CN207363321U - Water supply first-aid repair weather proof enclosure device - Google Patents

Water supply first-aid repair weather proof enclosure device Download PDF

Info

Publication number
CN207363321U
CN207363321U CN201721314153.9U CN201721314153U CN207363321U CN 207363321 U CN207363321 U CN 207363321U CN 201721314153 U CN201721314153 U CN 201721314153U CN 207363321 U CN207363321 U CN 207363321U
Authority
CN
China
Prior art keywords
supporting
retaining system
vertical frame
cross
enclosure device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721314153.9U
Other languages
Chinese (zh)
Inventor
袁东升
山广泉
纪丕欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ji'nan Puli Municipal Pipe Network Engineering Co Ltd
Original Assignee
Ji'nan Puli Municipal Pipe Network Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ji'nan Puli Municipal Pipe Network Engineering Co Ltd filed Critical Ji'nan Puli Municipal Pipe Network Engineering Co Ltd
Priority to CN201721314153.9U priority Critical patent/CN207363321U/en
Application granted granted Critical
Publication of CN207363321U publication Critical patent/CN207363321U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model discloses a kind of water supply first-aid repair weather proof enclosure device, it solves the problems, such as during water supply first-aid repair existing in the prior art that enclosing can not be realized and effectively goes along with sb. to guard him, construction site can be isolated with periphery, construction is set to be independent of each other with current, and it can keep out wind and rain, is sun-proof, optimize water supply first-aid repair personnel's operating environment, its technical solution is:Including the first supporting and retaining system and the second supporting and retaining system being oppositely arranged, ceiling is set between the first supporting and retaining system and the second supporting and retaining system top;The 3rd supporting and retaining system is connected between first supporting and retaining system and the second supporting and retaining system one end, the 4th supporting and retaining system is connected between the first supporting and retaining system and second supporting and retaining system the other end, first, second, third, fourth supporting and retaining system surrounds enclosed construction;First supporting and retaining system and the second supporting and retaining system include the first vertical frame for being arranged on both ends, set multiple telescopic supporting components between the first vertical frame, are separated between telescopic supporting component by upright bar.

Description

Water supply first-aid repair weather proof enclosure device
Technical field
Water supply first-aid repair enclosing Technique field is the utility model is related to, dress is gone along with sb. to guard him more particularly to a kind of water supply first-aid repair weather proof Put.
Background technology
With the fast development of economic society and the continuous lifting of people's living standard, user to the qualities of water services and Demand is also higher and higher, puts the urgent task in face of water supply industry how is renewed product variety and upgraded product quality on the premise of safety in production is done a good job of it The means of services and quality, meet user demand.An important ring of the work as water services is dealt with emergencies and dangerous situations and is rushed to repair in water supply, is both to influence The key factor of service quality, and be the important leverage that water supply security is stablized.Huge water supply pipe net system is in Urbanization Construction Period, unavoidably runs into various burst water leakage situations, need to have rational emergency preplan to a wide range of water supply condition that interrupts, to quick-fried Run affairs therefore make fast reaction, it is necessary to resume water supply as early as possible by rushing to repair within the time as short as possible, and applied in water supply first-aid repair During work, all it is to need present Construction Specifications place installation enclosure device, traffic areas and construction area is separated.
At present, the enclosure device that water supply first-aid repair uses only arranges an enclosing at the construction field (site), its safeguard function reaches Less than totally enclosed requirement, also it is easy for influencing periphery wagon flow, the current safety of the stream of people;Existing enclosing is all that fixed dimension is consolidated Determine size, can not be adjusted, taken up a large area according to site operation environment, and can only be by artificially carrying, transport gets up to have all It is more inconvenient;The road caution effect unobvious of existing enclosing at the same time, be easy to cause security incident;Water supply first-aid repair requires timeliness, Run into wind and rain weather still need to continue job execution, but existing enclosing can not realize it is windproof keep off the rain, not only bad for scene repairing Construction, while can also influence the health of construction personnel.
In conclusion can not realize the problem of effectively going along with sb. to guard him for enclosing during water supply first-aid repair in the prior art, still lack Weary effective solution.
Utility model content
In order to overcome the above-mentioned deficiencies of the prior art, the utility model provides a kind of water supply first-aid repair weather proof and goes along with sb. to guard him dress Put, it can isolate construction site with periphery, construction is independent of each other with current, and can keep out wind and rain, is sun-proof, and optimization water supply is robbed Repair personnel's operating environment;
Further, the utility model uses following technical proposals:
Water supply first-aid repair weather proof enclosure device, including the first supporting and retaining system and the second supporting and retaining system being oppositely arranged, the first supporting and retaining system and Ceiling is set between at the top of two supporting and retaining systems;The 3rd supporting and retaining system, the first supporting and retaining system are connected between first supporting and retaining system and the second supporting and retaining system one end And second connect the 4th supporting and retaining system between supporting and retaining system the other end, first, second, third, fourth supporting and retaining system surrounds enclosed construction;
First supporting and retaining system and the second supporting and retaining system include being arranged on first vertical frame at both ends, the first vertical frame it Between multiple telescopic supporting components are set, separated between telescopic supporting component by upright bar.
Further, the ceiling includes the first cross-brace skeleton and the second cross-brace bone of interval setpoint distance Frame, between first, second cross-brace skeleton connection multiple longitudinal bracing skeletons are set, be laid with tarpaulin on longitudinal bracing skeleton.
Further, the first cross-brace skeleton is erected at the top of the first supporting and retaining system, and the second cross-brace skeleton is set up At the top of the second supporting and retaining system.
Preferably, the longitudinal bracing skeleton is arc-shaped.
Further, the longitudinal bracing skeleton lower part connection reinforcement supporting rod.
Further, the telescopic supporting component is scissors stretching structure, and scissors stretching structure is arranged between two upright bars Or between upright bar, the first vertical frame.
Further, Collapsible rack is set between first vertical frame and upright bar top.
Further, it is also provided with Collapsible rack between the upright bar top.
Further, cross bar is set in the middle part of first vertical frame, and cross bar top sets decoration iron skill, and cross bar lower part is set Put cross link.
Preferably, the setting position of first supporting and retaining system and the second supporting and retaining system is equipped with the green plant of plastics.
Further, the 3rd supporting and retaining system and the 4th supporting and retaining system include being arranged on second vertical frame at both ends, and second Upset fence is set between vertical frame, fence is overturn and the second vertical frame is rotatablely connected.
Further, cross bar is set in the middle part of second vertical frame, and cross bar top sets decoration iron skill, and cross bar lower part is set Put cross link.
Further, the setting position of first supporting and retaining system and the second supporting and retaining system hangs promotional plate.Promotional plate is set, not only It can inform that periphery is passed through the construction purpose of personnel on site, while the high quality service theory of water utilities water supply first-aid repair is presented in city In face of the people.
Further, first supporting and retaining system and second block setting flashing warning light.Flashing warning light is set, can be very Good plays a warning role.
Further, the first vertical frame end side sets multiple pulleys, sets and hangs at the top of the first vertical frame Hook.
Further, the second vertical frame end side sets multiple pulleys, sets and hangs at the top of the second vertical frame Hook.
Further, the upright bar sidepiece sets multiple pulleys, and hook is set at the top of upright bar.
Further, the first cross-brace skeleton and the second cross-brace skeleton bottom carry multiple grafting blocks, Fluting is set at the top of the upright bar, and fluting is equipped with grafting block, and the cross section of fluting and grafting block is in convex shape.
Further, the first cross-brace skeleton, the second cross-brace skeleton and longitudinal bracing skeleton are the Black Warrior Rock fiber is made.
Further, the tarpaulin lower part is detachably connected with cloth for keeping out rain, and cloth for keeping out rain with tarpaulin junction by extending to One supporting and retaining system or the second supporting and retaining system bottom.
Further, the upright bar sidepiece detachably sets supporting rod.When wind and rain is larger, installation supporting rod plays upright bar Strengthen supporting role, avoid supporting and retaining system because wind-force is larger skew caused by security incident.
Compared with prior art, the beneficial effects of the utility model are:
The enclosure device of the utility model surrounds enclosed construction by setting first, second, third, fourth supporting and retaining system, can Water supply first-aid repair construction site and the periphery stream of people, wagon flow are kept apart, construction is independent of each other with current, and also can preferably protect The current stream of people of barrier, the safety of wagon flow.
The enclosure device of the utility model sets ceiling at the top of supporting and retaining system, can keep out wind and rain, is sun-proof, and preferably optimization supplies Water repair personnel's operating environment, and can be as field operation lobby, interim headquarter, provide yard for commanding Ground;Telescopic supporting component is set between vertical frame, telescopic supporting component can be drawn according to construction site actual environment Stretch, it is more practical, while placement process is also more succinct, flexible.
The enclosure device of the utility model is arranged to vertical frame in corner junction, while fence is played the role of, Visual space observation periphery wagon flow, stream of people's situation can be provided to construction personnel, avoid the construction infection of construction personnel at the scene from arriving Normal pass, and then trigger security incident.
The enclosure device of the utility model sets hook, dress is gone along with sb. to guard him in transport at vertical frame end set pulley, top When putting, drawstring can be hung up on hook, pulls drawstring supporting and retaining system easily can be towed movement, unloads, frees without artificial remove Manpower.
The support frame of the enclosure device ceiling of the utility model and upright bar are mating by fluting, grafting block, can be very It is convenient to realize the two connection, and fluting and grafting block are all provided with being set to convex shape, can firmly it be connected together after the two connection, It is not easy to disengage, stability is more preferable.
The enclosure device of the utility model sets dismountable cloth for keeping out rain in tarpaulin lower part, when wind and rain is larger by cloth for keeping out rain Tarpaulin bottom is connected to, whole enclosure device can be covered up, effectively avoid interior construction personnel from drenching with rain, and also can guarantee that wind What water supply first-aid repair worked under rainy day gas is normally carried out.
Brief description of the drawings
The accompanying drawings which form a part of this application are used for providing further understanding of the present application, and the application's shows Meaning property embodiment and its explanation are used to explain the application, do not form the improper restriction to the application.
Fig. 1 coordinates schematic side view for first, second supporting and retaining system of the utility model enclosure device and ceiling;
Fig. 2 is the utility model enclosure device schematic front view;
Fig. 3 is the utility model enclosure device schematic side view;
Fig. 4 is the first cross-brace skeleton and the bottom view of grafting block junction;
Fig. 5 is upright bar top-slitting schematic diagram;
In figure, 1 first supporting and retaining system, 2 second supporting and retaining systems, 3 ceilings, 4 the 3rd supporting and retaining systems, 5 first vertical frames, 6 telescopic supporting components, 7 upright bars, 8 first cross-brace skeletons, 9 longitudinal bracing skeletons, 10 tarpaulins, 11 strengthen supporting rod, and 12 Collapsible racks, 13 is horizontal Bar, 14 decoration iron skills, 15 cross links, 16 second vertical frames, 17 upset fences, 18 flashing warning lights, 19 pulleys, 20 hang Hook, 21 grafting blocks, 22 flutings.
Embodiment
It is noted that described further below is all illustrative, it is intended to provides further instruction to the application.It is unless another Indicate, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative It is also intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " bag Include " when, it indicates existing characteristics, step, operation, device, component and/or combinations thereof.
As background technology is introduced, it enclosing during water supply first-aid repair exists in the prior art can not realize and effectively go along with sb. to guard him The problem of, in order to solve technical problem as above, present applicant proposes a kind of water supply first-aid repair weather proof enclosure device.
In a kind of typical embodiment of the application, as shown in Figure 1, there is provided dress is gone along with sb. to guard him in a kind of water supply first-aid repair weather proof Put, including the first supporting and retaining system 1 and the second supporting and retaining system 2 being oppositely arranged, ceiling 3 is set between the first supporting and retaining system 1 and the top of the second supporting and retaining system 2; The 3rd supporting and retaining system 4 is connected between 2 one end of first supporting and retaining system 1 and the second supporting and retaining system, between 2 the other end of the first supporting and retaining system 1 and the second supporting and retaining system The 4th supporting and retaining system (not shown) is connected, the first supporting and retaining system 1, the second supporting and retaining system 2, the 3rd supporting and retaining system 3, the 4th supporting and retaining system surround closed knot Structure;By setting first, second, third, fourth supporting and retaining system, enclosed construction is surrounded, can be by water supply first-aid repair construction site and periphery The stream of people, wagon flow are kept apart, and construction is independent of each other with current, and also can preferably ensure the current stream of people, the safety of wagon flow.
First supporting and retaining system 1 and the second supporting and retaining system 2 include the first vertical frame 5 for being arranged on both ends, the first vertical frame 5 it Between multiple telescopic supporting components 6 are set, separated between telescopic supporting component 6 by upright bar 7.Telescopic supporting component 6 stretches for scissors Structure, scissors stretching structure are arranged between two upright bars 7 or between upright bar 7, the first vertical frame 5.There is matter in practicality Raising, according to construction site actual environment, stretching, shorten telescopic supporting size of components, and compared to old-fashioned enclosing, placement process is more Add succinct, flexible, and more accurately made rational planning for construction area using the isolation property of enclosing, meeting safe construction condition In the case of, construction area area is reduced, had both played due protective action, more reduce because of the public space shared by construction, carry The construction site periphery stream of people, the passability and security of wagon flow are risen, reduces the influence caused by sudden first-aid repair construction as far as possible.
Ceiling 3 includes the first cross-brace skeleton 8 of interval setpoint distance and the second cross-brace skeleton (does not show in figure Go out), the multiple longitudinal bracing skeletons 9 of connection setting, longitudinal bracing between the first cross-brace skeleton 8, the second cross-brace skeleton Tarpaulin 10 is laid with skeleton 9.
First cross-brace skeleton 8 is erected at the top of the first supporting and retaining system 1, and the second cross-brace skeleton is erected at the second supporting and retaining system 2 Top.
Longitudinal bracing skeleton 9 is arc-shaped.9 lower part connection reinforcement supporting rod 11 of longitudinal bracing skeleton, strengthens support frame Support force.
Collapsible rack 12 is set between first vertical frame 5 and the top of upright bar 7.Upright bar 7 is also provided with rolling between top Folded stent 12.When supporting and retaining system is shortened, Collapsible rack 12 and then folding, do not interfere with the normal flexible of telescopic supporting component 6.
The middle part of first vertical frame 5 sets cross bar 13, and 13 top of cross bar sets decoration iron skill 14, and 13 lower part of cross bar, which is set, hands over Pitch connecting rod 15.Vertical frame is arranged on enclosure device edge, while fence is played the role of, can provide and regard to construction personnel Feel space observation periphery wagon flow, stream of people's situation, avoid the construction infection of construction personnel at the scene to normal pass, and then trigger peace Full accident.
The setting position of first supporting and retaining system 1 and the second supporting and retaining system 2 is equipped with the green plant of plastics.Decoration iron skill is set on vertical frame, Blocked in branch and the green plant of plastics is set, add decorative, artistry, in visually, psychological mitigate citizen because of first-aid repair construction institute The negative emotions of generation, the urban water supply repairing scenery together with water affair group characteristic is made by optimizing service measures.
3rd supporting and retaining system 4 and the 4th supporting and retaining system include the second vertical frame 16 for being arranged on both ends, the second vertical frame 16 Between set upset fence 17, upset fence 17 be rotatablely connected with the second vertical frame 16, upset fence 17 upset opening for Construction personnel passes in and out.
The middle part of second vertical frame 16 sets cross bar 13, and 13 top of cross bar sets decoration iron skill 14, and 13 lower part of cross bar is set Cross link 15.
The setting position of first supporting and retaining system 1 and the second supporting and retaining system 2 hangs promotional plate.Promotional plate is set, can not only be informed week While the construction purpose for the personnel on site that passes through, while the high quality service theory of water utilities water supply first-aid repair is presented in face of citizen.
Flashing warning light 18 is set in first supporting and retaining system 1 and the second supporting and retaining system 2.Flashing warning light is set, can be very good to play Warning function.
First vertical frame, 5 end side sets multiple pulleys 19, and the top of the first vertical frame 5 sets hook 20.Second 16 end side of vertical frame sets multiple pulleys 19, and the top of the second vertical frame 16 sets hook 20.7 sidepiece of upright bar sets more A pulley, the top of upright bar 7 set hook.Pulley is set in vertical frame, pole tip, top sets hook, gone along with sb. to guard him in transport During device, drawstring can be hung up on hook, pulls drawstring supporting and retaining system easily can be towed movement, unloads, frees without artificial remove Manpower.
First cross-brace skeleton 8 and the second cross-brace skeleton bottom carry multiple grafting blocks 21, and the top of upright bar 7 is set Fluting 22 is put, fluting 22 is equipped with grafting block 21, and the cross section of fluting 22 and grafting block 21 is in convex shape.
First cross-brace skeleton 8, the second cross-brace skeleton and longitudinal bracing skeleton 9 are that basalt fibre is made. Its weight can not only be mitigated, be more convenient transport, moreover it is possible to have more preferable intensity, antiseptic property.
10 lower part of tarpaulin is detachably connected with cloth for keeping out rain, cloth for keeping out rain by with 10 junction of tarpaulin extend to the first supporting and retaining system 1 or Second supporting and retaining system, 2 bottom.Tarpaulin can be connected with cloth for keeping out rain by latch closure, i.e., multiple rings, cloth for keeping out rain top are worn in tarpaulin lower part Band latch closure, snaps onto and connection is completed on ring;The two can also be connected by zipper, and band is drawn at the top of tarpaulin bottom and cloth for keeping out rain Chain.
7 sidepiece of upright bar detachably sets supporting rod.When wind and rain is larger, installation supporting rod, which plays upright bar, strengthens support work With, avoid supporting and retaining system because wind-force is larger skew caused by security incident.
The foregoing is merely the preferred embodiment of the application, the application is not limited to, for the skill of this area For art personnel, the application can have various modifications and variations.It is all within spirit herein and principle, made any repair Change, equivalent substitution, improvement etc., should be included within the protection domain of the application.

