CN207351319U - Subregion demolition blasting network apparatus when nonel tube plays blast hole extension - Google Patents

Subregion demolition blasting network apparatus when nonel tube plays blast hole extension Download PDF

Info

Publication number
CN207351319U
CN207351319U CN201721407524.8U CN201721407524U CN207351319U CN 207351319 U CN207351319 U CN 207351319U CN 201721407524 U CN201721407524 U CN 201721407524U CN 207351319 U CN207351319 U CN 207351319U
Authority
CN
China
Prior art keywords
area
network
group
blasting
connector
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201721407524.8U
Other languages
Chinese (zh)
Inventor
程贵海
陈善江
凌宇恒
蒙少明
覃翔
张勤彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University
Original Assignee
Guangxi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University filed Critical Guangxi University
Priority to CN201721407524.8U priority Critical patent/CN207351319U/en
Application granted granted Critical
Publication of CN207351319U publication Critical patent/CN207351319U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

Subregion demolition blasting network apparatus when a kind of nonel tube plays blast hole extension, the network apparatus are made of initiator, nonel tube, the blasting charge, connector, low section detonator and high section detonator, it is characterised in that:Nonel tube is divided into bus, connecting line, wire jumper, interval line, group top-stitching and blasthole line, by structure multi-region blasting network device;And by accurately calculating network delay time, in different groups of different areas or same area, have and wire jumper is connected to by connector between the position of identical burst time point.The utility model creatively employs wire jumper technology, the factor that may be destroyed by analyzing network, it is accurate to calculate network delay time, from between other areas or group a network circuit is connect in the position of identical burst time point, unicom between Shi Liang areas or group, realize that propagation of explosion is stablized at network, maltilevel security guarantee is provided to realize that the demolition blasting that is delayed outside large apertures is optimal demolition effect.

Description

Subregion demolition blasting network apparatus when nonel tube plays blast hole extension
Technical field
Control Blasting technology is the utility model is related to, is specially the demolition blasting network dress of nonel tube detonation Put.
Background technology
Blasting network is the technological core of various Engineering Control explosions, its reliability determines the success or failure of engineering explosion.Remove Explosion is relatively conventional in life, and the implementation of the blasting engineering includes the design of blasting scheme, the selection of explosive, network skill Art protection etc., wherein blasting network reliability is particularly important because closely bound up with demolition effect.
Domestic and foreign scholars have been carried out a series of researchs for demolition blasting relevant issues.At abroad, Monjezi etc. (Monjezi M, Singh T N, Khandelwal M, etal. Prediction and analysis of blast parameters using artificial neural network[J]. Noise & Vibration Worldwide, 2006,37(5):8-16)Blasting result is predicted and analyzed by artificial neural network model, blasting scheme is optimized with this. High-speed photography and Video Document of the country, Feng Shuyu et al. according to a large amount of concrete frame structure blasting and dismantling engineerings, analyze Contact between explosive and blasting parameter(City controlled blasting [M].Beijing:China Railway Press, 1987).Zheng Ping Xu etc. By close range photogrammetric system and data quantitative analysis building demolition blasting collapsing procedure is combined, explosion thing is obtained and collapsed Key parameter in journey(High-rise Chimney of Reinforced Concrete blasting cut supporting part destroys observational study.Chinese Journal of Rock Mechanics and Engineering, 2006, 25(2):3513-3517).The prediction of the BP neural network to mining cost and the method for Controlling model such as Hu Yonghui, Blasting parameter can be optimized exactly, new approaches are provided for blasting excavation design(Sedimentary rock type based on BP neural network The prediction of mine blasting cost of winning and Controlling model.Chinese Mining Industry, 2013, (11):75-79+87).It is quick-fried to removing both at home and abroad In place of though the research of broken relevant issues has more worth reference, rarely have people with regard to demolition blasting network reliability to demolition effect Influence to carry out special analysis and research, and achievement in research is not ideal enough.
The cluster coupling device that Chinese patent application 201520623702.5 discloses a kind of blasting network, its blasthole is interior to be used The other Nonel detonator of high section, in units of single column or subregional wall, Nonel detonator is bundled into cluster within every 20, i.e., One " greatly grab ", then each " greatly grab " is with 2 Nonel detonator propagation of explosions, then every 2 are connected with detonator with four-way afterwards The detonator of propagation of explosion detonator, forms the circuit of closing, and two detonators are finally drawn from the blasting circuit circuit of compound closing Detonation station is led to as main detonating line.
Chinese patent 201,720,066,846 .4 discloses a kind of blasting circuit arrangement apparatus, including blasthole, bridge pier and bridge Some blastholes blasthole of different floor gaps (in Building demolition explosion can also be) are both provided with face;Blasthole network connects Using layered arrangement, the blasthole in every layer is connected into the circuit of closure by positive propagation of explosion detonator and reverse propagation of explosion detonator;Then The horizontal closure network of different interlayers is coupled into the closure to be formed on stereo directional again by positive detonator and reverse detonator Network;Multiple shot points finally are set on a horizontal closed circuit wherein.The technology passes through two on bridge in-plane Propagation of explosion detonator on a direction forms small closed circuit;Solid is formed by the propagation of explosion detonator in both direction on vertical direction The closed circuit in direction, ultimately forms two-way closure crossings on different level multi-point shooting blasting circuit.But blasting circuit arrangement dress Put and be only applicable to electric blasting circuit.
The purpose of this utility model is to design a kind of nonel tube detonation of reliability for effectively improving blasting network Subregion demolition blasting network apparatus during the extension of hole.
The content of the invention
In order to solve the deficiencies in the prior art, the purpose of this utility model, which is that design is a kind of, realizes that leading for propagation of explosion is stablized at network Demolition blasting network apparatus when booster plays blast hole extension.
The utility model is realized in this way:Subregion demolition blasting network fills when a kind of nonel tube plays blast hole extension Put, the network apparatus is by initiator, enough nonel tubes, enough blastings charge, multiple connectors, multiple low section detonators Formed with multiple high section detonators, it is characterised in that:
Nonel tube is divided into bus, connecting line, wire jumper, interval line, group top-stitching and blasthole line;
Bus one end connects initiator, is divided into two-way after another termination Bussing connector:All the way is connect by the Ith trivial top-stitching One end of I first connector in area;Another way connects first, the IIth area connector by being in series with the connecting line of low section detonator One end;
Ith first, area connector is further divided into two-way:The 1st group of the Ith area group top-stitching is connect all the way, is connected in the 1st group of group top-stitching There is the low section detonator of multi beam, cluster joins more blasthole lines around each low section detonator, and every blasthole line is another to be terminated with high section Detonator, high section detonator are loaded in the corresponding blasting charge;Another way meets the Ith area by being in series with the connecting line of low section detonator Two connectors;
Ith second, area connector is further divided into two-way:The 2nd group of the Ith area group top-stitching is connect all the way, is connected in the 2nd group of group top-stitching There is the low section detonator of multi beam, cluster joins more blasthole lines around each low section detonator, and every blasthole line is another to be terminated with high section Detonator, high section detonator are loaded in the corresponding blasting charge;Another way meets the Ith area by being in series with the connecting line of low section detonator Three connectors;
Afterwards and so on form the multigroup blasting network device in the Ith area;
IIth first, area connector is further divided into two-way:The IIth trivial top-stitching, the IIth trivial another termination of top-stitching are connect all the way IIth second, area connector, the IIth second, area connector are also further divided into two-way:The first via connects the 1st group of the IIth area group top-stitching, Second tunnel connects the 3rd, the IIth area connector by being in series with the connecting line of low section detonator;Each group network and the Ith area are each afterwards Networking road is identical;
IIth first, area connector another way meets company of first, the IIIth area by being in series with the connecting line of low section detonator Device is connect, the IIIth area each group network is identical with the IIth area each group network;
Afterwards and so on form multi-region blasting network device;
And:By accurately calculating network delay time, in different groups of different areas or same area, there is identical detonation Wire jumper is connected to by connector between the position at time point.
Preferably:Connector is three-way pipe and/or cluster coupling device.Also ordinary connector material and the connections such as four-way pipe can be used Mode, further includes logical common " greatly grab " mode.
Initiator described in the utility model is the initiator routinely used in large-scale demolition blasting.
For the building of the symmetric designs such as bridge, demolition blasting can generally also be designed to symmetrical blasting method, quite In being designed to two symmetrical great Qu by demolition blasting network apparatus described in the utility model, it is only necessary to by the explosion in Liang Ge great areas The bus of network apparatus is in parallel again(Cluster joins)It is followed by same initiator.
The utility model has the advantages that:The utility model creatively employs wire jumper technology, i.e., can by analyzing network Can the factor that can be destroyed, it is accurate to calculate network delay time, between other areas or group in the position of identical burst time point A network circuit is connect, unicom between Shi Liang areas or group, realizes that propagation of explosion is stablized at network.The utility model proposes networking security protection New method, provide maltilevel security guarantee to realize that the demolition blasting that is delayed outside large apertures is optimal demolition effect.
Brief description of the drawings
Fig. 1 is the blasting network schematic diagram of device of the utility model.
Fig. 2 is the blasting circuit schematic diagram at the one of which network of the utility model.
Fig. 3 is the detonation block plan of the embodiment of the utility model.
Fig. 4 a are the asymmetric section wire jumper figures of the embodiment of the utility model.
Fig. 4 b are the symmetric interval wire jumper figures of the embodiment of the utility model.
Fig. 5 be the embodiment of the utility model group between wire jumper figure.
In figure:Q-initiator, L-bus, T-three-way pipe, D1, D2 ... DN-interval line, G1, G2 ... Gn-group Top-stitching, H-blasthole, J-wire jumper.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings, but is not meant to in the utility model Any restriction held.
Such as Fig. 1 and Fig. 2, subregion demolition blasting network apparatus when a kind of nonel tube plays blast hole extension, the network apparatus By initiator Q, enough nonel tubes, enough blastings charge, multiple three-way pipe T, multiple low section detonator MS3 and multiple high Section detonator MS15 is formed, it is characterised in that:
Nonel tube is divided into bus L, connecting line, wire jumper J, interval line(D1、D2……DN), group top-stitching(G1、G2…… Gn)With blasthole line;
Bus L one end is divided into two-way after meeting initiator Q, another terminated bus three-way pipe T:Pass through the Ith trivial top-stitching all the way D1 connects one end of the Ith first three-way pipe T in area;Another way meets the IIth area by being in series with the connecting line of low section detonator MS3 One end of one three-way pipe T;
Ith first, area three-way pipe T is further divided into two-way:The 1st group of the Ith area group top-stitching G1 is met all the way, on the 1st group of group top-stitching G1 The low section detonator MS3 of multi beam is in series with, cluster joins more blasthole lines, the every blasthole line other end around each low section detonator MS3 High section detonator MS15 is connected to, high section detonator MS15 is loaded on the corresponding blasting charge and in corresponding blasthole H;Another way is led to Cross and be in series with the connecting line of low section detonator MS3 and meet second, the Ith area three-way pipe T;
Ith second, area three-way pipe T is further divided into two-way:The 2nd group of the Ith area group top-stitching G2 is met all the way, on the 2nd group of group top-stitching G2 The low section detonator MS3 of multi beam is in series with, cluster joins more blasthole lines, the every blasthole line other end around each low section detonator MS3 High section detonator MS15 is connected to, high section detonator MS15 is loaded on the corresponding blasting charge and in corresponding blasthole H;Another way is led to Cross and be in series with the connecting line of low section detonator MS3 and meet the 3rd, the Ith area three-way pipe T;
Afterwards and so on form the multigroup blasting network device in the Ith area;
IIth first, area three-way pipe T is further divided into two-way:The IIth trivial top-stitching D2 is met all the way, and the IIth trivial top-stitching D2 is another Second, the IIth area three-way pipe T is terminated, the IIth second, area three-way pipe T is also further divided into two-way:The first via connects the 1st group of the IIth area group Top-stitching, the second tunnel meet the 3rd, the IIth area three-way pipe T by being in series with the connecting line of low section detonator MS3;Each group network afterwards It is identical with the Ith area each group network;
IIth first, area three-way pipe T another ways meet the IIIth area first by being in series with the connecting line of low section detonator MS3 A three-way pipe T, the IIIth area each group network are identical with the IIth area each group network;
Afterwards and so on form multi-region blasting network device;
And:By accurately calculating network delay time, in different groups of different areas or same area, there is identical detonation Wire jumper J is connected to by three-way pipe T between the position at time point.
Fig. 3 is the embodiment for implementing demolition blasting to Guangxi Guigang bridge using the utility model principle design.
1st, the bridge is located at the Yu Jiangnan bank approach channels upstream of Guigang south loop, and east connects southern loop, east side Qiao Xiayou rivers Southern main road passes through, and about 79 m of northeast side has village residential house, and for 9.6 m of NATO to build new Bridge Foundation, northwest, southwest are building site, west There is southern loop in bis- bridges of about 230 m connections Yu Jiang, southern side to Jiangnan main road turntable.Surrounding enviroment are sufficiently complex, and construction of structures is more, Difficulty of construction is larger.Bridge to be torn open is half-through reinforced concrete ribbed arch bridge structure, bridge overall length 147.0 m, total 18.6 m of clear span, 9.0 m of bridge floor car lane, 2 × 3.0 m of non-motor vehicle and pavement, on arch bridge floor for 12 across 6.0 m, the continuous beam slab of monoblock type 72.0 m of structure, arch arc length are 105.3 m, a length of 107.2 m of hogback outer arc, a length of 103.5 m of soffit inner arc, vault away from High 13.0 m of bridge floor, bridge are made of abutment, approach span, main aperture across, arch rib, abutment foreground, pillar, sunpender etc..This separate explosion needs Main aperture is removed across, abutment foreground, pillar, arch rib;And abutment, approach span are without explosion, about 3100 m3 of whole project.
2nd, blasting scheme
2.1 blasting parameter
Since Guigang bridge environment is complicated, comminuted explosion is needed bridge reinforcement is fully disintegrated with concrete, so as to the later stage Underwater scarfing cinder.Main aperture across the part in navigation channel is carried out whole cloth holes and realizes to crush across, arch rib, abutment foreground, pillar, bridge floor etc. Property explosion, i.e., removed using the method for delay-porous Millisecond Controlled Blasting outside hole, its Bridge cloth hole is up to more than 5,000.
2.2 explosive
In view of blow-up point engineering-environment is complicated, nearby there is various electric wire networks, on the premise of demolition effect is not influenced from Detonation security standpoint sets out, and is detonated using non-electric initiation network.3 sections of 2# rock emulsion explosives, millisecond detonators are selected in explosion Detonator, 15 sections of Nonel detonators of millisecond, nonel tube, three-way pipe, detonating needle, colloid conducting wire, adhesive plaster and initiator etc..
2.3 network connection modes
Using the NONEL demolition network of delay outside hole-more Delay between holes, with high section detonator, hole in network connection mesoporous The low section detonator of external application, to ensure in hole after blasting cap initiation, the network of rear propagation of explosion detonator is not destroyed.Adopted in network connection mesoporous With 15 sections of Nonel detonator ignition charges, per beam, connection blasthole number is no more than 20, and using 2 hair 3 sections of detonator thunders of millisecond Pipe connects each beam, forms delay outside hole-more Delay between holes NONEL demolition networks.
2.4 firing order
The laterally and longitudinally tension of reinforcing bar and shear strength and concrete strength in blasting process are considered, by bridge knot The analysis in structure section, is divided into 8 fuze action zones by the bridge, and is divided into two symmetrical great Qu.With 50 between each area of each great Qu Ms carries out delays time to control, is divided into some groups again in each area, equally delays time to control is carried out with 50 ms between group, to be formed from bridge two Hold to centre(Ⅰ、Ⅰ′→Ⅱ、Ⅱ′→Ⅲ、Ⅲ′→Ⅳ、Ⅳ′)Blasting sequence, this method can effectively reduce Same millisecond blasting medicine Amount, and realize and Each part is progressively uniformly unloaded.
3 network reliabilities
3.1 reliability factors are analyzed
It is normal to blasthole more than 5,000 using delay-more Hole-hole short-delay blasting schemes outside hole in bridge demolition demolishing process Detonation, its blasting network are extremely complex.To avoid blasting network from destroying, to rationally design and optimize network, ensure blasting network The reliability of propagation of explosion.The non-artificial factor of destruction at demolition blasting network mainly has following three aspects;
(1)Blasting flyrock cut-out network connection
Since the uncertain factor of explosion produces a large amount of blasting flyrocks, network connection around may be damaged, There is phenomenon of miss-firing.
15 sections of detonators are used in hole, delay duration is 880 ± 60 ms;3 sections of detonators of hole external application, delay duration are 50 ± 10 Ms, minimum aperture is away from for 0.4 m, about 1950 m/s of detonator velocity of explosion.Ith, the most short safety of I ' area, first group of blasthole detonation is prolonged When about 820 ms of the time, every thereafter group of interval explosion most short safety delay time is 40 ms.Therefore, analysis detonation net is calculated Pass pops begin to propagation of explosion to last 1 blasthole hole in detonator the most long propagation of explosion time more than the delay time in the 1st blasthole hole, First quick-fried blasthole slungshot may damage rear quick-fried blasting circuit, must carry out corresponding security protection, just can guarantee that the peace at network Entirely.
(2)Blasting cap detonation product and metal fragment cut-out propagation of explosion network
After blasting cap detonation, explosion product and metal fragmentation are concentrated mainly on immediately below detonator both sides and afterbody.Wherein metal Fragment disperses with extremely strong directionality, is in spherical diffusion centered at the high explosive of detonator bottom, the initial velocity of metal fragment Degree is gradually reduced in air borne because being increased over time by drag effect.But the degree of metal fragment is big, and the propagation time is far small In the time being delayed outside detonator propagation of explosion and hole, fragmentation and metal jet that Nonel detonator explosion produces are easily to neighbouring detonator Have an impact, cause network propagation of explosion to interrupt or destroy surrounding network.
(3)Arch rib, which crushes to fall, pounds suspension road
About 107 m of arch arc length, vault fall with larger huge away from 0~13 m of bridge floor, blasting broken stone after explosion Impact force may destroy other networks of bridge floor.
It is most short along vertical bridge floor direction fall time since blasting broken stone disperses with non-directiveness, and cause arch rib The main cause that lower section network is destroyed.Bridge arch is the IV, the IV ' area, most short safety delay time=820+40 × 4 of its blasthole propagation of explosion= 980 ms, about propagation of explosion can calculate first group of blasthole about at ribbed arch 3/5 according to the safe delay time and start to the 16th beam blasthole It is quick-fried, most short=70 ms or so.Therefore floorings network about 21~30 m distances of propagation of explosion, can not finish floorings network propagation of explosion, The network of bridge floor under arch rib may be caused to destroy.
Based on above-mentioned network destructive factor, quantitative calculating is carried out to the propagation of explosion of blasting network reliability and has been analyzed, explosion It is the principal element for causing demolition blasting network reliability that slungshot, detonator metal fragment cut-out network and dismounting thing, which pound suspension road,. In order to realize that more blastholes and all detonators are effectively detonated, avoid because occurring miss-firing during propagation of explosion, interrupt and the accident such as blind big gun, or even lead Blast action direction is caused to change so as to produce blasting damage, improvement demolition effect is good, improves blasting quality, should pay much attention to network Safety, and the security protection of network reliability is carried out, ensure the propagation of explosion of networking security.
3.2 safeguard procedures
Extensive demolition blasting, requires height, using the detonation for the porous Millisecond Controlled Blasting that be delayed outside hole to blasting technique Mode, blasting circuit detonation propagation reliability of nonel tube are related to the success or failure of whole blasting engineering, and the importance of networking security protection is well imagined. , as breach, technological innovation will be carried out at blasting network weakest link, network reliability is improved to optimize network design.
(1)Wire jumper technology
Wire jumper technology refers to the factor that may be destroyed by analyzing network, accurate to calculate network delay time, from it A network line is connect between his area or group in the position of identical burst time point, unicom between Shi Liang areas or group, realizes that network is stablized Propagation of explosion.
1)Section wire jumper
Ith, the time-delayed safe time in I ' area is about 820 ms, and network can stablize 13 beam of propagation of explosion about 15~22m;IIIth, III ' area Delay time is about 760 ms, about about 15~21 m of 12 beam of propagation of explosion under the influence of area I, I ';Ith area and IIIth area part to be removed Network propagation of explosion can finish within the effective delay time, will not be damaged by factors such as blasting flyrocks.
IIth, II ' is big with the quantities at IV, IV ' place to be torn open of area, and the number of the boring hole is more, density is big and propagation of explosion distance, Yi Shouxian The influence of quick-fried blasthole and destroy network, the safety prevention measure at network must be taken.Ith, I ' be located at III, III ' area it is right under floorings IIth, smaller can be neglected is destroyed at network on II ' and IV, IV ' bridge floor.Section wire jumper technology is used in II, II ' and IV, IV ' area.Through Networking security calculates and analyzes the 13rd beam in first group of II the 3rd Zu He of area of Ke, IVth areas, in IVth areas of the 13rd Shu He of the 7th group of IIth area Wire jumper between second group of the 16th beam, is hereafter spaced 6 beam wire jumpers once, as shown in Fig. 4 a;IIth, the 15th beam in every group of II ' area and Wire jumper after 25th beam, is hereafter spaced 10 beam wire jumpers once, as shown in Fig. 4 b.
2)Wire jumper between group
IIth, II ' area's the number of the boring hole is more, and section wire jumper can not ensure the networking security in the region, so II, II ' area is at the same time Using wire jumper technology between group:Wire jumper and the 2nd group of the 12nd beam and the 5th group between 1st group of the 13rd beam and the 4th group of the 10th beam 9th interfascicular wire jumper, is hereafter spaced 6 beam wire jumpers once.It is interconnected, detonates from two to intermediate symmetry, such as between each group network Shown in Fig. 5.
(2)The gland or bedding of flexible material
Since floorings blasthole is intensive, during propagation of explosion detonator easily because front-seat blasthole is first quick-fried, blasting network be easier to by Metal fragment cut-out or slungshot are pounded disconnected.Therefore, often occur network propagation of explosion to interrupt in engineering explosion and cause local blind big gun or refuse Quick-fried phenomenon, can cause blast action direction to change initiation accident when serious.
This engineering uses the short-delay blasting that is delayed outside hole, uses flexible material gland outside hole on delay detonator before explosion, Influence of the fragment to disperse in blasting process to network can effectively be weakened.In view of this quantities is big and cost, gathers materials on the spot and adopt Covered and be pressed on detonator with sandbag, also there is certain protective action to network.With flexible material bedding about 3/5 under arch rib at bridge floor On the network of plate, to slow down blasting network because of arch rib blasting flyrock or influence of the metal fragment to blasting network of dispersing.
3.3 Engineering application analysis
This demolition blasting engineering uses the form of more blasthole small pit goafs, and be delayed network feature outside combined hole, utilizes wire jumper skill Art designs blasting network and blasting scheme, its Bridge cloth hole is up to more than 5,000.In whole blasting engineering implementation process, substantially by According to design method propagation of explosion, do not occur the failure of any influence demolition effect, and demolition effect meets design requirement, complies fully with pre- Phase effect.It is mainly manifested in:1. realize the completely broken of bridge structure, and reinforcing bar separates situation with concrete and reaches expected effect Fruit, underwater scarfing cinder operation are implemented smooth;2. using the elementary errors demolition by controlled blasting technology that is delayed outside the hole of wire jumper Technology design, pass through Stringent control is satisfied by with section explosive quantity and firing order, blasting vibration velocity, stone fling distance and other aspects《Shotfiring safety Code》Related request;3. it is smaller to implement influence of the explosion to surrounding environment and river, and there is no any unknown safety is hidden Suffer from.
4 conclusions
(1)By calculating analysis to the factor for influencing blasting network reliability, show for conventional blasting method network reliability Protection, networking security propagation of explosion can be realized by conventional art means.
(2)For extensive, complicated blasting engineering, using the short-delay blasting that is delayed outside hole, using wire jumper technology and pass through The gland of flexible material can effectively improve the reliability of blasting network.
(3)It is good by the blasting network reliability that is delayed outside the hole of wire jumper technology by case, design, using simple and direct And demolition effect is good, valuable reference frame is also provided for large-scale mine blasting excavation, possesses preferable promote in fact Trample meaning.

Claims (2)

1. a kind of nonel tube rise blast hole extension when subregion demolition blasting network apparatus, the network apparatus by initiator, enough Nonel tube, enough blastings charge, multiple connectors, multiple low section detonators and multiple high section detonators composition, it is special Sign is:
Nonel tube is divided into bus, connecting line, wire jumper, interval line, group top-stitching and blasthole line;
Bus one end connects initiator, is divided into two-way after another termination Bussing connector:The Ith area is connect by the Ith trivial top-stitching all the way One end of first connector;Another way connect the IIth first connector in area by being in series with the connecting line of low section detonator one End;
Ith first, area connector is further divided into two-way:The 1st group of the Ith area group top-stitching is connect all the way, is in series with the 1st group of group top-stitching more The low section detonator of beam, each cluster joins more blasthole lines around low section detonator, and every blasthole line is another to be terminated with high section detonator, High section detonator is loaded in the corresponding blasting charge;Another way meets second, the Ith area by being in series with the connecting line of low section detonator Connector;
Ith second, area connector is further divided into two-way:The 2nd group of the Ith area group top-stitching is connect all the way, is in series with the 2nd group of group top-stitching more The low section detonator of beam, each cluster joins more blasthole lines around low section detonator, and every blasthole line is another to be terminated with high section detonator, High section detonator is loaded in the corresponding blasting charge;Another way meets the 3rd, the Ith area by being in series with the connecting line of low section detonator Connector;
Afterwards and so on form the multigroup blasting network device in the Ith area;
IIth first, area connector is further divided into two-way:The IIth trivial top-stitching, the IIth trivial another termination the IIth of top-stitching are connect all the way Second, area connector, the IIth second, area connector are also further divided into two-way:The first via connects the 1st group of the IIth area group top-stitching, and second Road connects the 3rd, the IIth area connector by being in series with the connecting line of low section detonator;Each group network and each networking in the Ith area afterwards Road is identical;
IIth first, area connector another way connects first, the IIIth area connector by being in series with the connecting line of low section detonator, IIIth area each group network is identical with the IIth area each group network;
Afterwards and so on form multi-region blasting network device;
And:By accurately calculating network delay time, in different groups of different areas or same area, there is the identical burst time Wire jumper is connected to by connector between the position of point.
Subregion demolition blasting network apparatus when 2. nonel tube according to claim 1 plays blast hole extension, its feature exist In:Connector is three-way pipe and/or cluster coupling device.
CN201721407524.8U 2017-10-30 2017-10-30 Subregion demolition blasting network apparatus when nonel tube plays blast hole extension Withdrawn - After Issue CN207351319U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721407524.8U CN207351319U (en) 2017-10-30 2017-10-30 Subregion demolition blasting network apparatus when nonel tube plays blast hole extension

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721407524.8U CN207351319U (en) 2017-10-30 2017-10-30 Subregion demolition blasting network apparatus when nonel tube plays blast hole extension

Publications (1)

Publication Number Publication Date
CN207351319U true CN207351319U (en) 2018-05-11

Family

ID=62353203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721407524.8U Withdrawn - After Issue CN207351319U (en) 2017-10-30 2017-10-30 Subregion demolition blasting network apparatus when nonel tube plays blast hole extension

Country Status (1)

Country Link
CN (1) CN207351319U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107576237A (en) * 2017-10-30 2018-01-12 广西大学 Subregion demolition blasting network apparatus when nonel tube plays blast hole extension
CN111207641A (en) * 2020-01-08 2020-05-29 重庆中环建设有限公司 Delay design method for ensuring safety of digital-detonator mixed network
CN114046700A (en) * 2021-11-30 2022-02-15 湖南柿竹园有色金属有限责任公司 Intelligent detonation network system during hole epitaxy and detonation method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107576237A (en) * 2017-10-30 2018-01-12 广西大学 Subregion demolition blasting network apparatus when nonel tube plays blast hole extension
CN107576237B (en) * 2017-10-30 2023-07-21 广西大学 Partition demolition blasting network device for non-electric blasting tube blasthole epitaxy
CN111207641A (en) * 2020-01-08 2020-05-29 重庆中环建设有限公司 Delay design method for ensuring safety of digital-detonator mixed network
CN111207641B (en) * 2020-01-08 2021-01-05 重庆中环建设有限公司 Delay design method for ensuring safety of digital-detonator mixed network
CN114046700A (en) * 2021-11-30 2022-02-15 湖南柿竹园有色金属有限责任公司 Intelligent detonation network system during hole epitaxy and detonation method thereof

Similar Documents

Publication Publication Date Title
CN102606159B (en) Medium thick heavy-pitch crushed ore body frame type artificial top downward segmenting cemented filling method
CN207351319U (en) Subregion demolition blasting network apparatus when nonel tube plays blast hole extension
CN102927867B (en) Vibration absorbing method for cut presplitting blasting
CN108661643A (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN109139104B (en) Drainage construction method for tunnel penetrating through clastic rock steep-dip reverse-thrust water-rich fault
CN107576237A (en) Subregion demolition blasting network apparatus when nonel tube plays blast hole extension
CN106288988A (en) Intelligence carbon dioxide blasting technology method
CN111411962A (en) Coal mine rock burst treatment method
CN111442701B (en) Refined blasting construction method for narrow deep foundation pit under complex geological condition
CN105823386A (en) Method for blasting demolition of reinforced concrete supporting beam in foundation pit
CN107060773B (en) A kind of underground chamber drilling and blasting method damping excavation method of static(al) explosion presplitting shock insulation
CN106225613A (en) A kind of efficient segmentation method of ignition in tunnel excavating process
CN110230495A (en) A kind of subway station double -side approach construction Core Soil excavation method
CN103362077A (en) Construction method for dismounting haplopore box type arch bridge by virtue of water pressure short hole and medium-length hole comprehensive decrepitation method
CN110219650B (en) Deep hole subsequent filling mining method in environment reconstruction stage
CN107328322A (en) Cable-stayed type truss bridge blasting method is held under one kind
CN112228079B (en) Construction method for newly-built tunnel by crossing existing line at small angle
CN116658178B (en) Ultra-small clear distance tunnel subsection differential blasting vibration reduction and isolation construction method
CN111780633B (en) Step-type rapid excavation method for IV-V-level surrounding rock lower step of double-track tunnel
CN103233739A (en) Mining method for thick and large ore pillar under filling body package
CN112923821A (en) Drilling and blasting tunneling method for reducing and fixing rock resistance
CN114018112B (en) Nuclear island and corridor foundation pit negative excavation blasting structure and blasting method
CN113091542A (en) Railway blasting construction method
CN110530220A (en) A kind of blasting technology for reservoir dam
CN110823031A (en) Blasting construction method for shallow tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20180511

Effective date of abandoning: 20230721

AV01 Patent right actively abandoned

Granted publication date: 20180511

Effective date of abandoning: 20230721