Prior art keywords
waste gas
main exhaust
exhaust pipeline
integrated system
pollution control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721033881.2U
Other languages
Chinese (zh)
Inventor
杨林鲜
易友元
曾福厚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Baolan Environmental Protection Co ltd
Original Assignee
Shandong Baolan Environmental Protection Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Baolan Environmental Protection Engineering Co Ltd filed Critical Shandong Baolan Environmental Protection Engineering Co Ltd
Priority to CN201721033881.2U priority Critical patent/CN207137673U/en
Application granted granted Critical
Publication of CN207137673U publication Critical patent/CN207137673U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses a kind of rubbish waste gas pollution control and treatment integrated system, including waste incineration workshop, at least one waste gas collection device is set at the top of the waste incineration workshop, the waste gas collection device connects the first main exhaust pipeline, the first main exhaust pipeline exhaust end sets exhaust blower, the exhaust blower connects the second main exhaust pipeline, the critical point of the second main exhaust pipeline is deep into settling tank bottom, the settling tank top sets the first sealing cover body, the first sealing cover body connects the 3rd main exhaust pipeline, the 3rd main exhaust pipeline is deep into neutralization pond bottom;The neutralization pond top sets the second sealing cover body, and the second sealing cover body is communicated with gas cleaning plant by the 4th main exhaust pipeline, and the gas cleaning plant gas outlet sets flue gas analyzer.Rubbish waste gas pollution control and treatment integrated system provided by the utility model, effectively solve the problems, such as flue dust caused by current waste incineration and pernicious gas pollution living environment.

Description

一种垃圾废气治理成套系统A complete set of waste gas treatment system

技术领域technical field

本实用新型涉及垃圾废气治理领域,具体涉及一种垃圾废气治理成套系统。The utility model relates to the field of waste gas treatment, in particular to a complete system for waste gas treatment.

背景技术Background technique

随着经济水平的提高,各种生活垃圾和工业垃圾愈来愈多,焚烧是处理垃圾的常用手段,然而垃圾焚烧时会产生大量的烟尘、二氧化硫、二氧化氮、一氧化氮等有害气体,对大气造成了严重的污染,严重影响人的身体健康。目前,垃圾的焚烧一般选择远离市区的空旷地带,常常采用露天焚烧,对焚烧产生的烟尘或有害气体直接排放到大气中并没有专门的废气治理系统。With the improvement of the economic level, there are more and more various domestic garbage and industrial garbage. Incineration is a common means of garbage disposal. However, a large amount of smoke, sulfur dioxide, nitrogen dioxide, nitrogen monoxide and other harmful gases will be produced during garbage incineration. It has caused serious pollution to the atmosphere and seriously affected people's health. At present, garbage incineration generally chooses open areas far away from urban areas, often using open-air incineration, and there is no special waste gas treatment system for direct discharge of smoke or harmful gases generated by incineration into the atmosphere.

为了解决上述问题,亟需发明一种垃圾焚烧时治理产生的废气的治理系统,以解决目前垃圾焚烧时产生的烟尘和有害气体直接排放到大气中严重污染人类生存环境的问题。In order to solve the above problems, it is urgent to invent a treatment system for waste gas generated during waste incineration, so as to solve the problem that the smoke and harmful gases generated during waste incineration are directly discharged into the atmosphere and seriously pollute the human living environment.

实用新型内容Utility model content

本实用新型的目的在于提供一种垃圾废气治理成套系统。The purpose of the utility model is to provide a complete system for waste gas treatment.

为达到上述目的,本实用新型采用的技术方案如下:In order to achieve the above object, the technical scheme adopted by the utility model is as follows:

一种垃圾废气治理成套系统,包括垃圾焚烧车间,所述垃圾焚烧车间顶部设置至少一个废气收集装置,所述垃圾焚烧车间顶部设置一层铁纱网,所述铁纱网位于废气收集装置的下部;A complete set of waste gas treatment system, including a waste incineration workshop, at least one waste gas collection device is installed on the top of the waste incineration workshop, and a layer of iron gauze is installed on the top of the waste incineration workshop, and the iron gauze is located at the lower part of the waste gas collection device ;

所述废气收集装置连通第一主排气管道,所述第一主排气管道排气端设置排风机,所述排风机连通第二主排气管道,所述第二主排气管道的关口深入到沉降池底部,所述沉降池上部设置第一密封罩体,所述第一密封罩体连通第三主排气管道,所述第三主排气管道深入到中和池底部;The waste gas collection device communicates with the first main exhaust pipe, the exhaust end of the first main exhaust pipe is provided with an exhaust fan, and the exhaust fan communicates with the second main exhaust pipe, and the gate of the second main exhaust pipe Go deep into the bottom of the settling tank, the upper part of the settling tank is provided with a first sealing cover, the first sealing cover communicates with the third main exhaust pipeline, and the third main exhaust pipeline goes deep into the bottom of the neutralization tank;

所述中和池上部设置第二密封罩体,所述第二密封罩体通过第四主排气管道连通有气体净化装置,所述气体净化装置出气口设置烟气分析仪。A second sealing cover is arranged on the upper part of the neutralization tank, and the second sealing cover is connected with a gas purification device through the fourth main exhaust pipe, and a flue gas analyzer is installed at the gas outlet of the gas purification device.

进一步的,所述废气收集装置位4~12组,所述废气收集装置包括倒漏斗状的吸气盘和第一副排气管,所述第一副排气管连通第一主排气管道。Further, the waste gas collection devices are located in 4-12 groups, and the waste gas collection devices include an inverted funnel-shaped suction plate and a first auxiliary exhaust pipe, and the first auxiliary exhaust pipe communicates with the first main exhaust pipe. .

进一步的,所述垃圾焚烧车间设置补气管,所述补气管下管口深入到垃圾焚烧车间底部。Further, the waste incineration plant is equipped with an air supply pipe, and the lower nozzle of the air supply pipe goes deep into the bottom of the waste incineration plant.

进一步的,所述第三主排气管道连通至少一个第二副排气管,所述第二副排气管均匀设置排气孔。Further, the third main exhaust pipe communicates with at least one second auxiliary exhaust pipe, and the second auxiliary exhaust pipe is uniformly provided with exhaust holes.

进一步的,所述第二副排气管为3~12根,所述第二副排气管均匀的布置在中和池底面并进行固定。Further, there are 3 to 12 second auxiliary exhaust pipes, and the second auxiliary exhaust pipes are evenly arranged on the bottom surface of the neutralization pool and fixed.

进一步的,所述气体净化装置包括净化装置箱体、活性炭吸附层、冷触媒过滤网,所述活性炭吸附层和冷触媒过滤网依次设置在净化装置箱体内部。Further, the gas purification device includes a purification device box, an activated carbon adsorption layer, and a cold catalyst filter, and the activated carbon adsorption layer and the cold catalyst filter are sequentially arranged inside the purification device box.

进一步的,所述净化装置箱体内部设置有副排风机,所述烟气分析仪位于副排风机的排风侧。Further, an auxiliary exhaust fan is arranged inside the box of the purification device, and the flue gas analyzer is located on the exhaust side of the auxiliary exhaust fan.

进一步的,所述补气管进气口处设置鼓风机。Further, a blower is provided at the inlet of the air supply pipe.

与现有技术相比,本实用新型具有以下有益效果:Compared with the prior art, the utility model has the following beneficial effects:

1、本实用新型提供的垃圾废气治理成套系统,垃圾焚烧时会产生大量的烟尘,垃圾焚烧车间的铁纱网初步的进行过滤烟尘,沉降池中预先加满清水,可以进一步的清洗废气中所携带的烟尘,烟尘清除效果优异,避免垃圾焚烧所产生的烟尘进入到大气中造成雾霾的情况。1. The complete waste gas treatment system provided by this utility model will produce a large amount of smoke and dust when the waste is incinerated. The iron gauze in the waste incineration workshop will initially filter the smoke and dust, and the sedimentation tank will be filled with clean water in advance to further clean the waste gas. The smoke and dust carried, the smoke and dust removal effect is excellent, and the smoke and dust generated by garbage incineration can be avoided from entering the atmosphere to cause smog.

2、本实用新型提供的垃圾废气治理成套系统,其中的中和池可以吸收中和垃圾焚烧所产生的二氧化硫、二氧化氮等酸性气体,有效的解决了垃圾有害酸性气体进入大气中造成酸雨的问题。2. The utility model provides a complete set of waste gas treatment system, in which the neutralization pool can absorb and neutralize acid gases such as sulfur dioxide and nitrogen dioxide produced by waste incineration, effectively solving the problem of acid rain caused by harmful acid gases entering the atmosphere from waste question.

本实用新型提供的垃圾废气治理成套系统,结构简单、使用方便,可以有效的去除垃圾焚烧所产生的烟尘,以及二氧化硫、二氧化氮等有害气体,有效的解决了垃圾焚烧严重污染大气环境的问题。The complete waste gas treatment system provided by the utility model has a simple structure and is easy to use, and can effectively remove smoke and dust produced by waste incineration, as well as harmful gases such as sulfur dioxide and nitrogen dioxide, and effectively solve the problem of serious pollution of the atmospheric environment by waste incineration .

显然,根据本实用新型的上述内容,按照本领域的普通技术知识和惯用手段,在不脱离本实用新型上述基本技术思想前提下,还可以做出其它多种形式的修改、替换或变更。Obviously, according to the above content of the utility model, according to the common technical knowledge and conventional means in this field, without departing from the above basic technical idea of the utility model, other modifications, replacements or changes can also be made in various forms.

以下通过具体实施方式,对本实用新型的上述内容再作进一步的详细说明;但不应将此理解为本实用新型上述主题的范围仅限于以下的实例;凡基于本实用新型的构思所实现的技术均属于本实用新型的范围。Below by way of specific implementation, the above-mentioned content of the present utility model is described in further detail; But this should not be interpreted as the scope of the above-mentioned theme of the present utility model is limited to the following examples; All belong to the scope of the present utility model.

附图说明Description of drawings

图1为本实用新型一种垃圾废气治理成套系统结构示意图;Fig. 1 is a schematic structural diagram of a complete system for waste gas treatment of the utility model;

图2为本实用新型一种垃圾废气治理成套系统第二副排气管结构剖视图;Fig. 2 is a cross-sectional view of the structure of the second auxiliary exhaust pipe of a complete set of waste gas treatment system of the present invention;

图中:In the picture:

1-垃圾焚烧车间;2-废气收集装置;3-铁纱网;4-第一主排气管道;5-排风机;6-第二主排气管道;7-沉降池;8-第一密封罩体;9-第三主排气管道;10-中和池;11-第二密封罩体;12-第四主排气管道;13-气体净化装置;14-烟气分析仪;21-吸气盘;22-第一副排气管;23-第二副排气管;24-排气孔;31-补气管;32-净化装置箱体;33-活性炭吸附层;34-冷触媒过滤网;35-副排风机;36-鼓风机。1-Waste incineration workshop; 2-Exhaust gas collection device; 3-Iron gauze; 4-First main exhaust pipe; 5-Exhaust fan; 6-Second main exhaust pipe; 7-Settlement tank; 8-First Sealed cover; 9-third main exhaust pipe; 10-neutralization tank; 11-second sealed cover; 12-fourth main exhaust pipe; 13-gas purification device; 14-flue gas analyzer; 21 -suction plate; 22-first auxiliary exhaust pipe; 23-second auxiliary exhaust pipe; 24-exhaust hole; 31-air supply pipe; 32-purification device box; 33-activated carbon adsorption layer; Catalyst filter screen; 35-secondary exhaust fan; 36-blower.

具体实施方式Detailed ways

为了使本实用新型的目的、技术方案及优点更加清楚明白,以下结合附图,对本实用新型作进一步详细说明。In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model will be further described in detail below in conjunction with the accompanying drawings.

如图1~2所示,一种垃圾废气治理成套系统,包括垃圾焚烧车间(1),所述垃圾焚烧车间(1)顶部设置至少一个废气收集装置(2),所述垃圾焚烧车间(1)顶部设置一层铁纱网(3),所述铁纱网(3)位于废气收集装置(2)的下部;As shown in Figures 1-2, a complete waste gas treatment system includes a waste incineration workshop (1), at least one waste gas collection device (2) is arranged on the top of the waste incineration workshop (1), and the waste incineration workshop (1) ) is provided with a layer of iron gauze (3) on the top, and the iron gauze (3) is located at the bottom of the waste gas collection device (2);

