CN207090875U - A kind of tower barrel of wind generating set saddle platform cable hanging apparatus - Google Patents
A kind of tower barrel of wind generating set saddle platform cable hanging apparatus Download PDFInfo
- Publication number
- CN207090875U CN207090875U CN201721002655.8U CN201721002655U CN207090875U CN 207090875 U CN207090875 U CN 207090875U CN 201721002655 U CN201721002655 U CN 201721002655U CN 207090875 U CN207090875 U CN 207090875U
- Authority
- CN
- China
- Prior art keywords
- cable
- hanger
- steel wire
- wire rope
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
A kind of tower barrel of wind generating set saddle platform cable hanging apparatus, including electric block, steel wire rope, fixed pulley and at least two hangers, the electric block is removably mounted on tower barrel platform, the steel wire rope is connected with electric block, the steel wire rope is used for crane cable, at least two hanger is arranged on tower wall, the fixed pulley is located in one of on hanger, the steel wire penetrating fixed pulley and end of the steel wire rope is with treating that crane cable is connected, another hanger temporarily positions the cable lifted.The utility model provides a kind of easy disassembly, effectively avoids damaging paint in tower, saves the tower barrel of wind generating set saddle platform cable hanging apparatus of cable hoisting time.
Description
Technical field
It the utility model is related to wind-driven generator field, more particularly to a kind of wind-driven generator tower inner cable lifting dress
Put.
Background technology
At present, the laying form of cable has two kinds in wind power generating set:When top-down laying, second, under
Laying on and.Wherein the first laying form is relatively simple, only need to be by cable toward decentralization, and second of laying form is then
Need upward lifting of the mechanical device by cable by root.Then for second of laying form, existing lifting mode is direct
An electric block is arranged above in tower top cable, hauling cable with pull rope up lifts.And such lifting mode has one
The defects of determining:First, electric block is directly hung on tower wall, there is the risk that collision tower causes paint to damage;Second, electricity
Need the position of electric block installation is higher during the direct trailing cable of dynamic cucurbit, make its dismounting inconvenience.
The content of the invention
In order to overcome being easily damaged in tower for existing wind-driven generator tower inner cable lifting mode to paint, dismount inconvenience
Deficiency, the utility model provides a kind of easy disassembly, effectively avoids damaging paint in tower, saves the wind of cable hoisting time
Power generator group tower saddle platform cable hanging apparatus.
Technical scheme is used by the utility model solves its technical problem:
A kind of tower barrel of wind generating set saddle platform cable hanging apparatus, including electric block, steel wire rope, fixed pulley
With at least two hangers, the electric block is removably mounted on tower barrel platform, and the steel wire rope is connected with electric block,
The steel wire rope is used for crane cable, and at least two hanger is arranged on tower wall, and the fixed pulley is located therein one
On individual hanger, the steel wire penetrating fixed pulley and end of the steel wire rope is with treating that crane cable is connected, another hanger
Temporarily position the cable lifted.
Further, the installation of the electric block need to be parallel to cable present position;
Further, the hanger has two, and the hanger is preset on tower wall, and one of them is used to install institute
Fixed pulley is stated, another is used for temporarily fixation and has lifted cable.
In the utility model, during the hanger temporarily fixed lifting cable in place, the installation of this cable is fixed and next
The lifting of root cable can be carried out synchronously, save the substantial amounts of time.The length of described two hangers can just make to be arranged on institute
The center of gravity for stating the fixed pulley on hanger is in above the hoisting port of cable, ensures that cable can lift vertically upward.
The beneficial effects of the utility model are mainly manifested in:Simple in construction, installation and removal are convenient, and electric block is arranged on
It is convenient at any time with installing at any time on platform, and paint in tower will not be damaged, cable can be easily along the direction of steel wire rope
Lifting;During crane cable, by being preset in hanger and fixed pulley on tower wall, thus it is possible to vary the direction of draw of cable, and it is another
The individual hanger for being fitted without fixed pulley can be used for the temporarily cable of fixed lifting in place, electric block is spared lifting
Next cable, it installation is fixed cable and crane cable while carry out, save the substantial amounts of working time.
Brief description of the drawings
Fig. 1 is a kind of operating diagram of tower barrel of wind generating set saddle platform cable hanging apparatus, wherein, 1, electricity
Dynamic cucurbit;2nd, steel wire rope (the cable string bag);3rd, fixed pulley;4th, hanger;5th, hanger;6th, cable;7th, platform.
Embodiment
The utility model is further described below in conjunction with the accompanying drawings.
Reference picture 1, a kind of tower barrel of wind generating set saddle platform cable hanging apparatus, including electric block 1, steel wire
Rope 2, fixed pulley 3, hanger 4 and hanger 5, the electric block 1 are installed on platform 7 parallel to cable testing bridge, the steel wire rope 2
Total length matching tower height, one end are wound on the electric block 1, and the other end pulls cable 6 through fixed pulley 3, described
Fixed pulley 3 is arranged on hanger 4, and the hanger 4 and hanger 5 are pre-welded on tower wall, and the hanger 5 is used for temporarily fixed
The cable 6 of lifting in place;
Further, when the hanger 5 temporarily fixes the cable 6 of lifting in place, the installation of this cable is fixed and next electricity
The lifting of cable can be carried out synchronously, save the substantial amounts of time;
Further, the fixed pulley 3 both may be mounted on hanger 4, can also be arranged on hanger 5, described fixed sliding
3 lighter weights are taken turns, are removed and installed simple and convenient;
Further, the length of the hanger 4 and hanger 5 can just make the fixed pulley being arranged on the hanger
3 center of gravity is in above the hoisting port of cable 6, than ensureing that cable can lift vertically upward;
In the present embodiment, the electric block 1 and the fixed pulley 3 are detachable, and the electric block 1 needs to hang in tower
It is arranged on when filling cable on platform 7, the fixed pulley 3 is arranged on hanger 4, and the steel wire rope 2 is wrapped in described electronic
On cucurbit 1;
In the hoisting process of cable, the steel wire rope 2 is passed through into the fixed pulley 3, starts the electric block 1, will
The steel wire rope 2 fixes the head end of the steel wire rope 2 and cable 6, with the electric block 1 afterwards in place toward rope is put under tower
Cable is up lifted, after lifting in place, the cable 6 is fixed on the hanger 5, removes the steel wire on cable 6
Rope 2, repeat more than action carry out the lifting of next cable, and simultaneously, being temporarily fixed to cable 6 on the hanger 5 can be with
Carry out the installation with crane span structure and fix work;
, can be by the fixed pulley 3 from the hanger after cable installation on the cable testing bridge of the side of hanger 5
Pull down, changed on the hanger 5 on 4, and the hanger 4 is used for temporarily fixed cable, is repeated in above work, completes all
The lifting work of cable.
Although by the utility model combination specific implementation is described, in personage known to the art,
It will be apparent according to the replacement made, modification and change mentioned above.Therefore, substitute, change and become such
When change is fallen into spirit and scope by the claims of the present utility model, it should be included in the utility model.
Claims (3)
- A kind of 1. tower barrel of wind generating set saddle platform cable hanging apparatus, it is characterised in that:Including electric block, steel wire Rope, fixed pulley and at least two hangers, the electric block are removably mounted on tower barrel platform, the steel wire rope with it is electronic Cucurbit connects, and the steel wire rope is used for crane cable, and at least two hanger is arranged on tower wall, the fixed pulley position In on one of hanger, the steel wire penetrating fixed pulley and end of the steel wire rope is with treating that crane cable is connected, in addition One hanger temporarily positions the cable lifted.
- A kind of 2. tower barrel of wind generating set saddle platform cable hanging apparatus as claimed in claim 1, it is characterised in that: The installation of the electric block need to be parallel to cable present position.
- 3. a kind of tower barrel of wind generating set saddle platform cable hanging apparatus as claimed in claim 1 or 2, its feature exist In:The hanger has two, and the hanger is preset on tower wall, and one of them is used to install the fixed pulley, in addition One is used for temporarily fixation and has lifted cable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721002655.8U CN207090875U (en) | 2017-08-11 | 2017-08-11 | A kind of tower barrel of wind generating set saddle platform cable hanging apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721002655.8U CN207090875U (en) | 2017-08-11 | 2017-08-11 | A kind of tower barrel of wind generating set saddle platform cable hanging apparatus |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207090875U true CN207090875U (en) | 2018-03-13 |
Family
ID=61540901
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721002655.8U Active CN207090875U (en) | 2017-08-11 | 2017-08-11 | A kind of tower barrel of wind generating set saddle platform cable hanging apparatus |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207090875U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107324235A (en) * | 2017-08-11 | 2017-11-07 | 浙江运达风电股份有限公司 | A kind of tower barrel of wind generating set saddle platform cable hanging apparatus |
-
2017
- 2017-08-11 CN CN201721002655.8U patent/CN207090875U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107324235A (en) * | 2017-08-11 | 2017-11-07 | 浙江运达风电股份有限公司 | A kind of tower barrel of wind generating set saddle platform cable hanging apparatus |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205953370U (en) | Perpendicular transport means of unitized curtain wall | |
CN206502579U (en) | Power pole hoisting device | |
CN206538144U (en) | A kind of liftable mobile electrical maintenance of equipment device | |
CN106986261A (en) | Gantry electroplating assembly line Special running of standby suspender is installed | |
CN107324235A (en) | A kind of tower barrel of wind generating set saddle platform cable hanging apparatus | |
CN207090875U (en) | A kind of tower barrel of wind generating set saddle platform cable hanging apparatus | |
CN102237654B (en) | Method for replacing jumper string using tool at double angle hanging point | |
CN202474703U (en) | Overhead ground wire lifting mechanism | |
CN205838410U (en) | Blower fan hoisting mechanism | |
CN205061416U (en) | OG fan tegillum hoist device | |
CN102320522B (en) | Hoisting in-place method for allowing large equipment to pass through ultrahigh hole | |
CN206680062U (en) | A kind of prefabricated part hanging instrument | |
CN207098443U (en) | A kind of helicopter live-line maintenance operation hanging basket | |
CN107381397B (en) | Quick safe hoist device of cable in wind generating set tower section of thick bamboo | |
CN201285999Y (en) | Soft ladder for high voltage line maintenance | |
CN207090869U (en) | A kind of tower barrel of wind generating set inner cable fast and safely hanging apparatus | |
CN205802755U (en) | A kind of efficient lifting device for changing dust-removal cloth-bag | |
CN202353095U (en) | Wire lifting arrangement structure for 8-bundled conductors on straight-path tower | |
CN203423430U (en) | Insulator maintenance device | |
CN206244263U (en) | Construction of Silo special hanger | |
CN206735628U (en) | Gantry electroplating assembly line Special running of standby suspender is installed | |
CN205668869U (en) | A kind of boom hoisting for dredge pump maintenance | |
CN109353952A (en) | A kind of lifting device of transformer suitable for extreme terrain | |
CN204858412U (en) | Distribution lines cable and wire tied in a bundle set up and pass through ware with sharp pole | |
CN205901178U (en) | Concrete pole tower overhead earth wire hoisting device |