CN207158660U - A kind of standard knot unit of tower crane - Google Patents

A kind of standard knot unit of tower crane Download PDF

Info

Publication number
CN207158660U
CN207158660U CN201721156616.3U CN201721156616U CN207158660U CN 207158660 U CN207158660 U CN 207158660U CN 201721156616 U CN201721156616 U CN 201721156616U CN 207158660 U CN207158660 U CN 207158660U
Authority
CN
China
Prior art keywords
standard knot
fixed
tower crane
bolt
screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721156616.3U
Other languages
Chinese (zh)
Inventor
龙见军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA NUCLEAR INDUSTRY HUATAI CONSTRUCTION Co Ltd
Original Assignee
CHINA NUCLEAR INDUSTRY HUATAI CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA NUCLEAR INDUSTRY HUATAI CONSTRUCTION Co Ltd filed Critical CHINA NUCLEAR INDUSTRY HUATAI CONSTRUCTION Co Ltd
Priority to CN201721156616.3U priority Critical patent/CN207158660U/en
Application granted granted Critical
Publication of CN207158660U publication Critical patent/CN207158660U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of standard knot unit of tower crane, including the vertical standard knot placed on the ground, the standard knot is in cuboid framework structure, screw is provided with the top of the standard knot, the standard knot bottom is fixed with motor, the motor is provided with downward output shaft, and compression elastic piece is fixed with the output shaft, and the one end of the compression elastic piece away from output shaft is fixed with the bolt coordinated with screw.This standard knot is during installation and removal, bolt fixed standard section is used without being arrived on operating personnel at standard knot, but utilize motor driven bolt lock standardization section, it not only ensure that the safety of operating personnel, the automaticity of tower crane installation is also improved, accelerates the speed of the installation and removal of tower crane.

Description

A kind of standard knot unit of tower crane
Technical field
It the utility model is related to a kind of tower crane device, the standard knot unit of more particularly to a kind of tower crane.
Background technology
Tower crane is crane gear the most frequently used on a kind of construction site, and high composition is connect using a section assembly of standard knot Its tower body, for the construction raw material such as the reinforcing bar of lifting construction, wood stupefied, concrete and steel pipe.
At present, the standard knot of the tower crane of in the market as shown in Figure 1, including support bar 21 and connecting rod 22 form it is rectangular Body frame structure, the angle of standard knot 2 are provided with screw 4, when installing standard knot 2, upper strata standard knot 2 are hung into lower floor's standard knot 2 Top, the screw 4 on each angle are interconnected, and operating personnel are inserted in screw 4 using bearing pin and fix the adjacent standard of two sections Section 2.
Although this kind of standard knot can respectively save and be overlapped mutually fixation, when installing standard knot, it is necessary to which operating personnel exist It is upper at the standard knot lifted after carrying out safety measure, manually it is fixed;And standard knot hoisting process is unstable Property, very big potential safety hazard is brought to operating personnel.
Utility model content
The purpose of this utility model is to provide a kind of standard knot unit of tower crane, is carried out without operating personnel close to standard knot It is fixed, so as to ensure that the safety of operating personnel.
Above-mentioned technical purpose of the present utility model technical scheme is that:A kind of standard knot of tower crane Unit, including the vertical standard knot placed on the ground, the standard knot is in cuboid framework structure, is set at the top of the standard knot There is screw, the standard knot bottom is fixed with motor, and the motor is provided with downward output shaft, pressure is fixed with the output shaft Contracting elastic component, the one end of the compression elastic piece away from output shaft are fixed with the bolt coordinated with screw.
By using above-mentioned technical proposal, during assembling, upper strata standard knot is placed into lower floor's standard knot using boom hoisting On, after the mutual pairing of screw of bolt and lower floor's standard knot on the standard knot of upper strata, start motor driven bolt and rotate, screw up into To fix two adjacent sections standard knot in screw.And the compression elastic piece set between bolt and the output shaft of motor, give The space that bolt moves along screw direction.During dismounting, start motor reversal, bolt exits from screw, you can separate upper strata mark Quasi- section and lower floor's standard knot;This standard knot uses during installation and removal without being arrived on operating personnel at standard knot Bolt fixed standard section, but motor driven bolt lock standardization section is utilized, the safety of operating personnel is not only ensure that, is also improved The automaticity of tower crane installation, accelerate the speed of the installation and removal of tower crane.
Further, the standard knot top horizontal is provided with steel wire rope.
By using above-mentioned technical proposal, when standard knot is installed, operating personnel are generally required first on standard knot in connection The part of convenient lifting, after good standard knot to be fixed, then it is upper remove part to standard knot top, it is cumbersome;Therefore each Save standard knot top horizontal and one steel wire rope is set, need to only catch on steel wire rope when lifting by crane standard knot can complete to lift by crane, and fix After standard knot, unclamping steel wire rope can continue to lift by crane next section standard knot;Without, to operation on standard knot, ensureing on operating personnel The safety of operating personnel, and without the part of the convenient lifting of repeated disassembled and assembled, save the plenty of time.
Further, the steel wire rope is in relaxed state under normal conditions, is interval with two pieces of folders on the steel wire rope downwards Plywood, when the steel wire rope is in lifting state, two pieces of sandwich panel lower ends are mutually supported and closed.
By using above-mentioned technical proposal, when lifting standard knot is installed, boom hoisting be placed on two pieces of sandwich panels it Between, to hang oneself dynamic standard knot when, loose steel wire rope stress is exceptionally straight, make originally the sandwich panel in vertical state to boom hoisting Rotate, two pieces of sandwich panel lower ends are mutually supported and closed, and so as to pin boom hoisting, prevent boom hoisting from rocking on a steel cord, influence Lifting safety.
Further, the standard knot bottom is equiped with fixed bin, and the motor is placed in fixed bin, the fixed bin Bottom, which is provided with, supplies the perforate that shaft stretches out.
By using above-mentioned technical proposal, because mounted standard knot can be long-term use of in outdoor, therefore, in order to prevent Motor is put into the fixed bin of standard knot bottom setting by rain erosion by motor.And in order to not influence the use of motor, solid Determine cassette bottom portion and be provided with perforate, the output shaft of power supply machine passes through.
Further, the standard knot bottom is corresponding with screw is fixed with sleeve, the output shaft, compression elastic piece and spiral shell Bolt is placed in sleeve.
By using above-mentioned technical proposal, due to the setting of compression elastic piece, when motor driven bolt rotates, bolt can be with Shaken with compression elastic piece, influence the installation of standard knot;Therefore, one on output shaft, compression elastic piece and bolt coat It individual sleeve, can not only protect bolt not to be etched, extend its usage time, bolt can also be prevented to rock, facilitate motor will Bolt is screwed into screw.In addition, bolt is stabilized in sleeve, and sleeve is fixed on standard knot, and then consolidated upper strata mark The connection of quasi- section and lower floor's standard knot.
Further, fixed block is fixed with the top of the standard knot, the screw is arranged in fixed block, the fixed block Bottom is fixed with the nut coordinated with bolt.
By using above-mentioned technical proposal, a nut is placed in fixed block bottom, after bolt is screwed into nut, to bolt When applying pulling force, fixed block can block nut, prevent bolt from departing from fixed block, so as to the company between further stability criteria section Connect.
Further, some guide grooves to stretch out are provided with the top of the standard knot, some guide grooves are in outside Open shape to set, the directive wheel that the standard knot bottom is provided with and guide groove coordinates.
By using above-mentioned technical proposal, when installing standard knot, in order that bolt and screw alignment, using guide groove and lead Coordinate to wheel, standard knot is progressively alignd in lifting, so as to facilitate motor driven bolt to be screwed among screw.
Further, the surface of the guide groove and directive wheel is coated with identification layer.
By using above-mentioned technical proposal, because no operating personnel are guided on standard knot, lifting personnel are difficult to Align standard knot;Therefore, applied on guide groove and directive wheel and be covered with identification layer, make the quick capturing position of lifting personnel, and by Guide groove and directive wheel alignment standard knot.
In summary, the utility model has the advantages that:
1. by the bolt of motor driven, automatic rotating bolt is sealed into screw progress, realizes the automatic of standard knot Change sealed installation, without, to installing manually on standard knot, ensure that the safety of operating personnel on operating personnel;
2. by guide groove and directive wheel, when lifting by crane installation, the placement of standard knot is oriented to, realizes the quick of standard knot Alignment.
Brief description of the drawings
Fig. 1 is prior art overall structure diagram;
Fig. 2 is a kind of overall structure diagram of the standard knot unit of tower crane of the utility model;
Fig. 3 is the enlarged drawing of part A in Fig. 2;
Fig. 4 is the enlarged drawing of part B in Fig. 2;
Fig. 5 is the explosive view of two neighboring standard knot;
Fig. 6 is the explosive view of bolt and threaded bore portion.
In figure, 1, ground;2nd, standard knot;21st, support bar;22nd, connecting rod;3rd, fixed bin;31st, perforate;32nd, motor;33、 Output shaft;34th, compression elastic piece;35th, bolt;36th, sleeve;4th, screw;41st, storage tank;42nd, nut;43rd, fixed block;5th, lead To groove;51st, directive wheel;52nd, it is open;6th, steel wire rope;61st, sandwich panel;62nd, through hole;7th, boom hoisting;8th, base section.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment:
A kind of standard knot unit of tower crane, as shown in Fig. 2 including multiple standard knots 2, describe for convenience, in this implementation In example, the installation with regard to two standard knots 2 illustrates.On ground 1 base section 8, lifting personnel's profit are fixed with using built-in fitting Standard knot 2 is hung on base section 8 with boom hoisting 7, the tower body that standard knot 2 and base section 8 are spliced to form is fixed on vertically On ground 1.As shown in Fig. 2 standard knot 2 includes the support bar 21 being vertically arranged and the connecting rod 22 for connecting each support bar 21, branch Strut 21 and connecting rod 22 surround a cuboid framework structure.Fixing device is provided between two adjacent sections standard knot 2, this Kind fixing device can realize automatic locking and the unlatching of two adjacent sections standard knot 2, enterprising without arriving standard knot 2 on operating personnel Row installation, ensure that the safety of operating personnel.
As shown in Figure 5 and Figure 6, fixing device includes being arranged on the fixed bin 3 of the bottom of standard knot 2, and fixed bin is mounted in support In the angle that bar 21 and connecting rod 22 surround.It is placed with motor 32 in fixed bin 3, the output shaft 33 that the one end of motor 32 is set is from fixation The perforate 31 that the bottom of box 3 is opened is stretched out, and output shaft 33 is set straight down;Compression elastic piece 34 is connected with output shaft 33, Here, compression elastic piece 34 selects spring, and bolt 35 is fixed with end of the compression elastic piece 34 away from output shaft 33.
In addition, as shown in Figure 5 and Figure 6, outside output shaft 33, compression elastic piece 34 and bolt 35 being cased with one is fixed on branch Sleeve 36 on strut 21, here, the length of sleeve 36 are output shaft 33, compression elastic piece 34 and bolt 35 under relaxed state Length summation, so that bolt 35 can be normally screwed into screw 4.In order to ensure the security of standard knot 2, in the bottom of sleeve 36 A hole passed through for the screw parts of bolt 35 is formed to contract, and fitted bolt 35 is provided with the inwall of hole Screw thread, so, the screw thread in sleeve 36 tighten together bolt 35 and upper strata standard knot 2.
As shown in Figure 5 and Figure 6, fixing device also includes the fixed fixed block 43 in the top of standard knot 2, and fixed block 43 is mounted in branch In the angle that strut 21 and connecting rod 22 surround.The screw 4 coordinated with bolt 35 is provided with fixed block 43, upper strata standard knot 2 is hung After being alignd to the top of lower floor's standard knot 2, motor 32 drives bolt 35 to rotate and is screwed into screw 4, and two section standard knots 2 can be fixed as One entirety.In addition, being provided with storage tank 41 in the bottom of fixed block 43, nut 42 is placed with storage tank 41, bolt 35 is entering admittedly It is screwed into after determining the bottom of block 43 in nut 42, further fastens the connection between two adjacent sections standard knot 2.
As Fig. 2 shows, guide groove 5 is fixed with obliquely on four angles at the top of standard knot 2, guide groove 5 is flared out shape Set.The setting as shown in figure 5, guide groove 5 takes the shape of the letter U, and U-shaped opening 52 is inwardly set;Filled on four angles of the bottom of standard knot 2 There is the directive wheel 51 for coordinating guide groove 5;When upper strata standard knot 2 is hung above lower floor's standard knot 2, directive wheel 51 is along guiding Groove 5 slides to the junction of guide groove 5 and standard knot 2 by portion, two adjacent sections standard knot 2 is alignd.So, fixing device is coordinated It can be achieved with quick alignment and the locking of standard knot 2.
As shown in Figures 2 to 4, each top horizontal of standard knot 2 is fixed with steel wire rope 6, and steel wire rope 6 is diagonally set Put, two pieces of sandwich panels 61 are fixed with the midfeather of steel wire rope 6, when not in use, steel wire rope 6 is in relaxed state, two pieces of sandwich panels 61 are not in contact with each other.Between boom hoisting 7 is placed into two pieces of sandwich panels 61, steel wire rope 6 is hung, makes steel wire rope 6 exceptionally straight, at this moment, The sandwich panel 61 of script vertical state rotates to boom hoisting 7, and lower end is mutually supported and closed, and prevents boom hoisting 7 from being shaken on steel wire rope 6 It is dynamic.Here, sandwich panel 61 selects two pieces of identical triangular plates, and triangular plate is while be fixed on steel wire rope 6, after lifting mutually The centre on the both sides of fitting is provided with the through hole 62 for accommodating suspension hook.
The course of work:After base section 8 below by standard knot 2 installs, standard knot is installed one by one using boom hoisting 7 2, boom hoisting 7 pulls steel wire rope 6, and steel wire rope 6 is tightened, and sandwich panel 61 clamps boom hoisting 7;Lifting personnel are according to guide groove 5 The identification layer that other positions are different from the surface of directive wheel 51 is lifted, and hangs standard knot 2 to mounted standard knot 2 Top.Directive wheel 51 slides downwards in guide groove 5, upper strata standard knot 2 is fallen on lower floor's standard knot 2, starts motor 32, band Dynamic bolt 35 is screwed into screw 4, fixes two adjacent standard knots 2;Boom hoisting 7 is moved down, steel wire rope 6 loses pulling force, folder Plywood 61 is decontroled, and boom hoisting 7 removes, and is continued to lift by crane lower section standard knot 2 and is installed, untill reaching ideal height.
Described above is only preferred embodiment of the present utility model, and the scope of protection of the utility model is not limited merely to Above-described embodiment, all technical schemes belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to Go out, for those skilled in the art, some improvement under the premise of the utility model principle is not departed from and Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.

Claims (8)

1. a kind of standard knot unit of tower crane, including it is placed on ground vertically(1)On standard knot(2), the standard knot(2)It is in Cuboid framework structure, it is characterised in that:The standard knot(2)Top is provided with screw(4), the standard knot(2)Bottom is fixed There is motor(32), the motor(32)Provided with downward output shaft(33), the output shaft(33)On be fixed with compression elastic piece (34), the compression elastic piece(34)Away from output shaft(33)One end be fixed with and screw(4)The bolt of cooperation(35).
A kind of 2. standard knot unit of tower crane according to claim 1, it is characterised in that:The standard knot(2)Top water It is flat to be provided with steel wire rope(6).
A kind of 3. standard knot unit of tower crane according to claim 2, it is characterised in that:The steel wire rope(6)In normality It is in relaxed state down, the steel wire rope(6)On be interval with two pieces of sandwich panels downwards(61), the steel wire rope(6)In lifting During state, two pieces of sandwich panels(61)Lower end is mutually supported and closed.
A kind of 4. standard knot unit of tower crane according to claim 1, it is characterised in that:The standard knot(2)Bottom fills Provided with fixed bin(3), the motor(32)It is placed on fixed bin(3)In, the fixed bin(3)Bottom is provided with feeding shaft(33) The perforate of stretching(31).
A kind of 5. standard knot unit of tower crane according to claim 1, it is characterised in that:The standard knot(2)Bottom with Screw(4)It is corresponding to be fixed with sleeve(36), the output shaft(33), compression elastic piece(34)And bolt(35)It is placed on sleeve (36)It is interior.
A kind of 6. standard knot unit of tower crane according to claim 1, it is characterised in that:The standard knot(2)Top is consolidated Surely there is fixed block(43), the screw(4)It is arranged on fixed block(43)In, the fixed block(43)Bottom is fixed with and bolt (35)The nut of cooperation(42).
A kind of 7. standard knot unit of tower crane according to claim 1, it is characterised in that:The standard knot(2)Top is set There are some guide grooves to stretch out(5), some guide grooves(5)Set in shape is flared out, the standard knot(2)Bottom It is provided with and guide groove(5)The directive wheel of cooperation(51).
A kind of 8. standard knot unit of tower crane according to claim 7, it is characterised in that:The guide groove(5)And guiding Wheel(51)Surface be coated with identification layer.
CN201721156616.3U 2017-09-08 2017-09-08 A kind of standard knot unit of tower crane Active CN207158660U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721156616.3U CN207158660U (en) 2017-09-08 2017-09-08 A kind of standard knot unit of tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721156616.3U CN207158660U (en) 2017-09-08 2017-09-08 A kind of standard knot unit of tower crane

Publications (1)

Publication Number Publication Date
CN207158660U true CN207158660U (en) 2018-03-30

Family

ID=61720929

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721156616.3U Active CN207158660U (en) 2017-09-08 2017-09-08 A kind of standard knot unit of tower crane

Country Status (1)

Country Link
CN (1) CN207158660U (en)

Similar Documents

Publication Publication Date Title
CN208869129U (en) Telescopic building hoist day beam is set in elevator traction
CN111217266A (en) Working method of assembly type wall body hoisting device with good stability
CN207158660U (en) A kind of standard knot unit of tower crane
CN102061810B (en) Construction method of safe flat net positioned on periphery of building
CN107069533B (en) A kind of super UHV Overhead Transmission Line tangent tower ground wire lifting tool
CN207016392U (en) Detecting robot of pipe downhole device
CN211341686U (en) Hanging basket support system
CN205805002U (en) A kind of safety rope fixing device for job site
CN106044564B (en) The blind installation method for wearing installation guide frame
CN209976169U (en) A anti-wind seals way board for road construction
CN208454342U (en) A kind of safety of tower crane platform and standard knot install conjoined device
CN103541557A (en) Simple device for vertical steel pipe
CN202988556U (en) Special lifting appliance for angle-steel type frame body
CN203583900U (en) Simple device for erecting steel pipe
CN211775988U (en) Steel construction high-rise tower high altitude protector
CN203429559U (en) Suspension bridge anchor system steel anchor rod hoisting tool
CN209555785U (en) A kind of external quality of pier coating decoration platform suitable for high pier bridge
CN208345716U (en) A kind of nacelle device
CN207122125U (en) A kind of means for fastening scaffolding
CN206693723U (en) Transmission tower
CN206636239U (en) A kind of suspension installation system for being used to install interlayer girder steel
CN201485204U (en) Gas tank hanging device
CN110106810A (en) Wave plate is installed on the positioning device and its construction method of fence upright
CN203284125U (en) Movable crane for small offshore platform
CN205035045U (en) A hanging flower basket guider for applying paint two curve type cooling tower inner walls

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant