CN207260636U - Pipe die reinforced column supporting member - Google Patents

Pipe die reinforced column supporting member Download PDF

Info

Publication number
CN207260636U
CN207260636U CN201721318624.3U CN201721318624U CN207260636U CN 207260636 U CN207260636 U CN 207260636U CN 201721318624 U CN201721318624 U CN 201721318624U CN 207260636 U CN207260636 U CN 207260636U
Authority
CN
China
Prior art keywords
pipe die
column
construction
supporting member
die plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721318624.3U
Other languages
Chinese (zh)
Other versions
CN207260636U8 (en
Inventor
解永灿
李硕翔
郑艳秋
董鑫
徐梓铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Chengtou Zhonghe Construction Group Co ltd
Original Assignee
Yunnan Chengtou Zhonghe Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Chengtou Zhonghe Construction Group Co ltd filed Critical Yunnan Chengtou Zhonghe Construction Group Co ltd
Priority to CN201721318624.3U priority Critical patent/CN207260636U8/en
Application granted granted Critical
Publication of CN207260636U publication Critical patent/CN207260636U/en
Publication of CN207260636U8 publication Critical patent/CN207260636U8/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Pipe die reinforced column supporting member, it is related to building engineering construction field, it is supported and is formed it is characterized in that the component is the house beam bottom that floor slab back casting band is connected to by several pipe die columns, the pipe die column is made of column reinforcing bar, concrete and pipe die plate, house beam bottom of the column bar connecting at floor slab back casting band, for pipe die sleeve-board on the outside of column reinforcing bar, concreting forms armored concrete in pipe die plate in pipe die plate.The pipe die reinforced column supporting member combination of the utility model is flexible, it is vertebration, it is easy to operate, location arrangements can be carried out according to different engineering demands, construction circulation material, labour cost can effectively be saved, construct with place structure sheaf and complete at the same time at the same time, structure safety is not influenced, ensures working security, after the completion of floor slab back casting belt construction, only need to remove on pipe die column, quantities is small, convenient construction, is conducive to propelling construction construction, accelerate construction progress, be conducive to improve market economy benefit.

Description

Pipe die reinforced column supporting member
Technical field
It the utility model is related to building engineering construction field, and in particular to during architectural engineering floor slab back casting belt construction, Pipe die reinforced column supporting member in its main frame body supporting removal.
Background technology
, it is necessary to formwork-support be set up, in order to construction during the floor post empiricism of architectural engineering It is smoothed out.After the floor has been constructed, when supporting frame is removed, taken to ensure the structure safety at floor slab back casting band Temporary support component.At present carry out when building of floor late poured band support template, generally use fastener steel tube formula supporting rack into Row construction, generally requires to set up the more huge formwork-support of volume, and after the completion of construction that formwork-support is overall Remove, this is taken, the process of tearing open often results in construction circulation material and the excessive of labour cost is used and wasted, and cost is higher and holds The operating surface for taking subsequent construction is easily caused, and delays construction progress.
The content of the invention
Technical problem to be solved in the utility model is the formwork-support at current architectural engineering floor slab back casting band Come carry out the support of floor slab back casting band when possessed material cost it is high, it is time-consuming and laborious, easily cause and excessive take constructing operation face The problem of, there is provided a kind of succinct reliable pipe die reinforced column supporting member.
Pipe die reinforced column supporting member, it is characterised in that the component is to be connected to floor by several pipe die columns House beam bottom at post-cast strip is supported and is formed, and the pipe die column is made of column reinforcing bar, concrete and pipe die plate, institute The column reinforcing bar stated is several, the house beam bottom being connected at floor slab back casting band, and pipe die sleeve-board is on the outside of column reinforcing bar, concrete It is cast in pipe die plate, armored concrete is formed in pipe die plate.
The pipe die plate is PVC drain pipe, and pipe die board diameter is at least 20cm.
When carrying out floor slab construction, the quantity and position of column reinforcing bar are determined according to floor actual conditions, by column reinforcing bar The beam bottom being connected at floor slab back casting band, pipe die sleeve-board on the outside of column reinforcing bar, and the floor harden structure beam slab pour it is mixed , together will be in concreting to pipe die plate, with the advance pipe die reinforced column being supported at post-cast strip of formation during solidifying soil Supporting member, when floor construction supporting frame is removed, retains the pipe die reinforced column supporting member, so that it is guaranteed that floor Beam slab at post-cast strip will not be because of at this time without the overall primary structure member of formation, the damage for shifting to an earlier date stress and being subjected to, after floor After pouring the concreting completion of band place, then carry out the dismounting of pipe die reinforced column supporting member, it is ensured that construction it is smooth Complete.
The pipe die reinforced column supporting member of the utility model is using pvc pipe as pipe die plate, and combination is flexible, structure Tightly, it is easy to operate, location arrangements can be carried out according to different engineering demands, can effectively save construction circulation material, people Expenses of labour is used, and is constructed with place structure sheaf and is completed at the same time at the same time, while does not influence structure safety, ensures the security of construction, in building After the completion of board post poured band construction, it is only necessary to pipe die column to be removed, quantities is small, convenient construction, is conducive to propelling construction construction, Accelerate construction progress, be conducive to improve market economy benefit.
Brief description of the drawings
Fig. 1 uses schematic diagram for the pipe die reinforced column supporting member of the utility model;
Fig. 2 is pipe die column section figure;
Wherein, pipe die column 1, pipe die plate 2, armored concrete 3, house beam 4, post-cast strip 5.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and examples.
Embodiment 1:Pipe die reinforced column supporting member, the component are to be connected to floor by several pipe die columns 1 4 bottom of house beam at post-cast strip 5 is supported and is formed, and the pipe die column 1 is by 2 groups of column reinforcing bar, concrete and pipe die plate Into the column reinforcing bar is several, and 4 bottom of house beam being connected at floor slab back casting band 5, pipe die plate 2 is placed on outside column reinforcing bar Side, pipe die plate 2 are PVC drain pipe, and 2 diameter of pipe die plate is at least 20cm, and concreting is in pipe die plate 2, in pipe die plate 2 Form armored concrete 3.
When carrying out floor slab construction, the quantity and position of column reinforcing bar are determined according to floor actual conditions, by column reinforcing bar 4 end of beam bottom being connected at floor slab back casting band 5, pipe die plate 2 is sleeved on the outside of column reinforcing bar, and is poured in the beam slab of the floor harden structure During concrete, together by concreting to pipe die plate 2, pipe die column 1 is formed, is supported in advance at post-cast strip 5 with forming Pipe die reinforced column supporting member, when floor construction supporting frame is removed, retains pipe die reinforced column support Component, so that it is guaranteed that the beam slab at floor slab back casting band 5 will not form overall primary structure member because of no at this time, shifts to an earlier date stress and meets with The damage received, after treating that 5 concretings are completed at floor slab back casting band, then carries out tearing open for pipe die reinforced column supporting member Remove, it is ensured that construction smoothly completes.

Claims (2)

1. pipe die reinforced column supporting member, it is characterised in that the component is to be connected to building by several pipe die columns (1) House beam (4) bottom at board post poured band (5) place is supported and is formed, and the pipe die column (1) is by column reinforcing bar, concrete and pipe Template (2) forms, and the column reinforcing bar is several, is connected to house beam (4) bottom at floor slab back casting band (5) place, pipe die plate (2) it is placed on the outside of column reinforcing bar, concreting forms armored concrete (3) in pipe die plate (2) in pipe die plate (2).
2. pipe die reinforced column supporting member according to claim 1, it is characterised in that the pipe die plate (2) is PVC drain pipe, pipe die plate (2) diameter are at least 20cm.
CN201721318624.3U 2017-10-13 2017-10-13 Pipe die reinforced column supporting member Active CN207260636U8 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721318624.3U CN207260636U8 (en) 2017-10-13 2017-10-13 Pipe die reinforced column supporting member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721318624.3U CN207260636U8 (en) 2017-10-13 2017-10-13 Pipe die reinforced column supporting member

Publications (2)

Publication Number Publication Date
CN207260636U true CN207260636U (en) 2018-04-20
CN207260636U8 CN207260636U8 (en) 2018-06-15

Family

ID=61917203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721318624.3U Active CN207260636U8 (en) 2017-10-13 2017-10-13 Pipe die reinforced column supporting member

Country Status (1)

Country Link
CN (1) CN207260636U8 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459474A (en) * 2020-11-27 2021-03-09 上海宝冶集团有限公司 Method for supporting single post of post-cast strip PVC pipe mould plain concrete
CN113389379A (en) * 2021-06-25 2021-09-14 深圳市建设(集团)有限公司 Construction method of post-cast strip floor with independent support

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459474A (en) * 2020-11-27 2021-03-09 上海宝冶集团有限公司 Method for supporting single post of post-cast strip PVC pipe mould plain concrete
CN113389379A (en) * 2021-06-25 2021-09-14 深圳市建设(集团)有限公司 Construction method of post-cast strip floor with independent support

Also Published As

Publication number Publication date
CN207260636U8 (en) 2018-06-15

Similar Documents

Publication Publication Date Title
CN104594500B (en) Integrated slab column formwork structure system and construction method
CN207568180U (en) Water stopping thresholds formwork ruggedized construction
CN203247600U (en) Equipment foundation bolt preformed hole die
CN206233596U (en) Building block exterior wall constructional column concrete casting device
CN207260636U (en) Pipe die reinforced column supporting member
CN106968435A (en) A kind of formwork reinforcement system of L-type shear wall with short piers one-piece casting construction
CN102535746A (en) Concrete-filled steel tube column and casting method thereof
CN206174120U (en) Prefabricated constructional column and structure thereof
CN207812625U (en) Special-shaped gutter template integrated apparatus
CN203924669U (en) A kind of precast concrete scaffold base and making mould thereof
CN106320373A (en) Supporting system at position of post-pouring belt of underground garage roof and construction method
CN202401668U (en) Concrete column structure of steel pipe
CN207260574U (en) Template fixing system of building waterproof structure
CN206319592U (en) A kind of post-cast strip concrete side plugging structure
CN207672389U (en) Roadbed concrete curb cast-in-place mould
CN207997396U (en) One kind exempting from formwork constructional column shaper
CN203613790U (en) Steel wire mesh and form combined inclined reinforced concrete floor slab construction device
CN206319404U (en) A kind of building precast exterior sheathing
CN206267425U (en) A kind of device for being used in turn steel bar horse-shaped bench
CN213014377U (en) Basement roof seals post-cast strip structure in advance
CN205209847U (en) Concrete sample making devices who contains built -in longitudinal reinforcement
CN209723594U (en) A kind of positioning of assembled architecture reinforcing bar and check device
CN209228032U (en) Regularization formwork inside-corner reinforcing device
CN207646941U (en) A kind of Constructional Col-umn Construction combination tool
CN208428458U (en) A kind of reinforcing bar tire fixture of precast segment box beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CU01 Correction of utility model
CU01 Correction of utility model

Correction item: Patentee

Correct: Yunnan city public investment and Construction Group Co., Ltd.

False: Yunnan City Public Investment Co Construction Group Co., Ltd.

False: Yunnan City Public Investment Co Construction Group Co., Ltd.

Number: 16-02

Volume: 34

Correction item: Patentee

Correct: Yunnan city public investment and Construction Group Co., Ltd.

False: Yunnan City Public Investment Co Construction Group Co., Ltd.

Number: 16-02

Page: The title page

Volume: 34