CN110530220A - A kind of blasting technology for reservoir dam - Google Patents

A kind of blasting technology for reservoir dam Download PDF

Info

Publication number
CN110530220A
CN110530220A CN201910871411.0A CN201910871411A CN110530220A CN 110530220 A CN110530220 A CN 110530220A CN 201910871411 A CN201910871411 A CN 201910871411A CN 110530220 A CN110530220 A CN 110530220A
Authority
CN
China
Prior art keywords
hole
blasting
reservoir dam
temporary plug
blasting technology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910871411.0A
Other languages
Chinese (zh)
Inventor
蒋文斌
刘士兵
伍锡南
刘广勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Nanling Engineering Co Ltd
Original Assignee
Hunan Nanling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Nanling Engineering Co Ltd filed Critical Hunan Nanling Engineering Co Ltd
Priority to CN201910871411.0A priority Critical patent/CN110530220A/en
Publication of CN110530220A publication Critical patent/CN110530220A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of blasting technologies for reservoir dam, comprising the following steps: S1 excavates the diversion tunnel for the permanent blockage that one end conducting is external, one end extends to drainpipe;S2, demolition blasting permanent blockage;S3, demolition blasting temporary plug.Blasting technology in the present invention can effectively form the diversion tunnel of a communicated drainage pipe, effectively improve drainage efficiency, accelerate reservoir and be vented speed, advantageously ensure that the progress of duration.

Description

A kind of blasting technology for reservoir dam
Technical field
A kind of engineering explosion technical field of the present invention, and in particular to blasting technology for reservoir dam.
Background technique
Explosion is common a kind of construction means in mining industry construction or civil engineering.It needs to process explosion in construction area Hole, the native lycopod of addition explosive progress is dynamic in blast hole or rock is scraped.Reservoir dam will appear leakage as time goes by and ask Topic, when leakage increases to a certain extent, it may be desirable to reservoir is vented to carry out comprehensive, thorough seepage treatment to dam.But Be under partial picture, the proper drainage system of reservoir cannot within the desired time complete unwatering inventory's water, influence the duration.It examines Consider part reservoir dam and the construction period is provided with drainpipe, but drainpipe passes through armored concrete knot after dam is built up The temporary plug and permanent blockage of structure block, and the present invention provides a kind of leading for communicated drainage pipe of constructing out on reservoir dam Flow the blasting technology in hole.
Summary of the invention
A kind of technical solution that the present invention uses is:
A kind of blasting technology for reservoir dam, comprising the following steps:
S1 excavates the diversion tunnel for the permanent blockage that one end conducting is external, one end extends to drainpipe;
S2, demolition blasting permanent blockage;
S3, demolition blasting temporary plug.
Preferably, base tunnel is first tunneled in S3, then global blowup removes the temporary plug.
Preferably, S3 the following steps are included:
A development blasting by the way of V-cut on the outer end face of the temporary plug goes out the base tunnel;
Blasthole, temporary plug described in demolition blasting is arranged in b on the outer end face of the temporary plug.
Preferably, the cross section of the base tunnel is less than the face area of the temporary plug, the length of the temporary plug For L, the length of interval of the base tunnel is [0.6L, 0.75L], is tunneled using horizontal multistage wedge shot.
Preferably, development blasting, each Excavation Length are 2m to the base tunnel several times, when driving surplus is less than 2m, pick It is surplus into length.
Preferably, the cross-sectional area ratio of the cross section of the base tunnel and the temporary plug is 0.2-0.25.
Preferably, the blasthole is drilled using hand air drill, and the blasthole diameter is set as 42mm.
Preferably, the blasthole includes via hole, periphery hole and blast hole, wherein the blast hole is located at intermediate region, The via hole and the periphery hole are arranged around the blast hole.
Preferably, the linear charging density of the blast hole, the via hole and the periphery hole is respectively 1kg/m, 1kg/m And 0.5kg/m.
Preferably, each blast hole respectively arranges that hair MS1~MS10 millisecond time-delay is led in the position of hole depth 1/3,2/3 Booster detonator, in outside hole by detonator cluster articulation, using two MS1 sections of Nonel detonator propagation of explosions of hair at cluster interlink point, each branch again into Row cluster connection is formed using two MS1 section Nonel detonator propagation of explosions of hair and is sent out instant electric detonator concatenated using two behind compound circuit and excite The Nonel detonator of propagation of explosion extends to the safe initiation point initiation outside water conservancy diversion hole outlet by 500m propagation of explosion conducting wire.
The beneficial effects of the present invention are:
Blasting technology in the present invention can effectively form the diversion tunnel of a communicated drainage pipe, effectively improve draining effect Rate accelerates reservoir and is vented speed, advantageously ensures that the progress of duration.
Specific embodiment
The present invention is a kind of blasting technology for reservoir dam, comprising the following steps:
S1 excavates the diversion tunnel for the permanent blockage that one end conducting is external, one end extends to drainpipe;
S2, demolition blasting permanent blockage;
S3, demolition blasting temporary plug.
The diversion tunnel that a communicated drainage pipe can be effectively formed in this way effectively improves drainage efficiency, accelerates reservoir and puts Air speed degree advantageously ensures that the progress of duration.
In order to avoid being impacted to dam, in step S2 and S3, it is all made of and first tunnels out certain compensation space, then Carry out the mode of demolition blasting.It is farther from reservoir since permanent blockage is located at the rear end of temporary plug, it can repeatedly explosion tear open Remove, without too consider at its end facing water whether can onepull remove.And temporary plug needs to guarantee primary quick-fried due to nearly water Forcible entry removes, and it is excessive otherwise to be mended quick-fried difficulty under water, therefore the explosion of temporary plug is required higher.
So being limited in detail in the present embodiment with the demolition blasting of temporary plug.
Preferably, base tunnel is first tunneled in S3, then global blowup removes temporary plug.Specifically, S3 the following steps are included:
A development blasting by the way of V-cut on the outer end face of temporary plug goes out base tunnel;
Blasthole, demolition blasting temporary plug is arranged in b on the outer end face of temporary plug.
The setting of the base tunnel increases the area for facing the sky scope of freedom, provides enough compensation spaces, V-cut clipping Power is small, creates good condition for explosion.
Preferably, the cross section of base tunnel is less than the face area of temporary plug, and the length of temporary plug is L, the length of base tunnel Spending section is [0.6L, 0.75L], is tunneled using horizontal multistage wedge shot.In actual mechanical process, base tunnel is quick-fried several times Broken driving, each Excavation Length is 2m, and when tunneling surplus less than 2m, Excavation Length is surplus, for example Excavation Length is 5m, Then it is divided into the 3 separate explosions driving of 2m, 2m and 1m.
And the cross section of base tunnel and the cross-sectional area ratio of temporary plug are 0.2-0.25.It opens up position and is located at interim block up The middle position of the top and bottom of plug.
Blasthole is drilled using hand air drill, and blasthole diameter is set as 42mm.Blasthole is specifically divided into via hole, periphery hole and quick-fried Holes, wherein blast hole is located at intermediate region, via hole and periphery hole and is arranged around blast hole.Blast hole on base tunnel inner face There are three types of specifications, and one tilts down 20 °, hole depth 0.2L, secondly 45 °, hole depth 0.4L are tilted down, thirdly horizontally disposed, hole Deep 0.1L.Also, upstream face of the blasthole apart from temporary plug at least 0.08L.Via hole, periphery hole and blast hole load fried Medicine, the linear charging density of blast hole, via hole and periphery hole are respectively 1kg/m, 1kg/m and 0.5kg/m.And each blast hole Respectively arrange hair MS1~MS10 millisecond time-delay Nonel detonator in the position of hole depth 1/3,2/3, in outside hole by detonator cluster articulation, Using two MS1 sections of Nonel detonator propagation of explosions of hair at cluster interlink point, each branch carries out cluster connection again, using two MS1 sections of detonator thunders of hair Pipe propagation of explosion forms behind compound circuit and send out concatenated instant electric detonator using two and excite the Nonel detonator of propagation of explosion, passed by 500m Quick-fried conducting wire extends to the safe initiation point initiation outside water conservancy diversion hole outlet.
By wide 6m, high 6.6m, long 6m temporary plug for, base tunnel is designed as wide 3.5m, high 2.5m, depth 4.35m, and sets It sets in the central area of temporary plug.Periphery hole is arranged 26, and is a circle evenly around base tunnel arrangement.Via hole, which is set to, leads The upper area in hole, and in three layers of distribution in 6 holes, 7 holes, 7 holes.Blast hole is arranged 68, and is arranged at base tunnel inner face.Tool Body include 10 horizontal wedge cutters, 28 lateral apertures, 20 angling holes for tilting down 20 °, 10 tilt down 45 ° Angling hole.Wherein 10 wedge cutters are distributed at two vertical column bilateral symmetries, and lateral aperture is evenly distributed on wedge cutter Two sides, 20 ° of angling hole horizontal arrangements are in the lower section of lateral aperture and wedge cutter, and 45 ° of angling hole horizontal arrangements are in 20 ° of angling holes Lower section.Wedge cutter bottom hole pitch 0.2m, aperture are away from 1.3m, remaining pitch-row 0.3m;Temporary plug surrounding via hole pitch-row 0.5 ~0.8m;Periphery hole pitch-row 0.5m.The blasthole being arranged in this way, when being loaded, being ignited using explosive above-mentioned, can be safe, It is one step completed to remove temporary plug completely, and dam and neighboring buildings will not be impacted simultaneously.
Above-mentioned blasting technology can effectively remove temporary plug, and temporary plug, which excavates base tunnel and increases, faces the sky scope of freedom Area provides enough compensation spaces, and V-cut clipping power is small, creates good condition for explosion.And it rationally designs The total footage of temporary plug excavation with guide pit, the reserved thickness for blocking end facing water, blasthole hole depth be to ensure that blocking do not destroyed by hydraulic pressure, The key of sliding is not generated, can provide reliable guarantee for shotfiring safety operation.Use horizontal multistage wedge-shaped simultaneously and vertical wedge shape Slotting technology is combined, can be interacted along two, axis opposite scope of freedom directions of blocking, vertical wedge cut is along blasthole axis 20 ° generate wedge with 45 ° of directions, exacerbate the destruction of temporary plug upstream face support shuttering and armored concrete blocking.
Above-described embodiment is preferred embodiment of the invention, and the present invention can also have other embodiments.The technology of this field Personnel can also make equivalent deformation or replacement on the premise of without prejudice to spirit of the invention, these equivalent variation or replacement are wrapped It is contained in range set by the claim of this application.

Claims (10)

1. a kind of blasting technology for reservoir dam, which comprises the following steps:
S1 excavates the diversion tunnel for the permanent blockage that one end conducting is external, one end extends to drainpipe;
S2, demolition blasting permanent blockage;
S3, demolition blasting temporary plug.
2. a kind of blasting technology for reservoir dam as described in claim 1, which is characterized in that first driving is led in S3 Hole, then global blowup remove the temporary plug.
3. a kind of blasting technology for reservoir dam as claimed in claim 2, which is characterized in that S3 the following steps are included:
A development blasting by the way of V-cut on the outer end face of the temporary plug goes out the base tunnel;
Blasthole, temporary plug described in demolition blasting is arranged in b on the outer end face of the temporary plug.
4. a kind of blasting technology for reservoir dam as claimed in claim 3, which is characterized in that the cross section of the base tunnel Less than the face area of the temporary plug, the length of the temporary plug is L, the length of interval of the base tunnel be [0.6L, 0.75L], it is tunneled using horizontal multistage wedge shot.
5. a kind of blasting technology for reservoir dam as claimed in claim 4, which is characterized in that the base tunnel is quick-fried several times Broken driving, each Excavation Length are 2m, and when tunneling surplus less than 2m, Excavation Length is surplus.
6. a kind of blasting technology for reservoir dam as claimed in claim 3, which is characterized in that the cross section of the base tunnel Cross-sectional area ratio with the temporary plug is 0.2-0.25.
7. a kind of blasting technology for reservoir dam as claimed in claim 3, which is characterized in that the blasthole uses hand wind Drilling, and the blasthole diameter is set as 42mm.
8. a kind of blasting technology for reservoir dam as claimed in claim 3, which is characterized in that the blasthole includes auxiliary Hole, periphery hole and blast hole, wherein the blast hole is located at intermediate region, the via hole and the periphery hole around described quick-fried Holes setting.
9. a kind of blasting technology for reservoir dam as claimed in claim 8, which is characterized in that the blast hole, described The linear charging density of via hole and the periphery hole is respectively 1kg/m, 1kg/m and 0.5kg/m.
10. a kind of blasting technology for reservoir dam as claimed in claim 8, which is characterized in that each blast hole Respectively arrange hair MS1~MS10 millisecond time-delay Nonel detonator in the position of hole depth 1/3,2/3, in outside hole by detonator cluster articulation, Using two MS1 sections of Nonel detonator propagation of explosions of hair at cluster interlink point, each branch carries out cluster connection again, using two MS1 sections of detonator thunders of hair Pipe propagation of explosion forms behind compound circuit and send out concatenated instant electric detonator using two and excite the Nonel detonator of propagation of explosion, passed by 500m Quick-fried conducting wire extends to the safe initiation point initiation outside water conservancy diversion hole outlet.
CN201910871411.0A 2019-09-16 2019-09-16 A kind of blasting technology for reservoir dam Pending CN110530220A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910871411.0A CN110530220A (en) 2019-09-16 2019-09-16 A kind of blasting technology for reservoir dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910871411.0A CN110530220A (en) 2019-09-16 2019-09-16 A kind of blasting technology for reservoir dam

Publications (1)

Publication Number Publication Date
CN110530220A true CN110530220A (en) 2019-12-03

Family

ID=68668655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910871411.0A Pending CN110530220A (en) 2019-09-16 2019-09-16 A kind of blasting technology for reservoir dam

Country Status (1)

Country Link
CN (1) CN110530220A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111780638A (en) * 2020-07-01 2020-10-16 中国水利水电第十六工程局有限公司 Blasting demolition method for overflow dam section of old dam

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
蒋文斌等: "白云水电站大坝导流洞临时堵塞爆破", 《工程爆破》 *
谭界雄等: "白云水电站混凝土面板堆石坝渗漏处理技术", 《人民长江》 *
韩可林等: "导流隧洞封堵混凝土内放水洞爆破开挖控制技术", 《湖南水利水电》 *
黄昌献等: "放空管可爆堵头技术在洞巴面板堆石坝的应用", 《红河水》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111780638A (en) * 2020-07-01 2020-10-16 中国水利水电第十六工程局有限公司 Blasting demolition method for overflow dam section of old dam
CN111780638B (en) * 2020-07-01 2023-07-21 中国水利水电第十六工程局有限公司 Blasting demolition method for overflow dam segment of old dam

Similar Documents

Publication Publication Date Title
CN101270967B (en) Stress-relief blasting method
KR100780916B1 (en) Digging a method of construction base rock environmental pollution using many free face
KR100358780B1 (en) Tunnel Blasting Method for using Air Tube
CN106091848B (en) It is a kind of to realize overlength, the method for high inclination-angle tunnel anchorage top bar explosion
CN103244180B (en) Gob-side entry driving surrounding rock control method using remaining small pillars
CN104532818A (en) Treatment method for strip mine goaf
CN104819670B (en) Pre-drilling mesopore shaft excavation blasting method
CN102494571A (en) Construction method for damped blasting of tunnels
CN107060773B (en) A kind of underground chamber drilling and blasting method damping excavation method of static(al) explosion presplitting shock insulation
CN111102892B (en) Wedge-shaped cut blast hole arrangement method suitable for blasting excavation of deep-buried tunnel
CN104457466B (en) A kind of blasting method of tunnel open excavation section
CN105865281A (en) Method for transverse open excavation controlled blasting construction adjacent to power station and booster station
CN110530220A (en) A kind of blasting technology for reservoir dam
CN112880501B (en) Flight-limited hole drilling and blasting method for controlling tunnel blasting flyrock
CN109405688A (en) Close on the blasting construction method in existing operation tunnel
US20230168069A1 (en) Annular shaped-charge housing for blasting and method of using the same
KR100438028B1 (en) A tunnel blasting method favorable to the environment,which utilizes pre-splitting and an upper center cut
CN112964143B (en) Three-time blasting method for hollow hole straight-hole cut
CN112945035B (en) Construction method for pre-splitting blasting excavation of middle and lower layers of diversion tunnel
CN103075936B (en) Rock pillar rockburst step-by-step relief water filling blasting method in deep-buried tunnel penetrating process
CN109341451A (en) A kind of damped blasting of tunnels structure and construction
CN209295800U (en) A kind of damped blasting of tunnels structure
CN111220036B (en) Blasting method for pilot tunnel at lower section of vertical shaft water curtain roadway
CN210570271U (en) Cut hole structure for tunnel blasting tunneling engineering
CN103075935A (en) Rockblast stress relief water storage guide hole type blasting method for deep-buried round tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191203

RJ01 Rejection of invention patent application after publication