所述废气收集装置(2)连通第一主排气管道(4),所述第一主排气管道(4)排气端设置排风机(5),所述排风机(5)连通第二主排气管道(6),所述第二主排气管道(6)的关口深入到沉降池(7)底部,,所述沉降池中预先装满清水以便于除去废气中的烟尘,所述沉降池(7)上部设置第一密封罩体(8),所述第一密封罩体(8)连通第三主排气管道(9),所述第三主排气管道(9)深入到中和池(10)底部,中和池中预先装满碱性溶液(氢氧化钠溶液或者碳酸钠溶液等)以便于中和吸收废气中的二氧化硫和二氧化氮等酸性气体;The waste gas collection device (2) communicates with the first main exhaust pipe (4), the exhaust end of the first main exhaust pipe (4) is provided with an exhaust fan (5), and the exhaust fan (5) communicates with the second Main exhaust pipe (6), the juncture of the second main exhaust pipe (6) goes deep into the bottom of the sedimentation tank (7), and the clear water is pre-filled in the sedimentation tank so as to remove smoke and dust in the waste gas, the The upper part of the settling tank (7) is provided with a first sealing cover (8), and the first sealing cover (8) communicates with the third main exhaust pipe (9), and the third main exhaust pipe (9) goes deep into At the bottom of the neutralization tank (10), the neutralization tank is pre-filled with an alkaline solution (sodium hydroxide solution or sodium carbonate solution, etc.) so as to neutralize and absorb acid gases such as sulfur dioxide and nitrogen dioxide in the waste gas;

所述中和池(10)上部设置第二密封罩体(11),所述第二密封罩体(11)通过第四主排气管道(12)连通有气体净化装置(13),所述气体净化装置(13)出气口设置烟气分析仪(14),烟气分析仪为山东保蓝环保工程有限公司的GC-100型烟气分析仪。The upper part of the neutralization tank (10) is provided with a second sealing cover (11), and the second sealing cover (11) is communicated with a gas purification device (13) through the fourth main exhaust pipe (12). A flue gas analyzer (14) is arranged at the gas outlet of the gas purification device (13), and the flue gas analyzer is a GC-100 flue gas analyzer of Shandong Baolan Environmental Protection Engineering Co., Ltd.

进一步的,所述废气收集装置(2)位4~12组,所述废气收集装置(2)包括倒漏斗状的吸气盘(21)和第一副排气管(22),所述第一副排气管(22)连通第一主排气管道(4)。Further, the waste gas collection devices (2) are located in groups of 4 to 12, and the waste gas collection devices (2) include an inverted funnel-shaped suction plate (21) and a first auxiliary exhaust pipe (22). A secondary exhaust pipe (22) communicates with the first main exhaust pipe (4).

进一步的,所述垃圾焚烧车间(1)设置补气管(31),所述补气管(31)下管口深入到垃圾焚烧车间(1)底部。Further, the waste incineration plant (1) is provided with an air supply pipe (31), and the lower nozzle of the air supply pipe (31) goes deep into the bottom of the waste incineration plant (1).

进一步的,所述第三主排气管道(9)连通至少一个第二副排气管(23),所述第二副排气管(23)均匀设置排气孔(24)。Further, the third main exhaust pipe (9) communicates with at least one second auxiliary exhaust pipe (23), and the second auxiliary exhaust pipe (23) is uniformly provided with exhaust holes (24).

进一步的,所述第二副排气管(23)为3~12根,所述第二副排气管(23)均匀的布置在中和池(10)底面并进行固定,使得废气充分的进入到中和池中使废气中的二氧化硫、二氧化氮等酸性气体充分被中和池中的碱性液体吸收中和,有效的除去了垃圾废气中的酸性气体。Further, there are 3 to 12 second auxiliary exhaust pipes (23), and the second auxiliary exhaust pipes (23) are evenly arranged on the bottom surface of the neutralization tank (10) and fixed so that the exhaust gas is fully Entering into the neutralization tank, the acid gases such as sulfur dioxide and nitrogen dioxide in the exhaust gas are fully absorbed and neutralized by the alkaline liquid in the neutralization tank, effectively removing the acid gas in the waste gas.

进一步的,所述气体净化装置(13)包括净化装置箱体(32)、活性炭吸附层(33)、所述活性炭吸附层(33)呈蜂窝状,冷触媒过滤网(34),所述活性炭吸附层(33)和冷触媒过滤网(34)依次设置在净化装置箱体(32)内部。Further, the gas purification device (13) includes a purification device box (32), an activated carbon adsorption layer (33), the activated carbon adsorption layer (33) is honeycomb-shaped, a cold catalyst filter screen (34), and the activated carbon The adsorption layer (33) and the cold catalyst filter screen (34) are sequentially arranged inside the purification device box body (32).

进一步的,所述净化装置箱体(32)内部设置有副排风机(35),所述烟气分析仪(14)位于副排风机(35)的排风侧。Further, an auxiliary exhaust fan (35) is arranged inside the purification device box (32), and the flue gas analyzer (14) is located on the exhaust side of the auxiliary exhaust fan (35).

进一步的,所述补气管(31)进气口处设置鼓风机(36)。Further, a blower (36) is provided at the inlet of the air supply pipe (31).

当然,本实用新型还可有其它多种实施方式,在不背离本实用新型精神及其实质的情况下,熟悉本领域的技术人员可根据本实用新型作出各种相应的改变和变形,但这些相应的改变和变形都应属于本实用新型所附的权利要求的保护范围。Certainly, the utility model also can have other multiple implementation modes, under the situation of not departing from the spirit and essence of the utility model, those skilled in the art can make various corresponding changes and distortions according to the utility model, but these Corresponding changes and deformations should all belong to the scope of protection of the appended claims of the utility model.

Claims (8)

  1. A kind of 1. rubbish waste gas pollution control and treatment integrated system, it is characterised in that:Including waste incineration workshop (1), the waste incineration car Between at least one waste gas collection device (2) is set at the top of (1), one layer of gauze screen is set at the top of the waste incineration workshop (1) (3), the gauze screen (3) is located at the bottom of waste gas collection device (2);
    The waste gas collection device (2) connects the first main exhaust pipeline (4), and the first main exhaust pipeline (4) exhaust end is set Exhaust blower (5), the exhaust blower (5) connect the second main exhaust pipeline (6), and the critical point of the second main exhaust pipeline (6) is goed deep into To settling tank (7) bottom, settling tank (7) top sets the first sealing cover body (8), the first sealing cover body (8) connection 3rd main exhaust pipeline (9), the 3rd main exhaust pipeline (9) are deep into neutralization pond (10) bottom;
    Neutralization pond (10) top sets the second sealing cover body (11), and the second sealing cover body (11) passes through the 4th main exhaust Pipeline (12) is communicated with gas cleaning plant (13), and gas cleaning plant (13) gas outlet sets flue gas analyzer (14).
  2. A kind of 2. rubbish waste gas pollution control and treatment integrated system according to claim 1, it is characterised in that:The waste gas collection device (2) 4~12 groups of position, the waste gas collection device (2) include funnelform suction disk (21) and the first secondary blast pipe (22), institute State the first secondary blast pipe (22) and connect the first main exhaust pipeline (4).
  3. A kind of 3. rubbish waste gas pollution control and treatment integrated system according to claim 1, it is characterised in that:The waste incineration workshop (1) blowdown pipe (31) is set, and blowdown pipe (31) lower nozzle is deep into waste incineration workshop (1) bottom.
  4. A kind of 4. rubbish waste gas pollution control and treatment integrated system according to claim 1, it is characterised in that:3rd main exhaust Road (9) connects at least one second secondary blast pipe (23), and the second secondary blast pipe (23) is uniformly arranged steam vent (24).
  5. A kind of 5. rubbish waste gas pollution control and treatment integrated system according to claim 4, it is characterised in that:The second secondary blast pipe (23) it is 3~12, the second secondary blast pipe (23) is uniformly arranged in neutralization pond (10) bottom surface and is fixed.
  6. A kind of 6. rubbish waste gas pollution control and treatment integrated system according to claim 1, it is characterised in that:The gas cleaning plant (13) purifier casing (32), activated carbon adsorption layer (33), cold catalyst screen pack (34), the activated carbon adsorption layer are included (33) and cold catalyst screen pack (34) is successively set on purifier casing (32) inside.
  7. A kind of 7. rubbish waste gas pollution control and treatment integrated system according to claim 6, it is characterised in that:The purifier casing (32) secondary exhaust blower (35) is internally provided with, the flue gas analyzer (14) is located at the air draft side of secondary exhaust blower (35).
  8. A kind of 8. rubbish waste gas pollution control and treatment integrated system according to claim 3, it is characterised in that:The blowdown pipe (31) is entered Air blower (36) is set at gas port.
CN201721033881.2U 2017-08-17 2017-08-17 A kind of rubbish waste gas pollution control and treatment integrated system Expired - Fee Related CN207137673U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721033881.2U CN207137673U (en) 2017-08-17 2017-08-17 A kind of rubbish waste gas pollution control and treatment integrated system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721033881.2U CN207137673U (en) 2017-08-17 2017-08-17 A kind of rubbish waste gas pollution control and treatment integrated system

Publications (1)

Publication Number Publication Date
CN207137673U true CN207137673U (en) 2018-03-27

Family

ID=61665703

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721033881.2U Expired - Fee Related CN207137673U (en) 2017-08-17 2017-08-17 A kind of rubbish waste gas pollution control and treatment integrated system

Country Status (1)

Country Link
CN (1) CN207137673U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108730991A (en) * 2018-05-25 2018-11-02 王玲 Domestic waste burns environmental protection processing apparatus
CN109530134A (en) * 2018-11-20 2019-03-29 马美香 A kind of coal mine spraying wind leaking stoppage macromolecule sprayed on material jet printing protecting device
CN110384993A (en) * 2019-06-10 2019-10-29 孙铭婧 A kind of boiler discharge fume dust remover

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108730991A (en) * 2018-05-25 2018-11-02 王玲 Domestic waste burns environmental protection processing apparatus
CN109530134A (en) * 2018-11-20 2019-03-29 马美香 A kind of coal mine spraying wind leaking stoppage macromolecule sprayed on material jet printing protecting device
CN110384993A (en) * 2019-06-10 2019-10-29 孙铭婧 A kind of boiler discharge fume dust remover

Similar Documents

Publication Publication Date Title
CN207137673U (en) A kind of rubbish waste gas pollution control and treatment integrated system
CN209735306U (en) A waste gas collection and treatment device
CN201596433U (en) A purification device for dust removal and oil removal in chimneys
CN205672766U (en) A kind of efficiently industrial fumes energy-saving purifier
CN205340455U (en) SOx/NOx control fume treatment auxiliary
CN204543902U (en) One way of life garbage flash mineralization treater gas cleaning plant
CN110180311A (en) A kind of flue gas graded processing device of garbage incinerating power plant
CN205323493U (en) Boiler waste gas treating device
CN201105203Y (en) Ring grid showering spume dust removing and desulferizing device
CN208436563U (en) A kind of flue gas desulfurization waste heat recycle device
CN2675231Y (en) Combined type flue desulfurizing and dust-removing purifier
CN204911130U (en) Energy -concerving and environment -protective dust removal, sulphur removal, smoke abatement system
CN204601965U (en) A kind of garbage incinerating tail gas cleaning system
CN209791104U (en) filter bag type dust removal device
CN211328895U (en) An energy-saving and environmentally friendly waste gas treatment device
CN201470304U (en) Double-flange washable spray pipe of gas scrubber and deodorization tower
CN105107324A (en) Energy-saving and environment-friendly dust removal, desulfurization and smoke removal system
CN208372651U (en) A kind of chemical gases recyclable device
CN206823412U (en) A kind of traveling-grate stoker fume purifying apparatus
CN113713569A (en) Flue gas purification device of steel sintering machine
CN207667418U (en) A kind of desulphurization denitration equipment with cleaning function
CN219290973U (en) Industrial boiler waste gas treatment device
CN207445988U (en) A kind of energy conservation and environmental protection emission reduction device for power plant
CN211051235U (en) A new type of high-efficiency exhaust gas purification device
CN221693107U (en) Filter equipment that greenhouse gas discharged

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No.1-48, Beishi village, hi tech Zone, Zibo City, Shandong Province

Patentee after: Shandong Baolan Environmental Protection Co.,Ltd.

Address before: No.1-48, Beishi village, hi tech Zone, Zibo City, Shandong Province

Patentee before: SHANDONG BAOLAN EP Co.,Ltd.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180327

CF01 Termination of patent right due to non-payment of annual fee