move after the dismounting of tower crane I.
CN201721327560.3U 2017-10-16 2017-10-16 Thermal power generation unit tower boiler lifting machine arrangement Active CN207375632U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721327560.3U CN207375632U (en) 2017-10-16 2017-10-16 Thermal power generation unit tower boiler lifting machine arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721327560.3U CN207375632U (en) 2017-10-16 2017-10-16 Thermal power generation unit tower boiler lifting machine arrangement

Publications (1)

Publication Number Publication Date
CN207375632U true CN207375632U (en) 2018-05-18

Family

ID=62338537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721327560.3U Active CN207375632U (en) 2017-10-16 2017-10-16 Thermal power generation unit tower boiler lifting machine arrangement

Country Status (1)

Country Link
CN (1) CN207375632U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108758602A (en) * 2018-08-11 2018-11-06 中国电建集团贵州电力设计研究院有限公司 A kind of construction method for boiler girder lifting

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108758602A (en) * 2018-08-11 2018-11-06 中国电建集团贵州电力设计研究院有限公司 A kind of construction method for boiler girder lifting

Similar Documents

Publication Publication Date Title
CN103161168B (en) Detachable prestress supporting frame system
CN103266779A (en) Lifting slippage construction device for crossing horizontal obstacle and method thereof
CN207375632U (en) Thermal power generation unit tower boiler lifting machine arrangement
CN202298606U (en) Descending frame for mounting reinforcement cage of pile foundation
CN107572376A (en) Thermal power generation unit tower boiler lifting machine arrangement and hanging method
CN202226539U (en) Main beam structure of bridge crane
CN106379811B (en) Unit side coal bunker structure π type boiler structural design mechanical arrangement structures and hanging method
CN203392387U (en) Hydraulic transfer device
CN206511832U (en) Unit side coal bunker structure π type boiler structural design mechanical arrangement structures
CN203924659U (en) Hanging frame type construction platform device
CN107934742A (en) Combustion engine lifting device and crawler type combustion engine hanging apparatus
CN208814490U (en) A kind of novel drainage ditch cover plate hanging apparatus
CN207645603U (en) One kind being used for rectangular shield machine hoisting appliance
CN103395683A (en) U-shaped horizontal hoisting welding tool
CN207645633U (en) A kind of reversal hanger for Rectangular Tunnel combined type section of jurisdiction
CN201817830U (en) Simple dual-purpose machine for excavating and hoisting in constructional engineering over water
CN203393721U (en) Inner support main purlin component
CN202988576U (en) Simple and easy chain hoist lifting support
CN202467221U (en) Power plant main workshop steel roof truss hoisting lifting device
CN202401386U (en) Cable bridge for frame bridge
CN207581192U (en) Combustion engine lifting device and crawler type combustion engine hanging apparatus
CN206971767U (en) A kind of steel plate wall sliding erecting device of Super High Core Walls Structure
CN205616454U (en) Bridge crane girder assembly welding device
CN204897164U (en) A truss -like compensating beam for hoist and mount of large -scale electromechanical device
CN203903819U (en) Generator stator lifting device