CN207343498U - A kind of construction building site steel pipe scaffold straightener - Google Patents

A kind of construction building site steel pipe scaffold straightener Download PDF

Info

Publication number
CN207343498U
CN207343498U CN201721365098.6U CN201721365098U CN207343498U CN 207343498 U CN207343498 U CN 207343498U CN 201721365098 U CN201721365098 U CN 201721365098U CN 207343498 U CN207343498 U CN 207343498U
Authority
CN
China
Prior art keywords
stress frame
steel pipe
straightener
pipe scaffold
building site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721365098.6U
Other languages
Chinese (zh)
Inventor
王久江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Wuzhou Highway Engineering Co Ltd
Original Assignee
Dalian Wuzhou Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Wuzhou Highway Engineering Co Ltd filed Critical Dalian Wuzhou Highway Engineering Co Ltd
Priority to CN201721365098.6U priority Critical patent/CN207343498U/en
Application granted granted Critical
Publication of CN207343498U publication Critical patent/CN207343498U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

It the utility model is related to construction engineering field, and in particular to a kind of construction building site steel pipe scaffold straightener.Technical solution is as follows:A kind of construction building site steel pipe scaffold straightener, upper stress frame connects composition framework with lower stress frame by middle transmission rod, hydraulic cylinder is fixedly installed on lower stress frame, mobile reinforcing crossbeam is installed on the hydraulic cylinder, rail plate is set between upper stress frame and lower stress frame, and the mobile reinforcing crossbeam both sides are slidably connected with the rail plate;A lower U-type groove is fixedly installed on the mobile reinforcing crossbeam, two lower U-type grooves are fixedly installed on the upper stress frame.The utility model solves the problems, such as that the artificial aligning efficiency in construction after steel pipe scaffold flexural deformation is low, intensity is big, quality is unstable, while straightening quality is ensured, improves production efficiency, realizes the economic benefit of bigger.

Description

A kind of construction building site steel pipe scaffold straightener
Technical field
It the utility model is related to construction engineering field, and in particular to a kind of construction building site steel pipe scaffold is aligned Device.
Background technology
Steel pipe scaffold is widely used in building engineering construction, in transport, erection, dismounting and storing process often Because a variety of causes causes tube bending to deform.Since scaffolding steel pipe is primarily subjected to vertically and horizontally both direction when in use Active force, can just be continuing with after only being aligned for curved scaffolding steel pipe.
General construction site uses artificial Loading Method or artificial hammering method for the scaffolding steel pipe of flexural deformation.Manually add Load method is exactly by the single-ended fixation of bending pipe fitting, and a fulcrum is set at arc of curvature reverse curvature, and the other end relies on itself strength of people Or gravity is aligned.Artificial hammering method is will to be lain in upwards at fixed platform at the reverse curvature of bending pipe fitting arc of curvature, people Work is impacted with sledgehammer, aligns bending part by the impact force of hammering.Both the above method is although easy to operate, but The shortcomings of relatively low there are efficiency in real work, labor intensity is big, and straightening quality is difficult to control, hammers in artificial hammering method It is improper in addition occur by steel pipe pound it is flat, pound it is flat cause pipe fitting to scrap situation, while there is also very big security risk.
Utility model content
The utility model provides a kind of construction building site steel pipe scaffold straightener, solves steel pipe feet in construction The problem of efficiency is low, intensity is big, quality is unstable is manually aligned after hand cradle flexural deformation, while straightening quality is ensured, Production efficiency is improved, realizes the economic benefit of bigger.
The technical solution of the utility model is as follows:A kind of construction building site steel pipe scaffold straightener, upper stress frame Frame connects composition framework with lower stress frame by middle transmission rod, and hydraulic cylinder, the liquid is fixedly installed on lower stress frame Mobile reinforcing crossbeam is installed on compressing cylinder, rail plate, the mobile reinforcing are set between upper stress frame and lower stress frame Crossbeam both sides are slidably connected with the rail plate;Be fixedly installed a lower U-type groove on the mobile reinforcing crossbeam, it is described on by Two lower U-type grooves are fixedly installed on power frame.The hydraulic cylinder is driven by motor, and the hydraulic oil is controlled by hand-operated direction valve The stretching and retraction of cylinder.
The beneficial effects of the utility model are:
1st, the utility model uses motor driven liquid pressure oil cylinder working, and straightening force is provided by hydraulic cylinder, manually need to only put Steel pipe is put and taken out, greatly reduces labor intensity, improves production efficiency, cost of labor expenditure is saved, adds Economic benefit.
2nd, the utility model is controlled using hydraulic system, the size of energy more precise control straightening force and aligning displacement Amount, greatly improves the quality of aligning, reduces rework rate.
3rd, the utility model is simple in structure, small, and transport easy to remove, component is sturdy and durable, and failure rate is low, suitable small Type construction site uses.
4th, rail plate is equipped with mobile reinforcing crossbeam both sides, prevents mobile reinforcing crossbeam because being deviated by lateral force.
5th, upper and lower aligning stress point is processed as U-shaped mold shape, prevents the sideslip of steel pipe in straightening process from overturning, at the same time Play the role of anti-flattening, shrivel.
Brief description of the drawings
Fig. 1 is a kind of construction building site steel pipe scaffold straightener three-dimensional structure diagram;
Fig. 2 is a kind of construction building site steel pipe scaffold straightener working state schematic representation.
Embodiment
As shown in Figure 1, 2, a kind of construction building site steel pipe scaffold straightener, upper stress frame 1 and lower stress frame Frame 3 is connected by middle transmission rod 2 forms framework, fixed setting hydraulic cylinder 4 on lower stress frame 3, on the hydraulic cylinder 4 The mobile reinforcing crossbeam 5 of installation, sets rail plate 6, the mobile reinforcing crossbeam 5 between upper stress frame 1 and lower stress frame 3 Both sides are slidably connected with the rail plate 6;Be fixedly installed a lower U-type groove 7 on the mobile reinforcing crossbeam 5, it is described on by Two lower U-type grooves 8 are fixedly installed on power frame 1;The hydraulic cylinder 4 is driven by motor, and the liquid is controlled by hand-operated direction valve The stretching and retraction of compressing cylinder 4.
Specific implementation process is as follows:After system normally starts, hand-operated direction valve is pulled, according to the bending of steel pipe 9 to be aligned Degree shrinks hydraulic cylinder 4, mobile reinforcing crossbeam 5 is moved down into suitable location, hand-operated direction valve is returned to middle position, is put into Steel pipe 9 to be aligned, makes its bending point be placed in the center of lower U-type groove 7, both ends raised portion is on the perpendicular bisector of upper U-type groove 8 and protects It is vertical to hold, and reversely pulls hand-operated direction valve, stretches out hydraulic cylinder 4, the moment pays close attention to the position of steel pipe 9 to be aligned and upper U-type groove 8 Put, ensure that steel pipe 9 to be aligned can accurately enter upper U-type groove 8, persistently pull hand-operated direction valve, make hydraulic cylinder 4 continue to stretch Go out, after aligning steel pipe 9 is straight, steel pipe is applied certain power according to tube bending degree and experience makes it be in slight antiarch shape State, to ensure after hydraulic cylinder 4 is retracted, steel pipe is just at straightened condition.Hand-operated direction valve is pulled hydraulic cylinder 4 to return Condense and put, hydraulic cylinder 4 is bounced back, mobile reinforcing crossbeam 5 moves down into suitable position, removes the steel pipe after aligning, a job Flow finishes, and the bending straightening of steel pipe scaffold is achieved.

Claims (2)

1. a kind of construction building site steel pipe scaffold straightener, it is characterised in that upper stress frame and lower stress frame lead to Transmission rod connection forms framework among crossing, and hydraulic cylinder is fixedly installed on lower stress frame, movement is installed on the hydraulic cylinder Crossbeam is reinforced, rail plate, the mobile reinforcing crossbeam both sides and the cunning are set between upper stress frame and lower stress frame Dynamic guide rail is slidably connected;A lower U-type groove is fixedly installed on the mobile reinforcing crossbeam, is fixedly installed on the upper stress frame Two lower U-type grooves.
2. construction building site steel pipe scaffold straightener according to claim 1, it is characterised in that the hydraulic oil Cylinder is driven by motor, and the stretching and retraction of the hydraulic cylinder are controlled by hand-operated direction valve.
CN201721365098.6U 2017-10-23 2017-10-23 A kind of construction building site steel pipe scaffold straightener Expired - Fee Related CN207343498U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721365098.6U CN207343498U (en) 2017-10-23 2017-10-23 A kind of construction building site steel pipe scaffold straightener

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721365098.6U CN207343498U (en) 2017-10-23 2017-10-23 A kind of construction building site steel pipe scaffold straightener

Publications (1)

Publication Number Publication Date
CN207343498U true CN207343498U (en) 2018-05-11

Family

ID=62355371

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721365098.6U Expired - Fee Related CN207343498U (en) 2017-10-23 2017-10-23 A kind of construction building site steel pipe scaffold straightener

Country Status (1)

Country Link
CN (1) CN207343498U (en)

Similar Documents

Publication Publication Date Title
CN105170836B (en) Portable many bending straighteners of function high tensile reinforcement at most and its operating method
CN203679102U (en) Full-automatic hydraulic mesh bending device
CN207343498U (en) A kind of construction building site steel pipe scaffold straightener
CN206578154U (en) Metal pipe correction machine
CN103075001A (en) Steel tube fastener slip form platform system
CN210127644U (en) A telescopic crowbar for construction engineering template demolishs construction
CN104959491B (en) The quick straightener of reinforcing bar and the method using its straightening reinforcing bar
CN208067189U (en) Portable reinforcing steel bar is bent straightening all-in-one machine
CN102182188B (en) Full hydraulic static pulling machine and method of underground diaphragm wall joint pipe
CN208996499U (en) A kind of traction device of house displacement
CN210936875U (en) Simple and convenient reinforcing bar straightening device
CN204912601U (en) Pile head bar straightening spanner
CN212792791U (en) Reinforcing bar shaping mechanical equipment for building
CN203044587U (en) Hydraulic correcting device
CN206396763U (en) It is applicable the rapid construction type slope retaining structure of underground structure
CN205217651U (en) Crooked correcting device of steel sheet pile
CN206981635U (en) A kind of Portable reinforcing steel bar bending apparatus
CN206843953U (en) Sizing auxiliary construction platform in a kind of high-speed railway pier
CN204770359U (en) Straight machine of fast speed adjusting of reinforcing bar
CN215889383U (en) Portable flexible concrete placement chute
CN104972020A (en) Pile head bar straightening wrench
CN204545038U (en) A kind of beam straightening instrument
CN210475067U (en) Device for bending and straightening steel pipe
CN201964024U (en) Socket type pipeline withstanding device
CN204402021U (en) A kind of large diameter shaft raise sliding formwork transformation grouting stage apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180511

CF01 Termination of patent right due to non-payment of annual fee