CN207035966U CN201720819637.2U CN201720819637U CN207035966U CN 207035966 U CN207035966 U CN 207035966U CN 201720819637 U CN201720819637 U CN 201720819637U CN 207035966 U CN207035966 U CN 207035966U
Authority
CN
China
Prior art keywords
area
explosion
main blast
buffer strip
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720819637.2U
Other languages
Chinese (zh)
Inventor
张义平
�田�浩
裴鹏
周俊
王建楠
严鸿海
肖中诚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou University
Original Assignee
Guizhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou University filed Critical Guizhou University
Priority to CN201720819637.2U priority Critical patent/CN207035966U/en
Application granted granted Critical
Publication of CN207035966U publication Critical patent/CN207035966U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of explosion shock dropping to buffer band structure, including main blast area, main blast hole, buffer strip, dashpot, presplit blasting area, pre- ceasma and secondary blasting hole;Main blast hole is offered in the main blast area;Pre- ceasma is offered in the presplit blasting area;Buffer strip is provided between the main blast area and presplit blasting area;Dashpot is offered in the buffer strip;The bottom of the dashpot offers secondary blasting hole.The utility model is disposed with presplit blasting area, buffer strip and main blast area, and detonated successively in explosion, strengthen the buffering shock dropping effect in presplit blasting area by buffer strip, the aperture of blast hole and fill out dose in the utility model presplit blasting area, buffer strip and main blast area and increase successively, the effect of reinforcement is played in the region of explosion to the region of first explosion afterwards, and the effect of buffering energy-absorbing is played in the region of first explosion to the region of rear explosion, so as to strengthen the protection effect of side slope while demolition effect is ensured.

Description

A kind of explosion shock dropping buffers band structure
Technical field
Blasting technique field is the utility model is related to, specially a kind of explosion shock dropping buffering band structure.
Background technology
With the continuous development of China's open-pit mining techniques, large-scale and super-huge surface mine is in brown, coloured and building materials Industry is continuously available exploitation, and mining depth is increasing.For big-and-middle-sized surface mine, onepull explosive payload may reach To tens tons, or even hundreds of tons, these explosions can all produce blasting effect, and the stability to slope rock mass brings certain shadow Ring, the explosion of particularly neighbouring side slope, formation to last slope and stably have a major impact.
Presplit blasting is the maximally effective Controlled blasting technique of neighbouring slope blasting, is characterized in pre- ceasma using not coupling Charge structure is closed, loads a small amount of explosive, pre- ceasma detonates in advance or pre- ceasma is detonated prior to main blast hole by elementary errors technology, To form crack, the influence of cut-off production resettlement side slope, but simple presplit blasting when burst region is close to building, its Shock dropping effect is limited, limits the progress of construction.
Then, inventor in view of this, adhere to the relevant industries for many years it is abundant design and develop and the experience of actual fabrication, Improvement is studied for existing structure and missing, there is provided a kind of explosion shock dropping buffers band structure, is had more more to reach Add the purpose of practical value.
The content of the invention
The purpose of this utility model is to provide a kind of explosion shock dropping buffering band structure, to solve to carry in above-mentioned background technology When burst region is close to building, its shock dropping effect is limited for the simple presplit blasting gone out, and the progress for limiting construction is asked Topic.
To achieve the above object, the utility model provides following technical scheme:A kind of explosion shock dropping buffers band structure, including
Main blast area, main blast hole, buffer strip, dashpot, presplit blasting area, pre- ceasma and secondary blasting hole;
Main blast hole is offered in the main blast area;Pre- ceasma is offered in the presplit blasting area;The main explosion Buffer strip is provided between area and presplit blasting area;Dashpot is offered in the buffer strip;The bottom of the dashpot offers Secondary blasting hole.
Preferably, the dashpot is provided with three altogether, and the depth of both sides dashpot is more than the depth of intermediate buffering groove.
Preferably, the aperture in the secondary blasting hole is less than the aperture of main blast hole.
Compared with prior art, the utility model has the advantages that:
1. the utility model is disposed with presplit blasting area, buffer strip and main blast area, and in explosion successively Detonation, strengthen the buffering shock dropping effect in presplit blasting area, further destruction caused by mitigating explosion side slope by buffer strip.
2. the aperture of blast hole and fill out dose in the utility model presplit blasting area, buffer strip and main blast area and increase successively Add, the effect of reinforcement is played in the region of rear explosion to the region of first explosion, and the region of first explosion is played to the region of rear explosion The effect of buffering energy-absorbing, so as to strengthen the protection effect of side slope while demolition effect is ensured.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is the utility model structure diagram.
In figure:1st, main blast area, 2, main blast hole, 3, buffer strip, 4, dashpot, 5, presplit blasting area, 6, pre- ceasma, 7, Secondary blasting hole.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Fig. 1-2 is referred to, the utility model provides a kind of technical scheme:A kind of explosion shock dropping buffers band structure, including
Main blast area 1, main blast hole 2, buffer strip 3, dashpot 4, presplit blasting area 5, pre- ceasma 6 and secondary blasting hole 7;
Main blast hole 2 is offered in main blast area 1;Pre- ceasma 6 is offered in presplit blasting area 5;Main blast area 1 and presplitting Buffer strip 3 is provided between blast area 5;Dashpot 4 is offered in buffer strip 3;The bottom of dashpot 4 offers secondary blasting hole 7.
In above-described embodiment, specifically, dashpot 4 is provided with three altogether, and the depth of both sides dashpot 4 is more than intermediate buffering The depth of groove 4, the dashpot 4 being just staggered are advantageous to improve the energy-absorbing effect of buffer strip 3.
In above-described embodiment, specifically, the aperture in secondary blasting hole 7 is less than the aperture of main blast hole 2, secondary blasting hole 7 Complemented each other with main blast hole 2, play a part of assistant reinforcement demolition effect.
Operation principle:
Explosion shock dropping buffering band structure is disposed with presplit blasting area 5, buffer strip 3 and main blast area 1, is detonating When, detonated successively by elementary errors technology, the presplit blasting area 5 detonated first forms crack, separates ensuing blast side slope Influence, after the explosion of presplit blasting area 5, to buffer strip 3 carry out explosion, due in buffer strip 3 secondary blasting hole 7 fill out dose compared with It is small, reinforcement explosion is carried out to buffer strip 3 by the main blast area 1 of last explosion, meanwhile, explosion forms the buffer strip in crack Energy-absorbing buffering is played a part of in the explosion of 3 pairs of main blast areas, with reference to presplit blasting area 5, strengthens shock dropping buffering effect, so as to improve The protection effect of side slope.
The standardized element that the utility model uses can commercially, shaped piece according to specification and accompanying drawing Record can carry out customized, the specific connected mode of each part is using bolt ripe in the prior art, rivet, weldering The conventional meanses such as connect, paste, part using model conventional in the prior art, will not be described in detail herein.
In summary, general principle, principal character and advantage of the present utility model has been shown and described above.The industry Technical staff it should be appreciated that the utility model is not restricted to the described embodiments, described in above-described embodiment and specification only It is to illustrate principle of the present utility model, on the premise of the spirit and scope of the utility model is not departed from, the utility model also has Various changes and modifications, these changes and improvements are both fallen within claimed the scope of the utility model.The requires of the utility model Protection domain is defined by appended claims and its effect thing.

Claims (3)

1. a kind of explosion shock dropping buffers band structure, it is characterised in that:Including
Main blast area, main blast hole, buffer strip, dashpot, presplit blasting area, pre- ceasma and secondary blasting hole;
Main blast hole is offered in the main blast area;Pre- ceasma is offered in the presplit blasting area;The main blast area with Buffer strip is provided between presplit blasting area;Dashpot is offered in the buffer strip;The bottom of the dashpot offers auxiliary Blast hole.
2. explosion shock dropping according to claim 1 buffers band structure, it is characterised in that:The dashpot is provided with three altogether, And the depth of both sides dashpot is more than the depth of intermediate buffering groove.
3. explosion shock dropping according to claim 1 buffers band structure, it is characterised in that:The aperture in the secondary blasting hole is small In the aperture of main blast hole.
CN201720819637.2U 2017-07-07 2017-07-07 A kind of explosion shock dropping buffers band structure Active CN207035966U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720819637.2U CN207035966U (en) 2017-07-07 2017-07-07 A kind of explosion shock dropping buffers band structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720819637.2U CN207035966U (en) 2017-07-07 2017-07-07 A kind of explosion shock dropping buffers band structure

Publications (1)

Publication Number Publication Date
CN207035966U true CN207035966U (en) 2018-02-23

Family

ID=61465901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720819637.2U Active CN207035966U (en) 2017-07-07 2017-07-07 A kind of explosion shock dropping buffers band structure

Country Status (1)

Country Link
CN (1) CN207035966U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107144194A (en) * 2017-07-07 2017-09-08 贵州大学 A kind of explosion shock dropping buffers band structure
CN110926287A (en) * 2019-12-20 2020-03-27 深圳市蛇口招商港湾工程有限公司 Cutting earth and rock excavation blasting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107144194A (en) * 2017-07-07 2017-09-08 贵州大学 A kind of explosion shock dropping buffers band structure
CN110926287A (en) * 2019-12-20 2020-03-27 深圳市蛇口招商港湾工程有限公司 Cutting earth and rock excavation blasting method

Similar Documents

Publication Publication Date Title
CN103696770B (en) Underground mining upward incise kerve method
CN207035966U (en) A kind of explosion shock dropping buffers band structure
CN109724484A (en) A kind of the undercut blast hole arragement construction and well completion method of blind courtyard simultaneous shaft sin king
CN109141149A (en) A kind of tunnel excavation hydraulic pressure demolition construction method
CN104154830A (en) Medium-length hole blasting method for underground mining
CN103541734A (en) Comprehensive damping method for blasting of tunnel passing through heritage conservation building
CN110645855B (en) Dust suppression blasting method for medium-length hole of strip mine
CN103575172A (en) Novel roadway blasting construction method
CN107339920B (en) The method of superdeep holes presplit blasting
CN103389015A (en) Subsection millisecond differential blasting method in blasthole
CN106121653A (en) One closes hole surface mine Ore stoping method
CN104048570A (en) Deep hole blasting filling method
CN109630120A (en) A kind of mining methods for the rich or poor co-layer ore body of low-angle dip
CN108756881A (en) A kind of bump preventing control method in solid coal column pressure coal region
CN103557758A (en) Expanded excavation region hole inside and outside combined delayed regional differential blasting network in tunnel blasting
CN107762511B (en) A kind of class strip-type coal-mining method cut top filling and close on goaf
CN107270791B (en) A kind of vertical shaft for mine explosion well completion method
CN109186390B (en) Open-air deep hole blasting water interval-coupled charging blasting method and special water column bag
CN107524444A (en) A kind of controlled blasting method for improving resuing stoping and falling ore deposit efficiency
CN108050902B (en) Tunnel blasting excavation method
CN110332865A (en) Deep high stress stope upper centripetal deep hole combined blasting method
CN107144194A (en) A kind of explosion shock dropping buffers band structure
CN103557756A (en) Advanced adit hole-by-hole delayed blasting network in tunnel blasting
CN103644788B (en) A kind of coal mine roadway burn cut eye increases prestige loading method