Claims (10)

1. water supply first-aid repair weather proof enclosure device, it is characterized in that, including the first supporting and retaining system and the second supporting and retaining system being oppositely arranged, first Ceiling is set between at the top of gear and the second supporting and retaining system;The 3rd supporting and retaining system is connected between first supporting and retaining system and the second supporting and retaining system one end, the The 4th supporting and retaining system is connected between one supporting and retaining system and second supporting and retaining system the other end, first, second, third, fourth supporting and retaining system surrounds closed knot Structure;
First supporting and retaining system and the second supporting and retaining system include the first vertical frame for being arranged on both ends, are set between the first vertical frame Multiple telescopic supporting components are put, are separated between telescopic supporting component by upright bar.
2. enclosure device as claimed in claim 1, it is characterized in that, the ceiling includes the first horizontal branch of interval setpoint distance Support bone frame and the second cross-brace skeleton, between first, second cross-brace skeleton connection multiple longitudinal bracing skeletons are set, indulge Tarpaulin is laid with to support frame.
3. enclosure device as claimed in claim 2, it is characterized in that, the first cross-brace skeleton is erected at the first supporting and retaining system top Portion, the second cross-brace skeleton are erected at the top of the second supporting and retaining system;The longitudinal bracing skeleton is arc-shaped;The longitudinal bracing skeleton Lower part connection reinforcement supporting rod.
4. enclosure device as claimed in claim 1, it is characterized in that, the telescopic supporting component is scissors stretching structure, scissors Stretching structure is arranged between two upright bars or between upright bar, the first vertical frame.
5. enclosure device as claimed in claim 1, it is characterized in that, being set between first vertical frame and upright bar top can Folding rack;Collapsible rack is also provided between at the top of the upright bar;The upright bar sidepiece detachably sets supporting rod.
6. enclosure device as claimed in claim 1, it is characterized in that, cross bar is set in the middle part of first vertical frame, on cross bar Portion sets decoration iron skill, and cross bar lower part sets cross link;The setting position of first supporting and retaining system and the second supporting and retaining system is equipped with modeling Expect green plant;The setting position of first supporting and retaining system and the second supporting and retaining system hangs promotional plate;First supporting and retaining system and second block Flashing warning light is set;
The first vertical frame end side sets multiple pulleys, and hook is set at the top of the first vertical frame;The upright bar side Portion sets multiple pulleys, and hook is set at the top of upright bar.
7. enclosure device as claimed in claim 1, it is characterized in that, the 3rd supporting and retaining system and the 4th supporting and retaining system include being arranged on two Second vertical frame of end, upset fence is set between the second vertical frame, and upset fence rotates company with the second vertical frame Connect;Cross bar is set in the middle part of second vertical frame, and cross bar top sets decoration iron skill, and cross bar lower part sets cross link.
8. enclosure device as claimed in claim 7, it is characterized in that, the second vertical frame end side sets multiple cunnings Wheel, the second vertical frame top set hook.
9. enclosure device as claimed in claim 2, it is characterized in that, the first cross-brace skeleton and the second cross-brace bone Frame bottom carries multiple grafting blocks, and fluting is set at the top of the upright bar, and fluting is equipped with grafting block, fluting and grafting block Cross section be in convex shape;The first cross-brace skeleton, the second cross-brace skeleton and longitudinal bracing skeleton are profound Military rock fiber is made.
10. enclosure device as claimed in claim 2, it is characterized in that, the tarpaulin lower part is detachably connected with cloth for keeping out rain, rain cover Cloth with tarpaulin junction by extending to the first supporting and retaining system or the second supporting and retaining system bottom.
CN201721314153.9U 2017-10-12 2017-10-12 Water supply first-aid repair weather proof enclosure device Active CN207363321U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721314153.9U CN207363321U (en) 2017-10-12 2017-10-12 Water supply first-aid repair weather proof enclosure device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721314153.9U CN207363321U (en) 2017-10-12 2017-10-12 Water supply first-aid repair weather proof enclosure device

Publications (1)

Publication Number Publication Date
CN207363321U true CN207363321U (en) 2018-05-15

Family

ID=62347268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721314153.9U Active CN207363321U (en) 2017-10-12 2017-10-12 Water supply first-aid repair weather proof enclosure device

Country Status (1)

Country Link
CN (1) CN207363321U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740601A (en) * 2017-10-12 2018-02-27 济南普利市政管网工程有限责任公司 Water supply first-aid repair weather proof enclosure device
CN112854034A (en) * 2021-01-15 2021-05-28 范菁 High-speed railway bridge combination crosswind shelters from ware

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740601A (en) * 2017-10-12 2018-02-27 济南普利市政管网工程有限责任公司 Water supply first-aid repair weather proof enclosure device
CN112854034A (en) * 2021-01-15 2021-05-28 范菁 High-speed railway bridge combination crosswind shelters from ware

Similar Documents

Publication Publication Date Title
CN207363321U (en) Water supply first-aid repair weather proof enclosure device
CN202830830U (en) Road barrier for regulating road crossing of pedestrians
CN105236277B (en) Full-automatic powered block car and its block method
CN107740601A (en) Water supply first-aid repair weather proof enclosure device
CN211499713U (en) All-steel attached lifting scaffold
CN209454737U (en) Across the track wire-binding device of vehicular
CN206487129U (en) Safety hanging cradle for industrial premises Construction of Steel Structure
CN205369880U (en) Safety hanging basket for constructional engineering
CN206385862U (en) Ceiling can pack up the warp knit web structure carport blocked with side
CN206570706U (en) A kind of road and bridge engineering protection device
CN211622540U (en) Hanging basket component for constructional engineering
CN205713050U (en) A kind of scaffold protection network of municipal works
CN208578156U (en) Fast assembling-disassembling can plug-type heat preservation steel structure
CN207525876U (en) A kind of balcony structure for being convenient for plant regulatory
CN207314895U (en) Building outer wall opening full-closed system
CN207646613U (en) Module assembling stent system
CN111005550A (en) Hanging basket component for constructional engineering
CN103967402A (en) Unit-combined intelligent window
CN107081550B (en) Draw and insert-type overhead welding platform and its installation method
CN221546461U (en) Movable folding pipe well portal fence protection device
CN207267791U (en) Tower crane enclosure device
CN203424543U (en) Novel portable assembly hammock
CN208849339U (en) A kind of transmission line high-altitude job platform
CN208686049U (en) It is a kind of convenient for quickly above and below scaffold
CN209933920U (en) Horizontal ladder suitable for obstacle field

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant