CN207265588U - Go out wall construction for pre-embedded pipe - Google Patents
Go out wall construction for pre-embedded pipe Download PDFInfo
- Publication number
- CN207265588U CN207265588U CN201720970171.6U CN201720970171U CN207265588U CN 207265588 U CN207265588 U CN 207265588U CN 201720970171 U CN201720970171 U CN 201720970171U CN 207265588 U CN207265588 U CN 207265588U
- Authority
- CN
- China
- Prior art keywords
- wall
- threaded connector
- connector coupling
- embedded pipe
- embedded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Go out wall construction for pre-embedded pipe the utility model discloses a kind of, this structure includes the cable conduit and wall form being embedded in advance in wall or floor, further include set Threaded Connector Coupling and wall outer cable spool, covering the connection of Threaded Connector Coupling one end, pre-embedded pipe goes out wall end, the other end is resisted against wall form wall, after wall form dismounting, wall outer cable spool is screwed into set Threaded Connector Coupling.This structure overcomes the defects of traditional pre-embedded pipe goes out wall mode, greatly facilitates construction operation, improves construction efficiency, reduces wall form loss, avoids spillage risk, reduces construction cost.
Description
Technical field
It the utility model is related to and a kind of go out wall construction for pre-embedded pipe.
Background technology
In construction operation, partial cables spool is embedded in all kinds of walls or floor.As shown in Figure 1, constructing
During operation, corresponding through hole is opened up on the wall form 2 that pre-embedded pipe 1 goes out wall displacement by form fixer mostly, so as to built-in line
Pipe 2 is pierced by.Period, it is desirable to which lead to the hole site is accurate, size is suitable, so improves the difficulty of perforate operation, reduces construction operation
Efficiency;Risk after wall form perforate at the same time during concreting there are spillage, influences pouring quality, and perforate causes one
Fixed wall form loss, waste of materials, improves cost.
The content of the invention
Technical problem to be solved in the utility model is to provide a kind of goes out wall construction, this structure gram for pre-embedded pipe
The defects of traditional pre-embedded pipe goes out wall mode has been taken, has greatly facilitated construction operation, has improved construction efficiency, has reduced wall form damage
Consumption, avoids spillage risk, reduces construction cost.
In order to solve the above technical problems, the wall construction that goes out that the utility model is used for pre-embedded pipe includes being embedded in wall or building in advance
Cable conduit and wall form in plate, further include set Threaded Connector Coupling and wall outer cable spool, set Threaded Connector Coupling one end connection institute
State that pre-embedded pipe goes out wall end, the other end is resisted against the wall form wall, after wall form dismounting, the wall outer cable
Spool is screwed into the set Threaded Connector Coupling.
Further, this structure further includes the first bridging buckle, the second bridging buckle and jumper, the first bridging buckle
The pre- cable conduit tube body being embedded in wall or floor and wall outer cable spool tube body are respectively arranged on the second bridging buckle,
Jumper one end connection the first bridging buckle, the set Threaded Connector Coupling is equipped with against the wall form wall end face to slit
Mouthful, the jumper other end is stretched into the set Threaded Connector Coupling from the gap, after wall form dismounting, the bridging
The line other end pulls out out of described gap and connects the second bridging buckle.
Further, the jumper is 4mm2Copper core flexible cord.
The wall construction that goes out for being used for pre-embedded pipe due to the utility model employs above-mentioned technical proposal, i.e. this structure includes pre-
The cable conduit and wall form being embedded in wall or floor, further include set Threaded Connector Coupling and wall outer cable spool, cover Threaded Connector Coupling one
Pre-embedded pipe goes out wall end, the other end is resisted against wall form wall for end connection, and after wall form dismounting, wall outer cable spool is screwed into
Cover Threaded Connector Coupling.This structure overcomes the defects of traditional pre-embedded pipe goes out wall mode, greatly facilitates construction operation, improves construction effect
Rate, reduces wall form loss, avoids spillage risk, reduce construction cost.
Brief description of the drawings
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is that traditional pre-embedded pipe goes out wall schematic diagram;
Fig. 2 is that the utility model goes out wall construction schematic diagram for pre-embedded pipe;
Fig. 3 is the schematic diagram that jumper stretches into set Threaded Connector Coupling through covering Threaded Connector Coupling gap in this structure.
Embodiment
Embodiment is as shown in Fig. 2, the wall construction that goes out that the utility model is used for pre-embedded pipe includes being embedded in wall or floor in advance
Interior cable conduit 1 and wall form 2, further include set Threaded Connector Coupling 3 and wall outer cable spool 4, the connection of 3 one end of the set Threaded Connector Coupling
The pre-embedded pipe 1 goes out wall end, the other end is resisted against 2 wall of wall form, after the wall form 2 dismounting, the wall
Outer cable spool 4 is screwed into the set Threaded Connector Coupling 3.
As shown in Figures 2 and 3, it is preferred that this structure further includes the 5, second bridging of the first bridging buckle buckle 6 and jumper
7, the first bridging buckle 5 and the second bridging buckle 6 are respectively arranged on the pre- cable conduit 1 being embedded in wall or floor and manage
Body and wall outer cable spool tube body 4, described 7 one end of jumper connection the first bridging buckle 5, the set Threaded Connector Coupling 3 against
The 2 wall end face of wall form is equipped with gap 31, and 7 other end of jumper stretches into the set Threaded Connector Coupling 3 from the gap 31
Interior, after the wall form 2 dismounting, 7 other end of jumper pulls out out of described gap 31 and connects described second
Bridging buckle 6.
Preferably, the jumper is 4mm2Copper core flexible cord.
This structure goes out wall end in pre-embedded pipe and sets set Threaded Connector Coupling, so as to avoid the operation work of the perforate on wall form
Sequence, after wall form dismounting, wall outer cable spool need to only be screwed into set Threaded Connector Coupling;Jumper requirement has been also applied for it at the same time
Spool.Construction operation is greatly so facilitated, wall form caused by avoiding wall form perforate is lost, especially for one
A little expensive customization wall forms, play the effect for reducing loss;Avoid position of opening inaccurately caused wall at the same time
Body model sheetinstallat is difficult, eliminates the risk of tapping spillage;Wall form is avoided in order to yield to spool position in installation process,
Causing between wall form docking to have some setbacks causes the situation of spillage, make wall or floor be molded it is more attractive.
Claims (3)
1. a kind of go out wall construction for pre-embedded pipe, including the cable conduit and wall form being embedded in advance in wall or floor,
It is characterized in that:Set Threaded Connector Coupling and wall outer cable spool are further included, described set Threaded Connector Coupling one end connects the pre-embedded pipe and goes out wall
End, the other end are resisted against the wall form wall, and after wall form dismounting, the wall outer cable spool is screwed into the set
Threaded Connector Coupling.
2. according to claim 1 go out wall construction for pre-embedded pipe, it is characterised in that:This structure further include first across
Buckle, the second bridging buckle and jumper are connect, the first bridging buckle and the second bridging buckle are respectively arranged on described pre- be embedded in
Cable conduit tube body and wall outer cable spool tube body in wall or floor, jumper one end connection the first bridging card
Button, the set Threaded Connector Coupling are equipped with gap against the wall form wall end face, and the jumper other end is stretched into from the gap
In the set Threaded Connector Coupling, after wall form dismounting, the jumper other end is pulled out and connected out of described gap
The second bridging buckle.
3. according to claim 2 go out wall construction for pre-embedded pipe, it is characterised in that:The jumper is 4mm2Copper
Core flexible cord.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720970171.6U CN207265588U (en) | 2017-08-04 | 2017-08-04 | Go out wall construction for pre-embedded pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720970171.6U CN207265588U (en) | 2017-08-04 | 2017-08-04 | Go out wall construction for pre-embedded pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207265588U true CN207265588U (en) | 2018-04-20 |
Family
ID=61924467
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720970171.6U Expired - Fee Related CN207265588U (en) | 2017-08-04 | 2017-08-04 | Go out wall construction for pre-embedded pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207265588U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109390888A (en) * | 2017-08-04 | 2019-02-26 | 上海宝冶集团有限公司 | Go out wall construction for pre-embedded pipe |
CN110230794A (en) * | 2019-05-31 | 2019-09-13 | 上海宝冶集团有限公司 | Street lamp installation method in electronic workshop |
-
2017
- 2017-08-04 CN CN201720970171.6U patent/CN207265588U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109390888A (en) * | 2017-08-04 | 2019-02-26 | 上海宝冶集团有限公司 | Go out wall construction for pre-embedded pipe |
CN110230794A (en) * | 2019-05-31 | 2019-09-13 | 上海宝冶集团有限公司 | Street lamp installation method in electronic workshop |
CN110230794B (en) * | 2019-05-31 | 2021-10-01 | 上海宝冶集团有限公司 | Street lamp installation method in electronic factory building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207265588U (en) | Go out wall construction for pre-embedded pipe | |
EP2093026A1 (en) | Canal inspection robots with digital data transmission | |
CN207211432U (en) | A kind of stifled slurry system of sleeve grouting | |
CN201562850U (en) | Winding device of information outlet | |
CN109972840A (en) | A kind of exterior wall joint part formwork erection structure and its erection method | |
CN109390888A (en) | Go out wall construction for pre-embedded pipe | |
CN206865057U (en) | A kind of wiring conduit connector | |
CN104632065A (en) | Tension tightness regulator for easily disassembled and folded yarn | |
CN201533085U (en) | Network cable socket | |
CN204983658U (en) | Prefabricated component is with box of pre -buried electric end and have prefabricated component of this box of electric end | |
CN108478056A (en) | A kind of burn prevention grabs dish device | |
CN209341178U (en) | The prefabricated dedicated wire box of superimposed sheet | |
CN208518334U (en) | Detachable Three-section water stop screw rod | |
CN111306426B (en) | High-efficient portable locator based on wireless sensor | |
CN103036191A (en) | Cable terminal for European-style branch box and ring main unit | |
CN209082770U (en) | A kind of connection structure of prefabricated sleeper and prefabricated panel | |
CN102817377B (en) | Double plug pin type fore shaft pipe | |
CN110409498A (en) | A kind of drawing-type detent is anti-to gush manhole lid device | |
CN218758762U (en) | Prefabricated wall pre-buried electromechanical position reinforcing member | |
CN205314594U (en) | Pre -buried structure of core section of thick bamboo board muscle protection | |
CN110535068A (en) | A kind of wall circuit threader used for architectural engineering | |
CN212802557U (en) | Template fixing device is pour to assembled building | |
CN212743147U (en) | Can have enough to meet need formula sleeve shutoff of being in milk and plumpness monitoring control ware | |
CN202009205U (en) | Embedded junction box cover plate | |
CN203174778U (en) | Concrete slab preformed hole blocking device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180420 |
|
CF01 | Termination of patent right due to non-payment of annual fee |