CN207121927U CN201720452918.9U CN201720452918U CN207121927U CN 207121927 U CN207121927 U CN 207121927U CN 201720452918 U CN201720452918 U CN 201720452918U CN 207121927 U CN207121927 U CN 207121927U
Authority
CN
China
Prior art keywords
cabin
pipe gallery
bilge tank
comprehensive
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720452918.9U
Other languages
Chinese (zh)
Inventor
宗金宇
尹力文
姜素云
张伟娜
阙良刚
邓成云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Capital Engineering and Research Incorporation Ltd
Zhongye Jingcheng Engineering Technology Co Ltd
Original Assignee
Zhongye Jingcheng Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongye Jingcheng Engineering Technology Co Ltd filed Critical Zhongye Jingcheng Engineering Technology Co Ltd
Priority to CN201720452918.9U priority Critical patent/CN207121927U/en
Application granted granted Critical
Publication of CN207121927U publication Critical patent/CN207121927U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The utility model provides a kind of prefabricated pipe gallery, including bilge tank (10), comprehensive cabin (20) and combustion gas cabin (30), bilge tank (10) is located at the right side of the prefabricated pipe gallery, combustion gas cabin (30) is located at the left side of the prefabricated pipe gallery, comprehensive cabin (20) are located between bilge tank (10) and combustion gas cabin (30), lower surface on the inside of bilge tank (10) is higher than the lower surface on the inside of comprehensive cabin (20), and the upper surface on the inside of bilge tank (10) is higher than the upper surface on the inside of comprehensive cabin (20).The prefabricated pipe gallery is solved when original sewage conduct buried depth is shallower, it is necessary to deepen the limitation that sewage conduct buried depth just can be included in pipe gallery.Sewage conduct can be effectively increased enters corridor scope, and does not increase the depth of burying of sewage conduct.

Description

Prefabricated pipe gallery
Technical field
It the utility model is related to a kind of prefabricated pipe gallery.
Background technology
Pipe gallery is to be built in Urban Underground to be used to accommodate the structures of two classes and above municipal engineering pipeline and attached set Apply.A tunnel space is built in Urban Underground, by electric power, the various utilities pipeline collection such as communication, combustion gas, heat supply, plumbing It is the important infrastructure and " life for ensureing city operations provided with special access hole, hoisting port and monitoring system in one Line ".The construction of pipe gallery can effectively eliminate city " slide fastener road ", ensure that road traffic is unobstructed, while ensure that underground utilities are pacified Battalion for the national games.
《Some opinions of the Party Central Committee, State Council on further strengthening urban planning and development control》In point out:It is every to build Region provided with pipe gallery, all kinds of pipelines must all enter corridor, and the region beyond pipeline must not newly-built pipeline.The Office of the State Council is sent out 【2015】No. 61 files are emphasized:Corridor must all be entered by having built all pipelines in the region of underground pipe gallery.Firmly build portion in Hold on June 17th, 2016 and promote Urban Underground pipe gallery to build teleconference, finally it is to be emphasized again that:Firmly to implement pipeline All enter the requirement of corridor, corridor must all be entered including coal gas, sewage by specifying all pipelines.
《City integrated piping lane engineering legislation》(GB50838-2015) included for rainwater, sewage and natural gas tube comprehensive The technical measures for closing piping lane are illustrated.It can meet the situation that rainwater, sewage include for orographic condition and drainage system, need Consideration includes rainwater, sewage in pipe gallery,《City integrated piping lane engineering legislation》(GB50838-2015) provided in Sewage includes pipe gallery planted agent and uses tube shaped.After sewage includes pipe gallery with pipeline, for the area that physical features is flat, Sewage conduct is gradually increased with gradient buried depth, and piping lane also can be with buried depth be increased, when the piping lane depth of burying is larger, often Cause to invest it is larger, when entering corridor sewage conduct buried depth in allowed limits, i.e., when piping lane earthing is more than 3 meters, to bilge tank Piping lane affiliated facility etc. setting and the factor that considers of other cabins it is essentially identical.
Existing pipe gallery is set using the space of 3 meters of earthing of the general requirement above bilge tank in blower fan interlayer Put blower fan to realize to the ventilation requirement of bilge tank, again may be by that this space realizes bilge tank feeds intake and realize other pipes Road crosses, as shown in Figure 1.
The defects of above-mentioned existing pipe gallery, has:
1st, when sewage conduct buried depth is shallower, it is impossible to realize the purpose that sewage conduct is included to pipe gallery.
2nd, when sewage conduct buried depth is shallower, if the pipe gallery shallow embedding including bilge tank set, it is impossible to meet The requirement that part is passed through by traffic control road from top, if crossing will cause buried depth larger and uneconomical from below
3rd, when sewage conduct buried depth is shallower, if the pipe gallery shallow embedding including bilge tank set, pipe gallery is each Cabin can not share hoisting port and carry out the work that feeds intake.
4th, when sewage conduct buried depth is shallower, if the pipe gallery shallow embedding including bilge tank set, comprehensive cabin pipeline Extraction will be limited by side bilge tank, and sewage conduct, which is drawn, also the problem of same.
5th, when sewage conduct buried depth is shallower, if the pipe gallery shallow embedding including bilge tank set, it will influence ground The facility of face upper part, such as greening etc..
Related terms are explained:
Sewage enters corridor:By gravity stream or the municipal wastewater drainage pipeline of pressure current, pipe gallery is included in the form of pipeline.
Utility model content
It is inconvenient to dock to solve the problems, such as the sewage conduct in existing pipe gallery with original sewage conduct, and this practicality is new Type provides a kind of prefabricated pipe gallery, the prefabricated pipe gallery solve when original sewage conduct buried depth is shallower, it is necessary to plus Deep sewage conduct buried depth just can be included in the limitation of pipe gallery.Sewage conduct can be effectively increased enters corridor scope, and not Increase the depth of burying of sewage conduct.
Technical scheme is used by the utility model solves its technical problem:A kind of prefabricated pipe gallery, it includes dirt Water tank, comprehensive cabin and combustion gas cabin, bilge tank are located at the right side of the prefabricated pipe gallery, and combustion gas freight space is in the prefabricated pipe gallery Left side, for comprehensive freight space between bilge tank and combustion gas cabin, the lower surface on the inside of bilge tank is higher than the lower surface on the inside of comprehensive cabin, dirty Upper surface on the inside of water tank is higher than the upper surface on the inside of comprehensive cabin.
Lower surface on the inside of bilge tank is less than the upper surface on the inside of comprehensive cabin, and the lower surface on the inside of bilge tank is higher than comprehensive cabin The midpoint between lower surface on the inside of the upper surface of inner side and comprehensive cabin.
The distance between lower surface on the inside of upper surface and bilge tank on the inside of bilge tank is the upper surface on the inside of comprehensive cabin The 75%~125% of distance between the lower surface on the inside of comprehensive cabin, comprehensive cabin and combustion gas cabin share the left side wall in comprehensive cabin, comprehensive The bottom for closing the top of the right side wall in cabin and the left side wall of bilge tank shares.
The prefabricated pipe gallery also includes draft chamber, and draft chamber is located at the top in comprehensive cabin, draft chamber and bilge tank or so Adjacent, the upper side wall in the shared comprehensive cabin in draft chamber and comprehensive cabin, the top of the left side wall of bilge tank and the right side wall of draft chamber are total to With the top of draft chamber can connect with ground ventilation mouth.
The upper side wall in comprehensive cabin is provided with the upper air vent that can be connected with draft chamber, and the top of the left side wall of sewage is provided with energy Enough side air vents connected with draft chamber.
Be provided with draft chamber and be used to extract the draft fan of gas in bilge tank, be provided with bilge tank sewage conduct buttress and Sewage conduct conduit saddle, sewage conduct conduit saddle are arranged on sewage conduct buttress.
Upper surface on the inside of draft chamber is concordant with the upper surface on the inside of bilge tank, and the left side wall of draft chamber is located at comprehensive cabin The surface of left side wall, the upper surface on the inside of combustion gas cabin is concordant with the upper surface on the inside of comprehensive cabin, the lower surface on the inside of combustion gas cabin It is concordant with the lower surface on the inside of comprehensive cabin.
The prefabricated pipe gallery also includes lifting room, and lifting room is located at the top in comprehensive cabin, lifts room and bilge tank or so It is adjacent, the upper side wall in the shared comprehensive cabin in lifting room and comprehensive cabin, lift the inside of room and the inside of bilge tank and be communicated as one, hang The top of dress room can connect with ground hoisting port.
The upper surface of lifting indoor is concordant with the upper surface on the inside of bilge tank, and the left side wall for lifting room is located at comprehensive cabin The surface of left side wall;Upper surface on the inside of bilge tank is provided with suspension hook;Or the upper surface of lifting indoor is provided with suspension hook;Or sewage The upper surface of cabin and lifting indoor is equipped with suspension hook.
The prefabricated pipe gallery also includes crossing sleeve pipe, crosses sleeve pipe through the top of the left side wall of bilge tank and bilge tank Right side wall top, cross the outside that sleeve pipe is located at comprehensive cabin and combustion gas cabin, cross outside sleeve pipe and be arranged with water string, waterproof Sleeve pipe is located in the left side wall and right side wall of bilge tank.
The beneficial effects of the utility model are:The prefabricated pipe gallery is solved when original sewage conduct buried depth is shallower, Need to deepen the limitation that sewage conduct buried depth just can be included in pipe gallery.By being targetedly that bilge tank sets side to send row Wind system, side lifting feeding system, and branch pipe(tube) solve shallow embedding sewage conduct and received by way of sleeve pipe crosses bilge tank Enter some problems that pipe gallery faces.What the utility model can be effectively increased sewage conduct enters corridor scope, and does not increase The depth of burying of sewage conduct.
Brief description of the drawings
The Figure of description for forming the part of the application is used for providing further understanding to of the present utility model, this practicality New schematic description and description is used to explain the utility model, does not form to improper restriction of the present utility model.
Fig. 1 is the structural representation of existing prefabricated pipe gallery.
Fig. 2 is the structural representation of prefabricated pipe gallery described in the utility model.
Fig. 3 is structural representation of the prefabricated pipe gallery described in the utility model at draft chamber.
Fig. 4 is structural representation of the prefabricated pipe gallery described in the utility model at lifting room.
Fig. 5 is that prefabricated pipe gallery described in the utility model is crossing the structural representation at sleeve pipe.
10th, bilge tank;11st, side air vent;12nd, sewage conduct buttress;13rd, sewage conduct conduit saddle;14th, sewage conduct;15、 Suspension hook;16th, sleeve pipe is crossed;17th, water string;
20th, comprehensive cabin;21st, upper air vent;22nd, middle water pipe;23rd, feed pipe;
30th, combustion gas cabin;31st, natural gas line;
40th, draft chamber;41st, draft fan;
50th, room is lifted;
60th, ground;61st, ground ventilation mouth;62nd, greenbelt;63rd, hoisting port.
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the application can phase Mutually combination.Describe the utility model in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
A kind of prefabricated pipe gallery, including bilge tank 10, comprehensive cabin 20 and combustion gas cabin 30, it is prefabricated comprehensive that bilge tank 10 is located at this The right side of piping lane is closed, combustion gas cabin 30 is located at the left side of the prefabricated pipe gallery, and comprehensive cabin 20 is located at bilge tank 10 and combustion gas cabin 30 Between, the lower surface of the inner side of bilge tank 10 is higher than the lower surface of the comprehensive inner side of cabin 20, and the upper surface of the inner side of bilge tank 10 is higher than comprehensive The upper surface of the inner side of cabin 20 is closed, as shown in Figure 2.
Sewage conduct 14 is provided with bilge tank 10, integrates and middle water pipe 22 and feed pipe 23 is provided with cabin 20, in comprehensive cabin 20 The cable such as electric power and communication is additionally provided with, natural gas line 31 is provided with combustion gas cabin 30.General original sewage conduct buried depth is shallower (2.0m being greater than, less than 3.5m), can be so as to after comprehensive cabin section and bilge tank section are using the set-up mode of above-mentioned staggered floor Sewage conduct in pipe gallery docks the problem of inconvenient with original sewage conduct.In addition, bilge tank 10, comprehensive cabin 20 and combustion Size in gas cabin 30 should meet that current personnel, sewage conduct transport and sewage conduct walkaround inspection etc. require.
In the present embodiment, the lower surface of the preferably inner side of bilge tank 10 is less than the upper surface of the comprehensive inner side of cabin 20, bilge tank The lower surface of 10 inner sides is higher than the midpoint between the upper surface of the comprehensive inner side of cabin 20 and the lower surface of the comprehensive inner side of cabin 20, as Fig. 2, Shown in Fig. 3, Fig. 4.The distance between the upper surface of the inner side of bilge tank 10 and the lower surface of the inner side of bilge tank 10 is in comprehensive cabins 20 The 75%~125% of distance, the i.e. internal height of bilge tank 10 are between the lower surface of the upper surface of side and the comprehensive inner side of cabin 20 The 75%~125% of the comprehensive internal height of cabin 20, the preferably internal height of bilge tank 10 are equal to the internal height in comprehensive cabin 20, Comprehensive cabin 20 and combustion gas cabin 30 share the left side wall in comprehensive cabin 20, i.e., the left side wall in comprehensive cabin 20 and the right side wall in combustion gas cabin 30 are Same side wall, the top and the bottom of the left side wall of bilge tank 10 of the right side wall in comprehensive cabin 20 share.
In the present embodiment, the prefabricated pipe gallery is pre-formed to be segmented, and the prefabricated pipe gallery of multistage is transported to existing Overall prefabricated pipe gallery is formed after the docking assembling of field.One section of prefabricated pipe gallery can be with as shown in Fig. 2 one section of prefabricated synthesis Piping lane can so that as shown in figure 3, the prefabricated pipe gallery also includes draft chamber 40, draft chamber 40 is located at the top in comprehensive cabin 20, Draft chamber 40 is adjacent with bilge tank 10 or so, the upper side wall in the shared comprehensive cabin 20 in draft chamber 40 and comprehensive cabin 20, bilge tank 10 The right side wall on the top of left side wall and draft chamber 40 shares, and the top of draft chamber 40 can connect with ground ventilation mouth 61.
In the present embodiment, the upper side wall in comprehensive cabin 20 is provided with the upper air vent 21 that can be connected with draft chamber 40, sewage The top of the left side wall in cabin 10 is provided with the side air vent 11 that can be connected with draft chamber 40.It is provided with draft chamber 40 and is used to extract dirt The draft fan 41 and exhaust duct of gas in water tank 10, bilge tank 10 is interior to be provided with sewage conduct buttress 12 and sewage conduct conduit saddle 13, sewage conduct conduit saddle 13 is arranged on sewage conduct buttress 12, and sewage conduct 14 is arranged on sewage conduct conduit saddle 13.It is comprehensive Air vent 21, draft chamber 40, ground ventilation mouth 61 and ground ventilation can be passed sequentially through by closing cabin 20, and bilge tank 10 can Pass sequentially through side air vent 11, draft fan 41, draft chamber 40 and ground ventilation mouth 61 and ground ventilation, sewage conduct branch Pier 12 (or support) can be adjusted according to the setting height(from bottom) of sewage conduct 14.
In the present embodiment, the upper surface of the inner side of draft chamber 40 is concordant with the upper surface of the inner side of bilge tank 10, draft chamber 40 Left side wall be located at comprehensive cabin 20 left side wall surface, the upper surface of the inner side of combustion gas cabin 30 with it is upper on the inside of comprehensive cabin 20 Flush, the lower surface of the inner side of combustion gas cabin 30 are concordant with the lower surface of the comprehensive inner side of cabin 20.
In the present embodiment, one section of prefabricated pipe gallery can be with as shown in figure 4, the prefabricated pipe gallery also includes lifting Room 50, lifting room 50 are located at the top in comprehensive cabin 20, and lifting room 50 is adjacent with bilge tank 10 or so, lifting room 50 and comprehensive cabin 20 The upper side wall in comprehensive cabin 20 is shared, the inside of room 50 and the inside of bilge tank 10 is lifted and is communicated as one, lift room 50 and sewage There is no isolate between cabin 10, the top of lifting room 50 can connect with ground hoisting port 63, and ground hoisting port 63 and ground lead to Air port 61 is straight structure.It can be lifted by lifting room 50 and ground hoisting port 63 into bilge tank 10 and comprehensive cabin 20 Feed intake.
It is preferred that the upper surface of the inner side of lifting room 50 is concordant with the upper surface of the inner side of bilge tank 10, the left side wall position of room 50 is lifted In the surface of the left side wall in comprehensive cabin 20, the upper surface of the inner side of bilge tank 10 is provided with suspension hook 15;Or the inner side of lifting room 50 is upper Surface is provided with suspension hook 15;Or the upper surface of bilge tank 10 and the inner side of lifting room 50 is equipped with suspension hook 15.
In the present embodiment, one section of prefabricated pipe gallery can be with as shown in figure 5, the prefabricated pipe gallery also includes crossing set Pipe 16, crosses that the center line of sleeve pipe 16 is horizontally disposed, crosses the central axis of sleeve pipe 16 in the prefabricated pipe gallery Length direction, cross sleeve pipe 16 through bilge tank 10 left side wall top and bilge tank 10 right side wall top, cross Sleeve pipe 16 is located at the outside in comprehensive cabin 20 and combustion gas cabin 30, crosses and is arranged with water string 17, water string 17 outside sleeve pipe 16 In in the left side wall and right side wall of bilge tank 10.Cross sleeve pipe 16 be used for for pipe gallery by-pass line pipeline cross it is current, Water string 17 is soft waterproof casing, and water string 17 can prevent the water of below ground from entering in bilge tank 10.
The prefabricated pipe gallery when in use can be largely using prefabricated pipe gallery section as shown in Figure 2, every several Prefabricated pipe gallery section as shown in Figure 2 uses a prefabricated pipe gallery section as shown in Fig. 3, Fig. 4 or Fig. 5, so as to combine Into complete pipe gallery.Prefabricated pipe gallery section wherein shown in Fig. 3, Fig. 4 or Fig. 5 also can be according to circumstances cast-in-place using part The mode of concrete is completed to make.
It is described above, only specific embodiment of the utility model, it is impossible to which the scope that utility model implemented, institute are limited with it With the displacement of its equivalent assemblies, or the equivalent variations made according to the utility model patent protection domain and modification, it should all still fall within The category that this patent is covered.In addition, between technical characteristic and technical characteristic in the utility model, technical characteristic and technical scheme Between, can be used with independent assortment between technical scheme and technical scheme.

Claims (10)

1. a kind of prefabricated pipe gallery, it is characterised in that the prefabricated pipe gallery includes bilge tank (10), comprehensive cabin (20) and fired Gas cabin (30), bilge tank (10) are located at the right side of the prefabricated pipe gallery, and combustion gas cabin (30) are located at a left side for the prefabricated pipe gallery Side, comprehensive cabin (20) are located between bilge tank (10) and combustion gas cabin (30), and the lower surface on the inside of bilge tank (10) is higher than comprehensive cabin (20) lower surface on the inside of, the upper surface on the inside of bilge tank (10) are higher than the upper surface on the inside of comprehensive cabin (20).
2. prefabricated pipe gallery according to claim 1, it is characterised in that the lower surface on the inside of bilge tank (10) is less than comprehensive The upper surface on the inside of cabin (20) is closed, the lower surface on the inside of bilge tank (10) is higher than upper surface and comprehensive cabin on the inside of comprehensive cabin (20) (20) midpoint between lower surface on the inside of.
3. prefabricated pipe gallery according to claim 2, it is characterised in that upper surface and sewage on the inside of bilge tank (10) The distance between lower surface on the inside of cabin (10) is the upper surface on the inside of comprehensive cabin (20) and the lower surface on the inside of comprehensive cabin (20) Between distance 75%~125%, comprehensive cabin (20) and combustion gas cabin (30) share the left side wall of comprehensive cabin (20), comprehensive cabin (20) Right side wall top and the bottom of the left side wall of bilge tank (10) share.
4. prefabricated pipe gallery according to claim 3, it is characterised in that the prefabricated pipe gallery also includes draft chamber (40), draft chamber (40) are located at the top of comprehensive cabin (20), and draft chamber (40) are adjacent with bilge tank (10) left and right, draft chamber (40) The upper side wall of comprehensive cabin (20), the top of the left side wall of bilge tank (10) and the right side of draft chamber (40) are shared with comprehensive cabin (20) Wall shares, and the top of draft chamber (40) can connect with ground ventilation mouth (61).
5. prefabricated pipe gallery according to claim 4, it is characterised in that the upper side wall of comprehensive cabin (20) is provided with can be with The upper air vent (21) of draft chamber (40) connection, the top of the left side wall of bilge tank (10) are provided with and can connected with draft chamber (40) Side air vent (11).
6. prefabricated pipe gallery according to claim 5, it is characterised in that be provided with draft chamber (40) and be used to extract sewage The draft fan (41) of cabin (10) interior gas, bilge tank (10) is interior to be provided with sewage conduct buttress (12) and sewage conduct conduit saddle (13), sewage conduct conduit saddle (13) is arranged on sewage conduct buttress (12).
7. prefabricated pipe gallery according to claim 4, it is characterised in that upper surface and sewage on the inside of draft chamber (40) Upper surface on the inside of cabin (10) is concordant, and the left side wall of draft chamber (40) is located at the surface of the left side wall of comprehensive cabin (20), combustion gas Upper surface on the inside of cabin (30) is concordant with the upper surface on the inside of comprehensive cabin (20), the lower surface on the inside of combustion gas cabin (30) and comprehensive cabin (20) lower surface on the inside of is concordant.
8. prefabricated pipe gallery according to claim 3, it is characterised in that the prefabricated pipe gallery also includes lifting room (50) top that room (50) are located at comprehensive cabin (20), is lifted, lifting room (50) is adjacent with bilge tank (10) left and right, lifts room (50) The upper side wall of comprehensive cabin (20) is shared with comprehensive cabin (20), the inside of lifting room (50) is connected with the inside of bilge tank (10) as one Body, the top of lifting room (50) can connect with ground hoisting port (63).
9. prefabricated pipe gallery according to claim 8, it is characterised in that upper surface and sewage on the inside of lifting room (50) Upper surface on the inside of cabin (10) is concordant, and the left side wall of lifting room (50) is located at the surface of the left side wall of comprehensive cabin (20);
Upper surface on the inside of bilge tank (10) is provided with suspension hook (15);
Or the upper surface on the inside of lifting room (50) is provided with suspension hook (15);
Or the upper surface on the inside of bilge tank (10) and lifting room (50) is equipped with suspension hook (15).
10. prefabricated pipe gallery according to claim 1, it is characterised in that the prefabricated pipe gallery also includes crossing set Manage (16), cross sleeve pipe (16) through the top of the left side wall of bilge tank (10) and the top of the right side wall of bilge tank (10), it is horizontal Sleeve-penetrating (16) is located at the outside of comprehensive cabin (20) and combustion gas cabin (30), crosses and is arranged with water string (17) outside sleeve pipe (16), Water string (17) is located in the left side wall and right side wall of bilge tank (10).
CN201720452918.9U 2017-04-27 2017-04-27 Prefabricated pipe gallery Active CN207121927U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720452918.9U CN207121927U (en) 2017-04-27 2017-04-27 Prefabricated pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720452918.9U CN207121927U (en) 2017-04-27 2017-04-27 Prefabricated pipe gallery

Publications (1)

Publication Number Publication Date
CN207121927U true CN207121927U (en) 2018-03-20

Family

ID=61615213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720452918.9U Active CN207121927U (en) 2017-04-27 2017-04-27 Prefabricated pipe gallery

Country Status (1)

Country Link
CN (1) CN207121927U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106906846A (en) * 2017-04-27 2017-06-30 中冶京诚工程技术有限公司 Prefabricated pipe gallery

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106906846A (en) * 2017-04-27 2017-06-30 中冶京诚工程技术有限公司 Prefabricated pipe gallery
CN106906846B (en) * 2017-04-27 2022-08-02 中冶京诚工程技术有限公司 Prefabricated comprehensive pipe gallery

Similar Documents

Publication Publication Date Title
CN106906846A (en) Prefabricated pipe gallery
CN107653906B (en) Vertically-arranged underground comprehensive pipe gallery and construction method
CN206090784U (en) Utility tunnel's sewer manhole group
CN106013215B (en) Three layers of class rectangle Urban Underground Complex
CN106013221B (en) Four layers of class rectangle Urban Underground Complex
CN106351254A (en) Multilayer urban underground comprehensive pipe gallery
CN105926676A (en) Comprehensive pipe rack system with sponge urban function
CN207685859U (en) A kind of underground pipe gallery
CN205688460U (en) Pipe gallery system with sponge city function
CN202164660U (en) Layered water intake gallery for earth surface reservoir
CN207121927U (en) Prefabricated pipe gallery
CN208605197U (en) A kind of building structure that subway driving section is built together with Urban Underground pipe gallery
CN201437729U (en) Cross-shaped intersection for comprehensive pipe canals
CN106013222B (en) Three circular cross section Urban Underground Complexes
CN108374432A (en) Pipe gallery integration exploitation is total to the open-cut station of structure with subway
CN205348223U (en) Node structure of being connected control center and two cabin utility tunnel
CN208121811U (en) Pipe gallery integration exploitation and subway are total to the open-cut station of structure
CN106638682A (en) Efficient-seismic-reduction quasi-rectangular city underground architecture complex
CN210766884U (en) Underground cover plate ditch suitable for pipeline collection
CN109469099A (en) Assembled underground pipe gallery
CN209907433U (en) Mud discharging and emptying system for overhauling water supply pipeline of corridor
CN205604295U (en) Utility tunnel dog -house structure
CN210507348U (en) Vertical shaft structure with step
CN104912100B (en) Pipe gallery synthetic assembly mouth
CN206581296U (en) Multichannel underground pipe gallery with ventilation escape mouth structure

Legal Events