CN207348246U - A kind of steel construction heat-insulation system construction - Google Patents

A kind of steel construction heat-insulation system construction Download PDF

Info

Publication number
CN207348246U
CN207348246U CN201721205903.9U CN201721205903U CN207348246U CN 207348246 U CN207348246 U CN 207348246U CN 201721205903 U CN201721205903 U CN 201721205903U CN 207348246 U CN207348246 U CN 207348246U
Authority
CN
China
Prior art keywords
steel
layer
screed
pedestal
heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721205903.9U
Other languages
Chinese (zh)
Inventor
徐立明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chuang Chuang Precision Equipment (anhui) Co Ltd
Original Assignee
Chuang Chuang Precision Equipment (anhui) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chuang Chuang Precision Equipment (anhui) Co Ltd filed Critical Chuang Chuang Precision Equipment (anhui) Co Ltd
Priority to CN201721205903.9U priority Critical patent/CN207348246U/en
Application granted granted Critical
Publication of CN207348246U publication Critical patent/CN207348246U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a kind of steel construction heat-insulation system construction,Including pedestal,Connecting seat and mortar cover,The pedestal is internally provided with extruded sheet,And the extruded sheet is fitted closely with pedestal,The right side of the extruded sheet is equipped with different in nature steel plate layer,And the different in nature steel plate layer is fitted closely with extruded sheet,The right side of the opposite sex steel plate layer is equipped with polymer modification adhesive mortar and screed-coat,And the screed-coat is fixed by polymer modification adhesive mortar with different in nature steel plate layer and bonded,It is combined into using the advantages of other steel construction heat-insulation systems,Equipped with flexible adhesion layer,To prevent because the change of the temperature difference of weather,The amount of deforming of expanding with heat and contract with cold of steel,Screed cracks,So as to cause EPS thermal insulation boards to come off,Flexible adhesion layer is specially designed with the left of EPS thermal insulation boards,Using flexible material,The deformation of itself can also be adjusted according to the deflection of steel while the intensity of itself is ensured,To ensure that EPS thermal insulation boards will not come off because of the deformation of steel.

Description

A kind of steel construction heat-insulation system construction
Technical field
Heat-insulation system technical field is the utility model is related to, is specially a kind of steel construction heat-insulation system construction.
Background technology
The structure that steel construction is made of steel material, is one of main building construction types.Structure is mainly by shaped steel With steel plate etc. made of the component composition such as girder steel, steel column, steel truss, generally use weld seam between each component or component, bolt or Rivet interlacement, is widely used in the fields such as large-sized workshop, venue, Super High, is more and more widely used in construction industry.
But existing steel construction heat-insulation system, the common heat-insulation system construction kept the temperature to steel construction use mortar mostly Direct sticking heat-preservation plate, although steel construction has good plasticity and toughness, temperature deformation amount is big, the fact that in construction Prove, sticking heat-preservation plate is using rigid materials such as adhesive mortars, it is difficult to the deflection of steel construction is adapted to, so as to cause mortar Layer cracking, thermal insulation board hollowing come off.
So how to design a kind of steel construction heat-insulation system construction, becoming us will currently solve the problems, such as.
Utility model content
The purpose of this utility model is to provide a kind of steel construction heat-insulation system construction, to solve to carry in above-mentioned background technology The common heat-insulation system kept the temperature to steel construction the construction gone out uses the direct sticking heat-preservation plate of mortar mostly, although steel construction has There are good plasticity and toughness, but the problems such as temperature deformation amount is big.
To achieve the above object, the utility model provides following technical solution:A kind of steel construction heat-insulation system construction, including Pedestal, connecting seat and mortar cover, the pedestal is internally provided with extruded sheet, and the extruded sheet is fitted closely with pedestal, The right side of the extruded sheet is equipped with different in nature steel plate layer, and the different in nature steel plate layer is fitted closely with extruded sheet, the opposite sex steel plate The right side of layer is equipped with polymer modification adhesive mortar and screed-coat, and the screed-coat passes through polymer modification with different in nature steel plate layer Adhesive mortar, which is fixed, to be bonded, and the right side of the mortar cover is equipped with waterproof layer, and between the waterproof layer and mortar cover It is arranged in parallel, the connecting seat is internally provided with screw hole and screw, and screw hole insertion is arranged in connecting seat, and each base All it is to be fixedly connected by connecting seat with screw between seat.
Preferably, the right side of the screed-coat is equipped with alkali resistant glass fibre open weave cloth, and the alkali resistant glass fibre open weave cloth is in " net Lattice " shape is covered on screed-coat.
Preferably, the right side of the waterproof layer is equipped with flexible adhesion layer, and the flexible adhesion that the flexible adhesion layer uses Material.
Preferably, the right side of the waterproof layer is equipped with EPS thermal insulation boards, and the EPS thermal insulation boards are using polystyrene Foamed plastics, its thickness are 5cm.
Preferably, the outer surface of the pedestal is equipped with fireprotection layer, and the fireprotection layer is using styrofoam fire proofing material.
Compared with prior art, the beneficial effects of the utility model are:This kind of steel construction heat-insulation system construction, using other The advantages of steel construction heat-insulation system, is combined into, equipped with flexible adhesion layer, to prevent because the change of the temperature difference of weather, steel Expand with heat and contract with cold the amount of deforming, screed cracking, so as to cause EPS thermal insulation boards to come off, is specially designed in the left side of EPS thermal insulation boards Flexible tack coat, using flexible material, while the intensity of itself is ensured can also according to the deflection of steel come The deformation of itself is adjusted, to ensure that EPS thermal insulation boards will not come off because of the deformation of steel, greatly improves EPS thermal insulation boards Stability, extends its service life, and equipped with fireprotection layer, to ensure the security of EPS thermal insulation boards, one is devised in its outer surface Layer fireprotection layer, can protect whole steel body structure, can also strive for more times for the escape of people in the event of unexpected, greatly Big improves its security, has good development prospect in future.
Brief description of the drawings
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the pedestal partial structural diagram of the utility model;
In figure:1- pedestals;2- opposite sex steel plate layers;3- polymer modification adhesive mortars;4- screed-coats;5- alkali-resisting glass fiber grids Cloth;6- mortar covers;7- waterproof layers;8- flexible adhesion layers;9-EPS thermal insulation boards;10- extruded sheets;11- connecting seats;12- spiral shells Hole;13- fireprotection layers;14- screws.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work All other embodiments obtained, shall fall within the protection scope of the present invention.
- 2 are please referred to Fig.1, the utility model provides a kind of technical solution:A kind of steel construction heat-insulation system construction, including base Seat 1, connecting seat 11 and mortar cover 6, the pedestal 1 is internally provided with extruded sheet 10, and the extruded sheet 10 and pedestal 1 are tight Closely connected conjunction, the right side of the extruded sheet 10 is equipped with different in nature steel plate layer 2, and the different in nature steel plate layer 2 is fitted closely with extruded sheet 10, The right side of the opposite sex steel plate layer 2 is equipped with polymer modification adhesive mortar 3 and screed-coat 4, and the screed-coat 4 and different in nature steel plate Layer 2 is fixed by polymer modification adhesive mortar 3 and bonded, and the right side of the mortar cover 6 is equipped with waterproof layer 7, and described anti- It is arranged in parallel between water layer 7 and mortar cover 6, the connecting seat 11 is internally provided with screw hole 12 and screw 14, and the spiral shell The insertion of hole 12 is arranged in connecting seat 11, and is to be fixedly connected by connecting seat 11 with screw 14 between each pedestal 1.
Preferably, the right side of the screed-coat 4 is equipped with alkali resistant glass fibre open weave cloth 5, and the alkali resistant glass fibre open weave cloth 5 is in " grid " shape is covered on screed-coat 4, has alkali resistance, pliability and stretching resistance, it is possible to increase the intensity of total, reduces The risk of cracking.
Preferably, the right side of the waterproof layer 7 is equipped with flexible adhesion layer 8, and the flexibility that the flexible adhesion layer 8 uses is glued Material is tied, the deformation of itself can also be adjusted according to the deflection of steel while the intensity of itself is ensured, to ensure EPS Thermal insulation board 9 will not come off because of the deformation of steel, greatly improve the stability of EPS thermal insulation boards 9.
Preferably, the right side of the waterproof layer 7 is equipped with EPS thermal insulation boards 9, and the EPS thermal insulation boards 9 are using polyphenyl second Alkene foamed plastics, its thickness are 5cm, can provide Insulation for total, allow temperature to reach balanced, while also can be Room plays insulation effect, greatly improves the practicality.
Preferably, the outer surface of the pedestal 1 is equipped with fireprotection layer 13, and the fireprotection layer 13 is prevented fires using styrofoam Material, can protect whole steel body structure, can also strive for more times for the escape of people in the event of unexpected, greatly Improve its security.
Operation principle:First, single steel body structure is used into screw by being arranged on the screw hole 12 inside connecting seat 11 14 being fixedly connected successively, secondly, different in nature steel plate layer 2 are installed on the right side of extruded sheet 10, such design can allow There is the space expanded with heat and contract with cold between steel plate and steel plate, then, polymer modification adhesive mortar is spread on the right side of different in nature steel plate layer 2 3 carry out the processing at interfaces, and thickness facilitates the bonding between polymer modification adhesive mortar 3 and screed-coat 4, Ran Hou in 2-3mm The right side of screed-coat 4 directly covers one layer of alkali resistant glass fibre open weave cloth 5, soft since alkali resistant glass fibre open weave cloth 5 has stronger alkali resistance Toughness, pull resistance, so as to greatly improve the overall stability and intensity of building, while also ensure that the security of building, Finally, Insulation is provided for total by EPS thermal insulation boards 9, allows temperature to reach balanced, while can also risen for room To insulation effect, the practicality is greatly improved, fireprotection layer 13 is also set up on the right side of EPS thermal insulation boards 9, can be protected whole Structure will not be destroyed by fire.
While there has been shown and described that the embodiment of the utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from the principle of the utility model and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of steel construction heat-insulation system construction, including pedestal (1), connecting seat (11) and mortar cover (6), its feature exist In:The pedestal (1) is internally provided with extruded sheet (10), and the extruded sheet (10) is fitted closely with pedestal (1), the extrusion molding The right side of plate (10) is equipped with different in nature steel plate layer (2), and the different in nature steel plate layer (2) fits closely with extruded sheet (10), described different Property steel plate layer (2) right side be equipped with polymer modification adhesive mortar (3) and screed-coat (4), and the screed-coat (4) and different in nature steel Flaggy (2) is bonded by the way that polymer modification adhesive mortar (3) is fixed, and the right side of the mortar cover (6) is equipped with waterproof layer (7), and between the waterproof layer (7) and mortar cover (6) it is arranged in parallel, the connecting seat (11) is internally provided with screw hole (12) and screw (14), and the screw hole (12) insertion is arranged in connecting seat (11), and is to pass through between each pedestal (1) Connecting seat (11) is fixedly connected with screw (14).
A kind of 2. steel construction heat-insulation system construction according to claim 1, it is characterised in that:The right side of the screed-coat (4) Side is equipped with alkali resistant glass fibre open weave cloth (5), and the alkali resistant glass fibre open weave cloth (5) is covered on screed-coat (4) in " grid " shape.
A kind of 3. steel construction heat-insulation system construction according to claim 1, it is characterised in that:The right side of the waterproof layer (7) Side is equipped with flexible adhesion layer (8), and the flexible bonding material that the flexible adhesion layer (8) uses.
A kind of 4. steel construction heat-insulation system construction according to claim 1, it is characterised in that:The right side of the waterproof layer (7) Side is equipped with EPS thermal insulation boards (9), and the EPS thermal insulation boards (9), using polystyrene foam plastics, its thickness is 5cm.
A kind of 5. steel construction heat-insulation system construction according to claim 1, it is characterised in that:The appearance of the pedestal (1) Face is equipped with fireprotection layer (13), and the fireprotection layer (13) is using styrofoam fire proofing material.
CN201721205903.9U 2017-09-20 2017-09-20 A kind of steel construction heat-insulation system construction Active CN207348246U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721205903.9U CN207348246U (en) 2017-09-20 2017-09-20 A kind of steel construction heat-insulation system construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721205903.9U CN207348246U (en) 2017-09-20 2017-09-20 A kind of steel construction heat-insulation system construction

Publications (1)

Publication Number Publication Date
CN207348246U true CN207348246U (en) 2018-05-11

Family

ID=62410428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721205903.9U Active CN207348246U (en) 2017-09-20 2017-09-20 A kind of steel construction heat-insulation system construction

Country Status (1)

Country Link
CN (1) CN207348246U (en)

Similar Documents

Publication Publication Date Title
CN205035932U (en) Prefabricated aerated concrete assembled heat preservation composite wall
CN106273702A (en) A kind of super thin shape metal composite layered product and production technology thereof
CN201145380Y (en) Novel composite ventilating pipeline
CN102121281A (en) Fireproof and heat insulation plate for outer wall of building
CN207348246U (en) A kind of steel construction heat-insulation system construction
CN201193757Y (en) Snap fastener type exterior thermal insulation stone-plastic composite board for hollow heat insulation external wall
CN202090509U (en) Low-carbon environment-friendly cellular light-weight compound wall board
CN103967143A (en) External wall heat insulation system
CN202627242U (en) Multifunctional double-mesh hard rock wool composite board
CN214111750U (en) Light high strength fire prevention thermal-insulation decorative integrated board
CN209082743U (en) A kind of fire proof construction insulation board
CN205224304U (en) Novel thermal insulation board
CN213952552U (en) Thermosetting composite polystyrene foam insulation board
CN203905190U (en) Foaming ceramic compound heat preservation plate and combination body of foaming ceramic compound heat preservation plates
CN105350734A (en) Building exterior wall insulation and expansion polystyrene board
CN203129356U (en) Brickwork and heat-radiating layer integrated green building outer wall
CN204199459U (en) Fireproof heated board
CN203213355U (en) Curtain wall integrating XPS (extruded polystyrene) heat insulation material and stone
CN206737311U (en) A kind of waveform decorative heat-preservation plate with relief pattern
CN112081259A (en) Building heat insulation structure, application and installation method
CN205617581U (en) Anti compound coiled material that splits of waterproof insulation
CN205688600U (en) Organic material composite extrusion warming plate
CN204163229U (en) A kind of polyphenyl plate composite mortar external thermal insulation system
CN207063306U (en) A kind of cast-in-place water-proof heat-preserving integrated plate of novel steel wire rack
CN104314187B (en) Fireproof heated board

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant