CN207249677U - A kind of construction site safety monitoring system integrated based on RFID and BIM - Google Patents
A kind of construction site safety monitoring system integrated based on RFID and BIM Download PDFInfo
- Publication number
- CN207249677U CN207249677U CN201721145054.2U CN201721145054U CN207249677U CN 207249677 U CN207249677 U CN 207249677U CN 201721145054 U CN201721145054 U CN 201721145054U CN 207249677 U CN207249677 U CN 207249677U
- Authority
- CN
- China
- Prior art keywords
- bim
- rfid
- construction site
- monitoring system
- site safety
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Alarm Systems (AREA)
Abstract
The utility model discloses a kind of construction site safety monitoring system integrated based on RFID and BIM, including information acquisition module, message processing module and Information application module;Described information acquisition module includes RFID tag and RFID reader, and described information processing module includes BIM analog platforms, and described information application module includes computer and mobile terminal;The RFID tag of the RFID reader scanning construction site, is then handled the data sending of collection to BIM analog platforms, then be real-time dynamicly presented on computer and mobile terminal.The utility model can realize that automatic data collection, information are automatically updated, monitored through whole process, realize the automating of construction safety, information-based, visualization, with no paper efficient monitoring, improve construction efficiency, saved cost.
Description
Technical field
The utility model belongs to construction site security monitoring field, and in particular to a kind of to be applied based on what RFID and BIM was integrated
Work site safety monitoring system.
Background technology
RFID(Radio Frequency Identification)That is radio RF recognition technology, is a kind of contactless
Automatic identification technology, for information gathering.Usually it is made of RFID tag and RFID reader.RFID tag Water-proof and oil-proof,
Paper, timber, plastic cement etc. can be penetrated to be identified, a variety of category informations can be stored and capacity is up to number more than 10M.Therefore, RFID
Label is suitably applied the more complicated environment in construction site.Weight equipment and safety of workers equipment are marked using RFID technique,
Alert when worker and equipment enter dangerous work field and will trigger and notify worker and related management person immediately, enhancing Field Force
Management.
BIM(Building Information Modeling)I.e. architecture information simulate, be construction project facility physics and
The numeral expression of functional characteristic.It is integrated with project information, supports the information interchange between each stage different participant and shares.
At the construction field (site) in security monitoring, BIM three-dimensional visualizations case verification effect in analysis, security control and monitoring potential danger
Significantly.With time course, the safety analyses such as structural conflict collision are carried out using BIM4D models, can be to the peace of work progress
Full problem is managed and early warning.For construction structure safety management, based on BIM4D technologies and Time variable structure analysis theories
Safety analysis, build Time variable structure safety analysis model, can solve the problems, such as Time variable structure continuously dynamic whole process analysis,
So that analysis result three-dimensional visualization.
Building construction process is related to the multi-party main body such as owner, construction, design, and job site personnel flowing is big, operation is three-dimensional
Intersect, environment DYNAMIC COMPLEX so that site safety monitoring factor is more and monitoring difficulty is big.By estimating the method with hand inspection
Carry out security monitoring, it is impossible to the timely and effectively generation of prevention and control accident.With the development of science and technology, the skill for security monitoring
Art is maked rapid progress, more using technologies such as GPS, video cameras at present.The utilization of these technologies is alleviated to a certain extent
The pressure at artificial supervision scene, improves supervisory efficiency.But the judgement for security monitoring state still relies primarily on pipe
The experience of reason personnel, associated monitoring information still by carrying out typing by hand, monitor state reflect not in time, inaccurate and acceptor
Sight has a great influence, it is impossible to realizes real-time, automation and the informationization of security monitoring.In addition, the transmission of information with linking up adopt more
With paper document and oral form, information is detained and utilization ratio is low.
The content of the invention
Goal of the invention:The utility model aim is in view of the deficiencies of the prior art, there is provided one kind is based on RFID and BIM collection
Into construction site safety monitoring system.The system can realize that automatic data collection, information are automatically updated, monitored through complete
Journey, realizes the automating of construction safety, information-based, visualization, with no paper efficient monitoring, improves construction efficiency, save
Cost.
Technical solution:A kind of construction site safety monitoring system integrated based on RFID and BIM, including information gathering mould
Block, message processing module and Information application module;
Described information acquisition module includes RFID tag and RFID reader, and described information processing module is simulated including BIM
Platform, described information application module include computer and mobile terminal;
The RFID tag of the RFID reader scanning construction site, then simulates the data sending of collection to BIM flat
Platform is handled, then is real-time dynamicly presented on computer and mobile terminal.
Further, the RFID tag is laid on the object in security risk, and the RFID reader, which is arranged in, to be applied
Work scene relevant position, construction site security control center are equipped with the computer, and site safety administrator is equipped with the movement
Terminal.
Further, the RFID tag includes memory, being capable of storage object information and process BIM interaction datas.
Further, the RFID tag includes positioner, can realize the real time location tracking of object.
Further, warning device is included on the computer and mobile terminal.
Beneficial effect:(1)The construction site safety monitoring system that RFID described in the utility model and BIM is integrated, passes through
RFID tag and RFID reader carry out the collection of construction site information, then transfer data to BIM analog platforms and carry out visually
Change is handled, and is finally real-time dynamicly presented on visual information on computer and mobile terminal, which can realize to applying
The real time location tracking of work live object, the visualization of presence states, dynamic monitor construction overall process.Not only increase construction
Efficiency, and saved construction cost.
(2)The utility model, with exchanging in time, owner is just integrated from the design phase, is set by the information sharing of BIM platforms
Meter, construction etc. participate in the multi-party management resource for carrying out Cooperative Security analysis, monitoring and processing, integrating each side of project, in time solution
The safety problem certainly occurred in project.Each side effectively cooperates, and collaboration solves the problems, such as, improves the efficiency and quality of construction.
Brief description of the drawings
Fig. 1 is that the module of the construction site safety monitoring system described in the utility model integrated based on RFID and BIM is illustrated
Figure.
Embodiment
Technical solutions of the utility model are described in detail below by attached drawing, but the scope of protection of the utility model
It is not limited to the embodiment.
Embodiment 1:As shown in Figure 1, the utility model includes information acquisition module, message processing module and Information application mould
Block.Information acquisition module includes RFID tag and RFID reader, is responsible for the collecting work to field data;Message processing module
Comprising BIM analog platforms, it is responsible for the three-dimensional visualization to collection in worksite data;Information application module includes computer and movement eventually
Mobile terminal in end, the mainly computer and safety management in construction site personnel's hand of construction site security control center, just
In real time inspection construction site condition information.
First, security risk inventory is drawn by safety analysis before construction, corresponds to monitored object in inventory and combine existing
The actual conditions of field, define construction site difference object RFID tag, and lay RFID reader in relevant work region;Construction
In, RFID reader to the RFID tag adhered on different objects by continuously scanning carry out locating and tracking, construction site object
RFID tag in the real time position, working region information, the process BIM interaction datas etc. that store just be passed to automatically by network
On BIM analog platforms, handled by BIM3D/4D model visualizations, the calculating of security control center at the construction field (site) is presented in dynamic
On mobile terminal in machine and site safety administrator's hand.
Enter dangerous region in the event of hidden danger, such as personnel, can in time at the construction field (site) by BIM3D/4D models
Alarm is sent on mobile terminal in the computer and site safety administrator's hand of security control center, easy to timely processing.Together
When, project participant can also enter system and real time inspection and participation and the timely processing of itself relevant hidden danger or accident.
As described above, although the utility model has been represented and described with reference to specific preferred embodiment, but it must not
It is construed to the limitation to the utility model itself.The spirit and scope of the utility model that appended claims define are not being departed from
Under the premise of, can various changes can be made in the form and details to it.
Claims (5)
- A kind of 1. construction site safety monitoring system integrated based on RFID and BIM, it is characterised in that:Including information gathering mould Block, message processing module and Information application module;Described information acquisition module includes RFID tag and RFID reader, and described information processing module includes BIM analog platforms, Described information application module includes computer and mobile terminal;The RFID tag of RFID reader scanning construction site, then by the data sending of collection to BIM analog platforms into Row processing, then be real-time dynamicly presented on computer and mobile terminal.
- 2. the construction site safety monitoring system according to claim 1 integrated based on RFID and BIM, it is characterised in that: The RFID tag is laid on the object in security risk, and the RFID reader arranges relevant position at the construction field (site), applies Work site safety control centre is equipped with the computer, and site safety administrator is equipped with the mobile terminal.
- 3. the construction site safety monitoring system according to claim 1 or 2 integrated based on RFID and BIM, its feature are existed In:The RFID tag includes memory, being capable of storage object information and process BIM interaction datas.
- 4. the construction site safety monitoring system according to claim 1 or 2 integrated based on RFID and BIM, its feature in: The RFID tag includes positioner, can realize the real time location tracking of object.
- 5. the construction site safety monitoring system according to claim 1 integrated based on RFID and BIM, it is characterised in that: Warning device is included on the computer and mobile terminal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721145054.2U CN207249677U (en) | 2017-09-08 | 2017-09-08 | A kind of construction site safety monitoring system integrated based on RFID and BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721145054.2U CN207249677U (en) | 2017-09-08 | 2017-09-08 | A kind of construction site safety monitoring system integrated based on RFID and BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207249677U true CN207249677U (en) | 2018-04-17 |
Family
ID=61887572
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721145054.2U Expired - Fee Related CN207249677U (en) | 2017-09-08 | 2017-09-08 | A kind of construction site safety monitoring system integrated based on RFID and BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207249677U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110189106A (en) * | 2019-06-03 | 2019-08-30 | 北京市市政四建设工程有限责任公司 | A kind of underground space wisdom construction personnel's management system based on RFID and BIM technology |
CN111650863A (en) * | 2020-06-09 | 2020-09-11 | 湖南城市学院 | Engineering safety monitoring instrument and monitoring method |
-
2017
- 2017-09-08 CN CN201721145054.2U patent/CN207249677U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110189106A (en) * | 2019-06-03 | 2019-08-30 | 北京市市政四建设工程有限责任公司 | A kind of underground space wisdom construction personnel's management system based on RFID and BIM technology |
CN110189106B (en) * | 2019-06-03 | 2021-12-21 | 北京市市政四建设工程有限责任公司 | Underground space intelligent constructor management system based on RFID and BIM technology |
CN111650863A (en) * | 2020-06-09 | 2020-09-11 | 湖南城市学院 | Engineering safety monitoring instrument and monitoring method |
CN111650863B (en) * | 2020-06-09 | 2022-07-08 | 湖南城市学院 | Engineering safety monitoring instrument and monitoring method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109978409B (en) | Multi-engineering enterprise-level intelligent construction site block chain management method | |
CN108520342A (en) | Platform of internet of things management method based on BIM and its system | |
CN111491257A (en) | Three-dimensional visual operation monitoring system for transformer substation and control method thereof | |
CN104808610B (en) | Machinery Control System and method based on BIM BIMs | |
CN102682620B (en) | The perception of container hargour travel condition of vehicle and positioning system and method | |
CN103984333A (en) | Monitoring and management system for power plant | |
CN106228208A (en) | Control system based on BIM and method | |
CN108876658A (en) | Prefabricated part hanging procedural information management method | |
CN103543706A (en) | Drainage internet-of-things system | |
CN103792909B (en) | Harbour Commercial Vehicle management of cargo handling system and method based on Internet of Things | |
CN109239697A (en) | One kind being based on three-dimensional visualization employee real-time positioning system and method | |
CN206077596U (en) | A kind of urban flooding monitors scheduling system on-line | |
CN207249677U (en) | A kind of construction site safety monitoring system integrated based on RFID and BIM | |
CN112907389A (en) | Land, air and space integrated intelligent construction site system and management method | |
CN103325030A (en) | Robot-based method for managing goods in internet of things | |
CN107948245A (en) | Project Management System based on BIM | |
CN203163853U (en) | Automatic weighing management system | |
CN204807371U (en) | On --spot sampling preparation monitor of concrete quality test block | |
CN116611684A (en) | Dynamic evaluation system and method for engineering project security risk | |
Cao et al. | A digital twin (DT) framework at design and construction phases | |
CN111131482A (en) | Intelligent monitoring closed-loop operation and maintenance system based on BIM three-terminal synchronous equipment | |
Jayanthi | IoT based-civil labour safety monitoring system in construction site | |
CN111321902B (en) | System and method for hoisting components on assembly building construction site | |
CN116187923A (en) | Port digital system | |
CN205596351U (en) | Underground works safe risk real -time prewarning device of being under construction based on thing networking |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180417 Termination date: 20200908 |