CN207375632U - Thermal power generation unit tower boiler lifting machine arrangement - Google Patents
Thermal power generation unit tower boiler lifting machine arrangement Download PDFInfo
- Publication number
- CN207375632U CN207375632U CN201721327560.3U CN201721327560U CN207375632U CN 207375632 U CN207375632 U CN 207375632U CN 201721327560 U CN201721327560 U CN 201721327560U CN 207375632 U CN207375632 U CN 207375632U
- Authority
- CN
- China
- Prior art keywords
- tower crane
- boiler
- tower
- crane
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model discloses a kind of thermal power generation unit tower boiler lifting machine arrangements, tower crane I including being responsible for the major-minor steelframe installation of boiler and board roof hoisting, tower crane II, the tower crane I is arranged in boiler furnace close to the one side of stokehold, the tower crane II is arranged in outside Boiler Furnace, the one side after stove, the major-minor steelframe installation of boiler and the lifting of large girder are completed in tower crane I and the cooperation of tower crane II, III position of reserved tower crane on the right side of boiler, tower crane III is used to install the lifting work of remaining equipment of boiler, after tower crane I is dismantled using tower crane II, shifting is filled to III position of tower crane, form tower crane III, the mechanical arrangement structure of the utility model, avoid the defects of big beam slab or the lifting of other eminence large components are using crawler crane, and save a large amount of machinery expenses, construction cost is saved.
Description
Technical field
The utility model is related to Heavy Equipment-hoisting technical fields, and in particular to a kind of thermal power generation unit tower boiler is hung
Fill mechanical arrangement structure.
Background technology
Electric power is the important energy source of the national economic development, and thermal power generation is China and many countries produce electric energy in the world
Main method.Thermal power generation carries out capital equipment --- boiler, steam turbine and the generator of energy conversion, and it is big main to be referred to as three
Machine, and boiler is then energy conversion most basic in three big hosts.Boiler plant quantity is more, weight is big, it is therefore desirable to match somebody with somebody
Put special hoisting machinery.
Currently used lifting machine allocation plan is in a stove left side or the one large-scale derrick crane of the right arrangement of stove, the machinery
It is responsible for boiler plant lifting, when later stage board roof hoisting calls in a giant caterpillar formula crane and carries out cooperation lifting temporarily again.
But with the fast development of China's power industry, the single-machine capacity of thermal power project is increasing, and boiler components are hung
Fill that difficulty is also higher and higher, previous mechanical arrangements and Hoisting Program can not meet the installation requirements of current large sized unit.
The more conventional boiler height of thermal power generation unit tower boiler is high, weight of equipment is big, and the later stage is risen using giant caterpillar formula
When heavy-duty machine coordinates large girder and the lifting of other eminence large components, crawler crane is in sling height, rate of load condensate and mechanical resistance
It cannot be met the requirements in terms of bar, giant caterpillar formula crane can not be used.
Utility model content
The defects of in order to solve the prior art, the purpose of this utility model are to provide a kind of thermal power generation unit tower boiler
Lifting machine arrangement.
A kind of thermal power generation unit tower boiler lifting machine arrangement of the utility model, it is major-minor including being responsible for boiler
Steelframe is installed and tower crane I, the tower crane II of board roof hoisting, tower crane I and the cooperation of tower crane II complete the installation of boiler major-minor steelframe and
The lifting of large girder, the tower crane I are arranged in boiler furnace and are arranged in Boiler Furnace close to the one side of stokehold, the tower crane II
Outside, the one side after stove, III position of reserved tower crane on the right side of boiler, for installing boiler, remaining sets tower crane at III position of tower crane
Standby lifting work.
Further, the tower crane I and tower crane II are detachable tower crane, and boiler is completed in tower crane I and the cooperation of tower crane II
The lifting of major-minor steelframe, large girder, tower crane II can also complete the dismounting of tower crane I, and tower crane I is facilitated to be moved to III position of tower crane.
Further, the tower crane I and II same period of tower crane arrangement, are used cooperatively, and can facilitate the major-minor steelframe installation of boiler
And the lifting of large girder, it avoids and carries out large girder and the lifting of other eminence large components using giant caterpillar formula crane,
So as to which effectively overcome that crawler crane cannot meet the requirements in terms of sling height, rate of load condensate and mechanical resistance bar lacks
It falls into.
Further, at III position of tower crane tower crane be tower crane I, i.e., tower crane III for tower crane I dismounting after assemble again and
Into in this way, realizing the secondary use of tower crane I, saving machinery expenses, saved construction cost.
The advantageous effect of utility model:
1st, the thermal power generation unit tower boiler lifting machine arrangement and installation method of the utility model, using the same period
The lifting of the major-minor steelframe of boiler and large girder is completed in tower crane I and tower crane II cooperation of arrangement, is avoided big in existing hanging method
Plate-girder and other eminence large components must call in a defects of crawler crane is lifted temporarily when lifting, thus gram
Crawler crane has been taken cannot be met the requirements in terms of sling height, rate of load condensate and mechanical resistance bar the problem of.
2nd, the utility model proposes targetedly big machinery arrangement side for the lifting of thermal power generation unit tower boiler
Case, working region can meet the lifting demand of each component of tower boiler, using only two tower cranes, save substantial amounts of machinery
Expense has saved construction cost.
Description of the drawings
The accompanying drawings which form a part of this application are used for providing further understanding of the present application, and the application's shows
Meaning property embodiment and its explanation do not form the restriction to the application for explaining the application.
Fig. 1 is the utility model thermal power generation unit tower boiler lifting machine arrangement schematic diagram;
Wherein:1. tower crane I, 2. tower cranes II, 3. tower cranes III.
Specific embodiment
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.It is unless another
It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field
The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root
According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative
It is also intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " bag
Include " when, indicate existing characteristics, step, operation, device, component and/or combination thereof.
As background technology is introduced, in the prior art the more conventional boiler height of thermal power generation unit tower boiler it is high,
Weight of equipment is big, when the later stage is lifted using giant caterpillar formula crane cooperation large girder and other eminence large components, crawler type
Crane cannot be met the requirements in terms of sling height, rate of load condensate and mechanical resistance bar, can not use giant caterpillar formula crane,
For this problem, present applicant proposes a kind of thermal power generation unit tower boiler lifting machine arrangement and hanging methods.
In a kind of exemplary embodiment of the application, the double reheat tower boiler that need to be lifted is arranged using side coal bunker, is hung
Mechanical arrangement structure is filled as shown in Figure 1, a kind of thermal power generation unit tower boiler lifting machine arrangement, including being responsible for boiler
The major-minor steel of boiler is completed in major-minor steelframe installation and tower crane I 1, the tower crane II 2 of board roof hoisting, tower crane I 1 and the cooperation of tower crane II 2
Frame is installed and the lifting of large girder, and the tower crane I 1 is arranged in boiler furnace close to the one side of stokehold, and the tower crane II 2 is arranged
Outside Boiler Furnace, III 3 position of tower crane is reserved on the one side after stove, boiler right side, and tower crane is used to install at III position of tower crane
The lifting work of remaining equipment of boiler.
In the present embodiment, according to the design feature of thermal power generation unit tower boiler, tower crane I 1 uses FHFZQ1700/
150t tower cranes, tower crane II 2 use FZQ2200B tower cranes.
The tower crane I and II same period of tower crane arrangement, are used cooperatively, and can cover the major-minor steelframe of boiler and large girder peace comprehensively
Region is filled, facilitates the major-minor steelframe installation of boiler and the lifting of large girder, avoids and carry out big plate using giant caterpillar formula crane
The lifting of beam and other eminence large components, so as to effectively overcome crawler crane in sling height, rate of load condensate and machinery
The defects of cannot being met the requirements in terms of anti-bar.
Tower crane III is moved to be filled on the right side of boiler after dismantling for tower crane I and formed at III position of tower crane, i.e., tower crane III is the two of tower crane I
Secondary utilization for the lifting work of boiler surplus equipment, effectively saves substantial amounts of machinery expenses, has saved construction cost.
A kind of thermal power generation unit tower boiler hanging method, including:
Step 1:Tower crane I is laid close to stokehold one side in boiler furnace, tower crane II is laid in one side after the stove outside stove.
Step 2:Coordinate the major-minor steelframe of covering boiler and large girder installation region comprehensively using tower crane I, tower crane II, complete pot
The installation of the major-minor steelframe of stove and the lifting of large girder.
Step 3:After completing board roof hoisting, tower crane I is removed using tower crane II, the shifting of tower crane I is attached at III position of tower crane,
Tower crane I after movement is used as tower crane III, and tower crane III removes tower crane II after installation is complete.
Step 4:The lifting work of boiler surplus equipment is completed using tower crane III.
Wherein tower crane I uses FHFZQ1700/150t tower cranes, and tower crane II uses FZQ2200B tower cranes.
In specific implementation, tower crane I and tower crane II are arranged for the same period, when being lifted to major-minor steelframe and large girder, adopt
It is used cooperatively with tower crane I and tower crane II, the installation site of tower crane I and tower crane II can cover major-minor steelframe and large girder area comprehensively
Domain, and the lifting of its workpiece is completed, a crawler type need to be called in temporarily by solving lifting large girder or other eminence large components
Crane the problem of lifting using crawler crane, meets the lifting of large-scale thermal power machine group tower boiler to crane
The requirement of tool;III installation site of tower crane can cover the region of boiler other equipment comprehensively, complete the lifting of boiler surplus equipment,
I secondary use of tower crane is realized, a large amount of machinery expenses is saved and saves construction cost.
It is above-mentioned although specific embodiments of the present invention are described with reference to the accompanying drawings, but not to this practicality newly
The limitation of type protection domain, those skilled in the art should understand that, on the basis of the technical solution of the utility model, ability
Field technique personnel need not make the creative labor the various modifications or changes that can be made still in the protection model of the utility model
Within enclosing.
Claims (4)
1. a kind of thermal power generation unit tower boiler lifting machine arrangement, which is characterized in that including being responsible for the major-minor steel of boiler
Frame is installed and tower crane I, the tower crane II of board roof hoisting, and the major-minor steelframe installation of boiler and big plate are completed in tower crane I and the cooperation of tower crane II
The lifting of beam, the tower crane I are arranged in boiler furnace and are arranged in close to the one side of stokehold, the tower crane II outside Boiler Furnace, position
The one side after stove, III position of reserved tower crane on the right side of boiler, tower crane is used to installing boiler remaining equipment at III position of tower crane
Lift work.
A kind of 2. thermal power generation unit tower boiler lifting machine arrangement as described in claim 1, which is characterized in that institute
It is detachable tower crane to state tower crane I and tower crane II.
A kind of 3. thermal power generation unit tower boiler lifting machine arrangement as described in claim 1, which is characterized in that institute
State tower crane I and II same period of tower crane arrangement.
A kind of 4. thermal power generation unit tower boiler lifting machine arrangement as described in claim 1, which is characterized in that institute
Tower crane III at III position of tower crane on the right side of boiler is stated to fill to move after the dismounting of tower crane I.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721327560.3U CN207375632U (en) | 2017-10-16 | 2017-10-16 | Thermal power generation unit tower boiler lifting machine arrangement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721327560.3U CN207375632U (en) | 2017-10-16 | 2017-10-16 | Thermal power generation unit tower boiler lifting machine arrangement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207375632U true CN207375632U (en) | 2018-05-18 |
Family
ID=62338537
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721327560.3U Active CN207375632U (en) | 2017-10-16 | 2017-10-16 | Thermal power generation unit tower boiler lifting machine arrangement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207375632U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108758602A (en) * | 2018-08-11 | 2018-11-06 | 中国电建集团贵州电力设计研究院有限公司 | A kind of construction method for boiler girder lifting |
-
2017
- 2017-10-16 CN CN201721327560.3U patent/CN207375632U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108758602A (en) * | 2018-08-11 | 2018-11-06 | 中国电建集团贵州电力设计研究院有限公司 | A kind of construction method for boiler girder lifting |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103161168B (en) | Detachable prestress supporting frame system | |
CN103266779A (en) | Lifting slippage construction device for crossing horizontal obstacle and method thereof | |
CN207375632U (en) | Thermal power generation unit tower boiler lifting machine arrangement | |
CN202298606U (en) | Descending frame for mounting reinforcement cage of pile foundation | |
CN107572376A (en) | Thermal power generation unit tower boiler lifting machine arrangement and hanging method | |
CN202226539U (en) | Main beam structure of bridge crane | |
CN106379811B (en) | Unit side coal bunker structure π type boiler structural design mechanical arrangement structures and hanging method | |
CN203392387U (en) | Hydraulic transfer device | |
CN206511832U (en) | Unit side coal bunker structure π type boiler structural design mechanical arrangement structures | |
CN203924659U (en) | Hanging frame type construction platform device | |
CN107934742A (en) | Combustion engine lifting device and crawler type combustion engine hanging apparatus | |
CN208814490U (en) | A kind of novel drainage ditch cover plate hanging apparatus | |
CN207645603U (en) | One kind being used for rectangular shield machine hoisting appliance | |
CN103395683A (en) | U-shaped horizontal hoisting welding tool | |
CN207645633U (en) | A kind of reversal hanger for Rectangular Tunnel combined type section of jurisdiction | |
CN201817830U (en) | Simple dual-purpose machine for excavating and hoisting in constructional engineering over water | |
CN203393721U (en) | Inner support main purlin component | |
CN202988576U (en) | Simple and easy chain hoist lifting support | |
CN202467221U (en) | Power plant main workshop steel roof truss hoisting lifting device | |
CN202401386U (en) | Cable bridge for frame bridge | |
CN207581192U (en) | Combustion engine lifting device and crawler type combustion engine hanging apparatus | |
CN206971767U (en) | A kind of steel plate wall sliding erecting device of Super High Core Walls Structure | |
CN205616454U (en) | Bridge crane girder assembly welding device | |
CN204897164U (en) | A truss -like compensating beam for hoist and mount of large -scale electromechanical device | |
CN203903819U (en) | Generator stator lifting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |