CN207211201U - A kind of pit shaft mould plate supporting device - Google Patents

A kind of pit shaft mould plate supporting device Download PDF

Info

Publication number
CN207211201U
CN207211201U CN201721176111.3U CN201721176111U CN207211201U CN 207211201 U CN207211201 U CN 207211201U CN 201721176111 U CN201721176111 U CN 201721176111U CN 207211201 U CN207211201 U CN 207211201U
Authority
CN
China
Prior art keywords
outer barrel
supporting device
fixed
knighthead
plate supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721176111.3U
Other languages
Chinese (zh)
Inventor
李爱家
薛彦军
赵炜
李元坤
赵成龙
王亚玲
李新强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN201721176111.3U priority Critical patent/CN207211201U/en
Application granted granted Critical
Publication of CN207211201U publication Critical patent/CN207211201U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a kind of pit shaft mould plate supporting device, its structure is:Including plug, some telescoping support units to connect successively being enclosed on plug;The structure of telescoping support unit is:Interior hollow stem including entangling plug, four outer barrels are disposed with from the bottom up along interior hollow stem, are connected between four outer barrels by elastic mechanism;Knighthead is connected with first outer barrel, one end of knighthead is movably attached in the middle part of support rail, and support rail one end is fixed on the second outer barrel, and the other end is fixed in template;3rd outer barrel and the 4th outer barrel are also same setting;In addition, it is both provided with clip on the first outer barrel and the second outer barrel.The utility model can realize narrow and small, deep well internal model installation, remove operation, not only save human and material resources, and construction technology is relatively simple, installation, convenient disassembly, shortens the engineering time.

Description

A kind of pit shaft mould plate supporting device
Technical field
Concrete pit construction field is the utility model is related to, particularly a kind of pit shaft mould plate supporting device.
Background technology
In metro depot, the construction of parking lot concrete pit, due to being limited by inspection shaft working space, it is difficult to apply In general form bracing system, it more can not meet and internal model dismounting operation carried out inside operating personnel's tripping in inspection shaft.
Two major classes are broadly divided into for cylindrical shape cast-in-place concrete structure, large cylinder-shaped structure mainly has hollow thin-wall Pier, silo, chimney, deep-well pump house etc..The ratio of application is wide the columnar structured creeping formworks of more than 8m, two-sided sliding formwork, one side Sliding formwork, the Turnover Form Construction Technology, common typified form supporting construction columnar structured below 8m.Middle-size and small-size thin wall cylinder-shaped structure Main rain, sewage inspection well, bridge pad reserving hole etc..For this class formation using relatively common rainy, sewage inspection Well combined steel, plank sheathing support system, bridge pad reserving hole are mainly molded work with pre-buried plastic conduit, coring etc. Skill.
It can be seen that though cylindrical shape concrete structure construction technology at home and abroad has many application technology and plant equipment, however, basement Well is most common due to operating environment, the limitation of operating space as metro depot, the drainage system underground structure in parking lot Construction method, template system and do not apply to.
Analyzed by most common construction method, circulation material:The similar engineering hitherto seen is mainly with group Steel, the construction method progress operation of plank sheathing progress internal model support are closed, internal model installation is installed according to " by lower from upper, staged and layered " Principle, operating personnel carries out formwork reinforcement in layer inside deep-well, and internal model support system also necessarily turns into be arrived on worker The unique passage and operating platform on ground.
Not only difficulty is big for such construction operation, and personnel's Zhi Li, dismounting template security context in small space is poor, disappears Time-consuming is grown.Operating personnel is also same to be examined in face of the hot environment that the concrete heat of hydration is brought of going into the well again, part operation personnel synthesis Consider above-mentioned factor, form removal of often no longer going into the well, and internal model is retained in deep-well, feel to also comply with reason.If well depth is not only Waste of materials, and raindrop erosion template can bring the defects of blocking drainage channel, greatly increase construction in later period and maintenance cost. Such method is only applicable to the construction of inferior grade temporary work, can not meet the matter of high-grade highway, high-speed railway, rail yard Amount requires.
Analyzed by the input situation of live human resources:Conventional internal model support is carried out in small space, it is not only difficult To ensure personal security, similarly it is difficult to ensure that the concrete quality of structure pours stabilization.Under normal circumstances, it is guarantee rolling stock section, stops Large number of cylindrical shape concrete architecture quality and construction speed in parking lot, the multiple operations of substantial amounts of people's work point need to be put into while carried out Excessive risk is vertical, form removal process, and manual work productivity ratio is extremely low, considerably increases construction cost.
Utility model content
The technical problem that the utility model solves is to provide a kind of pit shaft mould plate supporting device, the utility model device structure Make that simple, processing and fabricating cost is low, can be completely achieved terrestrial operation.
In order to solve the above technical problems, the technical solution adopted in the utility model is:
A kind of pit shaft mould plate supporting device, including the plug being vertically set in inspection shaft, are enclosed on the plug successively Some telescoping support units to connect;The structure of the telescoping support unit is:Interior hollow stem including entangling plug, edge The interior hollow stem and be disposed with the 4th outer barrel, the 3rd outer barrel, the second outer barrel and the first outer barrel from the bottom up;Described 4th Connected between outer barrel, the 3rd outer barrel, the second outer barrel and the first outer barrel by elastic mechanism;It is oblique that support is connected with first outer barrel Bar, one end of the knighthead are movably attached in the middle part of support rail, and described support rail one end is fixed on the second outer barrel, The other end is fixed in template;Knighthead and support rail are also equipped with 3rd outer barrel and the 4th outer barrel, its structure is:The Knighthead is connected with three outer barrels, one end of the knighthead is movably attached in the middle part of support rail, the support rail One end is fixed on the 4th outer barrel, and the other end is fixed in template;The first clip is provided with the first outer barrel, for by One outer barrel is fixed on interior hollow stem;The second clip is provided with the 3rd outer barrel, for the 3rd outer barrel to be fixed on into interior sky On core bar.
Further, the template uses and kills sharp gang form.
Further, the elastic mechanism is spring.
Further, the knighthead connects support rail by linkwork.
Further, pre-buried intubation is provided with inspection shaft bottom plate, the plug is inserted into pre-buried intubation.
Further, it is fixed with stroke pressure ring in the second outer barrel bottom.
Further, second outer barrel and the 3rd outer barrel and the elastic mechanism between them are integrally replaced with outside one Cylinder.
Compared with prior art, the beneficial effects of the utility model are:
The utility model device can realize that same period engineering quantity numerous narrow and small, deep well internal model are installed, dismantle operation; Human and material resources are not only saved, and construction technology is relatively simple, installation, convenient disassembly, so as to shorten the time of construction;Device Rigidity is big, stability is good and can recycle for several times, is hardly damaged, and causes the smooth degree in concrete formation face effectively to be protected Card;In addition, mine shaft depth, the needs of size that operating personnel can require according to design drawing, increase bearing height, profit temporarily It is adjusted with spring, hinged structures in support length, amplitude, so as to improve production efficiency, reduces material consumption band The construction cost come;Realize simultaneously and installation in hole, the requirement of dismounting template are carried out on ground, and safe operation process is reliable.
Brief description of the drawings
Fig. 1 is inspection shaft facade view in the utility model.
Fig. 2 is inspection shaft section plan in the utility model.
Fig. 3 is one of the utility model pit shaft mould plate supporting device scheme of installation.
Fig. 4 is the two of the utility model pit shaft mould plate supporting device scheme of installation.
Fig. 5 is that inspection shaft borehole wall concrete schematic diagram is poured in the utility model.
Fig. 6 is the utility model pit shaft mould plate supporting device dismounting schematic diagram.
Fig. 7 is telescoping support cellular construction schematic diagram in the utility model.
Fig. 8 is the template effect diagram that the utility model uses.
Fig. 9 is second of structural representation of telescoping support unit in the utility model.
Figure 10 is the third structural representation of telescoping support unit in the utility model.
In figure:1- inspection shaft side walls;2- inspection shaft bottom plates;3- borehole wall steel reinforcement cages;The pre-buried intubations of 4-;5- plugs;The telescopic branch of 6- Support unit;7- steel wire ropes;8- depression bars;9- chain blocks;10- supports;The clips of 11- first;Hollow stem in 12-;Outside 13- first Cylinder;The outer barrels of 14- second;The outer barrels of 15- the 3rd;16- knightheads;17- elastic mechanisms;The outer barrels of 18- the 4th;19- linkworks; 20- support rails;21- templates;The clips of 22- second;23- stroke pressure rings.
Embodiment
The utility model is described in more detail with reference to the accompanying drawings and detailed description.
Embodiment 1
A kind of pit shaft mould plate supporting device, its structure are in the utility model, including the plug being vertically set in inspection shaft 5, some telescoping support units 6 to connect successively being enclosed on the plug 5;The structure of the telescoping support unit 6 is: Interior hollow stem 12 including entangling plug 5, the 4th outer barrel the 18, the 3rd is disposed with from the bottom up along the interior hollow stem 12 Outer barrel 15, the second outer barrel 14 and the first outer barrel 13;4th outer barrel 18, the 3rd outer barrel 15, the second outer barrel 14 and first outer barrel Connected between 13 by elastic mechanism 17;Knighthead 16 is connected with first outer barrel 13, one end of the knighthead 16 is lived Dynamic to be connected to the middle part of support rail 20, described one end of support rail 20 is fixed on the second outer barrel 14, and the other end is fixed on template On 21;Knighthead 16 and support rail 20 are also equipped with 3rd outer barrel 15 and the 4th outer barrel 18, its structure is:3rd outer barrel Knighthead 16 is connected with 15, one end of the knighthead 16 is movably attached to the middle part of support rail 20, and the support is horizontal The one end of bar 20 is fixed on the 4th outer barrel 18, and the other end is fixed in template 21;The first fixation is provided with the first outer barrel 13 Button 11, for the first outer barrel 13 to be fixed on into interior hollow stem 12;The second clip 22 is provided with the 3rd outer barrel 15, is used for 3rd outer barrel 15 is fixed on interior hollow stem 12.
Technique effect is used for further lifting the utility model device, the template 21 uses and kills sharp gang form. The elastic mechanism 17 is spring.The knighthead 16 connects support rail 20 by linkwork 19.Set on inspection shaft bottom plate 2 Pre-buried intubation 4 is equipped with, the plug 5 is inserted into pre-buried intubation 4.
In the utility model, telescoping support unit 6 is combined using combined steel, steel rod elements and linkwork 19, Device is segmented installation of going into the well with reference to truck crane, loosens linkwork 19 using chain block 9, truck crane, which coordinates, is lifted out well. Operating personnel need to only stand can be controlled on ground to the utility model device.
In the utility model, plug 5 telescoping support unit 6 is played series connection, stably, support, overcome concrete lateral pressure Effect.Knighthead 16 and support rail 20 form retractable support component by linkwork 19, by spring, guide cylinder (i.e. Each outer barrel), clip by the overall force controlled of the template 21 of pit shaft in optimum state.Kill sharp gang form and use template Sharp principle is killed at corner negative and positive angle, effectively overcomes the puzzlement torn open at right angle and brought during internal model.
Embodiment 2
According to the described device of embodiment 1, when removing telescoping support unit 6, whole pit shaft mould plate supporting device, depression bar 8 can preferably press the first clip 11 corresponding to the first outer barrel 13, however, the second clip 22 of the 3rd outer barrel 15 presses just Relatively difficulty is, it is necessary to optimize.
On the basis of embodiment 1, the second clip 22 is subjected to cancellation processing, and by the second outer barrel 14 and the 3rd outer barrel 15 are merged into an outer barrel, cancel middle spring mechanism 17.When mounted, the first outer barrel 13 is controlled by depression bar 8, made outside first The protruding end of first clip 11 is pressed into the first outer barrel 13 by cylinder 13 in folding process, convex by elastic mechanism 17 at first Go out end ejection to block the first clip 11, realize that the entirety of support unit is fixed;When removing, first is controlled by depression bar 8 Clip 11, the protruding end of the first clip 11 is pressed into the first outer barrel 13, passes through elastic mechanism 17 at first, the first clip 11 protruding ends are ejected, and are stuck in the top of the second outer barrel 14, are realized that telescoping support unit 6 is overall and are hung out outside well.
Embodiment 3
On the basis of the described device of embodiment 1, acted on to overcome depression bar 8 to be difficult at the 3rd outer barrel 15, second Welding stroke pressure ring 23 in the bottom subrange of outer barrel 14.During installation, the first outer barrel 13 is controlled by depression bar 8, makes the first outer barrel 13 are pressed into the protruding end of the first clip 11 in first outer barrel 13 in folding process, pass through elastic mechanism 17, protruding end ejection First outer barrel 13 is blocked, realizes that telescoping support unit 6 is overall fixed.When removing, the first outer barrel is controlled by depression bar 8 13, make the first outer barrel 13 that the protruding end of the first clip 11 is pressed into the first outer barrel 13 in folding process, pass through bullet at first Property mechanism 17, while stroke pressure ring 23 is acted on the second clip 22, the second clip 22 is slipped into the 3rd outer barrel 15, with Just next stage retractable support rod member is loosened, and is realized that telescoping support unit 6 is overall and is hung out outside well.
The peace method of tearing open of the utility model pit shaft mould plate supporting device is entered below by specific installation and removal example Row describes in detail, wherein, the installation method comprises the following steps:
The first step:Inspection shaft deep basal pit is excavated, pours the concrete of inspection shaft bottom plate 2, and the pre-buried intubation 4 on inspection shaft bottom plate 2;The Two steps:The reinforcing bar of colligation inspection shaft side wall 1, it is interim fixed that periphery is carried out to the reinforcing bar of inspection shaft side wall 1 using Steel bar rack;3rd step:With Truck crane hangs in plug 5 in inspection shaft, inserts in pre-buried intubation 4;4th step:The telescoping support unit 6 of every meter of segmentation is led to Cross plug 5 to hang in inspection shaft, operating personnel stands on the job platform of outside, is urged to telescoping support unit 6 using depression bar 8 Precalculate the fixed position debugged;5th step:The 4th step process is repeated until each telescoping support unit 6 is installed, be fixed In place;6th step:Internal model concrete cover cushion block is installed in outside operating platform in operating personnel station;7th step:According to common process Outboard template is reinforced;8th step:Pour the concrete of inspection shaft side wall 1.
Inspection shaft concrete placings finish, and reach 2.5Mpa form removal conditions, you can device dismounting is carried out, it is specific as follows:
The first step:Operating personnel is stood in inspection shaft wellhead ground position, and depression bar 8 is goed deep into pit shaft to make telescoping support unit 6 the first clip 11 and the second clip 22 exit the fixed position of interior hollow stem 12;Second step:Will be prior using truck crane The ready support frame of simple wellhead chain block 9, which is hung, moves to pithead position, and operating personnel uses chain block 9 by telescopic branch The first clip 11 and the second clip 22 for supportting unit 6 are lifted, and realize the contracting bone function of telescoping support unit 6;3rd Step:Support 10, chain block 9 and telescoping support unit 6 are hung into deep-well by truck crane;4th step:It is straight to repeat the 3rd step To all parts, all safety is transferred from inspection shaft.
The utility model is applied to the numerous deep well of same period engineering quantity, the pit shaft model sheetinstallat of small space, dismounting Operation, it realizes operating personnel and need not gone into the well, the function that quickly well inner template support system is installed, dismantled;Device Simple structure, it is easy for construction, efficiently solve that the working space that original routine is vertical, form removal is brought is narrow and small, is in high temperature form removal Uncomfortable operating environment, the later stage because indwelling Form board tape come processing the problems such as.The utility model device can reach with similar work The requirement of journey concrete placings quality, and can are reused, during use securely and reliably, and improve operating efficiency, accelerate and apply Work progress, reduces construction cost.

Claims (7)

1. a kind of pit shaft mould plate supporting device, it is characterised in that including the plug (5) being vertically set in inspection shaft, be enclosed on described Some telescoping support units (6) to connect successively on plug (5);
The structure of the telescoping support unit (6) is:Interior hollow stem (12) including entangling plug (5), along the interior sky Core bar (12) is disposed with the 4th outer barrel (18), the 3rd outer barrel (15), the second outer barrel (14) and the first outer barrel from the bottom up (13);Pass through elastic mechanism between 4th outer barrel (18), the 3rd outer barrel (15), the second outer barrel (14) and the first outer barrel (13) (17) connect;
Knighthead (16) is connected with first outer barrel (13), one end of the knighthead (16) is movably attached to support rail (20) middle part, described support rail (20) one end are fixed on the second outer barrel (14), and the other end is fixed in template (21);
Knighthead (16) and support rail (20) are also equipped with 3rd outer barrel (15) and the 4th outer barrel (18), its structure is: Knighthead (16) is connected with 3rd outer barrel (15), one end of the knighthead (16) is movably attached to support rail (20) Middle part, described support rail (20) one end are fixed on the 4th outer barrel (18), and the other end is fixed in template (21);
The first clip (11) is provided with the first outer barrel (13), for the first outer barrel (13) to be fixed on into interior hollow stem (12) On;The second clip (22) is provided with the 3rd outer barrel (15), for the 3rd outer barrel (15) to be fixed on into interior hollow stem (12) On.
2. a kind of pit shaft mould plate supporting device as claimed in claim 1, it is characterised in that the template (21) uses and kills sharp group Shuttering.
3. a kind of pit shaft mould plate supporting device as claimed in claim 1, it is characterised in that the elastic mechanism (17) is bullet Spring.
4. a kind of pit shaft mould plate supporting device as claimed in claim 1, it is characterised in that the knighthead (16) passes through hinge Connection mechanism (19) connection support rail (20).
5. a kind of pit shaft mould plate supporting device as claimed in claim 1, it is characterised in that be provided with inspection shaft bottom plate (2) pre- Intubation (4) is buried, the plug (5) is inserted into pre-buried intubation (4).
6. a kind of pit shaft mould plate supporting device as claimed in claim 1, it is characterised in that in the second outer barrel (14) bottom It is fixed with stroke pressure ring (23).
7. a kind of pit shaft mould plate supporting device as claimed in claim 1, it is characterised in that second outer barrel (14) and the 3rd Outer barrel (15) and the elastic mechanism (17) between them integrally replace with an outer barrel.
CN201721176111.3U 2017-09-14 2017-09-14 A kind of pit shaft mould plate supporting device Expired - Fee Related CN207211201U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721176111.3U CN207211201U (en) 2017-09-14 2017-09-14 A kind of pit shaft mould plate supporting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721176111.3U CN207211201U (en) 2017-09-14 2017-09-14 A kind of pit shaft mould plate supporting device

Publications (1)

Publication Number Publication Date
CN207211201U true CN207211201U (en) 2018-04-10

Family

ID=61824750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721176111.3U Expired - Fee Related CN207211201U (en) 2017-09-14 2017-09-14 A kind of pit shaft mould plate supporting device

Country Status (1)

Country Link
CN (1) CN207211201U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109137986A (en) * 2018-08-09 2019-01-04 杭州江润科技有限公司 Urban road inspection shaft walling crib green promotes reinforced construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109137986A (en) * 2018-08-09 2019-01-04 杭州江润科技有限公司 Urban road inspection shaft walling crib green promotes reinforced construction method
CN109137986B (en) * 2018-08-09 2020-10-30 杭州江润科技有限公司 Green lifting and reinforcing construction method for manhole ring of urban road inspection well

Similar Documents

Publication Publication Date Title
CN105201106A (en) Construction method of double-shear wall template formwork at deformation joint
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN107386329A (en) A kind of pit shaft mould plate supporting device and its peace tear method open
CN106498844A (en) A kind of high speed railway box beam bridge floor pre-fabricated electric cables groove
CN106120584A (en) A kind of box culvert slip form construction device and method
CN207211201U (en) A kind of pit shaft mould plate supporting device
CN103419279A (en) T-beam formwork integral dismantling and longitudinal sliding construction method
CN111074950B (en) Pre-closed advanced water stop post-cast strip for basement outer wall and construction method
CN103074871A (en) Arc-shaped slope concrete sliding and lifting template
CN106284845A (en) A kind of post-cast strip reinforced concrete structural column independence support system construction method
CN109469100A (en) A kind of piping lane template integral support device
CN113502756A (en) Thin-wall pier hydraulic creeping formwork system and construction method thereof
CN211547804U (en) Cantilever type retaining wall rapid construction device
CN203200664U (en) Slip-form construction device for variable cross-section hollow high pier
CN106592438A (en) Two-column pier and middle tie beam construction method employing integral movement of trusses
CN205557349U (en) Device is changed to jib
CN209482350U (en) A kind of piping lane template integral support device
CN111140254A (en) Full-circle double-lining inverted arch construction template system for long-distance tunnel and template transferring method
CN101457587B (en) Template mutually lifting climbing apparatus and method
CN110453689A (en) Circular foundation pit lining wall formwork construction system and construction method
CN208009267U (en) A kind of middle cross beam tensioning protective platform
CN105178196A (en) Multiple-joint linkage type integrated formwork surrounding wet connection section and method
CN215749829U (en) Split type prefabricated box culvert template system
CN211665440U (en) CRTSIII plate type ballastless track bed plate reinforcing mesh
CN210361895U (en) Prefabricated field opening and closing door type protective steel plate trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180410

CF01 Termination of patent right due to non-payment of annual fee