CN207176790U
CN207176790U CN201721129175.8U CN201721129175U CN207176790U CN 207176790 U CN207176790 U CN 207176790U CN 201721129175 U CN201721129175 U CN 201721129175U CN 207176790 U CN207176790 U CN 207176790U
Authority
CN
China
Prior art keywords
bucket
earth
excavating
bucket body
fixed column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721129175.8U
Other languages
Chinese (zh)
Inventor
罗瑛莲
陈晓红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Senke Construction Co ltd
Original Assignee
Pinghu Senke Garden Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pinghu Senke Garden Engineering Co Ltd filed Critical Pinghu Senke Garden Engineering Co Ltd
Priority to CN201721129175.8U priority Critical patent/CN207176790U/en
Application granted granted Critical
Publication of CN207176790U publication Critical patent/CN207176790U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a kind of high efficiency cubic metre of earth and stone Excavating bucket, including bucket body, bucket ear and hanging hole, the bucket body upper end is fixedly connected with bucket ear and hanging hole, the hanging hole is positioned at bucket ear side, the bucket body is internally provided with fixed column, the fixed column upper end is provided with telescopic mast and spring, and the spring is located on the outside of telescopic mast, and the telescopic mast upper end is fixedly connected with pushing assisted plate.The utility model, when bucket body enters material, is dropped on pushing assisted plate by being provided with pushing assisted plate and fixed column, after telescopic mast is pressed into fixed column by pushing assisted plate stress, spring stress, when Excavating bucket pours out material, weight saving, spring eject pushing assisted plate, and material is released in Excavating bucket, prevent material from being accumulated in bucket, have the function that to improve operating efficiency, can effectively avoid traditional Excavating bucket, in the course of the work, have material absorption on headwall, take Excavating bucket space the problem of.

Description

A kind of high efficiency cubic metre of earth and stone Excavating bucket
Technical field
A kind of excavator equipment is the utility model is related to, more particularly to a kind of high efficiency cubic metre of earth and stone Excavating bucket.
Background technology
The cubic metre of earth and stone, it is the general name of the earthwork and the cubic meter of stone, is Tu Heshi, measurement unit is generally cubic meter, cubic metre of earth and stone work Journey includes digging watchman's wooden clapper of all native (stones) sides, fills, transports and draining, precipitation etc., and the cubic metre of earth and stone is typically widely present in In the excavation project of soil and stone, common earth and rock works has:Levelling of the land, foundation ditch(Groove)With pipe canal digging, road excavation, Civil air defense constructions and installations is excavated, terrace bankets, and roadbed filling and foundation ditch backfill, reasonable arrangement construction plan, is tried not to be arranged in Rainy season, while in order to reduce earth and rock works operating expenses, implement and do not account for or account for less farmland and arable land and be advantageous to make with changing The principle in field, will make the rational allocation scheme of the cubic metre of earth and stone, overall arrangement, and stonework is that one wide, amount is big, labour is numerous The engineering project of weight, in work progress, the condition of construction is also extremely complex.But a cubic meter Excavating bucket is conventionally used to, just In normal engineering, substantial amounts of soil is easily accumulated in bucket, takes the space in bucket, influences the efficiency of work, and in engineering Need to fill more scattered and soft soil when backfill, traditional Excavating bucket can not make soil dispersion, while traditional Bucket tooth can not be changed, and reduce overall service life.A kind of therefore, it is proposed that high efficiency cubic metre of earth and stone Excavating bucket.
Utility model content
Main purpose of the present utility model is to provide a kind of high efficiency cubic metre of earth and stone Excavating bucket, by be provided with pushing assisted plate and Fixed column, when bucket body enters material, drop on pushing assisted plate, after telescopic mast is pressed into fixed column by pushing assisted plate stress, bullet Spring stress, when Excavating bucket pours out material, weight saving, spring ejects pushing assisted plate, and material is released in Excavating bucket, prevents thing Material accumulates in bucket, has the function that to improve operating efficiency, can effectively avoid traditional Excavating bucket, in the course of the work, have Material is adsorbed on headwall, the problem of taking Excavating bucket space, and effectively can quickly be released in bucket material, be shortened The time of action is poured out, the efficiency of work is improved, by setting segmentation framework, according to requirement of engineering, manually passes through hook Segmentation framework is fixed on Excavating bucket with projection, material is entered by rounding knife group in bucket, reaches dispersed material volume Effect, can effectively avoid volume of material larger, enter bucket in after absorption on headwall, cause be difficult to take out to ask Topic, the dividing function of Excavating bucket is strengthened, improve the practicality of work, and can be effectively by soil, into bucket body Before crushed, improve efficiency during engineering, while easy for removal and installation, convenience during use improved, by setting Pin is put, manually pin is inserted into the slotted eye of bucket body, after being fixed by block tongue, reaches the work of bucket tooth easy to disassemble With, it can effectively avoid on traditional Excavating bucket, the problem of bucket tooth can not be changed, improve convenience during renewal part, and And can effectively it avoid because the problem of bucket tooth can not be changed, and caused Excavating bucket work quality reduces, improves work Efficiency, while the overall appearance effect of Excavating bucket can be effectively lifted, effectively can solve the problems, such as in background technology.
To achieve the above object, the technical scheme that the utility model is taken is:
A kind of high efficiency cubic metre of earth and stone Excavating bucket, including bucket body, bucket ear and hanging hole, the bucket body upper end are fixedly connected with bucket ear And hanging hole, the hanging hole are internally provided with fixed column positioned at bucket ear side, the bucket body, the fixed column upper end is provided with flexible Post and spring, the spring are located on the outside of telescopic mast, and the telescopic mast upper end is fixedly connected with pushing assisted plate.
Further, the bucket body surface is provided with segmentation framework, and segmentation framework upper end side is provided with hook, institute State segmentation framework lower end and be provided with projection, the segmentation framework surface is provided with rounding knife group, and the segmentation framework passes through hook It is fixedly connected with projection with bucket body.
Further, described bucket body one end is provided with bucket tooth and bucket tooth is fixedly connected by pin and block tongue with bucket body.
Further, the telescopic mast passes through spring and fixed column sleeve connection.
Further, the bucket body is the bucket body for setting grooved hole.
Compared with prior art, the utility model has the advantages that:
1. the utility model by being provided with pushing assisted plate and fixed column, when bucket body enters material, is dropped on pushing assisted plate, After telescopic mast is pressed into fixed column by pushing assisted plate stress, spring stress, when Excavating bucket pours out material, weight saving, spring Pushing assisted plate is ejected, material is released in Excavating bucket, prevents material from being accumulated in bucket, has the function that to improve operating efficiency, energy It is enough effectively to avoid traditional Excavating bucket, in the course of the work, there is material absorption on headwall, the problem of taking Excavating bucket space, And effectively material can be quickly released in bucket, shorten the time for pouring out action, improve the efficiency of work.
2. the utility model is by setting segmentation framework, according to requirement of engineering, manually by hook and projection by divided frame Frame is fixed on Excavating bucket, material is entered by rounding knife group in bucket, is haveed the function that dispersed material volume, can be effective Avoid volume of material larger, after entering in bucket absorption the problem of causing to be difficult to take out, strengthen Excavating bucket on headwall Dividing function, the practicality of work is improved, and can be crushed, improved before bucket body is entered effectively by soil Efficiency during engineering, at the same it is easy for removal and installation, improve convenience during use.
3. pin is manually inserted into the slotted eye of bucket body, consolidated by block tongue by setting pin by the utility model After fixed, have the function that bucket tooth easy to disassemble, can effectively avoid on traditional Excavating bucket that the problem of can not changing bucket tooth carries Convenience during renewal part has been risen, and can effectively have been avoided because bucket tooth can not be changed, caused Excavating bucket as received basis The problem of amount reduces, improves the efficiency of work, while can effectively lift the overall appearance effect of Excavating bucket.
Brief description of the drawings
Fig. 1 is a kind of side structure schematic view of high efficiency cubic metre of earth and stone Excavating bucket of the utility model.
Fig. 2 is a kind of fixed column structural representation of high efficiency cubic metre of earth and stone Excavating bucket of the utility model.
Fig. 3 is a kind of positive structure diagram of high efficiency cubic metre of earth and stone Excavating bucket of the utility model.
Fig. 4 is a kind of segmentation framework structural representation of high efficiency cubic metre of earth and stone Excavating bucket of the utility model.
Fig. 5 is a kind of Tooth structure schematic diagram of high efficiency cubic metre of earth and stone Excavating bucket of the utility model.
In figure:1st, bucket body;2nd, struggle against ear;3rd, hanging hole;4th, projection;5th, pin;6th, bucket tooth;7th, fixed column;8th, telescopic mast;9th, bullet Spring;10th, pushing assisted plate;11st, segmentation framework;12nd, link up with;13rd, rounding knife group;14th, block tongue.
Embodiment
Technological means, creation characteristic, reached purpose and effect to realize the utility model are easy to understand, below With reference to embodiment, the utility model is expanded on further.
As Figure 1-5, a kind of high efficiency cubic metre of earth and stone Excavating bucket, including bucket body 1, bucket ear 2 and hanging hole 3, on the bucket body 1 End is fixedly connected with bucket ear 2 and hanging hole 3, and the hanging hole 3 is internally provided with fixed column 7, institute positioned at bucket ear 2 side, the bucket body 1 State the upper end of fixed column 7 and be provided with telescopic mast 8 and spring 9, the spring 9 is located at the outside of telescopic mast 8, and the upper end of telescopic mast 8 is consolidated Surely it is connected with pushing assisted plate 10.
Wherein, the surface of bucket body 1 is provided with segmentation framework 11, and the upper end side of segmentation framework 11 is provided with hook 12, the lower end of segmentation framework 11 is provided with projection 4, and the surface of segmentation framework 11 is provided with rounding knife group 13, the segmentation Framework 11 is fixedly connected by hook 12 and projection 4 with bucket body 1.
Wherein, described one end of bucket body 1 is provided with bucket tooth 6 and bucket tooth 6 is fixedly connected by pin 5 and block tongue 14 with bucket body 1.
Wherein, the telescopic mast 8 passes through spring 9 and the sleeve connection of fixed column 7.
Wherein, the bucket body 1 is the bucket body for setting grooved hole.
It should be noted that the utility model is a kind of high efficiency cubic metre of earth and stone Excavating bucket, when in use, pass through the He of ear 2 of struggling against Hanging hole 3 is operated after bucket body 1 is attached with motion arm, when bucket body 1 enters material, is dropped on pushing assisted plate 10, is helped After telescopic mast 8 is pressed into fixed column 7 by the stress of push pedal 10, the stress of spring 9, when Excavating bucket pours out material, weight saving, bullet Spring 9 ejects pushing assisted plate 10, and material is released in Excavating bucket, prevents material from being accumulated in bucket, reaches the work for improving operating efficiency With, traditional Excavating bucket can be effectively avoided, in the course of the work, has material absorption on headwall, occupancy Excavating bucket space Problem, and effectively can quickly release material in bucket, the time for pouring out action is shortened, improves the effect of work Rate, according to requirement of engineering, manually segmentation framework 11 is fixed on Excavating bucket by hook 12 and projection 4, makes material through undue Cutter group 13 is entered in bucket, has the function that dispersed material volume, can effectively be avoided volume of material larger, be entered bucket Absorption the problem of causing to be difficult to take out, strengthens the dividing function of Excavating bucket, improves the practicality of work on headwall after interior Property, and can be crushed effectively by soil before bucket body is entered, efficiency during engineering is improved, at the same it is easy to disassemble And installation, convenience during use is improved, is manually inserted into pin 5 in the slotted eye of bucket body 1, is fixed by block tongue 14 Afterwards, have the function that bucket tooth easy to disassemble, can effectively avoid on traditional Excavating bucket, the problem of bucket tooth can not be changed, lifting Convenience during renewal part, and can effectively avoid because bucket tooth can not be changed, caused Excavating bucket work quality The problem of reduction, the efficiency of work is improved, while can effectively lift the overall appearance effect of Excavating bucket.
The advantages of general principle and principal character of the present utility model and the utility model has been shown and described above.One's own profession The technical staff of industry is it should be appreciated that the utility model is not restricted to the described embodiments, described in above-described embodiment and specification Simply illustrate principle of the present utility model, on the premise of the spirit and scope of the utility model is not departed from, the utility model is also Various changes and modifications are had, these changes and improvements are both fallen within claimed the scope of the utility model.The utility model Claimed scope is by appended claims and its equivalent thereof.

Claims (5)

1. a kind of high efficiency cubic metre of earth and stone Excavating bucket, including bucket body(1), bucket ear(2)And hanging hole(3), the bucket body(1)Upper end is fixed It is connected with bucket ear(2)And hanging hole(3), the hanging hole(3)Positioned at bucket ear(2)Side, it is characterised in that:The bucket body(1)It is internal It is provided with fixed column(7), the fixed column(7)Upper end is provided with telescopic mast(8)And spring(9), the spring(9)Positioned at flexible Post(8)Outside, the telescopic mast(8)Upper end is fixedly connected with pushing assisted plate(10).
A kind of 2. high efficiency cubic metre of earth and stone Excavating bucket according to claim 1, it is characterised in that:The bucket body(1)Surface is set It is equipped with segmentation framework(11), the segmentation framework(11)Upper end side is provided with hook(12), the segmentation framework(11)Lower end It is provided with projection(4), the segmentation framework(11)Surface is provided with rounding knife group(13), the segmentation framework(11)Pass through hook (12)And projection(4)With bucket body(1)It is fixedly connected.
A kind of 3. high efficiency cubic metre of earth and stone Excavating bucket according to claim 1, it is characterised in that:The bucket body(1)One end is set It is equipped with bucket tooth(6)And bucket tooth(6)Pass through pin(5)And block tongue(14)With bucket body(1)It is fixedly connected.
A kind of 4. high efficiency cubic metre of earth and stone Excavating bucket according to claim 1, it is characterised in that:The telescopic mast(8)Pass through Spring(9)With fixed column(7)Sleeve connection.
A kind of 5. high efficiency cubic metre of earth and stone Excavating bucket according to claim 1, it is characterised in that:The bucket body(1)To set The bucket body of grooved hole.
CN201721129175.8U 2017-09-05 2017-09-05 A kind of high efficiency cubic metre of earth and stone Excavating bucket Expired - Fee Related CN207176790U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721129175.8U CN207176790U (en) 2017-09-05 2017-09-05 A kind of high efficiency cubic metre of earth and stone Excavating bucket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721129175.8U CN207176790U (en) 2017-09-05 2017-09-05 A kind of high efficiency cubic metre of earth and stone Excavating bucket

Publications (1)

Publication Number Publication Date
CN207176790U true CN207176790U (en) 2018-04-03

Family

ID=61742966

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721129175.8U Expired - Fee Related CN207176790U (en) 2017-09-05 2017-09-05 A kind of high efficiency cubic metre of earth and stone Excavating bucket

Country Status (1)

Country Link
CN (1) CN207176790U (en)

Similar Documents

Publication Publication Date Title
CN102155009A (en) Crushed rock pile used for strengthening extremely soft soil foundation and construction method thereof
CN204023578U (en) Retaining Structure with Double-row Piles
CN103670448B (en) A kind of underground utilities protective device and apply the supporting method of this device
CN108049395A (en) A kind of anti-collapse impact holing construction method in complex karst place
CN107964995A (en) A kind of pile foundation borehole device
CN207176790U (en) A kind of high efficiency cubic metre of earth and stone Excavating bucket
CN205329445U (en) Compound resistance to compression road bed
CN207498973U (en) A kind of power station grout curtain cuts dirty drainage tube
CN208472716U (en) Crack geology mortar leakage prevention drill-pouring pilework
CN107975027B (en) Construction method for reinforcing soil body at shield launching and arrival end
CN108457279A (en) A kind of foundation pit enclosure structure cast-in-situ bored pile collapse hole in-situ treatment method
CN209523165U (en) A kind of hydraulic engineering dam configuration
CN201635765U (en) Sand throwing device for gob under highway
CN212052857U (en) Concrete buttress formula retaining wall structure permeates water
CN205024694U (en) Superplasticity concrete drilling bored concrete pile dado
CN106703021A (en) Construction method for pile cap of screw pile, and device thereof
CN103195077A (en) Dam foundation reinforcement frame structure and dam foundation reinforcement method
CN203129163U (en) Reinforcing framework structure for dam foundation
CN202450511U (en) Grouting device
CN203174586U (en) Concrete pipe pile for reinforcing railway soft soil foundation
CN209053086U (en) A kind of dual-purpose composite pile device of the pumping grouting of band rigidity tubing
CN202989785U (en) Light type bridge abutment forward-inclination reinforcing device
CN106351253A (en) Novel water conservancy project retaining wall
CN207392201U (en) A kind of packaged type slip casting platform
CN206844129U (en) A kind of new diagonal brace composite support device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 314000 No. 55, Zhangqiao section, 07 provincial road, Caoqiao street, Pinghu City, Jiaxing City, Zhejiang Province

Patentee after: Zhejiang Senke Construction Co.,Ltd.

Address before: 314000 No. 55, Zhangqiao section, 07 provincial road, Caoqiao street, Pinghu City, Jiaxing City, Zhejiang Province

Patentee before: PINGHU SENKE LANDSCAPE ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180403

CF01 Termination of patent right due to non-payment of annual fee